L&C Expedition v. Swenson, Hagen and Co. , 2023 ND 29 ( 2023 )


Menu:
  •                                                                                  FILED
    IN THE OFFICE OF THE
    CLERK OF SUPREME COURT
    FEBRUARY 16, 2023
    STATE OF NORTH DAKOTA
    IN THE SUPREME COURT
    STATE OF NORTH DAKOTA
    
    2023 ND 29
    L&C Expedition, LLC, and
    Williams Building Company, Inc.,                    Plaintiffs and Appellants
    v.
    Swenson, Hagen and Company, P.C.;
    Unlimited Excavating, LLC; and
    Hartze Construction, Inc.,                                       Defendants
    and
    International Fidelity Insurance Company,            Defendant and Appellee
    No. 20220169
    Appeal from the District Court of Mercer County, South Central Judicial
    District, the Honorable Bruce A. Romanick, Judge.
    AFFIRMED.
    Opinion of the Court by Jensen, Chief Justice.
    Bradley N. Wiederholt, Bismarck, ND, for plaintiffs and appellants.
    Robert J. Pathroff, Bismarck, ND, for defendant and appellee.
    L&C Expedition v. Swenson, Hagen and Co.
    No. 20220169
    Jensen, Chief Justice.
    [¶1] L&C Expedition, LLC (“L&C”) appeals from a judgment entered
    following the district court granting summary judgment in favor of
    International Fidelity Insurance Company (“IFIC”) and denying summary
    judgment to L&C. L&C argues the district court erred in finding a contractual
    limitation on the period to assert a claim was enforceable, erred in failing to
    apply N.D.C.C. § 9-08-05 to preclude modification of the applicable statute of
    limitations, and erred in interpreting N.D.C.C. § 22-03-03 as providing an
    exception to the prohibition against modifying the applicable statute of
    limitations. We affirm.
    I
    [¶2] L&C contracted with Unlimited Excavating (“Unlimited”) to perform
    work on a residential development project. The parties’ contract required
    Unlimited to obtain a performance bond. Unlimited obtained a performance
    bond through IFIC.
    [¶3] Unlimited completed its work in November 2016 and received final
    payment in July 2017. In 2019, L&C learned of major problems in the
    construction and notified Unlimited it needed to make repairs. Unlimited did
    not make the repairs and L&C demanded IFIC arrange for performance of
    Unlimited’s work per the terms of the performance bond. IFIC refused to
    arrange for performance. L&C subsequently initiated suit against IFIC in May
    2020 arguing L&C is entitled to recover $393,000 under the terms of the
    performance bond.
    [¶4] The performance bond provided the following: “[a]ny suit under this bond
    must be[] [i]nstituted before the expiration of two years from the date on which
    final payment under the subcontract falls due.” The parties do not dispute the
    district court’s finding L&C initiated its action outside the limitation period
    provided within the terms of the bond.
    1
    [¶5] L&C and IFIC both moved for summary judgment. The district court
    granted summary judgment in favor of IFIC, finding L&C’s claims against
    IFIC are time-barred by the two-year limitation for asserting a claim as
    provided within the terms of the performance bond.
    II
    [¶6] L&C argues the two-year time limitation provided in the performance
    bond is invalid. L&C asserts N.D.C.C. § 9-08-05 precludes parties from
    contracting for a period of limitation to bring a claim different than the
    applicable statute of limitations, and N.D.C.C. § 22-03-03 does not provide an
    exception to N.D.C.C. § 9-08-05.
    [¶7] We have outlined the standard of statutory interpretation as follows:
    Statutory interpretation is a question of law, which is fully
    reviewable on appeal. Nelson v. Johnson, 
    2010 ND 23
    , ¶ 12, 
    778 N.W.2d 773
    . The primary purpose of statutory interpretation is to
    determine the intention of the legislation. In re Estate of Elken,
    
    2007 ND 107
    , ¶ 7, 
    735 N.W.2d 842
    . Words in a statute are given
    their plain, ordinary, and commonly understood meaning, unless
    defined by statute or unless a contrary intention plainly appears.
    N.D.C.C. § 1-02-02. If the language of a statute is clear and
    unambiguous, “the letter of [the statute] is not to be disregarded
    under the pretext of pursuing its spirit.” N.D.C.C. § 1-02-05. If the
    language of the statute is ambiguous, however, a court may resort
    to extrinsic aids to interpret the statute. N.D.C.C. § 1-02-39.
    Bindas v. Bindas, 
    2019 ND 56
    , ¶ 10, 
    923 N.W.2d 803
     (quoting Ferguson v.
    Wallace-Ferguson, 
    2018 ND 122
    , ¶ 7, 
    911 N.W.2d 324
    ).
    [¶8] L&C argues N.D.C.C. § 9-08-05 voids any contractual provision which
    limits the time within which a party can enforce their right and N.D.C.C. § 22-
    03-03 does not provide for an exception. We disagree.
    [¶9] Section 9-08-05, N.D.C.C., provides:
    Every stipulation or condition in a contract by which any party
    thereto is restricted from enforcing that party’s rights under the
    2
    contract by the usual legal proceedings in the ordinary tribunals
    or which limits the time within which that party thus may enforce
    that party’s rights is void, except as otherwise specifically
    permitted by the laws of this state.
    Section 9-08-05, N.D.C.C., does void all provisions in a contract which limit the
    time within which a party can enforce their rights, but specifically allows for
    parties to limit the time for asserting a claim if another North Dakota law
    permits the limitation.
    [¶10] Section 22-03-03, N.D.C.C., provides: “[a] surety cannot be held beyond
    the express terms of the surety’s contract and if such contract prescribes a
    penalty for its breach, the surety cannot be liable in any case for more than the
    penalty.” The language of the statute is clear and unambiguous. The language
    of the statute provides a surety cannot be held beyond the terms in the contract
    nor held beyond the amount of liability provided for in the contract. A contract
    provision which limits the amount of time a party is allowed to bring suit is an
    express provision of the contract. Therefore, N.D.C.C. § 22-03-03 provides that
    if the parties contractually agree to a limitation on the time to bring a claim,
    the surety cannot be held beyond that limitation. N.D.C.C. § 22-03-03 serves
    as an exception under N.D.C.C. § 9-08-05.
    [¶11] L&C further argues Storing v. National Surety Co., 
    56 ND 14
    , 
    215 N.W. 875
     (1927) is controlling. In Storing, this Court invalidated a 15-month lawsuit
    deadline contained in a surety bond under Section 5927, Compiled Laws 1913.
    Section 5927 and N.D.C.C. § 9-08-05 are very similar but have one important
    difference. Section 5927, Compiled Laws 1913, read as follows:
    Every stipulation or condition in a contract by which any party
    thereto is restricted from enforcing his rights under the contract
    by the usual legal proceedings in the ordinary tribunals or which
    limits the time within which he may thus enforce his rights is void.
    N.D.C.C. § 9-08-05 provides:
    Every stipulation or condition in a contract by which any party
    thereto is restricted from enforcing that party’s rights under the
    contract by the usual legal proceedings in the ordinary tribunals
    3
    or which limits the time within which that party thus may enforce
    that party’s rights is void, except as otherwise specifically
    permitted by the laws of this state.
    [¶12] The primary difference between the two statutes is the addition of the
    phrase “except as otherwise specifically permitted by the laws of this state[]”
    in N.D.C.C. § 9-08-05. As discussed above, N.D.C.C. § 22-03-03 serves as an
    exception to Section 9-08-05. The statute analyzed in Storing did not provide
    for any exceptions. Storing is not controlling.
    [¶13] Section 22-03-03, N.D.C.C., provides a surety cannot be held beyond the
    express terms of the surety contract. Therefore, the contractual statute of
    limitations in the performance bond governs. The performance bond provides,
    “[a]ny suit under this bond must be[] [i]nstituted before the expiration of two
    years from the date on which final payment under the subcontract falls due.”
    The express terms of the contract provide that any suit must be brought within
    two years from final payment under the subcontract. Unlimited completed its
    work in November 2016 and received its last payment in July 2017. L&C
    initiated the proceedings in May 2020. L&C failed to initiate proceedings
    within two years after final payment was received by Unlimited and their
    claims against IFIC are barred.
    III
    [¶14] The two year limitation for asserting a claim provided for in the
    performance bond is enforceable, L&C failed to bring suit within two years,
    and L&C is barred from asserting its claims against IFIC. We affirm.
    [¶15] Jon J. Jensen, C.J.
    Daniel J. Crothers
    Lisa Fair McEvers
    Jerod E. Tufte
    Daniel D. Narum, D.J.
    [¶16] Gerald W. VandeWalle, who was a member of the Court when this matter
    was submitted, was disqualified and did not participate in this decision. The
    Honorable Daniel D. Narum, D.J., sitting.
    4
    [¶17] Justice Douglas A. Bahr was not a member of the Court when this matter
    was submitted and did not participate in the decision.
    5
    

Document Info

Docket Number: 20220169

Citation Numbers: 2023 ND 29

Judges: Jensen, Jon J.

Filed Date: 2/16/2023

Precedential Status: Precedential

Modified Date: 2/16/2023