City of Fargo v. Wieland , 2019 ND 286 ( 2019 )


Menu:
  •                 Filed 12/12/19 by Clerk of Supreme Court
    IN THE SUPREME COURT
    STATE OF NORTH DAKOTA
    
    2019 ND 286
    City of Fargo, a political subdivison
    of the State of North Dakota,                              Plaintiff and Appellee
    v.
    Karen C. Wieland,                                       Defendant and Appellant
    No. 20190153
    Appeal from the District Court of Cass County, East Central Judicial District,
    the Honorable John Charles Irby, Judge.
    AFFIRMED.
    Opinion of the Court by McEvers, Justice.
    Jane L. Dynes, Fargo, ND, for plaintiff and appellee.
    Jonathan T. Garaas, Fargo, ND, for defendant and appellant.
    City of Fargo v. Wieland
    No. 20190153
    McEvers, Justice.
    [¶1] Karen Wieland appeals from a judgment allowing the city of Fargo to
    take her property for flood mitigation purposes and awarding her $939,044.32
    in just compensation, attorney fees, costs, and statutory expenses. Because
    the district court did not misapply the law in concluding the taking of
    Wieland’s property was necessary for a public use, we affirm the judgment.
    I
    [¶2] Wieland owned a home located at Copperfield Court in Fargo. The
    property, which abuts Drain No. 27, frequently flooded. After the 2009 flood
    in Fargo, Wieland and other area residents asked the City to fix the banks on
    Drain No. 27 to provide flood protection, and the City began examining possible
    solutions to the flooding problems. The City engineering staff and consulting
    engineers held public information meetings with landowners in the
    Copperfield Court area. In February 2012, the City held a meeting with the
    landowners and informed them that the recommended flood protection plan
    would require the acquisition of the Wieland property and other property to
    build an earthen levee for permanent flood protection. In August 2012, the
    Board of City Commissioners approved the recommended project and directed
    staff to prepare implementation and funding plans for the project.
    [¶3] Wieland and the City for years discussed the voluntary acquisition of her
    property. The City eventually offered Wieland the property’s appraised value
    of $725,000 plus statutory costs and moving expenses. Wieland rejected the
    offer. On December 19, 2016, the City issued a “resolution of necessity” stating
    “it is necessary for the city of Fargo to acquire [Wieland’s property] to allow for
    such use as the construction of a flood protection project to protect the city of
    Fargo.” In Brandt v. City of Fargo, 
    2018 ND 26
    , ¶¶ 1, 14, 
    905 N.W.2d 764
    , we
    affirmed dismissal of Wieland’s challenge to the City’s resolution of necessity
    because there was no statutory basis authorizing the appeal.
    1
    [¶4] After further negotiations with Wieland failed, the City in April 2017
    brought this eminent domain action seeking to acquire Wieland’s property for
    flood protection purposes. The district court granted partial summary
    judgment concluding that permanent flood protection was a public use
    authorized by law and that the taking of Wieland’s property was necessary to
    the use. Following a trial, the jury awarded Wieland $850,000 as just
    compensation for the taking. The court awarded her an additional $89,044.32
    for attorney fees and other costs.
    II
    [¶5] Wieland argues the district court erred in granting summary judgment
    in favor of the City on the eminent domain questions of public use and
    necessity.
    [¶6] Our standard for reviewing summary judgments is well established.
    Summary judgment is a procedural device under
    N.D.R.Civ.P. 56(c) for promptly resolving a controversy on the
    merits without a trial if there are no genuine issues of material
    fact or inferences that can reasonably be drawn from undisputed
    facts, or if the only issues to be resolved are questions of law. The
    party seeking summary judgment must demonstrate there are no
    genuine issues of material fact and the case is appropriate for
    judgment as a matter of law. In deciding whether the district court
    appropriately granted summary judgment, we view the evidence
    in the light most favorable to the opposing party, giving that party
    the benefit of all favorable inferences which can reasonably be
    drawn from the record. A party opposing a motion for summary
    judgment cannot simply rely on the pleadings or on unsupported
    conclusory allegations. Rather, a party opposing a summary
    judgment motion must present competent admissible evidence by
    affidavit or other comparable means that raises an issue of
    material fact and must, if appropriate, draw the court’s attention
    to relevant evidence in the record raising an issue of material fact.
    When reasonable persons can reach only one conclusion from the
    evidence, a question of fact may become a matter of law for the
    court to decide. A district court’s decision on summary judgment is
    a question of law that we review de novo on the record.
    2
    Brock v. Price, 
    2019 ND 240
    , ¶ 10, 
    934 N.W.2d 5
     (quoting Smithberg v.
    Smithberg, 
    2019 ND 195
    , ¶ 6, 
    931 N.W.2d 211
    ).
    [¶7] Wieland argues the district court erred in granting summary judgment
    because she raised a genuine issue of material fact to preclude summary
    judgment, and because the City presented no evidence to support the court’s
    decision that the requirements of N.D.C.C. § 32-15-05 have been satisfied.
    Section 32-15-05, N.D.C.C., provides:
    Before property can be taken it must appear:
    1.    That the use to which it is to be applied is a use authorized
    by law.
    2.    That the taking is necessary to such use.
    3.    If already appropriated to some public use, that the public
    use to which it is to be applied is a more necessary public use.
    A
    [¶8] In Montana-Dakota Utils. Co. v. Behm, 
    2019 ND 139
    , ¶ 9, 
    927 N.W.2d 865
    , we discussed the requirement of “public use”:
    Where a property owner contests “public use” under
    N.D.C.C. ch. 32-15, “there is a presumption a use is public when
    the Legislature has declared it to be and we treat the Legislature’s
    decision with the deference due a coordinate branch of
    government.” City of Medora v. Golberg, 
    1997 ND 190
    , ¶ 8, 
    569 N.W.2d 257
    . Nevertheless, “the ultimate decision regarding
    whether a proposed use of property is, in fact, a public use is a
    judicial question.” 
    Id.
    The Legislature has declared “[f]lood control projects” to be a “public use” by
    giving municipalities the power:
    To acquire, construct, maintain, operate, finance, and control flood
    control projects, both within and adjacent to such municipality,
    and for such purpose to acquire the necessary real property and
    easements therefor by purchase and eminent domain, in
    accordance with chapter 32-15, and to adopt such ordinances as
    may reasonably be required to regulate the same.
    3
    N.D.C.C. § 40-05-01(67).
    [¶9] The City’s resolution of necessity in this case states:
    WHEREAS, the Red River of the North, its tributaries, and
    associated drain system, are prone to frequent flooding which
    presents significant risk to the inhabitants of the city, property,
    infrastructure, and the economy of the city of Fargo and the
    surrounding communities;
    WHEREAS, the city of Fargo has identified viable flood
    control and protection options;
    WHEREAS, the city of Fargo has undertaken considerable
    effort, at considerable expense, to construct flood control and
    protection projects to protect the city of Fargo from anticipated
    flood events;
    WHEREAS, the city of Fargo, based on information and
    recommendation provided by the city of Fargo Engineering
    Department and consulting engineers, have identified properties
    necessary to be acquired in order to accomplish real and
    meaningful flood protection to the inhabitants, property,
    infrastructure, and economy of the city of Fargo; and
    WHEREAS, the city of Fargo has, or will, continue to
    negotiate in good faith to secure the identified necessary
    properties.
    NOW THEREFORE, BE IT RESOLVED THAT the public
    use for the properties identified is a use provided for by law;
    BE IT FURTHER RESOLVED THAT it is necessary for the
    city of Fargo to acquire the following identified properties to allow
    for such use as the construction of a flood protection project to
    protect the city of Fargo: [Wieland’s property].
    [¶10] Wieland argues the City’s resolution of necessity is “fatally flawed”
    because it allows the City to “condemn first, decide what do to with the
    property later.” Wieland relies on City of Stockton v. Marina Towers LLC, 
    88 Cal.Rptr.3d 909
    , 921-22 (Cal. Ct. App. 2009), in which the court held a
    resolution of necessity describing a project as the “acquisition of additional
    land in conjunction with potential development” was invalid because it did not
    sufficiently define the project. The court reasoned:
    4
    We fail to discern how this language notifies the property
    owner and the public what project is intended for the property.
    The project is described as the “acquisition of additional land” in
    “conjunction with potential development.” But to say that the
    project is the “acquisition of additional land” is the same as saying
    the project is the condemnation itself. To state that the acquisition
    is “in conjunction” with potential development or that it is
    “consistent with” redevelopment activities going on in the area
    adds nothing[.]
    
    Id.
    [¶11] The City’s resolution of necessity in this case does not suffer from the
    same infirmities as the resolution invalidated in Marina Towers. The City
    specifically describes the purpose as a “flood protection project,” and this
    description is analogous to examples given by the Marina Towers court that it
    said would satisfy the requirement of a brief description of a public use: “A
    statement, for example, that the public use is an ‘elementary school and
    grounds’ or ‘right of way for a freeway’ or ‘open space to be maintained in its
    natural condition’ would satisfy this requirement.” 88 Cal.Rptr.3d at 921
    (internal citation omitted).
    [¶12] Wieland argues the resolution of necessity is invalid because N.D.C.C. §
    61-16.1-38 requires that “complete plans and specifications” for a dike “must
    be presented first to the state engineer.” Wieland’s argument fails because
    N.D.C.C. ch. 61-16.1 governs the operations of water resource districts, not
    municipalities.
    [¶13] Wieland also argues that, because at the time the resolution of necessity
    was adopted and the eminent domain action was commenced N.D.C.C. § 48-
    01.2-01(20) defined a “public improvement” as any improvement “on public or
    nonpublic land” exceeding the monetary threshold contained in N.D.C.C. § 48-
    01.2-02.1, the City was required to “procure plans, drawings, and specifications
    for the improvement from an architect or engineer” under N.D.C.C. § 48-01.2-
    02. Wieland’s attempt to apply the statutory bidding requirements in N.D.C.C.
    ch. 48-01.2 as a prerequisite to the issuance of a resolution of necessity and the
    commencement of an eminent domain action is misplaced. This Court has
    5
    recognized that a statute must be construed logically and not to produce an
    absurd result:
    In Haggar Co. v. Helvering, 
    308 U.S. 389
    , 394, 
    60 S.Ct. 337
    ,
    339, 
    84 L.Ed. 340
     (1940), the Supreme Court of the United States
    stated as follows:
    “All statutes must be construed in the light of their
    purpose. A literal reading of them which would lead to
    absurd results is to be avoided when they can be given a
    reasonable application consistent with their words and with
    the legislative purpose.”
    Fireman’s Fund Mortg. Corp. v. Smith, 
    436 N.W.2d 246
    , 247 (N.D. 1989).
    [¶14] The purpose of competitive bidding is not intended to be a prerequisite
    to a resolution of necessity; rather, the competitive bidding requirements were
    enacted for the benefit of the public to invite competition, prevent favoritism,
    fraud, and collusion, and secure the best work and supplies at the lowest price.
    See Becker Elec., Inc. v. City of Bismarck, 
    469 N.W.2d 159
    , 160 (N.D. 1991). It
    would be absurd to require contractors to submit detailed construction plans
    and bids for a proposed project that not only will occur years into the future,
    but is also contingent on the local governing body ever acquiring the property.
    Wieland’s argument ignores that the City did not adopt the resolution of
    necessity in a vacuum. Indeed, the City worked with its own engineers and
    consulting engineers for years to address Fargo’s flooding problems, and the
    engineers presented various plans and proposals. The City was provided
    detailed site plans and maps of the proposed project. We conclude the
    information presented by the engineers to the City was sufficient to satisfy the
    requirements of N.D.C.C. § 48-01.2-02.
    [¶15] The district court correctly determined as a matter of law that the City’s
    flood protection project was for a public use.
    B
    [¶16] Wieland argues the district court erred in ruling the proposed taking of
    her property was necessary for the public use.
    6
    [¶17] We have explained a court’s role in determining public necessity:
    To clarify the court’s role in the determination of the question of
    public necessity, we emphasize that the determination of a
    condemning authority to exercise the power of eminent domain for
    an authorized public use is solely a legislative or political question
    which is not subject to judicial review. . . . The court’s review of
    public necessity is limited to the question of whether the taking of
    the particular property sought to be condemned is reasonably
    suitable and usable for the authorized public use. Much latitude
    is given to the condemning authority to determine the location and
    the extent of the property to be acquired, and a taking is not
    objectionable merely because some other location might have been
    made or some other property obtained that would have been as
    suitable for the purpose. In the absence of bad faith, gross abuse
    of discretion, or fraud by the condemning authority in its
    determination that the property sought is necessary for the
    authorized use and is pursuant to specific statutory authority,
    such determination should not be disturbed by the courts.
    Behm, 
    2019 ND 139
    , ¶ 5, 
    927 N.W.2d 865
     (quoting Oakes Mun. Airport Auth.
    v. Wiese, 
    265 N.W.2d 697
    , 700 (N.D. 1978)). A district court may review
    additional evidence presented at eminent domain proceedings in deciding
    whether a local governing body abused its discretion in finding a taking was
    necessary. See City of Jamestown v. Leevers Supermarkerts, Inc., 
    552 N.W.2d 365
    , 371 (N.D. 1996).
    [¶18] The undisputed evidence in the record at the time of partial summary
    judgment established that after years of extensive professional studies on
    permanent flood protection for the Copperfield Court area, Wieland’s home
    could not remain at its location. Soil stability studies of the existing banks of
    Drain No. 27 indicated that a setback line was required to maintain safety and
    that nothing could be built between the setback line and Drain No. 27. Because
    of the setback distance from Drain No. 27 and the necessary maintenance area,
    the levee was required to be constructed on Wieland’s property. As the district
    court ruled, “[t]here was no evidence of any bad faith or fraud on the part of
    the City in seeking the acquisition of the Wieland property.” We conclude the
    7
    court correctly ruled as a matter of law that the proposed taking of Wieland’s
    property was necessary for the public use.
    C
    [¶19] Wieland argues the district court erred in ruling that permanent flood
    protection is a more necessary public use than any existing easements or drain
    dedication on her property. The question of greater necessity is for a court to
    resolve. See Bd. of Educ. of City of Minot v. Park Dist. of City of Minot, 
    70 N.W.2d 899
    , 905 (N.D. 1955). While generally the question of greater necessity
    is a finding of fact, here, the relevant facts are undisputed.
    [¶20] The record reflects that a drain dedication and drainage easement are
    located on Wieland’s property near Drain No. 27 and a utility easement is
    located on the street side of the property. It also appears the drain dedication,
    drain easement, and utility easement will not be repealed or extinguished by
    the levee. The evidence shows the levee is necessary to protect waters rising
    from the drain and to protect people and property in the area. The district
    court noted “[t]here was no evidence of any negative or adverse impact to other
    easements on the property by the construction of the earthen levee on the
    Wieland property.” We agree with the district court’s conclusion of law on this
    issue:
    [T]he existence of easements on the Wieland property are not in
    conflict with the intended use of the property by the City and that
    the easements and the earthen levee, when constructed, can co-
    exist and that, alternatively, permanent flood protection is a more
    necessary public use.
    [¶21] We conclude the City satisfied the elements necessary to take Wieland’s
    property.
    D
    [¶22] Wieland argues reversal is nevertheless required because the City failed
    to comply with a “statutory condition precedent to any condemnation action.”
    8
    [¶23] Wieland relies upon N.D.C.C. § 54-12-01.1, which at the relevant time
    provided:
    The attorney general, with the cooperation of appropriate state
    agencies, shall prepare pamphlets in readable format describing
    the eminent domain laws of this state. The pamphlets must
    include the reasons for condemnation, the procedures followed by
    condemnors as defined by section 32-15-01, how citizens may
    influence the condemnation process, and the rights of property
    owners and citizens affected by condemnation. The attorney
    general shall make copies of the pamphlets available to all
    condemnors who must be charged a price for the pamphlets
    sufficient to recover the costs of production. A condemnor shall
    present a copy of the pamphlet to a property owner prior to making
    an offer to purchase and initiating a condemnation action.
    The statute was amended in 2017 to delete the pamphlet requirement and to
    require condemnors to inform property owners of available online information
    contained on the Attorney General’s website. See 2017 N.D. Sess. Laws ch.
    366, § 4.
    [¶24] Although it is undisputed that Wieland did not receive a pamphlet from
    the City describing her rights, we reject her argument that receipt of a
    pamphlet is a condition precedent to an eminent domain action and reversal is
    therefore required. First, the pamphlet requirement in N.D.C.C. § 54-12-01.1
    is not mentioned in N.D.C.C. ch. 32-15, and the statute itself does not provide
    a remedy for a condemning authority’s failure to provide a pamphlet. ‘‘‘When
    no statutory remedy is provided for a statutory violation, we look to whether
    the victim of the violation was prejudiced’” because “‘absent a showing of
    prejudice, a statutory violation is not reversible error.’” Bayles v. N.D. Dep’t of
    Transp., 
    2015 ND 298
    , ¶ 17, 
    872 N.W.2d 626
     (quoting Johnson v. N.D. Workers
    Comp. Bureau, 
    539 N.W.2d 295
    , 298 (N.D. 1995)). Wieland was not prejudiced
    in this case because she was represented by an attorney during her
    negotiations with the City before the City made an offer. Wieland was aware
    of her rights through her attorney’s representation.
    9
    [¶25] We conclude the City’s failure to provide Wieland a pamphlet outlining
    her rights had no affect on the validity of the eminent domain action.
    III
    [¶26] Wieland argues this eminent domain action must be dismissed because
    the City failed to pay her post-judgment interest under N.D.C.C. § 28-20-34,
    which governs interest on judgments.
    [¶27] The record shows that judgment on the jury verdict was entered on
    January 15, 2019, and the City deposited $850,000 with the clerk of court on
    January 16, 2019, in accordance with N.D.C.C. § 32-15-29. An amended
    judgment awarding costs and fees was entered on March 13, 2019, and the City
    deposited an additional $89,044.32 with the clerk of court on March 13, 2019.
    Wieland argues the City’s failure to pay or deposit post-judgment interest at
    the legal rate along with the other money deposited by the City vitiates the
    condemnation proceedings because she has not received the entirety of just
    compensation due for the taking of her property. We reject Wieland’s
    argument that dismissal is warranted.
    [¶28] Wieland correctly claims the City was required to pay or deposit funds
    for the taking within 30 days of entry of final judgment. N.D.C.C. § 32-15-25.
    The City complied with this requirement by its deposits into court on January
    16 and March 13, 2019. Wieland also correctly claims N.D.C.C. § 32-15-26
    provides the district court with authority to “annul the entire proceedings” if
    the payment or deposit is not made as required. However, Wieland has
    provided no authority and we find none that require dismissal of the eminent
    domain action upon a failure to pay or deposit post-judgment interest. Rather,
    “[w]hen payments have been made as required in sections 32-15-25 and 32-15-
    26, the court must make a final order of condemnation, which must describe
    the property condemned and the purposes of such condemnation.” N.D.C.C. §
    32-15-27. That same section requires that “[a] copy of the order must be filed
    in the office of the recorder of the county and thereupon the property described
    therein shall vest in the plaintiff for the purposes therein specified.” Id.
    10
    [¶29] Section 32-15-29, N.D.C.C., addresses when a landowner can take or
    accept payment from the condemning authority or when the landowner can
    withdraw funds deposited by the judgment debtor. That section also limits the
    issues that can be reviewed during any subsequent appeal if the landowner
    accepts or withdraws funds. Id. However, neither that section nor others in
    ch. 32-15 address whether a landowner’s appeal in lieu of accepting or
    withdrawing funds requires the judgment debtor to pay post-judgment
    interest. Because Wieland has not raised this issue with the district court and
    briefed it for our review, we decline to expand Wieland’s request for relief
    beyond her argument this action must be dismissed due to the City’s failure to
    pay or deposit post-judgment interest.
    IV
    [¶30] It is unnecessary to address other arguments raised because they are
    unnecessary to the decision or are without merit. The judgment is affirmed.
    [¶31] Lisa Fair McEvers
    Daniel J. Crothers
    Jerod E. Tufte
    Jon J. Jensen
    Gerald W. VandeWalle, C.J.
    11