The Town of Black Mountain v. Lexon Insurance Company ( 2014 )


Menu:
  •                                  NO. COA14-740
    NORTH CAROLINA COURT OF APPEALS
    Filed: 16 December 2014
    THE TOWN OF BLACK MOUNTAIN, NORTH
    CAROLINA and THE COUNTY OF
    BUNCOMBE, NORTH CAROLINA,
    Plaintiffs,
    v.                                 Buncombe County
    No. 12 CVS 05118
    LEXON INSURANCE COMPANY and BOND
    SAFEGUARD INSURANCE COMPANY,
    Defendants.
    Appeal by defendants from order entered 4 March 2014 by
    Judge Gary M. Gavenus in Buncombe County Superior Court.             Heard
    in the Court of Appeals 20 October 2014.
    Cannon Law, P.C., by William E. Cannon, Jr. and Ronald E.
    Sneed, P.A., by Ronald E. Sneed, for plaintiffs-appellees.
    Shumaker, Loop & Kendrick, LLP, by William H. Sturges and
    Daniel R. Hansen, for defendants-appellants.
    HUNTER, Robert C., Judge.
    The Town of Black Mountain, North Carolina (“the Town”) and
    the   County     of     Buncombe,    North   Carolina      (“the   County”)
    (collectively “plaintiffs”) filed suit against Lexon Insurance
    Company    and   Bond    Safeguard   Insurance   Company    (“defendants”)
    seeking to enforce a series of subdivision performance bonds.
    -2-
    The trial court entered summary judgment in plaintiffs’ favor.
    On appeal, defendants argue that summary judgment for plaintiffs
    was improper because: (1) neither the Town nor the County has
    standing       to     enforce      the    bonds;       and   (2)        the    statute       of
    limitations for plaintiffs’ claim has run.
    After careful review, we affirm the trial court’s order.
    Background
    From March 2005 through February 2007, defendants entered
    into    four        subdivision     performance         bonds      (“the       bonds”)       as
    sureties for The Settings of Black Mountain, LLC and Richmarc
    Black Mountain, LLC (collectively “developers”).1                             Approval from
    the    County       for    the    developers      to    begin      construction         on    a
    residential         subdivision       was    conditioned           on     obtaining      the
    performance bonds to secure completion of the project.                                  Thus,
    the obligee on each of the bonds in question was the County, not
    the Town.       Each of the bonds contained a clause indicating that
    defendants, as sureties, would not be required to complete the
    infrastructure or pay the principal amount of the bond until
    they received a resolution from the obligee indicating that the
    improvements         had    not    been     installed        or    completed       by    the
    1
    Although plaintiffs named all four bonds in their complaint,
    the construction secured by one of the bonds has since been
    completed; thus, only three remaining bonds are the subject of
    plaintiffs’ claim.
    -3-
    developers.         The     bonds      also    contained          a    provision       holding
    defendants and the developers jointly and severally liable for
    any amounts due upon default.
    The real property that was secured by the bonds was annexed
    by the Town at varying times between May 2005 and February 2007.
    Defendants assert that they lacked knowledge of the annexation
    until 5 January 2012.                 In 2009, the Town sought confirmation
    from the developers that they intended and had the means to
    complete the infrastructure secured by the bonds.                                In a letter
    dated 23 October 2009, attorneys for the developers indicated
    that they were working toward closing a recapitalization loan.
    On   18    December      2009,   a    principal       in    one       of   the   development
    companies       stated    via    e-mail       that    “we    still         believe   we    have
    viable entities, though obviously troubled.                           We are committed to
    finishing our communities without need of the bonds[.]”                                Indeed,
    construction       activity      by    the    developers       continued         into     2010.
    Ultimately the companies failed.                     Richmarc Black Mountain, LLC
    filed its final annual report on 7 June 2011, and The Settings
    at   Black      Mountain,    LLC      was    administratively              dissolved      on    21
    August 2011.
    On    5   January     2012,      the    County       contacted        defendants         and
    asked if they would consent to an assignment of the bonds to the
    -4-
    Town.       In its inquiry, the County conceded that, due to the
    annexation, “Buncombe County no long[er] has any jurisdiction
    over    the     properties        and     cannot       enforce     any     rights       per    its
    ordinances.”          Defendants did not consent to the assignment.
    On   1    August       2011      and    20    December      2011,       the    Town    sent
    defendants           notice       that        the     developers         had     ceased        all
    construction activity.               On 22 June 2012, the County assigned its
    rights in the bonds to the Town, which accepted assignment on 9
    July 2012.           On that same day, the Town adopted a resolution
    finding the infrastructure to be incomplete.                                   The Town sent
    defendants notice of their claims under the bonds on 24 July
    2012.       Following         nonpayment        by     defendants,       plaintiffs          filed
    their complaint for breach of contract on 25 October 2012.                                    Both
    the County and the Town brought suit because they anticipated
    that defendants would challenge standing if either party sued
    separately;          thus,    their      claims       are   pled    in     the       alternative
    pursuant        to    Rule    8    of    the        North   Carolina       Rules       of    Civil
    Procedure.
    Plaintiffs and defendants each moved for summary judgment
    and were heard on their respective motions 10 February 2014.
    The trial court entered an order granting summary judgment for
    -5-
    plaintiffs on 4 March 2014.         Defendants filed timely notice of
    appeal.
    Discussion
    I. Standing
    Defendants first argue that neither the Town nor the County
    has standing to bring suit.          Specifically, defendants contend
    that once the Town annexed the property covered by the bonds,
    the bonds were extinguished, leaving no rights for the County to
    assign.    We disagree.
    “This     Court   reviews    orders    granting   summary   judgment   de
    novo.”     Foster v. Crandell, 
    181 N.C. App. 152
    , 164, 
    638 S.E.2d 526
    , 535 (2007).      Summary judgment is appropriate “only when the
    record shows that there is no genuine issue as to any material
    fact and that any party is entitled to a judgment as a matter of
    law.”     In re Will of Jones, 
    362 N.C. 569
    , 573, 
    669 S.E.2d 572
    ,
    576 (2008) (internal quotation marks omitted).              The burden of
    proof rests with the movant to show that summary judgment is
    appropriate.    Development Corp. v. James, 
    300 N.C. 631
    , 637, 
    268 S.E.2d 205
    , 209 (1980).         We review the record in the light most
    favorable to the non-moving party.           Caldwell v. Deese, 
    288 N.C. 375
    , 378, 
    218 S.E.2d 379
    , 381 (1975).
    -6-
    Defendants rely on Stillings v. City of Winston-Salem, 
    311 N.C. 689
    , 
    319 S.E.2d 233
     (1984), in support of their contention
    that the bonds were extinguished when the subject properties
    were annexed by the Town.           In Stillings, the Court stated the
    issue it considered as follows: “Does an exclusive solid waste
    collection franchise granted by a county remain effective in
    areas subsequently annexed by a city and thereby entitle the
    franchisees to compensation for a taking when the city, pursuant
    to     statutory   mandate,    begins       providing         its   own     garbage
    collection service?” 
    Id. at 691
    , 
    319 S.E.2d at 235
    .                       The Court
    answered this question in the negative.                 
    Id.
         In holding that
    the exclusive waste collection franchise entered into by the
    county and a private party terminated in the geographic areas
    annexed by the city, the Court noted that the garbage collection
    company, “had no rights which the [c]ity was bound to respect.”
    
    Id. at 694-96
    , 
    319 S.E.2d at 237-38
    .             According to the statutory
    mandate in N.C. Gen. Stat. § 160A-47, the city was required to
    provide     garbage    collection    services      without      charge      to   its
    residents in newly annexed areas.            Id.       at 694, 
    319 S.E.2d at 237
    .      Therefore,    annexation    created      a    conflict    between      the
    exclusive    franchise    rights     held   by    the    plaintiffs        and   the
    statutory mandate imposed on the city.                 In recognition of the
    -7-
    rule   that   “[c]orporations             which     receive      franchises    take    the
    granted privileges subject to the police power of the state,”
    the Court ultimately held that “[b]y annexation of the property
    in question, the county’s franchise terminated and the police
    power of the [c]ity became operative.”                    
    Id.
    Defendants argue that, pursuant to Stillings, “once a town
    annexes territory that is the subject of a private contract
    between     the    county     and     a       private    citizen,     the     annexation
    effectively nullifies the contract.”                      Thus, defendants contend
    that the bonds were extinguished when the annexation took place,
    rendering them unenforceable by either the County or the Town.
    We do not read Stillings so broadly.                       The Stillings Court
    did not hold that the franchise agreement between the garbage
    collection        company     and     the      county     was     terminated    in     its
    entirety;     rather,       the   contract        was    terminated    only    in    those
    geographical areas annexed by the city.                    See Stillings, 311 N.C.
    App. at 696, 
    319 S.E.2d at 238
    .                     Therefore, Stillings does not
    support   the      idea   that      annexation       automatically      terminates      an
    entire    agreement         between       a    county      and    a   private       party.
    Furthermore, the conflict between the exclusive waste collection
    franchise and the police powers of the annexing city was crucial
    to the Stillings Court’s holding.                       Here, unlike in Stillings,
    -8-
    the bonds do not conflict with the Town’s police power.                                There
    is no statute requiring the Town to behave adversely to the
    agreement       between       defendants       and     the    County.      Rather       than
    attempting to terminate the bonds, the Town seeks to enforce
    them.        This    situation       contrasts       sharply     with    the     facts    of
    Stillings, where the annexing city was required by statute to
    provide free garbage collection services in direct contravention
    of the exclusive franchise agreement between the county and the
    plaintiffs.         Based on these material distinctions, we decline to
    extend the Stillings holding to the facts of this case.
    We agree with defendants that the County lost standing to
    enforce the bonds after annexation.                          The bonds were created
    pursuant      to     the      County’s     “subdivision          control    ordinance,”
    allowing the County to “provide orderly growth and development”
    by     entering      into     surety     bonds       with     developers    to     “assure
    successful completion of required improvement.”                          See N.C. Gen.
    Stat.    §   153A-331       (2013).        But    the       County’s    power    to    issue
    subdivision         control       ordinances     was    geographically      limited       by
    N.C.     Gen.      Stat.      §    153A-122      (2013),       providing        that    such
    ordinances are only applicable “to any part of the county not
    within a city.”             Therefore, after annexation, the County no
    longer had statutory authority to call the bonds.                          The County’s
    -9-
    attorney      admitted   as     much    in     his    5    January     2012    e-mail    to
    defendants requesting their consent to assignment, wherein he
    stated that “Buncombe County no long[er] has any jurisdiction
    over    the    properties     and      cannot    enforce        any    rights    per    its
    ordinances.”       We    also    agree        with    defendants       that,    prior    to
    assignment, the Town did not have standing to enforce or call
    the bonds because it was not a party to the agreements.
    However,    we    find     nothing        in       the   law     or    within    the
    agreements themselves indicating that assignment of the bonds
    from the County to the Town was impermissible or without legal
    effect.       See North Carolina Bank & Trust Co. v. Williams, 
    201 N.C. 464
    , 465-66, 
    160 S.E. 484
    , 485-86 (1931) (holding that an
    indemnity bond was freely assignable as a chose in action).
    Indeed, defendants “do not contest the general law that, absent
    contrary      language   or   public      policy,         bonds   can    be    assigned.”
    Here, the bonds do not contain any language restricting their
    assignability, and we believe public policy favors assignability
    under     these   facts.          It     is     uncontested           that    substantial
    infrastructure remains incomplete as a result of the developers’
    financial troubles.         If neither the Town nor the County are able
    to call the bonds, defendants would in effect receive a windfall
    -10-
    by being released from their obligation to pay the sums owed
    under the bonds.
    Accordingly, we hold that the assignment of the bonds from
    the County to the Town was sufficient to allow the Town to
    enforce the agreements against defendants.                 Thus, the assignment
    conferred standing upon the Town to sue for the alleged breach
    of those agreements.         We affirm the trial court’s order as to
    this issue.
    II. Statute of Limitations
    Defendants also argue that summary judgment for plaintiffs
    was improper because their cause of action is time-barred by the
    statute of limitations.          We disagree.
    
    N.C. Gen. Stat. § 1-52
    (1)    (2013)      provides    that       actions
    concerning a “contract, obligation or liability arising out of a
    contract” have a three-year limitations period.                      Plaintiffs do
    not dispute that section 1-52 applies to claims for breach of
    contract.     However, they assert protection under the doctrine of
    nullum   tempus     occurrit       regi,     which    generally         allows      for
    governmental bodies to be exempt from statutory time limitations
    in bringing civil lawsuits.              In Rowan Cnty. Bd. of Educ. v.
    United   States    Gypsum   Co.,    
    87 N.C. App. 106
    ,   
    359 S.E.2d 814
    (1987)   (“Rowan    I”),    and   Rowan     Cnty.    Bd.    of    Educ.    v.   United
    -11-
    States Gypsum Co., 
    332 N.C. 1
    , 
    418 S.E.2d 648
     (1992) (“Rowan
    II”), our Courts analyzed the doctrine of nullum tempus in North
    Carolina and developed a framework for its application.                    “If the
    function at issue is governmental, time limitations do not run
    against the State or its subdivisions unless the statute at
    issue     expressly    includes    the       State.   If     the    function    is
    proprietary, time limitations do run against the State and its
    subdivisions unless the statute at issue expressly excludes the
    State.”     Rowan II, 
    332 N.C. at 9
    , 
    418 S.E.2d at 654
     (emphasis in
    original).
    Because section 1-52 is silent as to its application to the
    State     or   its    subdivisions,      this     issue     turns   on     whether
    plaintiffs      are   engaged     in     a    proprietary     or    governmental
    function.      The Rowan II Court noted that the distinction between
    governmental and proprietary action in the context of sovereign
    immunity is the same as the distinction to determine whether the
    State benefits from the protection of nullum tempus.                     Rowan II,
    
    332 N.C. at 9
    , 
    418 S.E.2d at 654
    .               Thus, the case most helpful
    to this analysis is Derwort v. Polk County, 
    129 N.C. App. 789
    ,
    
    501 S.E.2d 379
     (1998).
    In Derwort, the issue before this Court was whether Polk
    County’s enactment of a subdivision control ordinance pursuant
    -12-
    to sections 153A-121 and 153A-331 rendered it immune from suit
    under the public duty doctrine.                      Id. at 792, 
    501 S.E.2d at 381
    .
    The Court noted that section 153A-121 was included under the
    heading titled “Delegation and Exercise of the General Police
    Power,”       and    that      section    153A-331        allowed      counties      to   issue
    ordinances          “in    a   manner    that    .    .     .   will   create       conditions
    essential to public health, safety, and the general welfare.”
    
    Id.
            Citing Lynn v. Overlook Development, 
    98 N.C. App. 75
    , 78,
    
    389 S.E.2d 609
    , 611 (1990), it also noted that “[a] municipality
    ordinarily acts for the benefit of the public, not a specific
    individual, in providing protection to the public pursuant to
    its statutory police powers.”                    Id. at 791, 
    501 S.E.2d at 381
    .
    The Court went on to hold that “[t]he plain language of the
    statute and our case law thus indicate that subdivision control
    is     a    duty      owed     to   the    general          public,     not     a     specific
    individual,” and therefore the county was immune from suit by
    virtue of the public duty doctrine.                         Id. at 792, 
    501 S.E.2d at 381
    .
    However,           defendants     argue       that       City   of   Reidsville       v.
    Burton, 
    269 N.C. 206
    , 
    152 S.E.2d 147
     (1967), is more applicable
    than Derwort, and therefore, we should find that the act of
    suing under the bonds is a proprietary rather than governmental
    -13-
    function.     In Burton, the Court noted that generally municipal
    corporations       are   immune    from    application          of     a     statute        of
    limitations       because    “construction     and       maintenance             of    public
    streets     and    of    bridges    constituting         a     part        thereof         are
    governmental      functions[.]”      
    Id. at 210
    ,      
    152 S.E.2d at 151
    .
    However, the Court held that the City of Reidsville was engaged
    in a proprietary function when it sued for breach of contract
    with a private party in the construction of a bridge that was
    not used by the public, was not maintained by the city, and was
    not connected to any public streets.                     
    Id.
             Here, unlike in
    Burton, there is evidence in the record that the subdivision
    secured by the bonds allowed public access.                      Specifically, the
    developers were required to allow for limited public use of the
    subdivision       clubhouse.       Additionally,          the        developers            were
    required    to     include     easements    sufficient          for        the    Town      to
    maintain and access all waterlines.                Based on this distinction,
    we do not find Burton controlling.
    Here, the County entered into the bonds pursuant to section
    153A-331, the same statute utilized by Polk County in Derwort.
    Section 153A-331 provides that counties are authorized to enact
    subdivision       control    ordinances      for     a    variety          of     purposes
    consistent with their governmental police powers, such as: (1)
    -14-
    “provid[ing]      for     the   orderly    growth     and   development      of   the
    county”; (2) “creat[ing] conditions that substantially promote
    public     health,      safety,   and     the    general    welfare”;      and    (3)
    “provid[ing] for the more orderly development of subdivisions by
    requiring the construction of community service facilities in
    accordance with county plans, policies and standards.”                     
    Id.
        The
    statute goes on to allow counties to enter into bonds like those
    at issue in this case “[t]o assure compliance with these and
    other ordinance requirements[.]”               
    Id.
    Because the enabling statute allowing for the creation of
    the bonds between defendants and the County explicitly states
    that such bonds exist to “assure compliance” with subdivision
    ordinance requirements, which this Court has characterized as “a
    duty owed to the general public, not a specific individual,”
    Derwort,    129   N.C.     App.   at    792,    
    501 S.E.2d at 381
    ,    and   the
    subdivision is open to the public, we conclude that plaintiffs
    are engaged in a governmental function by attempting to enforce
    the bonds against defendants.              See also State Art Museum Bldg.
    Comm’n v. Travelers Indem. Co., 
    111 N.C. App. 330
    , 335, 
    432 S.E.2d 419
    , 422 (1993) (“A court may [] consider whether or not
    the State’s action is for the ‘common good of all’ and therefore
    governmental,        or     for        pecuniary      profit    and        therefore
    -15-
    proprietary.”); Sides v. Cabarrus Memorial Hospital, Inc., 
    287 N.C. 14
    ,    23,   
    213 S.E.2d 297
    ,      303     (1975)     (noting      that
    “governmental functions . . . are those historically performed
    by the government, and which are not ordinarily engaged in by
    private corporations.”).            Therefore, under the Rowan rulings,
    plaintiffs are not subject to the statutory time limitation in
    section 1-52.
    Even assuming that the County and the Town were engaged in
    a proprietary function sufficient to trigger the three-year time
    limitation in section 1-52, we would still find that summary
    judgment for plaintiffs is proper.              Defendants argue that this
    cause of action accrued before 25 October 2009, three years
    before the complaint was filed on 25 October 2012, because by
    that    time   plaintiffs    knew     or     should     have     known   that    the
    construction work would not be completed within a reasonable
    time.    We disagree.       The bonds themselves do not specify any
    particular date by which time the construction needed to be
    completed.       Although    there    is     evidence     that     the   Town    was
    concerned in mid-2009 by the relative lack of progress on the
    construction, as late as 18 December 2009, a principal in the
    development     companies    stated    that      they     were     “committed     to
    finishing [the] communities without need of the bonds.”                    Indeed,
    -16-
    construction       activity    by   the       developers     continued      well     into
    2010.         Therefore,   because       it    is   clear    that    the    developers
    themselves had not yet given up on the project, we disagree with
    defendants’ contention that there is a genuine issue of fact
    regarding whether plaintiffs knew or should have known prior to
    25 October 2009 that the project would not be completed within a
    reasonable time.
    Conclusion
    After careful review, we hold that the Town has standing to
    bring     suit     against     defendants           for     breach    of     contract.
    Furthermore, plaintiffs are engaged in a governmental function
    and     are    exempt   from    the      otherwise        applicable       statute    of
    limitation.         Therefore,      we    affirm      the    trial   court’s       order
    granting summary judgment for plaintiffs.
    AFFIRMED.
    Chief Judge McGEE and Judge STEELMAN concur.