ELJ, Inc. v. Jefferys ( 2014 )


Menu:
  • An unpublished opinion of the North Carolina Court of Appeals does not constitute
    controlling legal authority. Citation is disfavored, but may be permitted in accordance
    with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Procedure.
    NO. COA13-1420
    NORTH CAROLINA COURT OF APPEALS
    Filed: 1 July 2014
    ELJ, INC.,
    Plaintiff,
    v.                                      Onslow County
    No. 13-CVS-2383
    WILLIAM J. JEFFERYS AND A.C.
    SCHULTES OF CAROLINA, INC.,
    Defendants.
    Appeal by defendants from Order entered 10 September 2013
    by   Judge   Gary    E.   Trawick    in   Superior     Court,    Onlsow    County.
    Heard in the Court of Appeals 24 April 2014.
    Harris, Creech, Ward & Blackerby, P.A., by Luke A. Dalton
    and Jay C. Salsman, for plaintiff-appellee.
    Bugg & Wolf, P.A., by William R. Sparrow, for defendants-
    appellants.
    STROUD, Judge.
    William     Jefferys     and    A.C.    Schultes     of   Carolina,      Inc.
    (“defendants”) appeal from an order entered 10 September 2013
    denying their motion to compel arbitration. We affirm.
    I.     Background
    On 24 June 2013, ELJ, Inc. (“plaintiff”) filed a complaint
    in superior court, Craven County, against defendants. It alleged
    -2-
    that   defendant      Jefferys,       president     of   A.C.   Schultes,        made    a
    number of derogatory statements about ELJ while the parties were
    competing for construction bids in Pamlico County and Lenoir
    County. It alleged that these statements were defamatory per se
    and that they constituted unfair and deceptive trade practices.
    With consent of both parties, venue was moved to Onslow County.
    The    parties        had     previously      worked     together          on    a
    construction project in Farmville, North Carolina. A.C. Schultes
    was    the    prime     contractor      on   the     project     and       ELJ   was     a
    subcontractor.        The    subcontract     they    signed     for    that      project
    included an arbitration provision that required arbitration of
    “[a]ny claim arising out of or related to this Subcontract . . .
    .” Defendants filed a motion to compel mediation and arbitration
    on the basis of this provision.
    The superior court heard defendants’ motion on 3 September
    2013. By order entered 10 September 2013, the superior court
    denied defendants’ motion to compel mediation and arbitration.
    Defendants timely filed written notice of appeal to this Court.
    II.    Appellate Jurisdiction
    Defendants appeal from an interlocutory order denying their
    motion   to    compel       arbitration.     An   order   denying      a    motion      to
    compel arbitration affects a substantial right. Sillins v. Ness,
    -3-
    
    164 N.C. App. 755
    , 756, 
    596 S.E.2d 874
    , 875 (2004). Therefore,
    it is immediately appealable and this Court has jurisdiction to
    consider the appeal. 
    Id.
    III. Motion to Compel Arbitration
    Defendants        argue   that   the   trial    court    erred    in   denying
    their   motion   to    compel    arbitration       because   the     parties   had
    entered   into   a    contract   with      an   arbitration    provision       that
    covers plaintiff’s defamation claim. We disagree.
    As a general matter, public policy favors
    arbitration. However, before a dispute can
    be ordered resolved through arbitration,
    there   must   be  a   valid    agreement  to
    arbitrate.   Thus,  whether   a   dispute  is
    subject to arbitration is a matter of
    contract law. Parties to an arbitration must
    specify clearly the scope and terms of their
    agreement to arbitrate. Moreover, a party
    cannot be forced to submit to arbitration of
    any dispute unless he has agreed to do so.
    The question of whether a dispute is subject
    to arbitration is an issue for judicial
    determination. . . . [T]he trial court’s
    conclusion   as  to   whether  a   particular
    dispute is subject to arbitration is a
    conclusion of law, reviewable de novo by the
    appellate court.    [The determination of]
    [w]hether   a    dispute   is    subject   to
    arbitration involves a two pronged analysis;
    the court must ascertain both (1) whether
    the parties had a valid agreement to
    arbitrate, and also (2) whether the specific
    dispute falls within the substantive scope
    of that agreement.
    -4-
    Raspet v. Buck, 
    147 N.C. App. 133
    , 135-36, 
    554 S.E.2d 676
    , 678
    (2001) (citations and quotation marks omitted).
    “The     determination         of       whether     a     particular        claim    is
    arbitrable     is     controlled       by    the   language          of   the    parties’
    agreement.” Ruffin Woody And Associates, Inc. v. Person County,
    
    92 N.C. App. 129
    , 133, 
    374 S.E.2d 165
    , 168 (1988), disc. rev.
    denied, 
    324 N.C. 337
    , 
    378 S.E.2d 799
     (1989).
    Other courts have generally agreed that
    whether a claim falls within the scope of an
    arbitration clause and is thus subject to
    arbitration      depends    not     on   the
    characterization of the claim as tort or
    contract, but on the relationship of the
    claim   to   the    subject  matter   of the
    arbitration clause.
    Rodgers Builders, Inc. v. McQueen, 
    76 N.C. App. 16
    , 24, 
    331 S.E.2d 726
    , 731 (1985), disc. rev. denied, 
    315 N.C. 590
    , 
    341 S.E.2d 29
     (1986).
    Here, it is undisputed that the parties signed a contract
    with an arbitration clause. The only dispute concerns whether
    the tort claims fall within its scope.                        The primary contract
    between the Town of Farmville and A.C. Schultes concerned the
    construction     of    water   transmission           lines    for    Farmville.        A.C.
    Schultes   and      ELJ   signed   a    subcontract         that     required     ELJ    to
    provide certain labor and material in connection to the project.
    The subcontract contained the following arbitration provision:
    -5-
    6.2 ARBITRATION
    6.2.1 Any claim arising out of or related to
    this Subcontract, except claims as otherwise
    provided in Subparagraph 4.1.5[1] and except
    those waived in the Subcontract, shall be
    subject    to    arbitration.     Prior   to
    arbitration, the parties shall endeavor to
    resolve disputes by mediation in accordance
    with the provision of Paragraph 6.1.
    In    Rodgers    Builders,    Inc.       we    considered   an    arbitration
    clause similar to the one here. In that case, the arbitration
    clause provided: “‘All claims, disputes and other matters in
    question     between    the    Contractor           [plaintiff]   and     the       Owner
    [McQueen     Properties]      arising     out       of,   or   relating       to,    the
    Contract Documents or the breach thereof, . . . shall be decided
    by arbitration . . . .’” Id. at 18, 
    331 S.E.2d at 728
    .                                The
    subsequent claims in that case were tort claims related to “a
    dispute . . . concerning plaintiff’s alleged failure to complete
    the   project   within      the   time    specified       in   the     contract      and
    McQueen Properties’ subsequent refusal to pay a draw request in
    the amount of $177,000 submitted by plaintiff.” 
    Id.
     We observed
    that the tort claims were subject to arbitration because “[t]he
    actions which form the basis for the claims allegedly were taken
    for   the   purpose    of     defeating    plaintiff’s         claim    for     damages
    1
    This subparagraph concerned the authority of the prime
    contractor and architect to reject any work performed by ELJ
    that does not conform to the prime contract.
    -6-
    arising   under      the   contract.”    Id.    at     25,   
    331 S.E.2d at 732
    .
    Therefore, we concluded that the “alleged tortious conduct on
    the part of defendants . . . occurred in connection with, or as
    a part of, the formation of, performance under, or breach of the
    contract between plaintiff and McQueen Properties” and held that
    the claims were subject to arbitration. 
    Id.
    ELJ’s complaint alleged that the parties worked together on
    a   project    for   the   Town   of    Farmville      in    2009   and   2010,    the
    project covered by the subcontract discussed above. That project
    “ended    up   in    litigation,       with    [A.C.    Schultes]      filing     suit
    against ELJ.”        In 2012, a project in Grantsboro, Pamlico County,
    was posted for bid. ELJ alleged that defendant Jefferys made a
    number of defamatory statements to engineers for the Pamlico
    County project in order to convince the County to award the
    contract to A.C. Schultes instead of ELJ. There is no indication
    on the face of the complaint that the project in Pamlico County
    had anything to do with the Farmville project.
    Both parties also bid on a project in the Town of LaGrange,
    Lenoir County. ELJ alleged that defendant Jefferys also called
    an influential supplier on that project, the LaGrange mayor, and
    the LaGrange public works director to make several derogatory
    statements regarding ELJ’s past work. ELJ alleged that these
    -7-
    statements were made in an attempt to dissuade LaGrange from
    hiring ELJ to work on the project. There is no indication that
    this   project    had   anything    to   do    with   the     Farmville   project
    either.
    The only evident relevance of the Farmville project to the
    present claims is to explain how the parties knew each other
    prior to the later bids.           It is the conduct surrounding these
    later bid contests that gave rise to plaintiff’s claims here,
    not the performance or breach of the contract. Even assuming
    that Jeffreys’ allegedly derogatory statements were about ELJ’s
    performance of the Farmville project, we cannot say that these
    claims    are    “arising   out    of    or    related   to    [the   Farmville]
    Subcontract.”       See     Fontana       v.     Southeast       Anesthesiology
    Consultants, P.A., ___ N.C. App. ___, ___, 
    729 S.E.2d 80
    , 87
    (holding that a plaintiff’s tort claims were not covered by an
    arbitration agreement where “the facts underlying plaintiff’s
    allegations relating to the tort claims may have contributed to
    creating the environment which led to plaintiff’s termination,
    but they do not specifically pertain to a dispute concerning
    plaintiff’s termination.”), disc. rev. denied, 
    366 N.C. 394
    , 
    732 S.E.2d 478
     (2012).
    -8-
    The    alleged       defamatory      statements       were      made   after    the
    project, as well as the related litigation, was complete.                          They
    were not substantially related to the subcontract. Unlike in
    Rodgers Builders, Inc., the conduct giving rise to plaintiff’s
    tort claims did not occur “in connection with, or as a part of,
    the formation of, performance under, or breach of the contract
    between” the parties. 76 N.C. App. at 25, 
    331 S.E.2d at 732
    .
    Although defendants correctly observe that this arbitration
    provision is broad, it is not quite so broad as to reach all
    conduct   between       the   parties.      Given   the    lack      of    connection
    between the claims under consideration here and the contract
    containing   the        agreement     to     arbitrate,        we    conclude      that
    plaintiff is not required to arbitrate these claims. Therefore,
    we affirm the trial court’s denial of defendants’ motion to
    compel arbitration.
    IV.   Conclusion
    We conclude that the arbitration provision in the contract
    between the parties does not cover the unrelated tort claims
    later   brought    by    plaintiff.        Therefore,     we     affirm    the   trial
    court’s order denying defendants’ motion to compel arbitration.
    AFFIRMED.
    Judges HUNTER, JR., Robert N. and DILLON concur.
    -9-
    Report per Rule 30(e).