Pack and Company v. Meadow Lake Co ( 1992 )


Menu:
  •                               No.       91-232
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    1992
    PACK AND COMPANY, INC.,
    Plaintiff, Respondent and
    Cross-Appellant,
    -vs-
    MEADOW LAKE COUNTY WATER & SEWER DISTRICT;
    MEADOW LAKE DEVELOPMENT CORPORATION; MEADOW
    LAKE ESTATES REAL ESTATE, INC.; PETER E. TRACY,
    Defendants and Appellants.
    APPEAL FROM:    District Court of the Eleventh Judicial District,
    In and for the County of Flathead,
    The Honorable Michael H. Keedy, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Ward E. Taleff; Alexander, Baucus         &   Linnell, Great
    Falls, Montana
    For Respondent:
    Dana L. Christensen; Murphy, Robinson, Heckathorn        &
    Phillips, Kalispell, Montana
    Submitted on Briefs:    May 28, 1992
    JUN -2 1992                                 Decided:     June 2, 1992
    I
    Clerk
    Justice R. C. McDonough delivered the Opinion of the Court.
    Meadow Lake County Water and Sewer District, Meadow Lake
    Development Corporation, Meadow Lake Estates Real Estate, Inc., and
    Peter E. Tracy, appeal from a judgment of the Eleventh Judicial
    District Court, Flathead County, in favor of Pack and Company, Inc.
    We affirm in part and reverse in part.        We frame the following
    issues for appeal:
    1.    Whether the District Court erred in its damage award to
    Pack and Co., Inc., and in awarding Pack and Co., Inc. prejudgment
    interest; and
    2.    Whether the District Court erred in finding Peter Tracy
    individually liable.
    The dispute before us arose out of a contract between Meadow
    Lake County Water   &   Sewer District (Meadow Lake) and Pack and Co.,
    Inc. (Pack) entered into on October 1, 1985. The contract provided
    that Pack construct water and sewer improvements for a golf course
    near Columbia Falls, Montana.        Under the contract Pack was to
    install the necessary lines and connect those lines to the Columbia
    Falls facilities.       The contract also involved some road paving.
    The written agreement required completion of the project in 90
    days.     The plans and specifications were in accordance with the
    project engineer, Carver Engineering. The specifications provided
    for liquidated damages of $300 per day for each day beyond the
    deadline until the contract work was substantially completed.
    Evidence presented at trial revealed that the golf season begins in
    March and that it was important for the work to be completed before
    2
    the season got underway.
    On February 13, 1986, the parties executed a written change
    order. This order reflected a reduction of the contract price due
    to a decrease in the work required.              It also extended the
    completion date to May 1, 1986.         The project was substantially
    completed on July 7, 1986.
    Pack brought suit against Meadow Lake and Peter Tracy for
    amounts due on accounts in connection with the project.         Meadow
    Lake counterclaimed and the District Court after a non-jury trial
    found in favor of Meadow Lake, granting them liquidated damages.
    The liquidated damages were to be deducted from the total amount
    Pack claimed due. The District Court then rendered net judgment in
    favor of Pack.      Meadow Lake moved the District Court to correct
    mathematical errors. The motions were not ruled upon. Meadow Lake
    appeals.
    Our standard of review in reviewing findings of fact in a non-
    jury matter is clearly erroneous.        Interstate Production Credit
    Association v. DeSaye (1991), __ Mont.      -,     
    820 P.2d 1285
    .
    I
    Whether the District Court erred in its damage award to Pack
    and Co., Inc., and in awarding Pack and Co., Inc. prejudgment
    interest.
    The District Court found that Meadow Lake was entitled to
    liquidated damages totaling $15,900.00 from May 16, 1986 to July 7,
    1986.      It further found that Meadow Lake waived its right to
    receive liquidated damages from the date of contract completion on
    3
    May 1, 1986 to May 16, 1986 when they requested extra trenching and
    paving work. The District Court further found that Meadow Lake was
    entitled to an offset of $2,244.44 to reimburse it for damage Pack
    had done to an electrical line.       It also found Meadow Lake was
    entitled to an offset of $1,668.40 for unused sewer pipe.    All of
    which totals $19,812.84.
    The District Court found that Meadow Lake owed Pack money
    remaining on the contract with ten percent interest to the date of
    trial as compiled by the court, which came to $44,709.76.        It
    appears the District Court found, based on 5 31-1-106, MCA (1990),
    that work done over and beyond the contract was an open account
    subject to the applied ten percent interest. Meadow Lake retained
    $26,896.59 over the course of the contract payment.    The District
    Court found that Pack was also entitled to $7,103.75 remaining on
    the contract.
    Meadow Lake argues that the District Court made mathematical
    errors in its damage award.   The total amount of the judgment was
    $44,709.76, plus the $7,103.75 remaining on the contract, for a
    total of $51,813.51, in favor of Pack.     The total amount included
    prejudgment interest.
    Meadow Lake contends that the District Court added back into
    the award "retainage" which was already included in Pack's figures
    of amount due.   They argue this amounts to prejudgment interest and
    double recovery.   Under the contract, Meadow Lake was entitled to
    retain a certain percentage of the amount from each billing.
    According   to Meadow   Lake, the retainage of      $26,896.59, was
    4
    improperly added back.
    The amount due on the contract alone, as evidenced by Pack's
    demand letter, and as computed using Pack's explanatory invoice is
    $26,896.59.     After deducting the items of the finance and extra
    work charges, this is the same amount due as Meadow Lake agrees is
    the   retainage.     This ultimate amount due     on the contract,
    $26,896.59, is also supported by the findings of the District
    Court. Therefore there is to be subtracted from the $26,896.59 the
    amount of $15,900.00 in liquidated damages awarded to Meadow Lake,
    the offsets of $2,244.44 for the damage done by Pack to the
    electrical line and the $1,668.40 for the credit for the unused
    pipe.     This leaves a balance of $7,083.75 owing by Meadow Lake on
    the contract.
    Pack's explanatory invoice indicates four invoices remain
    unpaid.    Invoice #23120 indicates the amount due for flaging work,
    which is $377.45.       Invoice #23195 indicates the amount due for
    equipment rental, which is $100.00.      The amount due on the extra
    work, as reflected on invoice #23841, and Pack's explanation of
    account is $3,610.98.      The amount due on the lift station work,
    invoice #23840, is $5,156.48.     The total for the four outstanding
    invoices is $9,244.91.      Ten percent interest on this amount is
    allowed.      It appears from the record that the amount of the
    invoices was not contested, but which entity was liable was
    contested. The District Court found that Meadow Lake was liable,
    and that the remaining unpaid amounts are then subject to interest
    charges.    We agree.   Therefore, ten percent interest from the date
    5
    of the invoices to the date of judgment is allowed.
    As we stated in Safeco Insurance Co. v. Lovely Agency (1985),
    
    215 Mont. 420
    , 
    697 P.2d 1354
    , for prejudgment interest there must
    be an underlying monetary obligation, the amount of recovery must
    be certain or capable of being made certain by calculation and the
    right of recovery must rest on a certain day.       Here, all three
    criteria are met.      We   agree with   the   District   Court that
    prejudgment interest is allowable on the outstanding invoices. We
    conclude the District Court made a mathematical error in its award
    in favor of Pack.   The District Court was clearly erroneous.     We
    therefore reverse and remand to the District Court for the correct
    calculations.
    I11
    Whether the District Court erred in finding Peter Tracy
    individually liable.
    The District Court concluded that the named defendants owed
    Pack a total of $51,813.51.      However, Pack, in its complaint
    demanded judgment against Peter Tracy in the sum of $974.02, which
    did not involve Meadow Lake.     Pack renewed its demand in its
    amended complaint. Further, the pretrial order states that Pack is
    seeking $974.02 plus interest from Peter Tracy.
    Pack did not amend its complaint to reflect it was seeking to
    recover individually against Peter Tracy on the amounts owed to it
    by Meadow Lake. Therefore, we conclude the District Court erred in
    finding Peter Tracy individually liable for amounts other than
    reflected in the complaint, the amended complaint, and the pretrial
    6
    order.   We therefore reverse the District Court on this issue.
    Affirmed   in   part,   reversed   in   part,   and   remanded   for
    computation of the judgment in accordance with this opinion.
    Pursuant to Section I, Paragraph 3(c), Montana Supreme Court
    1988 Internal Operating Rules, this decision shall not be cited as
    precedent and shall be published by its filing as a public document
    with the Clerk of this Court and by a report of its result to the
    West Publishing Company.
    7
    