The following evidence was submitted:
Bill of lading, duly signed by defendant company, for car-load of lumber to be shipped by plaintiff, T. W. Watson, at Cedar Landing, Bertie County, N.C.
1. That on 1 October, 1906, the Rocky Mount Sash and Blind Company, at Rocky Mount, delivered to the Atlantic Coast Line Railroad Company, for T. W. Watson, at Cedar Landing, N.C. the owner and party in interest, a car-load of lumber and window frames, to be shipped and delivered at Cedar Landing to said Watson.
2. That the distance from Rocky Mount to Cedar Landing is 58 miles, and there is in that distance one intermediate point, towit, Williamston, N.C. where the defendant connects with the Norfolk and Southern Railroad Company by boat for Cedar Landing.
3. That said shipment was delivered to the plaintiff at Cedar Landing on 21 October, 1906.
4. That the entire route of the shipment and both terminal points are in North Carolina.
5. The defendant delivered to the plaintiff the bill of lading named, above referred to. *Page 172
The court instructed the jury, if they believed the evidence, to answer the first issue "Yes" and the second issue "$100." To this charge defendant excepted. Thereupon the court rendered judgment. Defendant excepted to the judgment, and appealed. After stating the case: In support of its exception to the charge of his Honor on the first issue, the defendant insists that (238) the only obligation assumed by the contract of carriage, evidenced by the bill of lading, was to transport within a reasonable time the articles to the point of destination, if on its line and if not, to transport and deliver to the next connecting carrier on the route to the final destination. In the absence of any evidence of a joint obligation, this is unquestionably true. It is further true that, if the consignee seeks to fix the carrier with liability, either by way of damages or for statutory penalty, the burden of proof is upon him to show that the goods were not transported, according to the contract, within a reasonable time.Walker v. R. R.,
137 N.C. 163 . In this case it is conceded that the articles were received by defendant at Rocky Mount, 1 October, 1906, to be transported and delivered to plaintiff at Cedar Landing, both points being in this State, and the distance separating them 58 miles; that they were delivered to plaintiff 22 October, 1906; that there was but one intermediate point between the place of shipment and destination. When the facts are admitted and but one reasonable inference can be drawn from them, the court should instruct the jury as a matter of law — this is elementary. In the absence of explanation, it would not seem open to debate that the time between the receipt and delivery of the articles was unreasonable. We do not understand counsel to controvert this proposition. Defendant insists that, conceding this to be true, it also appears that Williamston is, for the purpose of this shipment, the terminus of defendant's line, and that at that point the articles were delivered to and transported by the Norfolk and Southern Railroad Company to their final destination. It is clear that if within a reasonable time the defendant delivered the articles to the Norfolk and Southern Company, and the delay occurred upon that line, the defendant was exonerated and the liability was transferred to that company.The question therefore, is, Where does the burden of proof rest as to such transportation and delivery? We had occasion to discuss (239) this question in Meredith v. R. R.,
137 N.C. 478 , in an action for damages for a failure to transport goods in a reasonable time and deliver them in good condition. After a careful consideration of the *Page 173 authorities, we held that the means of proof being within the control of the contracting company, upon the well-settled exception to the general rule, the burden was upon it to account for the damaged condition of the goods. In Harper v. Express Co.,144 N.C. 639 , we held that the same principle would apply where the action was for wrongful delay, and that presumption of responsibility would arise against any one of the connecting carriers shown to have possession and control of goods after the delay occurred. We can perceive no good reason why the same principle should not control in an action for the statutory penalty for delay in transporting goods. As we said in Stone v. R. R.,144 N.C. 220 , the only purpose and effect of the statute is to enforce the common-law duty and penalize its breach. The defendant keeps a record of all shipments over its line by means of waybills, showing the date of receipt, date of arrival at the destination, together with all other data enabling its agents to keep trace of the shipment. It also takes a receipt from the connecting carrier to which shipments are delivered for transportation to the point of destination. This record is always made by and under the control of defendant's agents. The shipper or consignee only knows from his bill of lading when the goods are shipped and when delivered. It is manifest, upon every principle of fair dealing, that when he shows an unreasonable delay in the transportation, all matters in exoneration or defense should come from the defendant. To hold otherwise would be to render the legislation enacted for the enforcement of the duty of the carrier and protection of the "party aggrieved" of no effect — to keep the promise to the ear and break it to the sense. If, as in this case, the carrier may permit articles — lumber and window frames — doubtless shipped to meet an immediate necessity, to be delayed from 1 October to 22 October, a distance of 58 miles, and without (240) any explanation or information as to the cause or place of such delay, call upon the defendant to summon its agents, with its own records, to show when, where and how the delay occurred, the statute would be of little value as a remedy for the wrong done him. His Honor was, therefore, clearly correct in his instructions to the jury upon the first issue.The defendant excepts to the instruction upon the second issue. His Honor assumed that the entire delay occurred on the defendant's road. In the absence of any explanation, we are unable to perceive how any other rule can be applied. For the same reasons which fixed the burden of proof regarding the place or cause of the delay, we are constrained to hold that the defendant must be held liable for the entire delay. If, having the evidence in its possession to show the contrary, the defendant withholds it from the court, it has no just cause of complaint. In the absence, therefore, of any evidence showing when the article was *Page 174 delivered to the connecting carrier, the initial or contracting carrier will be charged with the entire time during which the unreasonable delay occurred. If it has discharged its full duty, or has partially done so, the evidence thereof is within its possession and not known to plaintiff.
His Honor directed the jury to answer the second issue "$100." This is upon the theory that there was a delay of twenty-one days, two being allowed at the shipping point and two days at the intermediate point, leaving seventeen days. The judgment of $100 is based upon a charge of $25 for the first day and $5 per day for fifteen days. It is stated in the brief that 21 October was Sunday. We presume that his Honor deducted that day. The defendant's counsel insist that the day of receipt and the day of delivery should be deducted, and from the time thus fixed the four days should be deducted. We do not think this a reasonable construction of the statute. The two days at the initial point are allowed for the purpose of giving a reasonable time to begin (241) the transportation. The forty-eight hours at each intermediate point are allowed for change of cars — if necessary, unloading and reloading. The defendant insists that, in view of the statute (Revisal, sec. 2613) prohibiting freight trains to run on Sundays, between sunrise and sunset, the Sundays intervening between the day of shipment and delivery should not be counted. This suggestion might be made effective on appeal to the Legislature, but the Court is not at liberty to adopt it, when the statute which imposes the penalty (Revisal, sec. 2632) contains no such provision. We should not read into the statute an exception which the Legislature has not seen proper to make. Davis v. R. R., ante, 207. It will be noticed that the carrier is only prohibited from running its train for a part of Sunday, between sunrise and sunset, and certainly in the present case there has been no hardship imposed in the matter of time. In a shipment where the entire distance was not over 58 miles there has been an allowance of five days as free time, and this was as favorable as the defendant could reasonably ask.
There has been no error of which the defendant can complain, and the judgment below is
Affirmed.
Cited: Collection Agency v. R. R.,
147 N.C. 594 . *Page 175(242)