Figgins v. Stevenson , 163 Mont. 425 ( 1973 )


Menu:
  •                            No. 12563
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1973
    WILLIE FIGGINS, d/b/a
    FIGGINS & SON EXCAVATING,
    Plaintiffs and Respondents,
    LESLIE B. STEVENSON and
    MARILYN R. STEVENSON,
    husband and wife,
    Defendants and Appellants.
    Appeal from: District Court of the Eighteenth Judicial District,
    Honorable W. W. Lessley, Judge presiding.
    Counsel of Record :
    For Appellants :
    Bennett and Bennett, Bozeman, Montana
    Lyman Bennett, 111 argued, Bozeman, Montana
    For Respondents:
    Bolinger and Wellcome, Bozeman, Montana
    Page Wellcome argued, Bozeman, Montana
    Submitted : December 4, 1973
    Decided : D j r ~ 8 1973
    Mr. Justice Wesley Castles delivered the Opinion of the Court.
    This is an appeal from a judgment for plaintiff entered
    after findings of fact and conclusions of law were made by the
    court sitting without a jury.    Trial was had in Gallatin County,
    the Hon. W. W. Lessley presiding.    The judgment was in the amount
    of $12,175.75, plus interest at 6% from July 1, 1972, and for
    attorney fees in the amount of $2,435.15.
    The case involves foreclosure of a mechanic's lien by
    the plaintiff, respondent and cross-appellant, upon campground
    premises owned by defendants, appellants.       On April 20, 1972,
    plaintiff, Willie Figgins, d/b/a Figgins    &   Son Excavating, enter-
    ed into a written contract with defendants Leslie B. Stevenson
    and Marilyn R. Stevenson, for the construction of a United Camp-
    ground near Bozeman.   Hereinafter the parties will be referred
    to as Figgins and Stevenson.
    The contract was for a fixed price of $19,474.75 and
    included waterline excavation and backfilling, powerline digging
    and backfilling, road blading, gravel and a lagoon.      Separate
    contractors were, under separate contracts, to do plumbing, elec-
    trical and building so that completion of Figgins' work was de-
    pendent on completion by the other contractors.      The sewage
    lagoon, covered by the contract, was deleted deducting an amount
    of $5,800 from the fixed price leaving a balance of $13,674.75.
    The contract provided that work was to commence as soon
    as the ground was unfrozen.    It then provided in pertinent part:
    "If the work is not substantially completed on
    May 27, 1972, then the Contractor shall be charged
    liquidated damages in the amount of $50.00 per
    day for each and every day that the completion
    date exceeds May 27, 1972.
    "The Contractor acknowledges that the Owner is
    relying upon the above stated completion date
    as a material inducement for his entering into
    this Contract. I'
    Then as to payment the contract provides:
    "Final payment
    "Final payment, constituting the entire unpaid
    balance of the Contract Sum, shall be paid
    by the Owner to the Contractor ten (10) days
    after Substantial Completion of the Work, pro-
    vided the work has then been completed, the
    Contract fully performed, and a final Certifi-
    cate for Payment has been issued by the * * *
    Owner. Final payment will be made as provided
    for hereinabove provided the Contractor furnishes
    the Owner with a mechanic's lien waiver for all
    labor and materials furnished the project by the
    Contractor and his suppliers."
    Under miscellaneous provisions are two other pertinent provisions
    in the contract:
    "8.3 The actual staking of the road, roadways,
    waterlines, sewer line, electrical line, lagoon
    location and septic location shall be done by
    Survo, Inc. (formerly Earl R. Best & Associates)
    on or before April 15, 1972.
    "8.5 The Contractor shall not be responsible
    for any liquidated damages as provided herein
    if there is any delay resulting from the staking
    of roads, and lines (defined herein) or result
    from the delay of other subcontractors failure
    to cooperate with the Contractor herein."
    The contract was prepared by Stevenson through his lawyer
    in Minnesota.    It was a printed standard form of agreement between
    owner and contractor with certain items stricken and other items
    typed in.
    On August 3, 1972, Figgins filed a lien against Steven-
    son's property in the amount of $14,019.75 for labor, equipment
    and materials.   On August 10, 1972, a complaint to foreclose
    the lien was filed.   Pursuant to section 45-513, R.C.M. 1947,
    Stevenson filed a cash bond as a substitute and had the lien
    discharged.   The suit continued against the bond.   On September
    19, 1972, an answer was filed, alleging that Figgins failed to
    complete the work on time, and counterclaimed, alleging that a
    breach of the contract in failing to complete the work on time
    resulted in loss of rentals and damage in an amount of $4,000;
    and further, that Figgins' negligence caused damage to Steven-
    son's building in an amount of $1,500.
    Trial was had before the coupt sitting without a jury.
    The dourt found in summary:    (1) that Figgins completed the
    work in the amount of $13,674.75 and that no additional work
    was done at the instance of Stevenson; but was done at the in-
    stance of another building contractor who had a contract with a
    subsidiary of Stevenson to build a building for Stevenson on the
    same premises; (2) that no damage to the building was proven by
    Stevenson; (3) that Figgins did not complete the work on time
    and owed penalty of 31 days at $50 per day for a total of $1,550,
    and (4) attorney fees were owed to Figgins.
    Thus the court found a net amount due Figgins of $12,175.75
    with interest from July 1, 1972, plus attorney fees.
    The issues asserted by Stevenson are four:
    (1) That the court erred in foreclosing the lien.
    (2) That attorney fees were improper and should have
    been allowed to Stevenson.
    (3) That interest was improper.
    (4) That damages, rather than the contractual penalty
    should have been allowed to Stevenson and further that the evi-
    dence showed damage to his building caused by Figgins.
    Figgins cross-appeals, claiming that the contractual
    penalty of $50 per day should not have been assessed against him
    under the evidence since, although his completion was late, the
    cause of the delay was the other subcontractors and Stevenson.
    First of all, in his reply brief, Stevenson charges
    that the cross-appeal of Figgins is not properly before the
    Court since Figgins did not file a separate notice of appeal
    under Rule 4, M.R.App.Civ.P.   Suffice it to say that ~igginsas
    respondent did, in his answering brief, set forth clearly his
    cross-appeal.     Rule 14, M.R.App.Civ.P.,   provides that this
    Court may review any ruling against respondent and reverse or
    affirm according to the substantial rights of the respective
    parties.    Accordingly, a cross-appeal by respondent's brief is
    sufficient to put the issue before this Court.
    As to issue No. 1, the thrust of Stevenson's argument
    is that since the contract specified, under the payment provision
    heretofore quoted, that payment was not due until (a) "final
    Certificate of Payment has been issued by the      * * *   Owner", and
    (b) lien waivers were furnished by the contractor; then those
    two matters are conditions precedent to payment being due.        Under
    that argument, apparently Stevenson would have us believe that
    so long as he never issued a certificate he would not be required
    to pay.     Obviously that is incorrect.
    As to the requirement of lien waivers, from Stevenson's
    testimony it is clear that Figgins completed the work in a satis-
    factory manner, but Stevenson claimed deductions for contract
    over-run and alleged damage to a building.       Stevenson knew the
    amount claimed due by Figgins under the contract plus extras;
    and he, together with his attorney, entered into settlement nego-
    tiations prior to the lien being foreclosed.       In July, prior to
    the filing of the lien, Stevenson wanted to pay $5,000 on the
    contract in exchange for lien waivers.       Figgins refused, insist-
    ing on the full amount.
    That lien waivers can be a condition precedent      is clear.
    Franklin v. Schultz, 
    23 Mont. 165
    , 
    57 P. 1037
    ; Riddell v. P.-W. H.
    &   V. Co., 
    27 Mont. 44
    , 
    69 P. 241
    ; Clifton-Applegate-Toole v.
    Drain Dist. No. 1, 
    82 Mont. 312
    , 
    267 P. 207
    .      However, where
    Stevenson refused to pay the contract balance and there was a
    dispute as to the amount due and owing under the contract, the
    rule does not apply.     If Stevenson had offered to pay the contract
    price, the rule would apply.      Figgins would then have been
    obligated to furnish the lien waivers.
    Stevenson also argues that before a lien can be valid,
    the contract amount must be proven.      In support he cites:    Greene
    Plbg.   &   Heating Co. v. Morris, 
    144 Mont. 234
    , 
    395 P.2d 252
    ;
    Luebben v. Metlen, 
    110 Mont. 350
    , 
    100 P.2d 935
    ; Thompson v. Cure,
    
    133 Mont. 273
    , 
    322 P.2d 323
    ; and Harsh Mont. Corp. v. Locke, 
    134 Mont. 150
    , 
    328 P.2d 926
    .      Those cases are not in point in the
    instant case.     Here, Stevenson admitted an amount of over $10,000
    was due.     An overstatement of the amount due, absent fraud or bad
    faith, does not invalidate a lien.       (See Hammond v. Knievel, 
    141 Mont. 433
    , 
    378 P.2d 388
    ; and Duval v. Fuchs, 
    141 Mont. 123
    , 
    375 P.2d 541
    , where an exaggeration by ten times was held to be fraud.)
    Thus the lien was valid.   It follows that attorney fees
    were proper.      Stevenson does not contest the amount of the fees;
    only whether they are proper.      Thus, issue No. 2 is answered.
    Issue No. 3, interest having been allowed from July 1,
    1972, we feel needs no discussion, since once the validity of the
    lien is established and the date of the completion of the contract
    established, under the circumstances here, the running of interest
    started.
    Issue No. 4, that damages other than the contractual
    penalty of $50 per day should have been allowed will be discussed
    with the cross-appeal of Figgins.      The district court allowed
    Stevenson a penalty of 31 days at $50 per day.      The court based
    this on the fact that the contract completion date was May 27,
    whereas Figgins did not finish until June 28.
    Under the contract provision heretofore quoted as para-
    graph 8.5, the contractor was not responsible for liquidated
    damages if the delay resulted from staking, delay of other sub-
    contractors' failure to cooperate.
    Here, the staking to be done under paragraph 8.3 here-
    tofore quoted was not done.    Stevenson explained this failure by
    saying that he, Stevenson, did the staking himself although he
    admitted he was not a surveyor nor engineer.   Witnesses for
    Figgins testified that there was no adequate staking. At best
    a conflict in evidence was presented.   But, it was more than a
    mere conflict in reality because Stevenson never had the staking
    done as he agreed.
    Moreover, Stevenson admitted that the lagoon was eliminated,
    the location of the well changed, the well and plumbing by a
    separate subcontractor delayed.   It followed that Figgins could
    not complete his work of backfilling until those items were done.
    The natural consequence of those matters was that Stevenson, who
    really superintended the whole job as his own contractor, was as
    much the cause of delay as were other subcontractors.     Stevenson
    argues that since the contract language reads "failure to cooper-
    ate" and no testimony in the literal sense of those words was
    offered, no showing was made of reasons for the delay past May 27.
    As we review the record, the opposite is shown, and we hold the
    district court was in error in finding any penalty due.    We
    therefore hold that Figgins is entitled to relief on his crass-
    appeal.    It follows then that appellant Stevenson's issue No. 4
    on damages is not meritorious.
    By what has been heretofore said, we affirm the judgment
    of the district court and modify it to include $1,550 and further
    attorney fees on this appeal in the amount of $500.    The cause
    is remanded to the district court for entry of judgment in accord-
    ance herewith.
    

Document Info

Docket Number: 12563

Citation Numbers: 163 Mont. 425, 517 P.2d 735, 1973 Mont. LEXIS 484

Judges: Castles, Harrison, Daly, Haswell

Filed Date: 12/28/1973

Precedential Status: Precedential

Modified Date: 11/10/2024