-
416 S.E.2d 607 (1992) 106 N.C. App. 383 KINSEY CONTRACTING COMPANY, INC., Plaintiff,
v.
CITY OF FAYETTEVILLE, A municipal corporation, Defendant.No. 9112SC637. Court of Appeals of North Carolina.
June 2, 1992. *608 Bryan, Jones, Johnson & Snow by James M. Johnson, Dunn, for plaintiff-appellant.
Reid, Lewis, Deese & Nance by Marland C. Reid, Fayetteville, for defendant-appellee.
ARNOLD, Judge.
Plaintiff argues the trial court erred in concluding that plaintiff failed to show that defendant's rejection of its bid was an abuse of discretion under N.C.Gen.Stat. § 143-128 (1990). In reviewing the decision of a local government to award a public contract " ``[i]t is a general rule that officers of a municipal corporation, in the letting of municipal contracts, perform not merely ministerial duties but duties of a judicial and discretionary nature, and that courts, in the absence of fraud or a palpable abuse of discretion, have no power to control their action.' " Mullen v. Town of Louisburg, 225 N.C. 53, 60, 33 S.E.2d 484, 488-89 (1945) (citations omitted).
The language upon which plaintiff relies in G.S. § 143-128(b) was added in 1989. When awarding contracts where the entire cost of the work exceeds one hundred thousand dollars, a municipality must "award the contract to the lowest responsible bidder or bidders for the total project." G.S. § 143-128(b) (emphasis added). *609 Plaintiff contends that this award standard does not allow factors other than cost to be taken into consideration and that defendant abused its discretion by considering other factors. We disagree.
While plaintiff argues "lowest responsible bidder" requires only that a contractor with the lowest bid have the proper license for the job, provide the necessary performance and payment bonds, and have adequate financial resources to perform the contract, the term "must be held to imply skill, judgment and integrity necessary to the faithful performance of the contract, as well as sufficient financial resources and ability." McQuillin Mun. Corp. § 29.73.05 (3d ed. revised 1990).
The general award standard for formal contracts is set out in N.C.Gen.Stat. § 143-129 and allows consideration of various factors. Given that this general award standard has been well-established for many years, it is unlikely that the legislature would attempt to promulgate a new award standard by omitting part of the established standard's language, "taking into consideration quality, performance and the time specified in the proposals for the performance of the contract." G.S. § 143-129. We construe the language used in G.S. § 143-128(b), "the lowest responsible bidder or bidders," to be an abbreviated reference to the general award standard set out in G.S. § 143-129. See also A. Fleming Bell, II, Construction Contracts with North Carolina Local Governments, 14-15 (2d ed.1991); Bluestein, North Carolina's "Lowest Responsible Bidder" Standard for Awarding Public Contracts, Popular Gov't, Winter 1992, at 16 n. 1.
Plaintiff next argues the trial court erred in finding no abuse of discretion by defendant because the evidence did not support this finding. Denial of a preliminary injunction is subject to de novo review based upon the facts and circumstances of the particular case. Electrical South, Inc. v. Lewis, 96 N.C.App. 160, 385 S.E.2d 352 (1989), review denied, 326 N.C. 595, 393 S.E.2d 876 (1990). When reviewing the evidence presented at the hearing, there is a presumption the trial court's decision was correct and the appellant has the burden of showing that the trial court erred. Id.
Defendant's consulting engineers requested that plaintiff and Crowder submit
by April 1, 1991, a list of references, a description of projects similar to the project under consideration, an experience record of projects completed by the bidders, a detailed inventory of personnel and equipment proposed to be used on the project, a detailed resume of the resident superintendent responsible for the project, banking, insurance and bonding company references, a list of any pending claims filed against the bidder, a list of all current projects under contract and other information necessary for Black & Veatch [the consulting engineers] to determine whether the Plaintiff and Crowder Construction Company, Inc. were responsible bidders within the meaning of N.C.G.S. 143-129.
Two sections of the Instructions to Bidders, (B-1) qualification of bidders and (B-10) award of contract, listed factors that would be used in determining the bidder's qualifications. The trial court found that
Plaintiff has failed to submit to Black & Veatch a copy of an audited financial statement, a list of any pending claims, resumes of supervisory personnel which the Plaintiff intended to assign to the construction project, or the identity of the proposed excavation contractor the Plaintiff intended to use to perform the excavation work required by the contract. Crowder Construction Company, Inc. timely submitted all information requested by Black & Veatch.
The consulting engineers supported their recommendation to defendant with a seven page document entitled "Discussion of Bids." Based on the evidence before it the trial court concluded that "the Plaintiff has failed to show that the rejection of the low bid of the Plaintiff was a result of any fraud, corruption, abuse of discretion or any other improper motive on behalf of the defendants[.]" Upon our review of the evidence *610 and the applicable statutes, we affirm the order of the trial court.
Affirmed.
WELLS and EAGLES, JJ., concur.
Document Info
Docket Number: 9112SC637
Citation Numbers: 416 S.E.2d 607, 106 N.C. App. 383, 1992 N.C. App. LEXIS 496, 1992 WL 118890
Judges: Arnold, Wells, Eagles
Filed Date: 6/2/1992
Precedential Status: Precedential
Modified Date: 10/19/2024