Morrison-Maierle, Inc. v. Selsco ( 1980 )


Menu:
  •                               No. 14757
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1979
    MORRISON-MAIERLE, INC.,
    a corporation,
    Plaintiff and Respondent,
    SELSCO, a Utah Corporation,
    qualified to do business in
    Montana,
    Defendant and Appellant.
    Appeal from:   District Court of the Eighteenth Judicial District,
    Honorable FrarkE. Blair, Judge presiding.
    Counsel of Record:
    For Appellant:
    G. Page Wellcome argued, Bozeman, Montana
    For Respondent :
    Berg, Angel, Morgan & Coil, Bozeman, Montana
    Gregory 0 Morgan argued, Bozeman, Montana
    .
    Submitted:   November 1, 1979
    Mr. Justice Daniel J. Shea delivered the Opinion of the Court.
    Defendant, Selsco Corporation, appeals from a judgment of
    the Gallatin County District Court foreclosing a mechanic's
    lien filed by the plaintiff, Morrison-Maierle, Inc., and denying
    defendant's counterclaim against the plaintiff for alleged
    negligence in relation to the planning and supervising of
    construction of defendant's campground.
    The defendant raises two major issues in this appeal.
    Selsco first contends that the mechanic's lien does not accurately
    describe the attached property and thus cannot be enforced to
    satisfy its judgment.     In relation to its counterclaim, Selsco
    asserts that the evidence presented at trial established as a
    matter of law that it was entitled to damages as a result of
    the plaintiff's failure to exercise care in planning and
    inspecting the project.
    The defendant, Selsco, a Utah corporation, (referred to
    herein as the owner), contracted with Morrison-Maierle, Inc.
    a Helena engineering firm, (referred to as engineers), for the
    development of a project called West Yellowstone United Campgrounds.
    Pursuant to their agreement with the owner, the engineers
    developed a plan for facilities to accommodate 500 campers, and
    provided regular inspection of construction to assure that the
    construction was properly performed.    All phases of the project
    were completed in July 1972.
    Soon after the campground opened the owner experienced
    difficulties with the newly constructed facilities, and refused
    to complete payments to the engineer.    The engineers filed
    suit on August 12, 1974, seeking payment of the amount still
    owed under the contract.    The complaint sought collection of
    this debt by enforcement of a mechanic's lien on the campground
    improvements.   The owner moved to dismiss the complaint alleging
    -2-
    that the mechanic's lien did not properly describe the property
    involved.    Later, the owner filed a counterclaim against the
    engineers.   This counterclaim was amended to allege additional
    defects in construction of the campground facilities allegedly
    caused by the engineer's negligence.
    After a nonjury trial, the court granted judgment of $22,945
    for the contractual debt, and $7,662.55 for costs and attorney
    fees.   The court denied the owner's counterclaim and ordered
    the judgment to be satisfied by foreclosure and sale of
    campground property.    The owner appeals this judgment.
    The owner contends that the mechanic's lien should not be
    enforced because it is not in strict compliance with the code's
    requirement that the lien contain a correct description of the
    charged property.    See section 71-3-511(1), MCA.   The lien
    states that Selsco owns or holds the charged land when in fact,
    Selsco occupies the land under a special use permit issued by
    the United States government.   We do not consider this to be
    fatal to the lien.
    Nor does the lien description fail to adequately describe
    the property to which it attaches.   Any error or mistake in the
    account or description does not affect the validity of the lien
    if the property can be identified by the description.      Section
    71-3-511(1), MCA.    Here, the lien gave the correct legal
    description of the land on which the structures were located and
    identified   the attached property together with "all improvements,
    structures and fixtures thereunto appertaining or affixed."
    The purpose of the statutory requirements for filing a
    description of the attached property is simply to give notice
    of the existence of the lien to interested third parties.       Cole
    v. Hunt (1949), 
    123 Mont. 256
    , 
    211 P.2d 417
    .    This purpose is
    not frustrated here where it is not argued that the attached
    improvements can be confused with any other structures in the
    area.     Furthermore, the lien description is made even more
    specific by the accounts filed with the lien which state that
    the engineers' bill is for "engineering services on United
    Campground, West Yellowstone, Montana."      A person reading
    the lien should readily conclude that the lien attaches to the
    campground facilities.    See Varco-Pruden v. Nelson (1979),
    - Mont.           , 
    593 P.2d 48
    ,   36 St.Rep. 704.   We conclude
    therefore that the lien documents taken as a whole adequately
    describe the property to which the lien attaches.
    In its appeal from the trial court's denial of its
    counterclaim, the essence of the owner's contentions is that
    the trial court had a duty, as a matter of law, to find
    that the engineers breached their contractual duties and
    that the owners were injured by this negligence in design
    and inspection.    We determine however, that there was substantial
    credible evidence upon which the trial court could deny the
    counterclaim.    The thrust of the argument by the owner is
    that the trial court should have believed its own expert
    testimony rather than the expert testimony from the engineers.
    The counterclaim alleged that the engineers failed to
    design and inspect the project in a workmanlike manner, and
    that the breach of this duty caused defects in four items for
    which it seeks damages:    the sewage lagoon (estimated damage
    (643,240); valve boxes (estimated damages $4,729); water lines
    (estimated damages $2,943); and loop roads (estimated damage
    $2,000).
    At trial, the owners attempted to prove by expert testimony
    that the engkmeers    had a duty of care to test the permeability
    of the lagoon's clay surface before its certification.       The
    engineers countered this evidence with the testimony of their
    chief engineer who stated that cracking in the lagoon's surface
    was caused by insufficient flow from campground units during
    the period of 1973 to 1977 when the occupancy rate of the
    -4-
    campground was roughly 13 percent of its designed capacity.
    We note in this regard, that it was in 1977 when the campground
    owners first attempted to fill the lagoon with water and then
    discovered that the cracks in the clay liner prevented the
    lagoon from filling.      The trial court was not bound by testimony
    of either expert, and it had the right to give greater weight
    to the engineer's testimony.      See Erickson v. Perrett (1977),
    Mont   .      , 
    572 P.2d 518
    ; Robertson v. Valhi, Inc. (La.App.
    1977), 
    345 So. 2d 149
    ; 32 C.J.S. Evidence 5572(1), at 669.
    Two of the remaining defects alleged in the owner's counter-
    claim, occurred as a result of time constraints placed on the
    engineers.       Water valves installed in the campground began to
    leak and did not meet the specifications of the engineers' plans.
    However, it is not disputed that the specified water valves were
    unavailable at the time the project neared completion, and the
    engineer to complete the project on schedule, purchased the
    best available substitute.
    The owner claims that cracking in the campground's loop
    roads was caused by the engineers' negligence, but uncontradicted
    testimony established that placing a permanent surface on the
    road would have delayed the scheduled opening of the campground.
    The parties did not decide upon a temporary surface until
    the owners had been fully informed that settling would likely
    occur in a temporary surface.
    The last contention concerning the counterclaim is that
    the engineers failed to lay the water lines according to
    design specifications and therefore that the water lines did
    not drain properly.      The owners argue that a reasonable
    inspection of the bedding of the water lines would have
    prevented the defect from occurring.
    The record indicates, however, that during the major portion
    of construction the engineers made almost continuous inspections
    -5-
    and they forwarded daily progress reports to the owner.    West
    Yellowstone United Campgrounds was a very large project and
    it is predictable that some faulty workmanship would go
    undetected by even careful inspection. An engineer is not
    an insurer of a project against defects nor does he guarantee
    that he will complete it to perfection.   He is required to
    exercise the care and competence expected of a member of his
    profession.    Bloomsburg Mills, Inc. v. Sordoni Construction
    Company (1960), 
    164 A.2d 201
    , 
    401 Pa. 358
    ; Gagne v. Bertran
    (1954), 43Ql.2d 481, 
    275 P.2d 15
    , 21; 6 C.J.S. Architects
    827, at 491-92.   The trial court heard the evidence and
    determined that the engineers exercised reasonable care.
    There was sufficient evidence to conclude that the engineers
    had not breached their duty of care.
    The remaining issue concerns the cost bill.    The owner
    contends that certain deposition expenses and a partial
    transcript of trial are not properly chargeable as costs or
    expenses of litigation.
    The engineers included two depositions as part of
    their costs.   Both witnesses later appeared and testified at
    trial. The engineers admit, however, that one of the depositions
    should not have been charged as costs, but contend that the
    costs of taking witness Wetstein's deposition should be
    awarded to them, because they furnished a copy of the deposition
    to the owner who used it as evidence at trial.     Since it was
    so used, we conclude that it was properly part of the costs
    of the action. The distinction is that if a deposition is
    taken solely for a party's own convenience, he cannot properly
    charge it to the other party as part of the costs.     Lovely v.
    Burroughs Corp. (1974), 
    165 Mont. 209
    , 
    527 P.2d 557
    , appeal
    after remand 
    169 Mont. 454
    , 
    548 P.2d 610
    ; Johnson v. Furgeson,
    Et Al. (1971), 
    158 Mont. 170
    , 
    489 P.2d 1032
    .     Here the copy
    -6-
    was furnished to the owner at the engineers' expenses, and
    used by the owner at trial.   It has no ground to complain.
    We hold, however, that the engineers could not properly
    order a partial transcript of the trial for use at the trial
    and charge it to the owner as part of the costs. It was
    not, under section 25-10-201, MCA, a reasonable and necessary
    expense.
    With the exception of the Wetstein deposition which
    should be excluded as an item of costs, the judgment of the
    #&-
    &-A
    District Court is affirmed.
    JUS i
    We Concur:
    Chief Justice
    Justices
    

Document Info

Docket Number: 14757

Judges: Shea, Haswell, Daly, Harrison, Sheehy

Filed Date: 2/25/1980

Precedential Status: Precedential

Modified Date: 11/10/2024