Shift Services v. Ames Savage Water Solutions , 2023 ND 237 ( 2023 )


Menu:
  •                                                                                FILED
    IN THE OFFICE OF THE
    CLERK OF SUPREME COURT
    DECEMBER 15, 2023
    STATE OF NORTH DAKOTA
    IN THE SUPREME COURT
    STATE OF NORTH DAKOTA
    
    2023 ND 237
    Shift Services, LLC,                                    Plaintiff and Appellant
    v.
    Ames Savage Water Solutions, LLC,                      Defendant and Appellee
    No. 20230217
    Appeal from the District Court of McKenzie County, Northwest Judicial
    District, the Honorable Robin A. Schmidt, Judge.
    AFFIRMED.
    Opinion of the Court by Jensen, Chief Justice.
    Jordon J. Evert, Williston, ND, for plaintiff and appellant.
    Trevor A. Hunter, Williston, ND, for defendant and appellee.
    Shift Services v. Ames Savage Water Solutions
    No. 20230217
    Jensen, Chief Justice.
    [¶1] Shift Services, LLC appeals from a judgment dismissing its breach of
    contract claim asserted against Ames Savage Water Solutions and the
    termination of a construction lien. Shift argues the district court erred when it
    concluded a change of circumstances did not exist relating to the contract
    between Shift and Ames; erred in finding that Ames did not approve and
    authorize additional work to be performed by Shift; erred in finding that the
    contract was not modified by the parties; and erred in interpreting and
    applying the law governing contracts and agency principles. We affirm.
    I
    [¶2] In February 2020, Ames accepted a written bid provided by Shift to
    repair a liner inside a water tank operated by Ames. The bid contained a fixed
    price of $39,500.00 which was to include all labor, material, and travel time to
    remove and install the new liner.
    [¶3] Prior to submitting the bid, Shift visited the water tank where “a thin
    crust of ice” was observed on the surface of the water left inside. Around the
    middle of March 2020, Shift commenced work on the water tank. After removal
    of a panel, a thicker amount of ice was observed.
    [¶4] On March 16, 2020, Shift sent Ames’ operational manager a text stating,
    “[t]he tank by Mandaree has a foot to two feet of ice in it also. Would you want
    us to remove it like we did the last one so you can get it done this week?” Ames’
    operational manager responded, “Yes, please.” This was the only written
    communication between the parties regarding ice removal. Shift attempted to
    remove the ice via a mini excavator but was unable to continue after the mini
    excavator fell into a sump hole at the bottom of the tank.
    [¶5] After the failed attempt to remove the ice with the mini excavator, shift
    initiated a conference call with Ames to inquire about subcontracting a hot oil
    truck company to melt the ice. During the conference call, the parties’
    1
    discussion was limited to the hourly rate of hot oil trucks. At that time, Shift
    believed the quantity of ice in the tank and the sump hole created unforeseen
    and unexpected circumstances giving Shift authority to proceed with a costly
    and time-consuming method of melting the ice.
    [¶6] Upon completion of the project, Ames paid the contracted amount. Shift
    also presented Ames with a bill for an additional $31,705.00 related to the ice
    removal. Ames refused to pay the additional $31,705.00 arguing it did not
    authorize the use of the hot oil trucks, rates, labor charges, or equipment
    charges outside the bid.
    [¶7] After Ames refused to pay the additional $31,705.00, Shift recorded a
    construction lien against the subject property and initiated an action alleging
    breach of contract and seeking to foreclose on the lien. The issue presented to
    the district court was whether the contract was modified to include the costs
    associated with the ice removal. The court found the original contract between
    Ames and Shift had not been modified because there was a lack of mutual
    assent to compensate Shift for the additional ice removal work and therefore,
    Ames did not breach the contract. The court dismissed Shift’s breach of
    contract claim and terminated the construction lien. Shift appealed.
    II
    [¶8] Shift advances numerous arguments challenging the district court’s
    factual determinations regarding mutual assent and modification. As an initial
    matter, we note that Shift does not challenge the formation or existence of the
    original contract and did not seek to render the initial contract void or voidable.
    Shift limits its argument to the assertion the contract was modified to include
    costs associated with ice removal and challenges the finding Ames did not
    approve and authorize additional ice removal work to be performed by Shift.
    [¶9] Modifications of a contract generally require the mutual assent of the
    parties. Spilovoy v. Gliege, 
    298 N.W.2d 377
    , 379 (N.D. 1980); 17A Am.Jur.2d
    Contracts § 500 (2004); N.D.C.C. §§ 9-09-05, 9-09-06. The determination of
    whether the required mutual assent existed is a question of fact which will not
    be set aside on appeal unless it is clearly erroneous. Hartman v. Grager, 2021
    
    2 ND 160
    , ¶¶ 14, 27, 
    964 N.W.2d 482
    . A finding of fact is clearly erroneous if it
    is not supported by any evidence, if, although there is some evidence to support
    the finding, a reviewing court is left with a definite and firm conviction a
    mistake has been made, or if the finding is induced by an erroneous conception
    of the law. Pfeifle v. Tanabe, 
    2000 ND 219
    , ¶ 7, 
    620 N.W.2d 167
    . “A trial court’s
    choice between two permissible views of the weight of the evidence is not
    clearly erroneous, and simply because we may have viewed the evidence
    differently does not entitle us to reverse the trial court.” Edward H. Schwartz
    Constr., Inc. v. Driessen, 
    2006 ND 15
    , ¶ 6, 
    709 N.W.2d 733
     (quoting Brandt v.
    Somerville, 
    2005 ND 35
    , ¶ 12, 
    692 N.W.2d 144
    ).
    [¶10] Although there may have been contrary evidence provided during the
    trial, the district court was provided evidence supporting a finding there was
    no mutual intent between Shift and Ames to modify their original agreement.
    That evidence included testimony Shift never disclosed to Ames that Shift
    intended to add an additional charge for the time, materials, or equipment to
    account for the increased cost associated with the removal of the ice. The
    evidence also included testimony that Shift did not identify the subcontractor
    it intended to use to assist with the removal of the ice, what equipment would
    be used during the removal process, the estimated number of hours that would
    be involved, or that the increased work would result in additional charges to
    Ames. The court was free to choose between any conflicts in the evidence in
    making its findings, there is evidence in the record to support the findings, the
    court did not misapply the law, and we are not left with a definite and firm
    conviction a mistake was made in the findings. We conclude the court’s finding
    there was insufficient mutual assent to modify the contract was not clearly
    erroneous.
    III
    [¶11] The district court’s finding there was a lack of mutual assent to modify
    the terms of the parties’ agreement was not clearly erroneous. We decline to
    address Shift’s remaining arguments as either unnecessary to our decision or
    without merit. We affirm.
    3
    [¶12] Jon J. Jensen, C.J.
    Daniel J. Crothers
    Lisa Fair McEvers
    Jerod E. Tufte
    Douglas A. Bahr
    4
    

Document Info

Docket Number: 20230217

Citation Numbers: 2023 ND 237

Judges: Jensen, Jon J.

Filed Date: 12/15/2023

Precedential Status: Precedential

Modified Date: 12/15/2023