Sherrodd Inc. v. Morrison-Knudsen ( 1991 )


Menu:
  •                               No.    90-347
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    JUL 23 1991
    Plaintiff and Appellant,                      t ' d 3hitL
    CLERK OF S U P R E M E COURT
    -vs-                                               STATE OF MONTANA
    MORRISON-KNUDSEN COMPANY, SCHLEKEWAY CONSTRUCTION INC.,                    COP
    CONSTRUCTION INC., and SAFECO INSURANCE COMPANY OF AMERICA,
    Defendants and Respondents.
    APPEAL FROM:     District Court of the Thirteenth Judicial District,
    In and for the County of Yellowstone,
    The Honorable Russell K. Fillner, Judge presiding.
    COUNSEL OF RECORD:
    For Appellant:
    Loren H. Torkelson and Frank Richter; Richter                &
    Torkelson, Billings, Montana.
    For Respondent:
    Urban L. Roth and James A. Poore; Poore, Roth &
    Robinson, Butte, Montana.  W. Anderson Forsythe;
    Moulton, Bellingham, Longo & Mather, Billings,
    Montana.
    Submitted on briefs:   May 16, 1991
    Filed:
    I
    Clerk
    Chief Justice J. A. Turnage delivered the Opinion of the Court.
    This action arises out of a construction contract on which
    plaintiff Sherrodd, Inc., was a subcontractor.      Sherrodd, Inc.,
    appeals from a summary judgment entered for defendants by the
    District Court for the Thirteenth Judicial District, Yellowstone
    County.   We affirm.
    The issue is whether the entry of summary judgment for
    defendants was proper.
    Sherrodd, Inc. (Sherrodd), is a family-owned Montana construc-
    tion corporation.      Sherrodd subcontracted with COP Construction
    (COP) to do certain earth-moving work involved in the construction
    of fifty family housing units in Forsyth, Montana, for the Army
    Corps of Engineers.    COP itself was a subcontractor to the general
    contractors Morrison-Knudsen Company, Inc. (Morrison-Knudsen), and
    Schlekeway Construction, Inc.     (Schlekeway).   Safeco Insurance
    Company of America (Safeco) provided COP'S payment bond on the job.
    Sherrodd contends that while its officer William Sherrodd was
    examining the building site in preparation for submitting a bid on
    this project, a representative of Morrison-Knudsen told him that
    there were 25,000 cubic yards of excavation to be performed on the
    job. It claims that its bid of $97,500 on the subcontract was made
    in reliance on that representation, based on $3.90 per cubic yard
    for 25,000 cubic yards. Morrison-Knudsen denies that its represen-
    tative made any such statement to William Sherrodd.
    Sherroddlsbid, and, in turn, COP1sbid including Sherroddls
    bid, were submitted and accepted.    Sherrodd began work before a
    written contract was signed.      While performing the earthwork,
    Sherrodd discovered that the quantity of work far exceeded 25,000
    cubic yards.
    The written contract between Sherrodd and COP provided that
    Sherrodd would perform earthwork in the quantity l1LSl1 for the
    consideration of $97,500. The parties agree that the letters ItLS1'
    mean lump sum.    Sherrodd contends that its officers signed the
    contract, even though by then they knew that the job involved more
    than 25,000 cubic yards of earthwork, because a COP officer
    threatened to withhold payment for work already done unless the
    contract was signed.     Sherrodd further contends that the COP
    officer verbally represented that a deal would be worked out
    wherein Sherrodd would be paid more than the sum provided for in
    the contract.    COP1s position is that it only agreed to assist
    Sherrodd in presenting a claim for additional compensation to the
    Army Corps of Engineers, based on differences in the moisture
    content of the soil from that stated in the bid proposal. That was
    done, but the claim was denied.
    In its l1StandardSubcontract provision^," the contract entered
    between Sherrodd and COP also provided that
    the Subcontractor has, by examination, satis-
    fied himself as to the  ...  character, quan-
    tity and kind of materials to be encountered
    . .  . No verbal agreement with any agent
    either before or after the execution of this
    Subcontract shall affect or modify any of the
    terms or obligations herein contained and this
    contract shall be conclusively considered as
    containing and expressing all of the terms and
    conditions agreed upon by the parties hereto.
    No changes  ...   shall be valid   ...  unless
    reduced to writing and signed by the parties
    hereto.
    Sherrodd was paid the $97,500 provided for in the contract.
    It brought this suit to set aside the price provisions in the
    contract and to recover quantum meruit plus tort damages.       Its
    legal theories were fraud, both actual and constructive, and breach
    of the covenant of good faith and fair dealing.    Defendants moved
    for summary judgment, which was granted based on the parol evidence
    rule regarding modification of written contracts.
    Summary judgment is proper when the pleadings, depositions,
    answers to interrogatories, and admissions on file, together with
    the affidavits, if any, show that there are no genuine issues of
    material fact and that the moving party is entitled to judgment as
    a matter of law.   Rule 56(c), M.R.Civ.P.   The District Court held
    that, under the parol evidence rule, Sherrodd could not introduce
    evidence of the alleged oral misrepresentations by either the
    Morrison-Knudsen representative or the COP officer. Therefore, it
    concluded that even taking the evidence in the light most favorable
    to Sherrodd, summary judgment for defendants was proper.
    The parol evidence rule is codified in Montana statutes.
    Section 28-2-904, MCA, provides that:
    The execution of a contract in writing, whe-
    ther the law requires it to be written or not,
    supersedes all the oral negotiations or stipu-
    lations concerning its matter which preceded
    or accompanied the execution of the instru-
    ment.
    Section 28-2-905, MCA, provides that when an agreement has been
    reduced to writing by the parties, there can be no evidence of the
    terms of the agreement other than the contents of the writing
    except when a mistake or imperfection of the writing is claimed or
    when the validity of the agreement is the fact in dispute.
    Although it mentions mutual mistake in its brief to this
    Court, Sherrodd did not rely on that theory in the proceedings
    below, as evidenced in the pretrial order and in the District
    Court's memorandum on the summary judgment.    We will not consider
    on appeal a theory not raised at the trial court level.    Morse v.
    Cremer (1982), 
    200 Mont. 71
    , 81, 
    647 P.2d 358
    , 363.
    A further exception is made to the parol evidence rule when
    fraud is alleged.     Section 28-2-905 (2), MCA.      However, that
    exception only applies when the alleged fraud does not relate
    directly to the subject of the contract.      Where an alleged oral
    promise directly contradicts the terms of an express written
    contract, the parol evidence rule applies. Continental Oil Co. v.
    Bell (1933), 
    94 Mont. 123
    , 133, 
    21 P.2d 65
    , 67. Accord, Superior
    Oil Company v. Vanderhoof (D. Mont. 1969), 
    297 F. Supp. 1086
    .
    Here, any reliance on the alleged fraudulent statement of the
    Morrison-Knudsen representative is contradicted by the terms of the
    written contract that Sherrodd has,        examination, satisfied
    himself as to the   . . . character, quantity and kind of materials
    to be enc~untered.`` contention that the $97,500 covered only
    The
    25,000 cubic yards of earthwork contradicts the terms of the
    written agreement that all "negotiations and agreementsttprior to
    the date of the contract are merged in the writing and that the
    work to be done is "lump sum." We conclude that the par01 evidence
    rule applies.      Because the written agreement supersedes all
    previous oral agreements, the rule prohibits admission of any
    evidence of the representation by the Morrison-Knudsen represen-
    tative.
    Next we consider Sherroddtsclaim that COP officers induced
    Sherrodd officers to sign the contract with the promise that more
    money would be paid than the contract provided.       Section 28-2-
    1602, MCA, provides that a written contract may be altered only by
    a subsequent contract in writing or by an executed oral agreement.
    Also, Sherroddtssubcontract provided that ItNochanges      . . . shall
    be valid   . . . unless reduced to writing and signed by   the parties
    hereto."    As the District Court noted, there is no allegation of
    a subsequent contract in writing, and if there had been an executed
    oral agreement to pay additional sums for the work, there would
    have been no reason for this lawsuit.
    Because of the inadmissibility of Sherroddts evidence as to
    alleged misrepresentations, the claim of breach of the covenant of
    good faith and fair dealing also fails. There is no allegation of
    any violation of the express terms of the written contract, as
    6
    would be required in this arms-length   contract under our opinion
    in Story v. City of Bozeman (1990), 
    242 Mont. 436
    , 
    791 P.2d 767
    .
    As we have stated,
    Commercial stability requires that parties to
    a contract may rely upon its express terms
    without worrying that the law will allow the
    other party to change the terms of the agree-
    ment at a later date.
    Baker v. Bailey (1989), 
    240 Mont. 139
    , 143, 
    782 P.2d 1286
    , 1288.
    The parol evidence rule is the public policy of Montana and
    it is clearly established by statute and the decisions of this
    Court.   If this public policy and rule is not upheld, contracting
    parties that include lawful provisions in written contracts would
    be under a cloud of uncertainty as to whether or not their written
    contracts may be relied upon.   The public policy and law does not
    permit such uncertainty to occur.
    We conclude that the compensation of Sherrodd is governed
    exclusively by the written contract and that Sherrodd's claims are
    barred under the parol evidence rule.   We hold that the District
    Court did not err in granting summary judgment for defendants.
    Affirmed.
    We concur:
    Justices
    Justice Terry N. Trieweiler dissenting.
    I dissent from the opinion of the majority.
    If the facts are as alleged by the plaintiff (and for purposes
    of this proceeding we must assume that they are), then the result
    of this case is that no party can be held accountable for its
    fraudulent conduct so long as it is in a sufficiently superior
    bargaining position to compel its victim to sign a document
    relieving it of liability.
    The facts, as alleged by the plaintiff, offend any reasonable
    sense of fairness.   No court should be so bound by a 58-year-old
    precedent that it cannot adapt to circumstances such as those
    presented in this case.
    The plaintiff was informed by Lou Castino, the construction
    manager for Schlekeway and Associates, that the project he was
    being asked to bid on involved moving 25,000 cubic yards of dirt.
    It was based on that information that he submitted his bid.   It was
    based on his bid that he was given an oral request to proceed with
    the work.
    After commencing work on the project, plaintiff realized that
    the amount of earth that had to be moved greatly exceeded 25,000
    cubic yards, and was actually more than twice that amount.    He had
    conversations with representatives of both COP Construction and
    Schlekeway and Associates, during which it was agreed that the
    amount of work to be performed would be recalculated, and during
    which the defendants agreed to compensate plaintiff on the basis
    9
    of the actual amount of work done, rather than the price which was
    originally agreed upon.
    By May 22, 1985, plaintiff had already been working on the
    project and had incurred substantial expenses and obligations to
    his own employees.     He had not been paid for his work, and was
    still operating without a written agreement.          It was on that date
    that he was requested by COP Construction's superintendent to sign
    the written contract which the defendants now assert as a bar to
    his cause of action.    He was advised that if he did not sign the
    agreement he would not receive the progress payment in the amount
    of $70,372.80 which was due. Without the progress payment he would
    not have been able to pay his current expenses and payroll.
    He was further advised that he would not be bound by the terms
    of the written agreement, but that he would be paid for the actual
    work done at the rate of $3.90 per cubic yard.
    Thereafter, the     amount   of   earth   work    to   be   done was
    recalculated at approximately 50,000 cubic yards.           On that basis,
    plaintiff tried to recover the full amount due, but payment was
    refused.   Instead, the defendants raised the written agreement as
    a bar to any further payment to the plaintiff.
    Because of the defendantst failure to pay the plaintiff the
    additional $100,000 to $120,000 which they owed him, plaintiff's
    business lost its ability to borrow money, lost its bonding, and
    was unable to complete additional contracts because of a lack of
    operating capital.   Plaintiff was unable to bid on contracts that
    10
    required bonding, and completely lost its ability to carry on
    business as it had in the past.         As a direct result of the
    defendants1 failure to pay the amounts due, plaintiff was unable
    to continue in business as a construction company, which it had
    done for the previous 30 years.
    If the plaintiff's allegations are true, then defendant COP
    Construction Company's conduct, at least, satisfies the elements
    of fraud.    See Poulsen, et al. v. Treasure State Industries,
    
    192 Mont. 69
    , 
    626 P.2d 822
     (1981). COP'S employees represented to
    the plaintiff that he would be paid for the full amount of work
    done, regardless of the written terms of the contract.        That
    representation was untrue and material, and COP'S superintendent
    either knew it was untrue or had no reason to believe that it was
    true. COP Construction intended that the plaintiff act in reliance
    upon that representation.   Plaintiff did rely on it, and had no
    reason to believe that COP'S superintendent would mislead him.   As
    a result, plaintiff has sustained the total loss of his business
    and substantial damages.
    The majority has affirmed the dismissal of plaintiff's claim
    based solely on the par01 evidence rule found at 5 28-2-904, MCA.
    That rule provides that a written agreement supersedes all oral
    negotiations which preceded or accompanied the execution of the
    instrument. Furthermore, 5 28-2-905, MCA, provides that the terms
    of a written agreement cannot be proven by evidence other than what
    is contained in the written document.
    11
    However, an important exception is found at      §   28-2-905 (2) ,
    MCA, which provides, in relevant part, as follows:
    This section does not exclude other evidence of the
    circumstances under which the agreement was made or to
    which it relates . . . or other evidence to explain . ..
    fraud.
    In addition, 5 28-2-1611, MCA, provides as follows:
    When, through fraud or a mutual mistake of the parties
    or a mistake of one party while the other at the time
    knew or suspected, a written contract does not truly
    express the intention of the parties, it may be revised
    on the application of a party aggrieved so as to express
    that intention, so far as it can be done without
    prejudice to rights acquired by third persons in good
    faith and for value.
    (Emphasis added.)
    In this case, in spite of the exceptions to the parol evidence
    rule set forth by statute above, the majority has chosen to rely
    on this Court's 58-year-old decision in Continental Oil v. Bell,
    
    94 Mont. 123
    , 133, 
    21 P.2d 65
    , 68 (1933). In that case, this Court
    held that parol evidence of fraud was not admissible when the oral
    promise directly contradicts a provision of the written contract.
    I would   not   follow   this   Court's   previous   decision   in
    Continental Oil for two reasons:
    1.   That decision made no specific reference to the statute
    which is controlling, and yet adds qualifications to the statute
    which were not included by the legislature.          The legislature
    provided that parol evidence could be offered to establish that a
    contract was induced by fraud. It made no exception where evidence
    of the fraudulent oral agreement contradicted a term in the written
    agreement.
    2.   To follow the decision in Continental Oil creates a
    terrible injustice, rewards fraudulent parties who are in a
    superior bargaining position, and totally defeats the purpose for
    which the fraud exception was provided to the par01 evidence rule.
    Based   on   this   decision, and   our   previous   decision   in
    Continental oil, all that a fraudulent party needs to do in order
    to avoid accountability for fraudulent conduct is to obtain the
    signature of his defrauded victim on a written agreement.
    The majority expresses concern that but for this decision
    general contractors would not be able to rely on written agreements
    with their subcontractors. However, general contractors who induce
    subcontractors to enter into a written agreement by fraudulent
    representations should find no security in the piece of paper which
    resulted from their culpable conduct.          Furthermore, a justice
    system worth its salt should have equal compassion for Montana's
    many subcontractors who, while operating without the benefit of
    legal advice, sign whatever is necessary in order to keep their
    operations afloat and their crews at work.        When what they have
    signed results from an obvious misrepresentation and causes them
    the kind of substantial damages and hardship that have resulted in
    this case, those subcontractors are entitled to the protection of
    Montana's laws and its courts.
    For these reasons, I dissent from the majority opinion.       I
    would reverse the judgment of the District Court and remand for a
    jury trial to determine the merits of the plaintiff's claim.    That
    is really all the protection that Montana's general contractors
    need.
    I concur with the foregoing dissent of Justice Trieweiler.
    

Document Info

Docket Number: 90-347

Filed Date: 7/23/1991

Precedential Status: Precedential

Modified Date: 10/30/2014