Delafield v. Lewis Mercer Construction Co. , 118 N.C. 105 ( 1896 )


Menu:
  • From the judgment rendered the Snow Steam Pump Company and Riter Conly appealed.

    The history of the case and the facts pertinent to the appeal are fully stated in the opinion of Chief Justice Faircloth. If we have been able to read the voluminous record in this case correctly, we find that in January, 1894, the plaintiff, Delafield, instituted this action against the Lewis Mercer Construction Company to recover the amount due on a promissory (107) note, for which he had previously attached defendant's property. Several other attachments had been levied on defendant's property. At February Term, 1894, the several creditors were made parties to this action and filed answers. At the same term the Chattanooga Foundry and Pipe Works was made a party defendant and allowed to interplead and set up its claim against the defendant. At Spring Term, 1894, the Snow Steam Pump Works showed to the court that it had a claim of $92 against defendant company, and it was ordered that said Snow Steam Pump Works be allowed to interplead as to the same and file an answer setting up said claim and be made a party for said purpose.

    It is alleged in other parts of the record that the Snow Steam Pump Works had another claim against defendant company, alleged to be secured by a mortgage on some of the property. At February Term, 1895, a motion of said steam pump works "to be stricken out as parties defendant to this action was refused, it appearing to the court that said steam pump works is a necessary party to the action." On 1 June, 1894, on its own application, the Snow Steam Pump Works obtained leave of the Judge presiding to bring an action against the receivers, previously appointed, to recover the machinery alleged to have been conveyed in said mortgage. At Spring Term, 1894, the following order was made: "It is, by consent, ordered that this action be referred to H. G. Connor to hear and consider the claims and demands of all parties to this action and all persons who shall become parties thereto or file claims in said action, and to find his conclusions of fact and law in regard to all contentions of such parties and *Page 69 claimants, and that he report," etc. After due notice to all parties in interest, the hearing was had before the referee, all parties being represented. The counsel of the Snow Steam Pump Works made a special appearance, "reserving all rights with respect to any (108) motions now pending in said cause," but offered no evidence before the referee.

    At May Term, 1895, the Snow Steam Pump Works filed an application to the court that the report of the referee be referred back to him for the purpose of hearing further evidence, etc., which motion was refused. At said term the report was confirmed and judgment rendered, from which only the Snow Steam Pump Works and the Chattanooga Foundry and Pipe Works appealed.

    The Snow Steam Pump Works filed no exceptions to the referee's report, either as to his conclusions of fact or law, nor any to the judgment, except (1) the refusal to rerefer the matter, which was a discretionary matter; (2) that there was error in ordering a distribution of the fund in the hands of the receivers until the appellant's separate actions are determined. This must be overruled, as no reason appears why such claims of this appellant could not have been determined in this action.

    The Chattanooga Foundry and Pipe Works' claim is for pipes and other material furnished the Lewis Mercer Construction Company for constructing waterworks in the city of New Bern under a written contract. It is admitted and agreed that the correspondence appearing in the record constitutes the whole of the contract entered into in the spring of 1893, under which a large amount of the material was shipped and delivered, and on 11 January, 1894, the Chattanooga company served a notice of stoppage in transitu on the railroad company at New Bern, on whose right of way some of the material still remained. In the view we take of this case, the alleged right of stoppage in transitu is unimportant.

    The contract being in writing, its construction is for the court and not for the jury. Sellars v. Johnson, 65 N.C. 104. Looking at the contract, we find that on 3 May, 1893, the Lewis (109) Mercer company sent an order to the Chattanooga company for material to build the New Bern waterworks. On 8 May they replied they would do so, setting forth particulars as to quantity, size, prize, etc., adding "Terms cash; immediate acceptance." On 10 May, 1893, the Lewis Mercer company said: "We can pay you cash in the following manner: We enclose you a card of the banking house to whom we have sold the city of New Bern waterworks bonds. They will accept your drafts on them at three months for all pipe delivered each month at New Bern, N.C. In reference to the firm of John F. *Page 70 Zebley Co., we refer you to the Citizens' Bank of New Bern, N.C. John F. Zebley Co. bought the bonds of the company which we organized, and furnished us with cash to build these works. Kindly advise us at once if you wish to enter order on above-mentioned terms, as we consider that when John F. Zebley Co. accept your drafts on them at three months it is equivalent to cash. Of course, you understand those acceptances carry 6 per cent interest." After some correspondence about freight, manner of shipping, etc., the Chattanooga company replied: "We wrote you on the 16th of the month, in which we accepted the terms and conditions upon pipe and specials delivered at New Bern, N.C. per your letter of 10 May. These terms were drafts to be made at three months for all pipe delivered each month at New Bern, N.C. I accepted the order by telegraph, but since have thought it would require some little explanation." These mutual statements are repeated in other communications, and instructions given for shipping, invoices ordered, etc. On 20 May, the Chattanooga company inquired of R. G. Dun Co., a mercantile agency of Baltimore, Md., as to the condition of John F. Zebley Co., (110) and received in reply: "Lewis Mercer Construction Company and Zebley considered good for drafts referred to." On 22 May, John F. Zebley Co. replied to Chattanooga company, "Will accept your three-months draft on us for pipe delivered each month to the Lewis Mercer Construction Company at New Bern, N.C." and gave references to three responsible parties.

    On 23 May the Chattanooga company said to the Lewis Mercer company, "We are ready now to commence shipment of pipe to you," stating that Zebley had agreed to accept drafts, etc. A few days later, at the instance of the Lewis Mercer company, Zebley Co. placed some of the bonds with the Chattanooga company as collaterals, and the shipments commenced. Late in 1893, or early in 1894, it developed that Zebley Co. and the Lewis Mercer company were insolvent.

    Our conclusion is that, by the terms and intent of the contract, the drafts drawn by the Chattanooga company and their acceptance by Zebley Co., and the deposit of the bonds of the city of New Bern with the former, was a discharge of the Lewis Mercer company from further liability on the contract for the pipe, etc., furnished by the Chattanooga company to the Lewis Mercer company. Symington v. McLin, 18 N.C. 298; Ligon v. Dunn,28 N.C. 133; Sellers v. Johnson, supra. We find similar conclusions arrived at in the following: Whitbeck v. Van-Ness, 11 Johns, 409; Eaton v. Cook,32 Vt. 58; Noel v. Murray, 3 Kernan, (N. Y.), 167.

    In Noel v. Murray, supra, it was held that "where the note is *Page 71 received on a precedent debt the presumption is that it was not taken as a payment, and the onus is upon the debtor to show that it was taken as a payment; but where it is received contemporaneously with the contracting of the debt the presumption is that it was taken in payment, and the burden of proving the contrary rests on the (111) creditor." This conclusion makes it unnecessary to consider the question of the right of stoppage in transitu, and all the exceptions of the Chattanooga company are overruled, as it has no claim against the Lewis Mercer company.

    The want of power in the court to appoint receivers, in a case like the present, to take charge of a partially constructed work and finish the enterprise, in which the public have no interest, has been suggested, and would present a serious question but for the fact that the receivers were appointed by consent of all interested parties, and there is no exception to that aspect of the order. In any completed enterprise in which the public are interested, and which is called a "going concern," the courts do not hesitate to make such appointments; for example, a running railroad. But how much further the court will go will be reserved for future consideration. The receivers were ordered to file their accounts of receipts and disbursements with the clerk and the cause retained for further hearing. That part of the judgment fixing the per cent of commissions for the receivers was premature, and must be reversed, and that matter will be adjusted when their work is finished. We cannot now see whether the allowance is too much or not. Modified as above stated, the judgment is affirmed.

    Affirmed as modified.

    Cited: Pump Works v. Dunn, 119 N.C. 79.

    (112)

Document Info

Citation Numbers: 24 S.E. 10, 118 N.C. 105

Judges: Faircloth

Filed Date: 2/5/1896

Precedential Status: Precedential

Modified Date: 10/19/2024