Schulz v. Helmers , 2021 ND 158 ( 2021 )


Menu:
  •                                                                                      FILED
    IN THE OFFICE OF THE
    CLERK OF SUPREME COURT
    AUGUST 19, 2021
    STATE OF NORTH DAKOTA
    IN THE SUPREME COURT
    STATE OF NORTH DAKOTA
    
    2021 ND 158
    Edwin Schulz,                                         Plaintiff and Appellant
    v.
    Adam Helmers,                                        Defendant and Appellee
    No. 20210025
    Appeal from the District Court of Grand Forks County, Northeast Central
    Judicial District, the Honorable Jay D. Knudson, Judge.
    AFFIRMED.
    Opinion of the Court by Crothers, Justice.
    Larry J. Richards, Grand Forks, ND, for plaintiff and appellant.
    Victoria A. Thoreson (argued) and Michael J. Morley (on brief), Grand Forks,
    ND, for defendant and appellee.
    Schulz v. Helmers
    No. 20210025
    Crothers, Justice.
    [¶1] Edwin Schulz appeals from a judgment following a bench trial on the
    damages to his barn, pole barn and shed. He argues the district court applied
    the wrong measure of damages in his breach of contract claim against Adam
    Helmers, whom he claims caused a fire that destroyed his buildings. We affirm.
    I
    [¶2] Schulz sued Helmers for negligence and breach of contract following a
    fire that destroyed a barn, pole barn and shed owned by Schulz. At the time of
    the fire, Schulz was leasing the farmstead to Helmers, including the three
    buildings. Helmers moved for summary judgment claiming Schulz had no
    damages and, in the alternative, requested the court rule as a matter of law
    that under either a contract or tort theory damages were limited to the
    diminution in value of the property. The district court denied the request to
    dismiss the case but limited damages on both claims to the diminution in value.
    Helmers subsequently admitted liability for the fire but denied “the nature and
    extent of the injuries and damages being claimed by [Schulz].” After a bench
    trial, the court awarded Schulz $21,663.57, offset by a payment under his
    insurance policy.
    II
    [¶3] The standard for reviewing a district court’s decision on a motion for
    summary judgment is well established:
    “Summary judgment is a procedural device for the prompt
    resolution of a controversy on the merits without a trial if there
    are no genuine issues of material fact or inferences that can
    reasonably be drawn from undisputed facts, or if the only issues to
    be resolved are questions of law. A party moving for summary
    judgment has the burden of showing there are no genuine issues
    of material fact and the moving party is entitled to judgment as a
    matter of law. In determining whether summary judgment was
    appropriately granted, we must view the evidence in the light most
    1
    favorable to the party opposing the motion, and that party will be
    given the benefit of all favorable inferences which can reasonably
    be drawn from the record. On appeal, this Court decides whether
    the information available to the district court precluded the
    existence of a genuine issue of material fact and entitled the
    moving party to judgment as a matter of law. Whether the district
    court properly granted summary judgment is a question of law
    which we review de novo on the entire record.”
    Three Aces Props. LLC v. United Rentals (N. Am.), Inc., 
    2020 ND 258
    , ¶ 8, 
    952 N.W.2d 64
     (quoting Feltman v. Gaustad, 
    2020 ND 89
    , ¶ 7, 
    942 N.W.2d 844
    ).
    [¶4] The district court’s conclusions of law are fully reviewable. Stuber v.
    Engel, 
    2017 ND 198
    , ¶ 10, 
    900 N.W.2d 230
    . The interpretation of a contract to
    determine its legal effect is a question of law, which is fully reviewable. Three
    Aces, 
    2020 ND 258
    , ¶ 10. General rules of contract interpretation apply to
    leases. 
    Id.
     We review the district court’s factual findings after a bench trial
    under the clearly erroneous standard. Stuber, ¶ 10. A finding of fact is clearly
    erroneous if it is induced by an erroneous view of the law, if no evidence
    supports the findings, or if, on the entire record, we are left with a definite and
    firm conviction a mistake has been made. 
    Id.
     We do not reweigh conflicts in
    evidence, and the district court’s choice between two permissible views of the
    weight of the evidence is not clearly erroneous. 
    Id.
     “The determination of the
    amount of damages caused by a breach of contract is a finding of fact.” Three
    Aces, ¶ 10.
    III
    [¶5] Schulz does not challenge the district court’s measure of damages on his
    tort claim; thus our review is limited to the contract claim. On that claim
    Schulz argues the proper measure of damages is the cost to replace the
    buildings, not the diminution in value. He contends that damages arising from
    a breach of contract are governed by terms of the lease, which provides: “The
    tenant will maintain the buildings and equipment during his tenancy in as
    good condition as at the beginning, normal wear and depreciation beyond
    tenant’s control excepted.” Schulz asserts this language imposes on Helmers a
    duty to replace the destroyed buildings.
    2
    [¶6] Section 32-03-09, N.D.C.C., describes the measure of damages for a
    breach of contract, stating:
    “For the breach of an obligation arising from contract, the measure
    of damages, except when otherwise expressly provided by the laws
    of this state, is the amount which will compensate the party
    aggrieved for all the detriment proximately caused thereby or
    which in the ordinary course of things would be likely to result
    therefrom. No damages can be recovered for a breach of contract if
    they are not clearly ascertainable in both their nature and origin.”
    [¶7] At issue here is Helmers’ obligation to maintain the leased property.
    “The word ‘maintain’ in its ordinary sense is defined as ‘to keep in a state of
    repair.’” Three Aces, 
    2020 ND 258
    , ¶ 30. After the judgment was issued in this
    case, we decided Three Aces, which addressed for the first time the appropriate
    measure of damages for a breach of contract claim related to the failure to
    repair under a lease. Id. at ¶ 15. The lease in Three Aces included a
    maintenance provision, stating, “Licensee shall maintain the parking area and
    fence, such parking area and fence shall be surrendered in a condition similar
    to that existing at the time Licensee took occupancy, subject to wear and tear
    caused by the ordinary operation of Licensee’s business on the Premises.” Id.
    at ¶ 11. The district court concluded the tenant had a duty to maintain the
    parking area and to surrender the parking area in a condition similar to that
    which existed when the lease began, and the tenant breached the lease by
    failing to repair the parking area. Id. at ¶ 12. However, the court determined
    the landlord was not entitled to damages for the breach because there was no
    diminution of value in the property as a result of the breach and any damages
    were mitigated by redevelopment of the property. Id. at ¶ 6.
    [¶8] On appeal, we reviewed the two measures of damages, stating:
    “We agree that the lesser of the cost to repair or the
    diminution in value is the proper measure of damages for a breach
    of a duty to repair in a lease. The rule for damages in construction
    contract cases is based on avoiding windfalls and economic waste,
    and the same rationale applies to damages for a breach of the duty
    to repair related to a lease. The cost to repair generally will be the
    correct measure, but it is only a place to start in determining the
    3
    correct amount of damages. The non-breaching party should not
    be awarded an amount that will put them in a better position than
    they would have been in if the breach never occurred. We conclude
    either the cost of repair or the diminution of value may be an
    appropriate measure of damages in this case.”
    Three Aces, 
    2020 ND 258
    , ¶ 18. Because the property was worth the same
    regardless of whether the repairs were made to the parking area, no damages
    were recoverable under the diminution of value measure. Id. at ¶ 19. However,
    the cost to repair the parking area would have been approximately $2.7
    million. Id. at ¶ 20. We concluded, “[T]he cost of repairing the property was
    significantly higher than the diminution in value. Thus repairing the property
    was economically impractical. Awarding damages based on the cost to repair
    would result in [the landlord] receiving a windfall. Diminution of value was
    the correct measure of damages in this case.” Id.
    [¶9] Here, Helmers admitted liability for causing the fire. Because Helmers
    can no longer “maintain the buildings and equipment during his tenancy in as
    good condition as at the beginning,” he breached his lease with Schulz, and
    Schulz is due damages for the breach. Section 32-03-09, N.D.C.C., provides the
    general measure of damages for breaching a contract. Specifically in the case
    of breaching a duty to repair in a lease, Three Aces construed this statute to
    mean the proper measure of damages is the lesser of the cost to repair and the
    diminution in value.
    [¶10] The district court found the total diminution in value of the three
    buildings was $21,663.57. The court noted that although the property as a
    whole may have a higher diminution in value than the combined diminution
    in value of the individual buildings, Schulz failed to present sufficient, credible
    evidence of a higher amount.
    [¶11] At trial, Helmers’ valuation expert testified the replacement costs would
    have been $83,615.41 for the barn, $31,247.54 for the pole barn and $14,488.77
    for the garage/shed, totaling $129,351.72. Thus, the replacement cost is
    approximately $107,688 more than the diminution of value measure. Similar
    to Three Aces, the cost to repair or replace is significantly higher than the
    4
    diminution of value, and Schulz would receive a windfall if Helmers were
    required to replace the buildings. Accordingly, the diminution of value is the
    appropriate measure of damages for Helmers’ breach of the lease.
    [¶12] The district court concluded N.D.C.C. § 32-03-09.1 applied to the breach
    of contract claim, which provides the measure of damages for an injury to
    property not arising from contract:
    “The measure of damages for injury to property caused by the
    breach of an obligation not arising from contract, except when
    otherwise expressly provided by law, is presumed to be the
    reasonable cost of repairs necessary to restore the property to the
    condition it was in immediately before the injury was inflicted and
    the reasonable value of the loss of use pending restoration of the
    property, unless restoration of the property within a reasonable
    period of time is impossible or impracticable, in which case the
    measure of damages is presumed to be the difference between the
    market value of the property immediately before and immediately
    after the injury and the reasonable value of the loss of use pending
    replacement of the property. Restoration of the property shall be
    deemed impracticable when the reasonable cost of necessary
    repairs and the reasonable value of the loss of use pending
    restoration is greater than the amount by which the market value
    of the property has been diminished because of the injury and the
    reasonable value of the loss of use pending replacement.”
    N.D.C.C. § 32-03-09.1 (emphasis added). Although this statute is similar to the
    rule established in Three Aces, the court used it in error because the statute
    applies to a breach of an obligation not arising from contract. Because the claim
    here is for breach of contract, N.D.C.C. § 32-03-09 is the applicable damages
    statute, and Three Aces, although decided after judgment in this case,
    addresses the appropriate measure of damages for a breach of contract claim
    related to the failure to repair under a lease. However, the court’s
    misapplication of the law is harmless error because diminution in value is the
    proper measure and the result is the same whether N.D.C.C. § 32-03-09.1 or
    the rule in Three Aces is applied. See Schmidt v. City of Minot, 
    2016 ND 175
    ,
    ¶ 16, 
    883 N.W.2d 909
     (stating that “[w]e will not set aside a correct result
    5
    merely because the district court’s reasoning is incorrect if the result is the
    same under the correct law and reasoning”).
    IV
    [¶13] We affirm the judgment, concluding the diminution of value is the
    appropriate measure of damages for Helmers’ breach of the lease.
    [¶14] Jon J. Jensen, C.J.
    Gerald W. VandeWalle
    Daniel J. Crothers
    Lisa Fair McEvers
    Jerod E. Tufte
    6
    

Document Info

Docket Number: 20210025

Citation Numbers: 2021 ND 158

Judges: Crothers, Daniel John

Filed Date: 8/19/2021

Precedential Status: Precedential

Modified Date: 8/19/2021