Empire Lath Plaster Inc. v. Ame ( 1993 )


Menu:
  •                                No.    92-090
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1993
    EMPIRE LATH    &   PLASTER, INC.,
    Plaintiff and Respondent,
    v.
    AMERICAN CASUALTY COMPANY O F
    READING, PENNSYLVANIA,
    Defendant and Appellant.
    APPEAL FROM:       District Court of the Thirteenth Judicial District,
    In and for the County of Yellowstone,
    The Honorable Russell K. Fillner, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Richard J. Andriolo, Berg, L i l l y ,
    Andriolo & Tollefsen, Bozeman, Montana
    For Respondent:
    P. Bruce Harper, Attorney at Law,
    ~illings, Montana
    Submitted on Briefs: May 28, 1992
    Decided:    February 11, 1993
    Filed:
    Justice Terry N. Trieweiler delivered the opinion of the Court.
    Defendant American Casualty Company of Reading, Pennsylvania
    (American Casualty), appeals from a default judgment of $58,049.40,
    entered in favor of Empire Lath       &   Plaster, Inc, ( ~ m p i r e ) on
    November 6, 1991, in the Thirteenth Judicial District Court,
    Yellowstone County.   ~mericanCasualty's subsequent motion to set
    aside the judgment was deemed denied pursuant to Rule 60(c),
    M.R.Civ.P., when the ~istrictCourt failed to rule on the motion
    within 45 days.
    We affirm.
    The sole issue for our consideration is whether the District
    Court abused its discretion when          it did not grant American
    Casualtylsmotion to set aside the default judgment.
    This   litigation   arises out   of    a   construction contract
    associated with the building of the Billings Parking Garage and
    City Hall Expansion Project.   In April 1990, the City of Billings
    awarded the general contract for the construction project to C        &   D
    Contractors, Inc. (CD), and CD thereafter subcontracted a portion
    of the project to Empire. In connection with the general contract,
    a bond in excess of $3 million was executed by American Casualty to
    guarantee payment to subcontractors for labor, material, and
    equipment supplied during the construction project.
    ~mpirecompleted its portion of the work on April 16, 1991,
    and submitted its final billing statement to CD which reflected an
    unpaid balance due Empire totalling $47,124.96. In addition to the
    amount owed under the subcontract, Empire had performed a "change
    for the project which had been authorized by CD and approved
    orderat
    by the project architect, at a cost of $1,200.00.
    At the same time Empire submitted its final statement, CD sent
    a letter to Empire confirming the outstanding balance due under the
    contract, but asserting that ~mpire had failed to 'ldiligently
    pursue its work in a timely manner.    CD claimed this failure to
    properly perform under the contract delayed the entire project and
    resulted in significant additional costs to CD.     No further facts
    nor specifics were ever provided to ~mpire regard to the alleged
    in
    contract breach.
    After computing the costs which it alleged were a result of
    Empireas delay, CD determined it would withhold $31,576.00, and
    tendered a check to Empire for $15,548.96.   The check contained a
    restrictive endorsement which provided that ~mpire'sendorsement
    would acknowledge final and conclusive payment for all work
    performed, and would release CD from any further liability under
    the subcontract.   Empire refused to execute the check due to the
    restrictions, and insisted on either full payment, or payment of
    the uncontested sum of $15,548.96, with an understanding that the
    parties would attempt to resolve the dispute over the remaining
    amount.
    Empire received no payments from CD, and on July 2, 1991,
    Empire submitted a notice to the city of Billings, CD, and American
    Casualty (as the surety for the project), stating that it had a
    claim of $47,124.96 against the bond for the work performed under
    the subcontract, and also for the $1,200.00 incurred for the change
    order.   Empire received no response from either CD or ~merican
    Casualty regarding the claim notice.
    On August 14, 1991, ~mpirefiled a complaint in ~istrictCourt
    against American Casualty in order to collect the outstanding
    balance owed to Empire which was guaranteed by the bond.       This
    civil action was filed in Yellowstone County as required by
    provisions contained in the bond; CD was not named as a defendant
    in the case because the subcontract between CD and Empire required
    venue in Lewis and Clark county.    The summons and complaint were
    served on American Casualtylslegal department on August 23, 1991.
    The Claims Analyst for ~mericanCasualty immediately forwarded
    the summons and complaint to CD, along with a letter tendering the
    defense of the action to CD as was apparently standard practice.
    Although American Casualty was in communication with CD on other
    matters, Empire's pending lawsuit was never discussed, and CD
    asserts that it had no knowledge of the action nor ever received
    American Casualty's letter tendering the defense of the action to
    CD.
    The District Court, based on an affidavit from the supervising
    architect of the construction project, found that Empire had fully
    and competently performed the requirements of the subcontract in a
    timely manner, and that there was no basis to withhold full payment
    to Empire.   The court concluded that Empire had complied with all
    conditions required by the bond, and was, therefore, entitled to
    recover from American Casualty under the bond.    The court entered
    a default judgment against American Casualty on November 6, 1991,
    for $58,049.40, which represented the contract amount due Empire,
    plus interest, the $1,200.00 incident to the change order, and
    attorney fees and costs of $170.39.
    The following day, American Casualty discovered that the
    default judgment had been entered and that no appearance had been
    made by CD on behalf of the surety. On November 14, 1991, American
    Casualty moved to set aside the default judgment, filed its answer
    to the complaint, and requested a trial on the merits.          The
    District Court did not rule on the motion within 45 days from the
    time it was filed, and the motion was, therefore, deemed denied
    pursuant to Rule 60(c), M.R.Civ.P.    From this denial of the motion
    to set aside the default judgment, American Casualty appeals.
    The issue presented is whether the District Court abused its
    discretion when it did not set aside the default judgment.
    American Casualty argues that the court should have granted relief
    from the judgment under Rule 55(c), M.R.Civ.P., which allows for
    the setting aside of a default judgment:
    For good cause shown the court may set aside an entry of
    default and, if a judgment by default has been entered,
    may likewise set it aside in accordance with Rule 60(b).
    Rule 60(b), M.R.Civ.P., states in pertinent part:
    On motion and upon such terms as are just, the court may
    relieve a party or a party's legal representative from a
    final judgment, order, or proceeding for the following
    reasons: (1) mistake, inadvertence, surprise, or
    excusable neglect   . . .    or (6) any other reason
    justifying relief from the operation of the judgment.
    Where a trial court fails to grant a motion to set aside a
    default judgment, the finding of even a slight abuse of discretion
    is sufficient to justify reversal of such an order. BoardofDirectors
    Edelweks Ownersw Assn. v. Mclntosh (1991), 
    251 Mont. 144
    , 
    822 P.2d 1080
    .
    In Lorhv.Newman (19841, 
    212 Mont. 359
    , 363, 
    688 P.2d 290
    , 293, we
    emphasized two basic tenets to be considered in setting aside
    default judgments: (1) every litigated case should be tried on its
    merits and judgments by default are not favored; and (2) trial
    courts have a certain amount of discretion when considering a
    motion to set aside a default judgment.              We have also clearly
    stated that the burden of proof rests on the party seeking to set
    aside the default judgment.          Siewingv.PearsonCo+ (1987), 
    226 Mont. 458
    , 461, 
    736 P.2d 120
    , 122.
    After considering these factors and applying the appropriate
    standard of review to the present case, we conclude that the
    District Court did not abuse its discretion when it failed to grant
    American Casualtytsmotion.
    American Casualty contends that the failure to file an answer
    was excusable neglect, and it is, therefore, entitled to relief
    from the judgment pursuant to Rule 6O(b), M.R.Civ.P.             However, in
    In re Manicrge of Castor   (19911, 2 4 
    9 Mont. 495
    , 
    817 P.2d 665
    , we
    emphasized that "mistake," inadvertence," and Itexcusableneglectw
    generally require some justification for an error beyond mere
    carelessness or ignorance of the law.              Castor, 817 P.2d a t 667
    (citing Lomas andNertIeton Co. v. Wieiey (7th C i r . 1989),   8 8 
    4 F.2d 965
    ,
    967).     In this instance, we conclude that American Casualtyls
    neglect was not justified and that the criteria of Rule 60(b) have
    not been satisfied.
    The bonding company asserts that it was standard practice to
    have CD take over the defense of actions filed against American
    Casualty.    American Casualty then maintains that after notifying
    CD, the claims analyst kept the complaint with other active files
    because she was purportedly monitoring negotiations between Empire
    and CD.     This resulted in the normal calendaring procedure being
    overlooked and, consequently, American Casualty did not check to
    see that a timely response had been filed. Furthermore, CD claims
    it never received the tender letter, and attributes this to the
    fact that CD was moving its offices and reducing office personnel
    at the time the letter was sent.
    Based on Blume v Metropolitan Life Insurance Company (1990) , 242 Mont
    .                                                         .
    465, 
    791 P.2d 784
    , where this Court found the district court abused
    its discretion when it refused to vacate a default judgment,
    American Casualty suggests the neglect in this situation is also
    inadvertent and excusable.       In Blume, certified mail containing a
    summons and complaint was delivered to the defendant company, but
    was apparently lost before anyone in a position of authority saw
    it.   After reviewing the record in this case, however, we conclude
    that the neglect demonstrated by both American Casualty and CD is
    not comparable to the inadvertence we excused in Blume.
    Unlike Blume, where the defendant company was unaware that the
    plaintiff was seriously considering filing suit and had no reason
    to suspect that a court appearance was necessary, neither American
    Casualty nor CD can profess ignorance of Empire's intention to
    pursue recovery under the bond. When Empire refused to execute the
    check for $15,548.96 because acceptance of this check would have
    released CD from further liability under the subcontract, CD was
    fully aware that Empire   was   challenging the unilateral withholding
    of payments.     Empire then complied with the required notice
    provisions prior to filing its complaint, thus giving both American
    Casualty and CD written notice of its claim against the bond and
    intent to seek recovery.
    The record shows that American Casualty was put on notice that
    Empire would assert its rights under the bond directly against the
    bonding company a minimum of five times prior to the filing of the
    complaint, and unlike the defendant in Blume,         the appropriate
    personnel did receive a copy of the summons and complaint. While
    it may have been reasonable to assign CD the responsibility of
    responding to Empire's complaint, American Casualty cannot justify
    its failure to follow-up on the matter.      This is particularly true
    in light of the following statement made in the August 27, 1991
    tender letter:
    P l e a s e acknowledge your acceptance of this tender of
    defense prior to the answer date and            furnish the
    undersigned with a copy of the answer.
    As the only defendant named in the case, American Casualty had the
    responsibility to follow-up on its own request and insure that CD
    received and accepted the tender, and was preparing an appearance
    on American Casualty's behalf.
    The neglect demonstrated in this case was not like the
    unintentional oversight in Blume, and is, therefore, not excusable.
    In addition to finding excusable neglect, the judgment of a
    district court can be set aside for "any other reason justifying
    relief from the operation of the judgment. It              Rule 60 (b)(6),
    M.R.Civ.P.      Generally, relief is afforded under this subsection
    only in extraordinary situations when circumstances go beyond those
    covered specifically in Rule 60(b)       .   C s o , 817 P.2d at 668; Fuller
    atr
    v.   Quire (6th Cir.   l990), 
    916 F.2d 358
    , 360.    After reviewing the
    record, we conclude that American Casualty has failed to establish
    any other reason which would justify relief from the operation of
    the default judgment.
    We hold the District Court did not abuse its discretion when
    it did not grant the motion to set aside the judgment entered
    against American Casualty.
    Af finned.
    We concur: