Bauer v. Cook ( 1978 )


Menu:
  •                               No. 13889
    IN THE SUPREMF: COURT OF THE STATE OF MONTANA
    1979
    B. J. BAUER, JR.,
    d/b/a BAUER CONSTRUCTION COMPANY,
    Plaintiff and Respondent,
    JAMES DAVID COOK and DIETA MARIA COOK,
    husband and wife,
    Defendants and Appellants.
    Appeal from:       District Court of the Fourth Judicial District,
    Honorable Jack L. Green, Judge presiding.
    Counsel of Record:
    For Appellants:
    Tipp and Hoven, Missoula, Montana
    Thomas W. Frizzell argued, and Raymond P. Tipp
    argued, Missoula, Montana
    For Respondent:
    Skelton and Knight, Missoula, Montana
    Robert Skelton argued, Missoula, Montana
    Submitted:   February 2, 1979
    Filed:   JUN
    Mr. Justice John C. Sheehy delivered the Opinion of the
    Court.
    This is an appeal from a judgment of the District
    Court, Missoula County, foreclosing a mechanic's lien on a
    dwelling house and directing defendants to pay the lien-
    holder's costs and attorney fees.
    In January 1975, James and Dieta Maria Cook contacted
    Blaisus J. Bauer, Jr., a building contractor, for the
    purpose of discussing the construction of a dwelling house
    on property located in Missoula County, Montana.     Bauer, who
    had been in the construction business since 1971 and had
    built approximately thirty houses in that time, agreed to
    build the home.    On February 19, 1975, the parties entered
    into a contract whereby Bauer agreed that the proposed house
    would be "turn-key" complete within ninety days after commence-
    ment of work.     The Cooks agreed to pay Bauer in the following
    manner :
    "A.   2 0 % of cost upon completion of floor.
    "B. 2 0 % of cost upon completion of framing,
    roofing and exterior windows & doors.
    "C. 2 0 % of cost upon completion of rough
    wiring, plumbing & heating.
    "D. 20% of cost upon completion of sheet
    rock and texturing.
    "E.   2 0 % of cost upon completion   . . ."
    The contract plans and specifications were presented to
    the Western Federal Savings and Loan Association of
    Missoula, Montana, for approval of a loan to finance the
    construction.     The loan was approved and an account
    opened whereby the funds were to be disbursed in accordance
    with the contract and Western Federal's disbursement in-
    structions, which required that all disbursement requests
    be approved and signed by the Cooks and a loan officer.
    Bauer began construction immediately.   Upon com-
    pletion of the floor, a building inspector for Western
    Federal inspected the work and approved a disbursement
    of $8,301.33 to Bauer.     The Cooks also approved the dis-
    bursement.     Upon completion of the framing, roofing, and
    exterior windows and doors, a similar procedure took place.
    Then, on April 1, 1975, after the building inspector had
    inspected the rough wiring, plumbing, and heating, and
    approved the disbursement, Dieta Cook refused to sign the
    disbursement request.    Mrs. Cook refused to give her signature
    because she felt Bauer had not performed his part of the
    contract.    A handwritten "Statement of Understanding" was
    given to Bauer by the Cooks, demanding that thirty-one
    items be completed before the disbursement request would
    be signed.    Bauer explained to the Cooks that he could not
    continue construction without the funds, but Mrs. Cook
    refused to change her position.
    On April 4, 1975, Bauer ceased work and did not return
    to the construction site.    Thereafter, four days later, he
    filed and perfected a mechanic's lien in the office of
    the Clerk and Recorder, Missoula County, under the provisions
    of section 45-501, et seq., R.C.M.   1947, now section
    71-3-501, et seq. MCA.    Bauer claimed the Cooks owed him
    $8,300 for labor and materials.    This amount was reduced
    to $3,000 after the Cooks paid $5,300 to various materialmen.
    A suit to foreclose on the lien was filed April 22,
    1975.    Trial was commenced without a jury, in District Court,
    Missoula County on April 19, 1976.    Three days later,
    due to calendar restrictions, the District Court ordered
    that the trial would be continued indefinitely.     On December
    9, 1976, the parties agreed to submit the case to the court
    without further testimony.    The District Court entered
    -3-
    findings of fact, conclusions of law and judgment of
    foreclosure on March 24, 1977.   Bauer was awarded $3,000
    as foreclosure of the mechanic's lien and $1,000 as
    reasonable attorney fees.
    On appeal, the Cooks have raised two issues:
    1.   Did Bauer abandon the project for which he had
    contracted, thereby rendering his filing of the mechanic's
    lien improper?
    2.   Did the District Court err in failing to reduce
    Bauer's recovery under the lien due to his defective
    performance of the contract?
    The general rule in Montana is that a mechanic's
    lien arises only upon completion (or substantial completion)
    of the contracted work.   Western Plumbing of Bozeman v.
    Garrison (1976), 
    171 Mont. 85
    , 
    556 P.2d 520
    .   However,
    the general rule does not apply if the laborer or material-
    man has been prevented from completing the work by the
    breach of the owner or a third party.   Intermountain Electric,
    Inc. v. Berndt (1974), 
    164 Mont. 67
    , 
    518 P.2d 1168
    .
    In the case on appeal the alleged breach occurred
    when the Cooks refused to sign the disbursement request
    which had been presented to them by Bauer.   The Cooks con-
    tend (1) under the circumstances, their refusal to sign
    did not constitute a breach of contract, and (2) if they
    did breach the contract, Bauer was nonetheless unjustified
    in abandoning the contract.
    In Gramrn v. Insurance Unlimited (1963), 
    141 Mont. 456
    ,
    
    378 P.2d 662
    , we said:
    "The rule is stated in Corbin on Contracts,
    § 946, as follows:
    "'The non-payment of an installment of money
    when due will always create a right of action
    for that money, but it will not always be a
    total breach.'
    "Thus, it depends upon the particular
    facts of each case whether or not non-
    payment of an installment is a total
    breach enabling the contractor to cease
    work, or whether it is merely a partial
    breach entitling the contractor to sue for
    the partial breach, but not permitting
    him to abandon the contract."
    The District Court concluded that Bauer completed
    the rough wiring, plumbing and heating on or about April
    1, 1975, and that the building inspector examined the work
    and approved the disbursement of $8,300 to Bauer, but Dieta
    Cook refused to sign the disbursement request.
    In reviewing findings of fact in a civil action tried
    by the District Court without a jury, this Court is confined
    to determining whether there is substantial credible evidence
    to support those findings.   Hornung v. Estate of Lagerquist
    (1970), 
    155 Mont. 412
    , 
    473 P.2d 541
    .   Although conflicts
    may exist in the evidence presented, it is the duty and
    function of the trial judge to resolve such conflicts.
    His findings will not be disturbed on appeal where they
    are based on substantial though conflicting evidence.
    Fausett v. Blanchard (1969), 
    154 Mont. 301
    , 
    463 P.2d 319
    ,
    Finally, in determining whether the trial court's findings
    are supported by substantial evidence this Court must view
    the evidence in the light most favorable to the prevailing
    party.   Hellickson v. Barrett Mobile Home Transport, Inc.
    (1973), 
    161 Mont. 455
    , 
    507 P.2d 523
    .
    The record here contains the testimony of the sub-
    contractors who installed the rough wiring, plumbing, and
    heating prior to the inspection and approval of the work
    by the employee of the lending institution.   We find that
    the District Court's findings are based on substantial
    evidence.   Since the installment payment was due, the
    Cook's refusal to sign the disbursement request constituted
    a breach of contract.   The remaining question then is,
    did the refusal to sign under these facts constitute
    a total breach of the parties' agreement, thereby
    justifying Bauer's abandonment of the contract?
    In Gramm, this Court upheld the District Court's
    foreclosure of the mechanic's lien because the underlying
    contract provided that the ability of the contractor
    to continue work was dependent upon prompt payment by the
    owner.     In addition, the contract stated that time was of
    the essence.     However, in Berndt, involving substantially
    the same question, we found nothing in the record to suggest
    the
    that / contractor's failure to make a payment actually
    the
    prevented , subcontractor-lienholder from completing the
    !
    work.     There was no evidence to indicate that the sub-
    contractor was entitled to demand any money from the
    contractor at the time it submitted a bill, nor was there
    any proof that prompt payment by the contractor and time
    were of the essence to completion of the work.    Finally,
    because the subcontractor did not go to the homeowners
    and ask them for payment of the bill or ask them if they
    wanted the work completed, we concluded the subcontractor
    had willfully and voluntarily abandoned the contract before
    there had been substantial performance of its terms.
    In Bauer's case, the agreement required the house
    to be "turn-key" complete within ninety days of commencement
    of work.     Proof that time was of the essence is found in
    Bauer's testimony:
    "Mrs. Cook and Jim Cook and myself discussed
    the fact that I wanted 120 days to build the
    house because I felt it was the kind of house
    that needed 120 days, but they were living
    in a motel and speed was of very major importance
    and so I, against my wishes, agreed to put it
    on 90 days . . ."
    Despite their desire to take possession of the house
    within ninety days of commencement of construction, the
    Cooks requested numerous changes in the plans and
    specifications of the house.     Those changes included
    repositioning the house on the foundation, relocating
    certain bay windows, putting additional beams in the
    living room, enlarging the overhang on the back of the
    roof, extending a gable five feet and repositioning the
    kitchen cabinets.   Also, the back wall had to be torn
    out for a new kitchen window, and the framing of the
    interior of the house was delayed considerably due to the
    Cooks' indecision concerning the size and type of fireplace
    that would be installed.
    Upon discovering that the Cooks did not intend to
    sign the disbursement request until he complied with the
    thirty-one demands contained in the "Statement of Under-
    standing", Bauer approached the Cooks on several occasions,
    explained that he could not continue his work without the
    funds, and requested that they sign the disbursement
    request.   When it became clear that the Cooks were not
    going to sign the document, Bauer abandoned the construction
    site and filed a mechanic's lien to protect his interests
    in the work done and materials furnished.
    Having determined that substantial evidence exists
    in the record upon which the District Court could reasonably
    conclude that the Cooks breached the contract, we now hold
    that due to the aforementioned circumstances the refusal
    to sign the disbursement request constituted a total breach
    of the contract which prevented Bauer from continuing con-
    struction and justified abandoning the jobsite.    The mechanic's
    lien was properly filed and foreclosed.
    The District Court's findings of fact, conclusions
    of law, and judgment make no mention of the Cooks' counter-
    claim for defective performance.    This Court adhers to the
    doctrine of implied findings which states that where a
    -7-
    court's findings are general in terms, any findings not
    specifically made, but necessary to the judgment, will be
    implied.       Ballenger v. Tillman (1958), 
    133 Mont. 369
    , 
    324 P.2d 1045
    .      However, where as here, the trial court has not
    entered judgment on a claim, nor made a general finding on
    such claim from which reasonable implications can be made,
    we cannot say that the claim is with or without merit.
    Similar circumstances arose in Claver v. Rosenquist (1972),
    
    160 Mont. 4
    , 
    499 P.2d 1235
    , in which the Court said:
    .
    ". . we hold that the district court should
    have entered findings of fact, conclusions
    of law and judgment determining the issues
    raised by defendant's counterclaims     ...
    No findings, one way or the other, were
    entered by the district court on these counter-
    claims, and no mention was made of any of the
    counterclaims in the district court's judgment.
    We hold that the district court should have
    made findings concerning these issues and
    entered judgment accordingly."
    We cannot imply from the District Court's judgment of
    foreclosure that the Cook's counterclaim for defective
    performance was necessarily without merit.
    In conclusion, the judgment of foreclosure is affirmed,
    but the cause is remanded to the District Court for entry of
    findings of fact, conclusions of law and a judgment dis-
    posing of the issues raised in the counterclaim.
    \
    CldL l.
    r
    %
    ,J
    +
    !L
    Justice'
    We Concur: