Baskett v. Goldammer ( 1997 )


Menu:
  •                               No. 96-636
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1997
    RICHARD M. BASKETT and KATHLEEN T. BASKETT,
    Plaintiffs and Respondents,
    v.
    RONALD W. GOLDAMMER, d/b/a GOLDAMMER
    CONSTRUCTION & DESIGN,
    Defendant and Appellant.
    and
    WILLIAM HOFF, d/b/a CUSTOM CABINETS UNLIMITED,
    Plaintiff and Respondent,
    RONALD W. GOLDAMMER, d/b/a GOLDAMMER
    CONSTRUCTION AND DESIGN, and RICHARD M. BASKETT
    and KATHLEEN T. BASKETT, Husband and Wife,
    Defendants and Respondents
    APPEAL FROM:    District Court of the Fourth Judicial District,
    In and for the County of Missoula,
    The Honorable Ed McLean, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Don Torgenrud; Attorney at Law;
    St. Ignatius, Montana
    For Respondents:
    Milton Datsopoulos; Datsopoulos, MacDonald
    & Lind; Missoula, Montana
    Submitted on Briefs: February 20, 1997
    Decided: March 25, 1997
    Filed:
    Justice Jim Regnier delivered the opinion of the Court.
    Pursuant to Section I, Paragraph 3(c), Montana Supreme Court
    1995 Internal Operating Rules, the following decision shall not be
    cited as precedent and shall be published by its filing as a public
    document with the Clerk of the Supreme Court and by a report of its
    result to State Reporter Publishing Company and West Publishing
    Company.
    Richard and Kathleen Baskett filed a motion in the Fourth
    Judicial District Court, Missoula County, for an order entering
    judgment pursuant to the settlement agreement. On August 15, 1996,
    after hearing testimony, the Fourth Judicial District Court entered
    its order granting the Basketts' motion, ordering Goldammer to
    remove his     construction lien, and    dismissing    the   case with
    prejudice.    Goldammer appeals.   We affirm.
    The issues on appeal are:
    1.    Was the settlement agreement an agreement for arbitration
    under the Montana Uniform Arbitration Act,      §     27-5-101 through
    -324, MCA?
    2.      If the settlement agreement was not a formal agreement
    for arbitration under the Montana Uniform Arbitration Act, did the
    District Court err in concluding that the agreement was properly
    executed and awarding judgment in favor of the Basketts?
    FACTUAL BACKGROUND
    In 1991, the Basketts purchased a house in Missoula and
    entered into a written contract with Goldammer by which Goldammer
    agreed to renovate the home. The Basketts originally intended to
    2
    remodel the home and sell it for a profit or keep the property as
    a rental home.    The written contract provided that the renovations
    would be completed in accordance with the detailed specifications
    for a fixed sum of $35,000. During the performance of the original
    contract the Basketts decided they wanted to live in the home after
    the construction was completed. They therefore requested upgraded
    materials and additional work to be completed by Goldammer.
    The additional changes were not reduced to writing but were
    agreed upon orally by the Basketts and Goldammer.           As the work
    progressed, disagreements arose between the parties involving what
    items of construction had been completed, the value of the extra
    work completed, and which items of work could be credited to the
    original written contract.       The Basketts prepared a proposed
    written change order and submitted it to Goldammer. In response to
    this change order, Goldammer submitted a proposal to the Basketts.
    The proposal was rejected by the Basketts as it proposed a change
    from a fixed contract price to a time and materials contract.
    On November 27, 1991, Goldammer advised the Basketts that the
    job would cost at least $87,000, and that figure did not include
    several   thousands   of   dollars   of   bills   he   anticipated   from
    subcontractors.     The Basketts had a meeting with Goldammer on
    November 29, 1991, and advised him that any additional payments
    they made would have to be jointly made to subcontractors and
    himself since the figures he provided showed substantial sums
    unpaid to subcontractors. Goldammer stated he could not complete
    the job under those circumstances and performed no additional work.
    The Basketts hired another builder and retained Goldammer's work
    crew to complete the work.     On December 19, 1991, Goldammer filed
    a construction lien on the Basketts ' property for amounts allegedly
    owed by the Basketts.         The Basketts brought suit to require
    Goldammer to remove the lien and Goldammer countersued. One of the
    subcontractors, William Hoff, d/b/a Custom Cabinets Unlimited,
    brought suit against Goldammer and the Basketts. The suit by Hoff
    was dismissed with the subcontractor assigning his claim to the
    Basketts .
    The     parties   then   participated   in   several   settlement
    conferences.    Eventually, the Basketts offered to Goldammer that
    they jointly employ an architect to make the determination of how
    much of the final project consisted of work that was provided by
    the contract, and how much consisted of work attributable to
    changes to the contract. The Basketts further offered that if the
    architect determined that any amount was owed by them to Goldammer,
    they would pay that amount and, on the other hand, if the architect
    determined that the Basketts had paid more than what was required
    of them, Goldammer would not have to pay the Basketts, but would be
    required only to remove his construction lien. This offer was
    reduced to a settlement agreement entered into by both parties.
    The settlement agreement provided that a Missoula-based architect,
    Eric Hefty, was to be employed to complete the terms of the
    agreement.     On July 6, 1995, the District Court entered an order
    approving the parties' agreement and requiring that the parties
    complete the agreement and report back to the court within thirty
    days of the architect's report.
    The parties had the opportunity to meet with Hefty, discuss
    the work that had been completed, and answer any questions Hefty
    had.     Hefty     issued his    report     on   October 20, 1995, which
    recommended that the construction lien be released.                 This report
    was supplemented by his report on November 3, 1995, in which Hefty
    included certain additional amounts that had been paid by the
    Basketts, showing that their total payments exceeded the amounts
    claimed by Goldammer.         Hefty issued a third and final report on
    February 29, 1996, which affirmed his earlier reports.
    On July 29, 1996, the District Court held an evidentiary
    hearing and heard testimony from Eric Hefty, George Bingham, an
    expert witness for Goldammer, and from Goldammer himself.                    Upon
    considering the evidence and testimony presented, and the briefs
    filed by the parties, the District Court entered its order granting
    the Basketts' motion and entered judgment in favor of the Basketts,
    and required Goldammer to remove his construction lien.               Goldammer
    appeals this order.
    ISSUE 1
    Was the settlement agreement an agreement for arbitration
    under the Montana Uniform Arbitration Act,              §    27-5-101 through
    -324, MCA?
    Goldammer    asserts    that   the    District       Court   abused    its
    discretion in confirming the arbitrator's award and in failing to
    find and conclude that the arbitrator exceeded his powers granted
    Goldammer fails to base his assertions upon the determination
    of the District Court to enforce the terms of the settlement
    agreement, and instead asserts that he is not bound by the results
    of the arbitration conducted by the architect.      The settlement
    agreement was not drafted pursuant to the arbitration requirements
    under the Montana Uniform Arbitration Act.    The judgment was not
    entered by Hefty but by the District Court. Goldammer's appeal of
    Hefty's determination is misplaced, as no formal arbitration
    pursuant to the Montana Uniform Arbitration Act was conducted.
    ISSUE 2
    If the settlement agreement was not a formal agreement for
    arbitration, did the District Court err in concluding that the
    agreement was properly executed and awarding judgment in favor of
    the Basketts?
    The District Court did not clearly define the architect's role
    as an arbitrator or master.   The parties and the court referred to
    Hefty both as a arbitrator and a settlement master. An overview of
    the facts and procedure followed, however, seem to best correspond
    to those of a master.    We therefore review the District Court's
    actions in approving the master's report and concluding that the
    agreement was properly executed under the standards of review for
    Rule 53, M.R.Civ.P.,which sets forth the authority of a master and
    the procedures to be followed by the trial court and the master.
    A review of the District Court's order demonstrates that the
    District Court did consider the master's findings set forth in his
    report in light of      the settlement agreement's terms.     Rule
    7
    53(e)(2), M.R.Civ.P., states that the trial court shall accept the
    master's findings of fact unless they are clearly erroneous.
    At the hearing on the master's report, Goldammer contended
    that Hefty inappropriately relied upon the market value of the
    house in making his findings and therefore exceeded the scope of
    his authority.   Goldammer raises this issue again on appeal and
    argues that the District Court incorrectly determined that Hefty
    did not rely on a market value analysis.   Hefty testified at the
    hearing that he did not rely upon a market value analysis in
    reaching his final determination.      Goldammer also contends on
    appeal that the District Court did not consider the testimony of
    his expert witness, Bingham, as to Hefty's possible reliance on a
    market value analysis. The District Court made a specific finding
    that Hefty relied upon market value only for informational purposes
    and did not use market value in determining the value of the change
    orders provided to the Basketts.    This finding is supported by
    substantial evidence in the record. This Court will not substitute
    its judgment for that of the trial court when the issue relates to
    the credibility of the witness or the weight given to certain
    evidence. Wunderlich v. Lumbermens Mut. Cas. Co. (1995), 
    270 Mont. 404
    , 409, 
    892 P.2d 563
    , 566.
    Absent any clear error, the master's findings of fact were
    properly accepted by the District Court.    See Fiedler v. Fiedler
    (l994), 
    266 Mont. 133
    , 
    879 P.2d 675
    .    The District Court did not
    find that the master's report contained anything clearly erroneous
    and therefore correctly concluded that the settlement agreement was
    binding upon the parties and should be enforced.      Although the
    District Court erred by not     following all of the procedures
    outlined in Rule 53, M.R.Civ.P., we conclude that the error was
    harmless and does not warrant reversal as it did not materially
    affect the rights of the party.      In re Marriage of Dreesbach
    (1994), 
    265 Mont. 216
    , 226, 
    875 P.2d 1018
    , 1024.
    After reviewing the record we determine that the District
    Court's finding that the settlement agreement was complied with was
    supported by substantial evidence in the record.   Furthermore, we
    determine that the District Court has not misapprehended the effect
    of the evidence, and our review of the record has not left us with
    a definite and firm conviction that a mistake has been made.
    Interstate Prod. Credit Ass'n v. DeSaye (1991), 
    250 Mont. 320
    , 322,
    
    820 P.2d 1285
    , 1287.
    We affirm.
    We Concur: