Richardson Grain Separator Co. v. Valier Elevator Co. , 67 Mont. 227 ( 1923 )


Menu:
  • HONOEABLE GEOEGE A. HOEKAN, District Judge,

    sitting in place of ME. CHIEF JUSTICE CALLAWAY, disqualified, delivered the opinion of the court.

    This is an action for the foreclosure of a materialman’s lien. It originated in the district court of Teton county. The plaintiff and appellant herein, Eichardson Grain Separator Company, is a Minnesota corporation, with its headquarters at *230Minneapolis, Minnesota. For convenience it shall be referred to as the Separator Company. The defendant Yalier Elevator Company is a Montana corporation engaged in the elevator business at Yalier, Montana. In this opinion we will designate it as the Elevator Company. The defendant Globe Construction Company is likewise a Montana corporation whose principal business seems to be the construction of grain elevators. We shall refer to it as the Construction Company.

    The complaint is in the usual form for the foreclosure of a materialman’s lien, except as to paragraph XI thereof, which reads thus: ‘ ‘ That the aforesaid machinery, material and appliances described in said lien account were sold by the plaintiff to the defendant Globe Construction Company, under a contract by which this plaintiff undertook and agreed to install said machinery in the elevator building of the defendant Yalier Elevator Company, and that the agreed price should not become due and payable, nor the title to said machinery pass, until said machinery had been received, installed and in successful operation. That said machinery was installed and in successful operation in the elevator building of the defendant Yalier Elevator Company, and was accepted and its operation approved by the defendant Globe Construction Company, on or about the 20th day of September, 1917.”

    The complaint alleges that the machinery was furnished between September 1, 1917, and October 1, 1917, and that the claim for lien was filed with the county clerk on November 22, 1917, and within ninety days from the furnishing and installing of the machinery and material described therein.

    The Elevator Company answered denying that the machinery was furnished between September 1, 1917, and October 1, 1917, or that the claim for lien was filed within ninety days from and after the time when the machinery was sold and delivered. As an affirmative defense it is alleged, in effect, that some time prior to July 6, 1917, the Construction Company and the Elevator Company entered into a contract whereby the former agreed to build and equip with necessary machinery and appli*231anees a grain elevator building on tbe tract of land described in the complaint; that the Separator Company on said day had full and complete knowledge of said contract; that on July 7, 1917, at the request of the Construction Company, the Separator Company sold and delivered to the former at Minneapolis, Minnesota, the machinery and appliances heretofore referred to; that the same were immediately shipped to the Construction Company and were actually received by the latter at Valier, Montana, on July 19, 1917; that at all times the Separator Company well knew that said machinery and appliances were to be installed in and attached to said elevator building and were to become a permanent fixture therein; that within ninety days after the said machinery and appliances were sold and delivered by the Separator Company to the Construction Company, and long prior to the filing of the Separator Company’s pretended lien, the said machinery and appliances were installed in the elevator building by the Construction Company and became and are permanent fixtures therein; that the Elevator Company knew that said machinery and appliances were received by the Construction Company on July 19, 1917; that the Elevator Company never had any notice or knowledge from the Separator Company, or otherwise, that the Construction Company had not been paid for said machinery and appliances until the Separator Company filed its pretended lien, and never had any notice or knowledge of the alleged agreement between the Separator Company and the Construction Company “that the agreed price should not become due or payable, nor the title to said machinery pass until said machinery had been received, installed and in successful operation,” or any other agreement or understanding between the Separator Company and the Construction Company, until receipt of the copy of the Separator Company’s complaint. Other allegations are contained in the answer, but we deem it unnecessary to refer to them.

    The Separator Company replied, putting in issue all new matter alleged in the answer of the Elevator Company. The *232cause was tried to the court without a jury. Certain findings of fact and conclusions of law were made by the court, upon which a final decree and judgment was entered in favor of the Elevator Company, holding the claim of lien invalid and dismissing the complaint as to said company. From that judgment plaintiff Separator Company appealed. There are five specifications of error, none of which it is necessary to set out in detail.

    The main question to be determined in this case is: Was the [1] claim for lien filed with the county clerk within ninety days after the machinery and appliances were furnished by the Separator Company to the Construction Company? (Rev. Codes 1921, sec. 8340.) The trial court in its findings answered this question in the negative, and this we must accept under the well-established rule of this court, unless it is opposed to the preponderance of the evidence. (Willis v. Pilot Butte Mining Co., 58 Mont. 26, 190 Pac. 124; Loud v. Hanson, 53 Mont. 445, 164 Pac. 544; Street v. Delta Mining Co., 42 Mont. 371, 112 Pac. 701; Kelly v. Granite Bi-Metallic C. M. Co., 41 Mont. 1, 108 Pac. 785; Bordeaux v. Bordeaux, 32 Mont. 159, 80 Pac. 6.)

    A careful examination of the record leads us to believe the [2] conclusion reached by the trial court should not be disturbed. We are compelled to analyze the evidence briefly. It shows that on June 16, 1917, a written contract was entered into between the Elevator Company and the Construction Company whereby the latter agreed to build and equip with necessary machinery and appliances an elevator at Valier, Montana, for the former; that the contract provided the machinery to be installed in said elevator should be theo exact machinery which was later furnished by the Separator Company; that the Separator Company had immediate notice and knowledge of the terms of the contract; that on June 4, 1917, the Construction Company entered into negotiations with the Separator Company for the purchase of the machinery in question by giving to one R. J. Carey, .the assistant manager of the Sepa*233rator Company, a requisition or order for said machinery, which reads as follows:

    “Globe Construction Company, Great Falls, Montana.

    “Order No. 143.

    ‘ ‘ To Bichardson Grain Separator Co., Minneapolis, Minn.:

    “Great Falls, Mont., June 4, 1917.

    “Terms:-.

    “Ship via.-■.

    “Quantity. Description. Price Per.

    1 No. 3 (D) Simplex grain cleaner...............$ 685 00

    1 No. 5-48" Bichardson wheat and oat separator.. 700 00

    1 20" Bichardson attrition mill, with auto feed and scalper ................................ 260 00

    1 gang of sieves for flax cleaning................. 37 00

    1 scalping sieve, No. 32/64, round perforations..... 5 50

    2 single sieves, No. 18/64, round perforations..... 11 00

    $1,698 50

    “Less 10%

    “Ship the above f. o. b. G. N. to Valier, Mont.

    “Globe Construction Company,

    “Per J. C. Hosch.”

    This requisition or order was accepted by the Separator Company, and on July 6, 1917, it loaded the machinery at Minneapolis, Minn.,- f. o. b., and at the same time sent a bill of lading or invoice to the Construction Company which reads as follows:

    “Bichardson Grain Separator Company,

    “Minneapolis. Winnipeg.

    “The Bichardson Oat Separators and Screening Machines.

    “Elevator and Flour Mill Sizes a Specialty.

    ‘“Minneapolis, Minn., July 6, 1917.

    “Sold Globe Construction Co., Great Falls, Mont.

    “Terms: Net 30 days, 2% 10.

    1-70" D Simplex..................... $ 685 00

    1 flax gang received Jul. 9, 1917........ 37 00

    *234Globe Construction Co.

    1 scalping sieve ....................... 5 50

    2 single sieves ........................ 11 00

    1 No. 5 48" Richardson oat Sep. No. 3104 700 00

    1 20" Richardson BB Att. mill and scalper 260 00

    $1,698 50

    10%............. 169 85 $1,528 65

    “Shipped to Yalier, Mont.

    “Entered General Journal 45.

    “Entered Cost Journal 21.

    “Route Gr. Northern Mat.

    “No. 36.

    “Your order number Req. 143.”

    The machinery arrived at Yalier, Montana, on either the 17th, 18th or 19th of July, 1917, and was immediately unloaded by the Construction Company and placed in a warehouse, where it remained until it was removed to the elevator of the Elevator Company, which removal took place at a date not later than August 17, 1917.

    Some evidence was presented by the Separator Company attempting to show a general oral agreement between it and the Construction Company prior to, but not contemporaneously with, the giving of the written order or requisition heretofore referred to, that the title to the machinery should not pass until the machinery was accepted, and that there was not a sale of said machinery until it was placed in the elevator, given a thirty days’ trial, and accepted as satisfactory. This evidence was admitted over the objection of the Elevator Company. Assuming, but not deciding, that this evidence was properly admitted, it is far from being convincing, for the record shows that at the time the contract was entered into between the Construction Company and the Elevator Company for the construction of the elevator a conversation occurred between the officers of the Elevator Company and one J. C. Hosch, the secretary and treasurer, and representative of the *235Construction Company, in which he informed three officers of the Elevator Company that his company could not purchase the machinery subject to trial. This evidence was not disputed. Further, the evidence is conclusive that neither the Separator Company nor the Construction Company gave the machinery a thirty days’ trial. When we consider this testimony in connection with the specific language used in the written requisition or order herein set out, directing that the machinery and appliances be shipped f. o. b., G. N. to Yalier, Montana, and the bill of lading or invoice forwarded to and received by the Construction Company containing the plain, certain and well-known business term “net 30 days 2%-10,” we are led to the logical conclusion that the oral agreement in regard to the terms of sale of the machinery was an afterthought rather than a forethought.

    A careful analysis of all the record in this case leads to the [3] conclusion, and it is so held, that when the order or requisition of June 4, 1917, was received by the Separator Company and accepted and the machinery and appliances therein specified were shipped f. o. b. Minneapolis, Minnesota, July 6, 1917, there was a completed sale of said machinery and appliances (Clark v. Lindsay & Co., 19 Mont. 1, 61 Am. St. Rep. 479, 47 Pac. 102), and that said machinery and appliances were on July 6, 1917, furnished by the Separator Company to the Construction Company within the meaning of section 8340 of the Revised Codes of 1921. (McEwen v. Union Bank & Trust Co., 35 Mont. 470, 90 Pac. 359.)

    The machinery and appliances having thus been furnished more than ninety days prior to November 22, 1917, when the claim for a lien was filed, the mechanic’s lien law was not complied with and the lien did not attach. The lower court was correct in awarding judgment to the defendant Elevator Company. The judgment is affirmed.

    Affirmed.

    Associate Justices Cooper, Holloway, Galen and Stark concur.

Document Info

Docket Number: No. 5,135

Citation Numbers: 67 Mont. 227, 215 P. 237

Judges: Cooper, Galen, Hoekan, Holloway, Stark

Filed Date: 5/12/1923

Precedential Status: Precedential

Modified Date: 9/9/2022