Lakeview Excavating, Inc. v. Dickey County , 2020 ND 67 ( 2020 )


Menu:
  •                 Filed 3/19/20 by Clerk of Supreme Court
    IN THE SUPREME COURT
    STATE OF NORTH DAKOTA
    
    2020 ND 67
    Lakeview Excavating, Inc.,                             Plaintiff and Appellant
    v.
    Dickey County and German Township,                  Defendants and Appellees
    No. 20190195
    Appeal from the District Court of Dickey County, Southeast Judicial District,
    the Honorable Daniel D. Narum, Judge.
    AFFIRMED.
    Opinion of the Court by Tufte, Justice.
    James M. Cailao (argued), Moorhead, Minnesota, and Jon R. Brakke (on brief),
    Fargo, North Dakota, for plaintiff and appellant.
    Austin T. Lafferty (argued) and Scott K. Porsborg (on brief), Special Assistant
    State’s Attorneys, Bismarck, North Dakota, for defendants and appellees.
    Lakeview Excavating, Inc. v. Dickey County
    No. 20190195
    Tufte, Justice.
    [¶1] Lakeview Excavating appeals a district court judgment dismissing its
    complaint against Dickey County and German Township (Defendants) for
    breach of contract, intentional fraud, and misrepresentation. The court ruled
    Lakeview breached its contracts with the Defendants, and held Lakeview’s tort
    claims against the Defendants were barred by the statute of limitations. We
    affirm.
    I
    [¶2] In the spring of 2012, the Defendants awarded to Lakeview three road
    construction project contracts funded by the Federal Emergency Management
    Agency (FEMA). The parties executed three identical contracts, one for each
    project. The contracts required Lakeview to provide the necessary documents
    to satisfy FEMA requirements for funding.
    [¶3] Lakeview had to use more material than was listed in the bid documents
    to complete the projects. Some of the material used by Lakeview was taken
    from private property without permission and resulted in litigation against
    Lakeview. See Taszarek v. Welken, 
    2016 ND 172
    , 
    883 N.W.2d 880
    ; Taszarek v.
    Lakeview Excavating, Inc., 
    2019 ND 168
    , 
    930 N.W.2d 98
    . Lakeview completed
    the road construction projects in August 2012.
    [¶4] In October 2016, Lakeview sued the Defendants for breach of contract,
    fraud, misrepresentation, and unlawful interference with business. Lakeview
    alleged the Defendants knew the material quantities listed in the bid
    documents provided by them were inaccurate when the documents were
    issued. Lakeview claimed that it relied on the quantities listed in the bid
    documents and that the shortage of materials available to Lakeview resulted
    in a significant cost increase and delayed the projects. Lakeview also claimed
    that because it had to devote more resources to the projects, it was unable to
    timely complete additional road construction work in Benson County.
    1
    [¶5] The Defendants denied Lakeview’s allegations and counterclaimed,
    alleging Lakeview breached the contracts because it failed to provide proper
    paperwork to satisfy FEMA requirements for funding. The Defendants claimed
    FEMA denied funding for the projects because Lakeview did not fulfill its
    obligations under the contracts.
    [¶6] Each party moved for summary judgment. The Defendants argued
    Lakeview’s claims were barred by the three-year statute of limitations. The
    Defendants asserted Lakeview knew in May 2012 that the Defendants were
    aware of the inaccurate material quantities. The Defendants also argued
    Lakeview breached the contracts for failing to provide documents necessary for
    FEMA funding. The Defendants stated FEMA’s denial of funding caused
    damages of $248,949.14.
    [¶7] The district court denied Lakeview’s motion and granted the Defendants’
    motion. The court concluded Lakeview’s tort claims against the Defendants
    were barred by the three-year statute of limitations. The court ruled Lakeview
    breached the contracts and entered a $249,600.64 judgment against Lakeview.
    II
    [¶8] Lakeview argues the district court erred in granting the Defendants’
    motion for summary judgment.
    [¶9] This Court’s standard of review for summary judgments is well
    established:
    Summary judgment is a procedural device under
    N.D.R.Civ.P. 56(c) for promptly resolving a controversy on the
    merits without a trial if there are no genuine issues of material
    fact or inferences that can reasonably be drawn from undisputed
    facts, or if the only issues to be resolved are questions of law. The
    party seeking summary judgment must demonstrate there are no
    genuine issues of material fact and the case is appropriate for
    judgment as a matter of law. In deciding whether the district court
    appropriately granted summary judgment, we view the evidence
    in the light most favorable to the opposing party, giving that party
    the benefit of all favorable inferences which can reasonably be
    2
    drawn from the record. A party opposing a motion for summary
    judgment cannot simply rely on the pleadings or on unsupported
    conclusory allegations. Rather, a party opposing a summary
    judgment motion must present competent admissible evidence by
    affidavit or other comparable means that raises an issue of
    material fact and must, if appropriate, draw the court’s attention
    to relevant evidence in the record raising an issue of material fact.
    When reasonable persons can reach only one conclusion from the
    evidence, a question of fact may become a matter of law for the
    court to decide. A district court’s decision on summary judgment is
    a question of law that we review de novo on the record.
    Brock v. Price, 
    2019 ND 240
    , ¶ 10, 
    934 N.W.2d 5
    (quoting Smithberg v.
    Smithberg, 
    2019 ND 195
    , ¶ 6, 
    931 N.W.2d 211
    ).
    III
    [¶10] Lakeview argues the district court erred in concluding what it alleges as
    its tort claims of actual fraud and intentional misrepresentation, negligent
    misrepresentation, and unlawful interference with business were barred by
    the statute of limitations.
    [¶11] Chapter 32-12.1, N.D.C.C., governs tort claims against political
    subdivisions. Finstad v. Ransom-Sargent Water Users, Inc., 
    2011 ND 215
    , ¶ 16,
    
    812 N.W.2d 323
    . An action brought under N.D.C.C. ch. 32-12.1 “must be
    commenced within three years after the claim for relief has accrued.” N.D.C.C.
    § 32-12.1-10.
    [¶12] Lakeview contends the limitations period began running in October 2014
    when a representative for the County stated the Defendants knew the material
    quantities listed in the bid documents were inaccurate when the documents
    were issued.
    Determining when a cause of action accrues is normally a question
    of fact, but it becomes a question of law when the material facts
    are undisputed. The statute of limitations generally begins to run
    from the commission of the wrongful act giving rise to the cause of
    action, unless an exception applies. The discovery rule is one
    exception, and under the discovery rule the accrual of a claim is
    3
    postponed until the plaintiff knew, or with the exercise of
    reasonable diligence should have known, of the wrongful act and
    its resulting injury. We have said, after acquiring knowledge of
    facts sufficient to put a person of ordinary intelligence on inquiry,
    a party has a responsibility to promptly find out what legal rights
    result from those facts, and failure to do so will be construed
    against the party. The discovery rule does not require full
    knowledge of the extent of an injury; rather, it only requires the
    party be aware of an injury.
    Ayling v. Sens, 
    2019 ND 114
    , ¶ 11, 
    926 N.W.2d 147
    .
    [¶13] Lakeview sued the Defendants in October 2016. The district court
    concluded Lakeview had notice of a possible claim and the statute of
    limitations began running on May 7, 2012:
    Lakeview’s tort claims arise from the allegation that the
    Defendants were aware the quantities were incorrect but
    deliberately circulated false bid documents nonetheless. It is
    indisputable from the deposition of Brian Welken that Lakeview
    learned the Defendants were aware the quantities were incorrect
    on May 7, 2012. At that moment, Lakeview was on notice that the
    Defendants were aware the quantities were incorrect. Lakeview
    had the responsibility to investigate and find out what legal
    ramifications may [have] resulted from the fact. As a result, the
    statute of limitations accrued in May 2012, and expired in May
    2015. This action was not brought until October 31, 2016. This is
    after the statute of limitations expired and the tort claims are
    therefore barred.
    [¶14] Lakeview contends the limitations period began running on October 21,
    2014. Charlie Russell, the County’s emergency management director, testified
    in a deposition that the County knew the material quantities listed in the bid
    documents were inaccurate when FEMA issued the documents. Lakeview
    claims Welken’s knowledge in May 2012 of the County’s awareness of
    inaccurate quantities was limited to a portion of a single project and not the
    whole project.
    4
    [¶15] In May 2012, Welken learned of the County’s awareness of material
    shortages during a conversation with Russell. At Welken’s deposition, he was
    asked, “[On May 7, 2012,] was your awareness of the material shortage
    confined to site 7-11?” Welken responded, “At that time it was confined to site
    7-11, but it was making us concerned about the rest of the projects after our
    conversation with Charlie [Russell].” Welken testified he became aware of
    additional material deficiencies as “the job was ongoing.” Although Welken
    knew in May 2012 about the County’s awareness of material deficiencies for
    only a portion of the project, he testified he was “concerned about the rest of
    the projects.” He testified he recognized additional shortages as the work
    continued. Welken’s initial knowledge in May 2012 and his subsequent
    knowledge of additional deficiencies as the job continued through its
    completion on August 15, 2012, should have led Lakeview to inquire whether
    the County knew of the material deficiencies for the whole project when it
    issued the bid documents. Ayling, 
    2019 ND 114
    , ¶ 11, 
    926 N.W.2d 147
    (stating
    the discovery rule does not require full knowledge of the extent of an injury).
    [¶16] We conclude the statute of limitations barred Lakeview’s tort claims
    when it sued the Defendants in October 2016. The district court did not err in
    granting the Defendants’ motion for summary judgment relating to Lakeview’s
    tort claims.
    IV
    [¶17] Lakeview asserts the district court erred in dismissing its breach of
    contract claim against the Defendants. Lakeview also argues the court erred
    in ruling Lakeview breached its contracts with the Defendants.
    [¶18] “A breach of contract is the nonperformance of a contractual duty when
    it is due.” Swenson v. Mahlum, 
    2019 ND 144
    , ¶ 19, 
    927 N.W.2d 850
    . A party
    asserting a breach of contract must prove: (1) the existence of a contract; (2) a
    breach of the contract; and (3) damages flowing from the breach.
    Id. 5 A
    [¶19] Lakeview’s complaint alleged, “The failure of Dickey County and German
    Township to allow reasonable accommodations for Lakeview to complete the
    Projects so that Lakeview could reallocate resources to Benson County constitutes
    a breach of the Defendants’ Contracts with Plaintiff.” Lakeview claims the
    material quantities contained in the bid documents were incorporated into the
    three contracts with the Defendants. Lakeview asserts the shortage of
    materials caused it to spend more time on the project and it was unable to
    complete the Benson County project on time, resulting in liquidated damages.
    [¶20] In dismissing Lakeview’s breach of contract claim, the district court
    concluded:
    The contracts between the parties lack any clause or
    provision which required the Defendants to allow reasonable
    accommodations for Lakeview’s work on other projects. Further,
    any alleged breach due to the incorrect quantities cannot be a
    breach because the contracts do not guarantee a specific quantity
    or even a correct quantity. Lakeview claims there is a genuine
    dispute of fact as to whether the Defendants’ alleged utilization of
    incorrect quantities is a breach of contract; however, there is no
    contractual provision that would have been breached by such.
    Accordingly, there is no genuine dispute of fact and Lakeview’s
    claim for breach of contract cannot succeed.
    [¶21] We agree with the district court. The contracts do not include a term
    specifying the material quantities for the job, nor do they require
    accommodations allowing Lakeview to work on other projects. The district
    court did not err in granting the Defendants’ motion for summary judgment on
    Lakeview’s breach of contract claim.
    B
    [¶22] Lakeview asserts the district court erred in concluding Lakeview
    breached its contracts with the Defendants.
    [¶23] The three contracts state, “The Contractor will be responsible for all
    documentation and paper work required to satisfy the FEMA requirements.”
    6
    FEMA denied funding for the road construction projects because “the
    contractor [Lakeview] failed to obtain the appropriate bonding required for the
    contract,” and Lakeview used materials from private property without
    permission and without completing a cultural survey at the site where the
    materials were taken. The district court ruled that under the contracts’
    language, there was no genuine dispute of fact that Lakeview breached its
    obligations under the contracts because it did not provide the required
    documents necessary for FEMA funding.
    [¶24] Lakeview does not dispute it did not obtain the bonds required by FEMA.
    Lakeview argues the Defendants should have requested or required Lakeview
    to obtain or submit the bonds required for FEMA funding. Lakeview also
    asserts that the County later accepted responsibility for not obtaining the
    bonds in its communications with FEMA.
    [¶25] We are not persuaded by Lakeview’s arguments. The three contracts
    plainly state “[Lakeview] will be responsible for all documentation and paper
    work required to satisfy the FEMA requirements” for funding. See N.D.C.C.
    § 9-07-02 (stating the “language of a contract is to govern its interpretation if
    the language is clear and explicit”). The contracts do not require the
    Defendants to request that Lakeview obtain or submit additional bonds. We
    conclude the district court did not err in granting summary judgment on the
    Defendants’ breach of contract claim.
    V
    [¶26] Lakeview’s remaining arguments are either without merit or not
    necessary to our decision. The judgment is affirmed.
    [¶27] Jerod E. Tufte
    Daniel J. Crothers
    Lisa Fair McEvers
    Gerald W. VandeWalle
    Jon J. Jensen, C.J.
    7