Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist. ( 2015 )


Menu:
  •                                      - 642 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    Facilities Cost M anagement Group, LLC,
    appellee and cross-appellant, v. Otoe County
    School District 66-0111, also known as
    Nebraska City Public Schools,
    appellant and cross-appellee.
    ___ N.W.2d ___
    Filed August 21, 2015.    No. S-14-380.
    1.	 Summary Judgment. An appellate court will affirm a lower court’s
    grant of summary judgment if the pleadings and admitted evidence show
    that there is no genuine issue as to any material facts or as to the ulti-
    mate inferences that may be drawn from the facts and that the moving
    party is entitled to judgment as a matter of law.
    2.	 Contracts. The meaning of a contract and whether a contract is ambigu-
    ous are questions of law.
    3.	 Judgments: Appeal and Error. When reviewing questions of law, an
    appellate court has an obligation to resolve the questions independently
    of the conclusion reached by the trial court.
    4.	 Jury Instructions: Appeal and Error. Whether a jury instruction is
    correct is a question of law, which an appellate court independently
    decides.
    5.	 Contracts. In interpreting a contract, a court must first determine, as a
    matter of law, whether the contract is ambiguous.
    6.	 ____. A contract written in clear and unambiguous language is not sub-
    ject to interpretation or construction and must be enforced according to
    its terms.
    7.	 Contracts: Words and Phrases. A contract is ambiguous when a word,
    phrase, or provision in the contract has, or is susceptible of, at least two
    reasonable but conflicting interpretations or meanings.
    8.	 Contracts. The meaning of an ambiguous contract is generally a ques-
    tion of fact.
    9.	 ____. Extrinsic evidence is not permitted to explain the terms of a con-
    tract that is not ambiguous.
    - 643 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    10.	 Contracts: Intent. When a contract is unambiguous, the intentions of
    the parties must be determined from the contract itself.
    11.	 Contracts. A court is not free to rewrite a contract or to speculate as to
    terms of the contract which the parties have not seen fit to include.
    12.	 ____. When a court has determined that ambiguity exits in a document,
    an interpretive meaning for the ambiguous word, phrase, or provision in
    the document is a question of fact for the fact finder.
    13.	 Contracts: Parol Evidence. A written instrument is open to explanation
    by parol evidence when its terms are susceptible to two constructions or
    where the language employed is vague or ambiguous.
    14.	 Jury Instructions: Proof: Appeal and Error. In an appeal based on
    a claim of an erroneous jury instruction, the appellant has the burden
    to show that the questioned instruction was prejudicial or otherwise
    adversely affected a substantial right of the appellant.
    Appeal from the District Court for Douglas County:
    J. Michael Coffey, Judge. Reversed and remanded for a
    new trial.
    Larry E. Welch, Sr., Larry E. Welch, Jr., and Damien J.
    Wright, of Welch Law Firm, P.C., for appellant.
    Steven E. Achelpohl and John A. Svoboda, of Gross &
    Welch, P.C., L.L.O., for appellee.
    Heavican, C.J., Wright, Connolly, McCormack, Miller-
    Lerman, and Cassel, JJ.
    Miller-Lerman, J.
    NATURE OF CASE
    Otoe County School District 66-0111, also known as
    Nebraska City Public Schools (the District), and Facilities
    Cost Management Group, LLC (FCMG), entered into a con-
    tract wherein FCMG would provide architectural, represent­
    ative, and managerial services in connection with the con-
    struction and renovation of three schools within the District.
    FCMG filed an amended complaint in the district court for
    Douglas County against the District, alleging that the District
    had breached the contract by failing to pay the full amount
    due under the contract, and FCMG sought approximately
    - 644 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    $2 million in damages. The parties filed cross-motions for
    partial summary judgment; the District generally argued that
    the contract was ambiguous, specifically sections 11.2 and
    12.7, and FCMG generally argued that the contract was not
    ambiguous. The district court granted FCMG’s motion and
    denied the District’s motion based upon its determinations
    that sections 11.2 and 12.7 were not ambiguous due to their
    language and the parties’ course of dealings.
    After a jury trial, the district court entered judgment on the
    jury’s verdict for FCMG in the amount of $1,972,993. The
    district court denied the District’s motion for judgment not-
    withstanding the verdict or for new trial. The District appeals,
    and FCMG cross-appeals. We determine that the district court
    did not err when it determined that section 12.7 of the contract
    is not ambiguous, but it erred when it determined that section
    11.2 is not ambiguous. Accordingly, the court committed preju-
    dicial error when it gave jury instruction No. 2, which stated
    that “the contract in this case is not ambiguous.” As explained
    below, we reverse, and remand for a new trial.
    STATEMENT OF FACTS
    The threshold issue presented in this appeal is whether
    sections 11.2 and 12.7 of the contract are ambiguous. The
    contract is based on a 1987 version of the American Institute
    of Architects’ “Standard Form of Agreement Between Owner
    and Architect.” As the Court of Special Appeals of Maryland
    has observed:
    The standard form contracts drafted by the [American
    Institute of Architects (AIA)] are widely used. One
    author has stated that the AIA documents are the most
    widely used standard form contracts in the construction
    industry. See 1 Steven G.M. Stein, Construction Law,
    ¶ 3.02[1][b] (Matthew Bender 1999)(footnote omitted)
    (stating that AIA forms “have the longest history and
    are the most widely used and well known of the stan-
    dard forms.”).
    - 645 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    Notre Dame v. Morabito, 
    132 Md. App. 158
    , 174, 
    752 A.2d 265
    , 273-74 (2000). However, the parties customized some
    sections of the contract, including sections 11.2 and 12.7 at
    issue in this case. The contract defines the District as the
    “Owner” and FCMG as the “Architect” even though the activi-
    ties of FCMG were not limited to architectural services.
    Pertinent sections of the contract are quoted below. Section
    11.2, one of the customized provisions of the contract, is titled
    “BASIC COMPENSATION,” and it provides:
    Fees shall be as outlined in the attached Recommended
    Compensation schedule as applicable to each component
    facility of the Project and shall be included in various
    categories of the Project Budget for Basic Services for
    Site and Construction work, Master Planning, Equipment,
    Additional Services for Remodeling and Additions,
    and Contingency allowances. Corresponding Project
    Reimbursable Expenses and costs for [the District’s]
    Representative/Project Management services shall also
    be paid as included in the Project Budget. These fees and
    costs are intended to be converted to Lump Sum amounts
    with the initial approval by the [District] and [FCMG] of
    the Project Scope, Budget, and concept to be advanced
    for funding. Lump Sum amounts and inclusions shall
    remain effective for the duration of the Project(s), except
    in the event of approved changes in the scope of work or
    alternatives to be bid adding two percent or more to the
    scope. In such event the Lump Sum fees and costs shall
    be increased proportionately to reflect the full percentage
    of changes.
    A grid is attached to most copies of the contract in the record.
    The grid appears to be a schedule of fees for various services.
    Section 12.7, another customized provision of the contract,
    is titled “RESPONSE TO DISTRICT’S REQUEST FOR
    PROPOSAL,” and it provides:
    The Architect’s Response to the District’s Request
    for Proposal is attached to this Agreement for general
    - 646 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    reference purposes including overviews of projects and
    serv­ices. [The District’s] approvals following execution
    of this Agreement and related to the scope of work on
    the individual projects and corresponding portions of
    Project Budgets during the various Phases shall incor-
    porate applicable adjustments through the projects [sic]
    development.
    The “Architect’s Response to the District’s Request for
    Proposal” referred to in section 12.7 is not attached to any
    copy of the contract in the record, and there is no such docu-
    ment bearing the title “Architect’s Response to the District’s
    Request for Proposal.” The parties may have been referring to
    exhibit 72, which is FCMG’s 72-page proposal submitted in
    response to the District’s request for proposals, and possibly
    in addition, exhibit 19, which is 21 pages of questions and
    answers exchanged between the parties.
    With respect to the background facts of this case, in March
    2007, the District issued a request for proposals in connec-
    tion with the construction and renovation of three schools
    within its school district. In response to the District’s request
    for proposals, FCMG submitted its proposal dated March 29,
    2007. FCMG’s proposal is in the record as exhibit 72. In its
    proposal, FCMG stated that it was to serve as the project’s
    architect, the District’s representative, and the project’s man-
    ager. Specifically, the proposal stated:
    FCMG is not a traditional architectural firm. We spe-
    cialize as independent Owner’s Representatives for pro-
    gram and project development and management services.
    From this independent perspective, we offer your District
    an opportunity to better control the costs, extended func-
    tion, and flexibility within the proposed facilities. We
    have the unique ability to offer guaranteed maximum cost
    options to assure that the bonds requested and approved
    by the voters will do the job . . . so that they know before
    they vote what they will receive . . . and also know that
    - 647 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    the quality will be consistent with today’s version of the
    Middle School success.
    With respect to rates for the project, FCMG’s proposal
    stated:
    FCMG negotiates its fees with its clients in order
    to provide the best value for the dollar and to respond
    directly to the nature of the actual projects selected to be
    funded or further developed. We utilize Lump Sum fees
    which are incorporated in the projects [sic] budgets. The
    examples in this Response each include allowances for all
    fees and expenses.
    ....
    We guarantee that the aggregate fees of our firm
    together with the Technical Services Consultants will
    not exceed typically published guidelines for full Basic
    Services of the entire professionals [sic] team.
    ....
    We encourage you to consider fees on a cost per square
    foot basis rather than simple percentage. Because our
    projects are typically 15% or more less in construction
    costs, technical fees typically follow suit and are less per
    square foot. Again, we encourage lump sum fees that pro-
    duce the lowest bottom line at project completion.
    After receiving FCMG’s proposal, the board of directors
    of the District sent FCMG a series of written questions con-
    cerning the proposal, and FCMG provided its answers in a
    document dated June 22, 2007. These questions and answers
    are in the record as exhibit 19. In response to the question
    “[d]o you have a guaranteed maximum price for the project,”
    FCMG stated:
    Yes. The $20.76 million figure provided the Board
    in our proposal response is an example of a guaran-
    teed maximum funding equal or greater in square foot-
    age and quality to that which the District had proposed
    in its recent study. Another alternative, one which pro-
    vided very substantially improved flexibility and square
    - 648 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    footage for educational delivery was also provided at a
    much lower cost than the recent study by others.
    Guaranteed maximum price options are clearly avail-
    able to the District in our planning approach. Following
    establishment of the exact scope of the work by the Board
    as it assesses various options and alternatives, we can be
    in a position to set maximum required bond proceeds and
    related funding for the group of projects.
    ....
    The budgets offering a nearly $4 million savings which
    FCMG presented to [the District] represents a guaranteed
    maximum price approach matched to input provided by
    the District through its previous study for equivalent or
    greater footage and quality for the group of projects.
    The District and FCMG entered into the contract, dated
    July 18, 2007, of which pertinent sections are quoted above.
    A bond to fund the project successfully passed in the fall of
    2007, and the project subsequently commenced. During com-
    pletion of the project, the board of the District made various
    changes to the project. FCMG at various times presented the
    District’s board with budget grids regarding the project, and
    FCMG regularly sent invoices to the District. The invoices
    were for work performed by various contractors and FCMG’s
    fees. The District paid the invoices from March 2008 until
    May 2009, when it stopped paying the invoices because it
    learned that the project was almost $2 million over budget.
    The parties seem to agree that contractors were paid and that
    the subject matter of this case is limited to amounts claimed
    by FCMG.
    On June 29, 2012, FCMG filed its complaint against the
    District alleging breach of contract and seeking $2,016,747.52
    in damages plus interest, attorney fees, and costs. FCMG filed
    an amended complaint on February 11, 2013, in which it added
    its claim of unjust enrichment. The District filed its answer
    to the amended complaint on March 13, in which it gener-
    ally denied FCMG’s allegations, raised various affirmative
    - 649 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    defenses, and brought counterclaims which it later abandoned.
    The unjust enrichment claim was abandoned at trial.
    The parties filed cross-motions for partial summary judg-
    ment on the issue of whether the contract was ambiguous,
    specifically sections 11.2 and 12.7, quoted above. The District
    reads the contract as providing for a guaranteed maximum
    price; but failing that interpretation, the District argued that
    the contract was ambiguous as to whether the parties intended
    to fix a guaranteed maximum price for the budget and, in the
    event increases were permitted, the method as to how to cal-
    culate FCMG’s fees for increases to the scope of the project.
    FCMG argued that the contract was not ambiguous, based
    on the language of the contract. FCMG further argued that
    the parties’ conduct during performance of the contract indi-
    cated the true intent of the parties as to the payment of costs
    and fees.
    After a hearing, the district court concluded that neither
    section 11.2 nor section 12.7 was ambiguous. The district
    court filed its order on February 11, 2014, in which it granted
    FCMG’s motion for partial summary judgment and denied the
    District’s motion for partial summary judgment. In its order,
    with regard to section 12.7, the court stated that “[o]ne issue
    is the effect to be given to [FCMG’s response] submitted . . .
    in response to questions from the [District] regarding the proj-
    ect.” The court quoted section 12.7 of the contract and found
    that “while the words ‘for general reference purposes’ are pos-
    sibly ambiguous they do not equate to incorporating [FCMG’s
    response] into the terms of the contract between [FCMG] and
    [the District] and, therefore, cannot be a basis to determine
    fees and costs pursuant to the contract.” With respect to sec-
    tion 11.2, the district court stated that the District routinely
    paid invoices submitted by FCMG from March 2008 through
    May 2009, and that therefore, “there was a course in dealing
    between the parties which evidences a lack of ambiguity in
    [section 11.2 of] the contract.” Accordingly, the court granted
    FCMG’s motion and denied the District’s motion for partial
    summary judgment.
    - 650 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    A jury trial was held February 10 through 14, 2014. When
    FCMG rested its case, the District moved for directed verdict,
    which the district court denied. At the close of all the evidence,
    both parties moved for directed verdict, and the court denied
    both motions. The case was submitted to the jury, and jury
    instruction No. 2 provided in pertinent part:
    The Court has determined as a matter of law that
    the following facts exist and that you must accept them
    as true:
    1. That the parties entered into a contract related to
    the construction/remodeling of three facilities for the
    [District] on August 9, 2007.
    2. That the Court has determined that the contract in
    this case is not ambiguous.
    (Emphasis supplied.)
    After trial, the jury returned a verdict in favor of FCMG
    in the amount of $1,972,993, and by order filed February 19,
    2014, the district court accepted the jury’s verdict and entered
    judgment for FCMG and against the District in the amount of
    $1,972,993. On February 27, the District filed its motion for
    judgment notwithstanding the verdict or, in the alternative, for
    new trial. The district court denied the District’s motion in an
    order filed April 1.
    The District appeals, and FCMG cross-appeals.
    ASSIGNMENTS OF ERROR
    The District claims 10 assignments of error on appeal,
    and FCMG claims one assignment of error on cross-appeal;
    however, we restate only those assignments of error of the
    District that are necessary for the disposition of this case.
    See Gray v. Kenney, 
    290 Neb. 888
    , 
    863 N.W.2d 127
    (2015)
    (stating appellate court is not obligated to engage in analy-
    sis that is not necessary to adjudicate case and controversy
    before it). The District claims the district court erred when it
    granted FCMG’s motion for partial summary judgment based
    upon the court’s determinations that sections 11.2 and 12.7
    of the contract are not ambiguous and that the concept of
    - 651 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    a guaranteed maximum price was not incorporated into the
    contract. The District also claims that the district court erred
    when it gave jury instruction No. 2, which stated that the con-
    tract was not ambiguous.
    On cross-appeal, FCMG raises an issue pertaining to interest
    allegedly owed to it by the District. Given our disposition of
    the District’s appeal, we need not reach the issue raised in the
    cross-appeal.
    STANDARDS OF REVIEW
    [1] An appellate court will affirm a lower court’s grant of
    summary judgment if the pleadings and admitted evidence
    show that there is no genuine issue as to any material facts
    or as to the ultimate inferences that may be drawn from the
    facts and that the moving party is entitled to judgment as a
    matter of law. Neun v. Ewing, 
    290 Neb. 963
    , 
    863 N.W.2d 187
    (2015).
    [2,3] The meaning of a contract and whether a contract is
    ambiguous are questions of law. David Fiala, Ltd. v. Harrison,
    
    290 Neb. 418
    , 
    860 N.W.2d 391
    (2015). When reviewing ques-
    tions of law, an appellate court has an obligation to resolve the
    questions independently of the conclusion reached by the trial
    court. 
    Id. [4] Whether
    a jury instruction is correct is a question of
    law, which an appellate court independently decides. Warner v.
    Simmons, 
    288 Neb. 472
    , 
    849 N.W.2d 475
    (2014).
    ANALYSIS
    The District claims that the district court erred when it
    determined that both section 11.2 and section 12.7 of the con-
    tract were not ambiguous. The District therefore argues that
    the court erred when it denied the District’s motion for partial
    summary judgment and granted FCMG’s motion for partial
    summary judgment. The District further claims that the court
    erred when it gave jury instruction No. 2, which states that
    “the contract in this case is not ambiguous.” As a matter of
    law, we conclude that section 12.7 is not ambiguous but that
    - 652 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    section 11.2 is ambiguous. That is, the court did not err when
    it determined that section 12.7 is not ambiguous, but it erred
    when it determined that section 11.2 is not ambiguous. As a
    result, the court erred when it entirely denied the District’s
    motion for partial summary judgment and entirely granted
    FCMG’s motion for partial summary judgment. Furthermore,
    based upon our determination that section 11.2 is ambiguous,
    the court erred when it gave jury instruction No. 2, which
    stated that the contract in this case as a whole is not ambigu-
    ous. The errors identified above require that we reverse, and
    remand for a new trial.
    [5-8] The rules of law applicable to this contract case are
    familiar. In interpreting a contract, a court must first deter-
    mine, as a matter of law, whether the contract is ambiguous.
    David Fiala, Ltd. v. 
    Harrison, supra
    . A contract written in
    clear and unambiguous language is not subject to interpretation
    or construction and must be enforced according to its terms.
    Davenport Ltd. Partnership v. 75th & Dodge I, L.P., 
    279 Neb. 615
    , 
    780 N.W.2d 416
    (2010). A contract is ambiguous when
    a word, phrase, or provision in the contract has, or is sus-
    ceptible of, at least two reasonable but conflicting interpreta-
    tions or meanings. David Fiala, Ltd. v. 
    Harrison, supra
    . The
    meaning of an ambiguous contract is generally a question of
    fact. Gary’s Implement v. Bridgeport Tractor Parts, 
    270 Neb. 286
    , 
    702 N.W.2d 355
    (2005). See, also, David Fiala, Ltd. v.
    
    Harrison, supra
    .
    Section 12.7 Is Not Ambiguous.
    The District would prefer that the contract be read as pro-
    viding a guaranteed maximum price and that it owes nothing
    further to FCMG. On appeal, the District argues that section
    12.7 of the contract is ambiguous, that exhibits 19 and 72
    are incorporated into the contract via section 12.7, and that
    by incorporating exhibits 19 and 72, the contract provides a
    guaranteed maximum price. The District challenges the district
    court’s ruling to the contrary. We reject this argument.
    - 653 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    In describing a guaranteed maximum price contract, the
    Indiana Court of Appeals has stated that “[a] guaranteed max-
    imum price provides a cap on a party’s financial obligations.
    It is the greatest amount a party is required to pay for the
    contracted services.” TRW, Inc. v. Fox Development Corp.,
    
    604 N.E.2d 626
    , 630 (Ind. App. 1992).
    Section 12.7 is a provision customized by the parties, and
    it provides:
    The Architect’s Response to the District’s Request
    for Proposal is attached to this Agreement for general
    reference purposes including overviews of projects and
    services. [The District’s] approvals following execution
    of this Agreement and related to the scope of work on
    the individual projects and corresponding portions of
    Project Budgets during the various Phases shall incor-
    porate applicable adjustments through the projects [sic]
    development.
    No copy of the contract in the record bears an attachment
    labeled “Architect’s Response to the District’s Request for
    Proposal” referred to in section 12.7, and there is no such
    document bearing that title in the record. The reference may be
    to exhibit 72 and/or exhibit 19.
    In its February 11, 2014, order, in which the district court
    granted partial summary judgment in favor of FCMG, the
    district court rejected the District’s argument that section 12.7
    was ambiguous. The court stated that “while the words ‘for
    general reference purposes’ are possibly ambiguous they do
    not equate to incorporating [FCMG’s responses] into the terms
    of the contract between [FCMG] and [the District] and, there-
    fore, cannot be a basis to determine fees and costs pursuant to
    the contract.”
    We agree with the district court that section 12.7 does not
    incorporate FCMG’s responses and the precontract negotia-
    tions into the contract. The expression “for general reference
    purposes,” interesting though it may be, contrasts with a pro-
    vision, common in contract law, which incorporates another
    document by reference. Compare Baker’s Supermarkets v.
    - 654 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    Feldman, 
    243 Neb. 684
    , 688, 
    502 N.W.2d 428
    , 432 (1993)
    (reading original lease and supplemental agreement as inte-
    grated where supplemental agreement stated that original
    lease was “‘by this reference deemed incorporated’”). Section
    12.7 simply does not incorporate FCMG’s responses into
    the contract.
    The District’s suggestion that section 12.7 is ambiguous
    and establishes a guaranteed maximum price is belied by other
    contract language. The standard language of section 5.2.2 pro-
    vides: “No fixed limit of Construction Cost shall be established
    as a condition of this Agreement by the furnishing, proposal
    or establishment of a Project budget, unless such fixed limit
    has been agreed upon in writing and signed by the parties
    hereto.” In Anderzhon/Architects v. 57 Oxbow II Partnership,
    
    250 Neb. 768
    , 
    553 N.W.2d 157
    (1996), we examined a contract
    that contained the exact standard language of section 5.2.2. In
    Anderzhon/Architects, the parties entered into the contract for
    the design and construction of a residential apartment complex.
    The parties had anticipated that the construction costs of the
    project would be approximately $27,000 to $30,000 per unit,
    but ultimately, the costs of construction were approximately
    $39,000 to $43,000 per unit. We noted that there was no writ-
    ten term in the contract which established a construction bud-
    get constraint and stated that “[s]ection 5.2.2 of the contract
    specifies that construction costs are not a condition of the
    agreement unless such a condition is made by the parties in
    writing.” 
    Id. at 775,
    553 N.W.2d at 161. We then noted that
    the record did not contain any evidence that the parties made a
    writing with respect to a fixed limit of construction costs, and
    we stated that the parties “intended the contract to be a final
    expression of the terms it contains with regard to the project
    budget limitations.” 
    Id. Similarly, in
    the present case, there is no language in the
    contract that the parties intended there to be a fixed budget
    with respect to construction costs or otherwise. As deter-
    mined above, section 12.7 is not ambiguous and does not
    incorporate any documents that would establish a guaranteed
    - 655 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    maximum price. Accordingly, we conclude that section 12.7 is
    not ambiguous and does not incorporate a guaranteed maxi-
    mum price into the contract and that therefore, the district
    court did not err when it so determined.
    Section 11.2 Is Ambiguous.
    The District also argues that section 11.2 of the contract
    dealing with increased charges is ambiguous and claims that
    the district court erred when it determined that it was not
    ambiguous in its order granting partial summary judgment in
    favor of FCMG. We agree with the District that section 11.2
    is ambiguous; the district court’s ruling to the contrary was
    reversible error.
    As stated above, section 11.2 is a provision customized by
    the parties and it provides:
    Fees shall be as outlined in the attached Recommended
    Compensation schedule as applicable to each component
    facility of the Project and shall be included in various
    categories of the Project Budget for Basic Services for
    Site and Construction work, Master Planning, Equipment,
    Additional Services for Remodeling and Additions,
    and Contingency allowances. Corresponding Project
    Reimbursable Expenses and costs for [the District’s]
    Representative/Project Management services shall also
    be paid as included in the Project Budget. These fees and
    costs are intended to be converted to Lump Sum amounts
    with the initial approval by the [District] and [FCMG] of
    the Project Scope, Budget, and concept to be advanced
    for funding. Lump Sum amounts and inclusions shall
    remain effective for the duration of the Project(s), except
    in the event of approved changes in the scope of work or
    alternatives to be bid adding two percent or more to the
    scope. In such event the Lump Sum fees and costs shall
    be increased proportionately to reflect the full percentage
    of changes.
    In its February 11, 2014, order, the district court deter-
    mined that section 11.2 is not ambiguous. In reaching its
    - 656 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    determination, the court looked to the parties’ course of deal-
    ing. The court noted that FCMG met with the board of the
    District in March 2008 to review the billing process and that
    the board continued to pay invoices submitted by FCMG
    through May 2009. The court then pointed to the parties’
    course of dealing “[a]s evidence of the manner in which fees
    on increases in the scope of the project were calculated . . . .”
    As an example demonstrating the basis for its ruling, the
    court noted invoice No. 29-1006, dated November 30, 2008,
    which stated that the original project area was 69,000 square
    feet and that 5,619 square feet had been added to the original
    area. The court stated that the additional square footage was
    billed at $9.22 per square foot, which was calculated based
    on the square footage cost of the original project area. The
    court observed that invoice No. 29-1006 was paid in full by
    the District, and that “[t]hus, there was a course in dealing
    between the parties which evidences a lack of ambiguity in the
    contract.” The district court erred in employing the foregoing
    approach to reaching its determination regarding ambiguity
    and, as a matter of law, erred in its result.
    [9,10] We have previously stated that extrinsic evidence
    is not permitted to explain the terms of a contract that is not
    ambiguous. Gary’s Implement v. Bridgeport Tractor Parts, 
    270 Neb. 286
    , 
    702 N.W.2d 355
    (2005); Spanish Oaks v. Hy-Vee,
    
    265 Neb. 133
    , 
    655 N.W.2d 390
    (2003). When a contract is
    unambiguous, the intentions of the parties must be deter-
    mined from the contract itself. Spanish Oaks v. 
    Hy-Vee, supra
    .
    Accordingly, if section 11.2 of the contract was not ambigu-
    ous, as the district court determined, then it was not appropri-
    ate for the district court to look to extrinsic evidence, such as
    the parties’ course of dealings, to so conclude.
    The District contends that the language of section 11.2 is
    ambiguous because it is not clear how the “scope of work” is
    to be determined, which in turn serves as a basis for increased
    fees and costs which, in the language of the contract, “shall be
    increased proportionately.”
    - 657 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    “[S]cope of work” is not a defined term in the contract. It
    is not clear what is encompassed by “scope of work.” There
    is some suggestion that square footage may be one way that
    scope of work may be determined, but there are arguably
    other ways to determine the scope of work under the contract.
    For example, FCMG asserts that the contract provides that
    “not only square footage increases, but increases relating to
    non-square footage items such as equipment and Owner’s
    Representative fees” are included in scope of work. Brief
    for appellee at 8. We conclude as a matter of law that sec-
    tion 11.2, and in particular “scope of work,” is ambiguous
    and that the district court erred when it determined that sec-
    tion 11.2 is not ambiguous and entered summary judgment
    orders accordingly.
    Jury Instruction No. 2 Was
    Prejudicial Error.
    The District claims that the district court erred when it
    gave jury instruction No. 2 because, inter alia, the contract
    was ambiguous and instruction No. 2 stated to the contrary.
    We understand, in addition, that the District believes jury
    instruction No. 2 was erroneous because it is confusing. In this
    regard, we note that during its deliberations, the jury sent out
    a note asking the court: “If we were to decide for [FCMG],
    are we allowed to reduce the amount of the award? And, if so,
    do we need to show how we calculated the reduced amount?”
    We determine that jury instruction No. 2 constituted prejudi-
    cial error.
    [11-13] We have stated that a court is not free to rewrite
    a contract or to speculate as to terms of the contract which
    the parties have not seen fit to include. Bedore v. Ranch Oil
    Co., 
    282 Neb. 553
    , 
    805 N.W.2d 68
    (2011). Rather, when a
    court has determined that ambiguity exits in a document, an
    interpretive meaning for the ambiguous word, phrase, or pro-
    vision in the document is a question of fact for the fact finder.
    David Fiala, Ltd. v. Harrison, 
    290 Neb. 418
    , 
    860 N.W.2d 391
    (2015). In this regard, we have stated in a jury case that when
    - 658 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    the terms of the contract are in dispute and the real intentions
    of the parties cannot be determined from the words used,
    the jury, not the court, should determine the issue from all
    the facts and circumstances. Gary’s Implement v. Bridgeport
    Tractor Parts, 
    270 Neb. 286
    , 
    702 N.W.2d 355
    (2005). A
    written instrument is open to explanation by parol evidence
    when its terms are susceptible to two constructions or where
    the language employed is vague or ambiguous. Davenport
    Ltd. Partnership v. 75th & Dodge I, L.P., 
    279 Neb. 615
    , 
    780 N.W.2d 416
    (2010).
    Because section 11.2 is ambiguous, parol evidence should
    have been permitted at trial and the court should have given
    the issue of the meaning of the ambiguous contract to the jury.
    However, in this case, the district court instructed the jury
    as follows:
    The Court has determined as a matter of law that
    the following facts exist and that you must accept them
    as true:
    1. That the parties entered into a contract related to
    the construction/remodeling of three facilities for the
    [District] on August 9, 2007.
    2. That the Court has determined that the contract in
    this case is not ambiguous.
    (Emphasis supplied.) We determine it was error for the court to
    instruct the jury that the contract in this case is not ambiguous.
    Rather, the court should have instructed the jury that section
    11.2 of the contract was ambiguous and that the jury was to
    determine its meaning.
    [14] Whether a jury instruction is correct is a question of
    law, which an appellate court independently decides. Warner
    v. Simmons, 
    288 Neb. 472
    , 
    849 N.W.2d 475
    (2014). In an
    appeal based on a claim of an erroneous jury instruction, the
    appellant has the burden to show that the questioned instruc-
    tion was prejudicial or otherwise adversely affected a substan-
    tial right of the appellant. 
    Id. We conclude
    that the district court’s error in the giving
    of jury instruction No. 2 was prejudicial and constitutes
    - 659 -
    Nebraska A dvance Sheets
    291 Nebraska R eports
    FACILITIES COST MGMT. GROUP v. OTOE CTY. SCH. DIST.
    Cite as 
    291 Neb. 642
    reversible error. Had the court not erroneously determined
    that section 11.2 was unambiguous and granted partial sum-
    mary judgment in favor of FCMG based upon this deter-
    mination, the parties could have presented evidence at trial
    with respect to the meaning of section 11.2, specifically the
    meaning of “scope of work.” The parties could have framed
    their arguments differently at trial to address the meaning of
    section 11.2 and how they believed the jury should interpret it
    and award damages, if any. Therefore, we determine that jury
    instruction No. 2, which stated that “the contract in this case
    is not ambiguous,” is prejudicial error, and we reverse, and
    remand for a new trial.
    Because we conclude that a new trial is required, we do not
    reach the District’s remaining assignments of error or FCMG’s
    assignment of error on cross-appeal. See Gray v. Kenney, 
    290 Neb. 888
    , 
    863 N.W.2d 127
    (2015) (stating appellate court is
    not obligated to engage in analysis that is not necessary to
    adjudicate case and controversy before it).
    CONCLUSION
    We determine that the district court did not err when it
    determined that section 12.7 of the contract was not ambigu-
    ous, but did err when it determined that section 11.2 of the
    contract was not ambiguous. Accordingly, the district court
    prejudicially erred when it gave jury instruction No. 2, which
    stated that the contract in this case is not ambiguous. For
    the reasons explained above, we reverse, and remand for a
    new trial.
    R eversed and remanded for a new trial.
    Stephan, J., not participating.