Carey v. City of Hastings ( 2013 )


Menu:
  •                            CASES DETERMINED
    IN THE
    SUPREME COURT OF NEBRASKA
    Mike Carey and Becky Carey, appellees, v.
    City of Hastings, Nebraska, a municipal
    corporation, appellant.
    ___ N.W.2d ___
    Filed December 13, 2013.      No. S-13-110.
    1.	 Administrative Law: Evidence: Appeal and Error. In reviewing the decision
    of an administrative board on a petition in error, both the district court and the
    appellate court review the decision of the board to determine whether it acted
    within its jurisdiction and whether the decision of the board is supported by
    sufficient relevant evidence. The evidence is sufficient, as a matter of law, if an
    administrative board could reasonably find the facts as it did on the basis of the
    testimony and exhibits contained in the record before it.
    2.	 Statutes. The interpretation of statutes and regulations presents questions
    of law.
    3.	 Judgments: Appeal and Error. An appellate court independently reviews ques-
    tions of law decided by a lower court.
    4.	 Jurisdiction: Words and Phrases. Subject matter jurisdiction is the power of a
    tribunal to hear and determine a case in the general class or category to which
    the proceedings in question belong and to deal with the general subject mat-
    ter involved.
    5.	 ____: ____. Personal jurisdiction is the power of a tribunal to subject and bind a
    particular person or entity to its decisions.
    6.	 Statutes: Appeal and Error. In the absence of a statutory indication to the con-
    trary, an appellate court gives words in a statute their ordinary meaning.
    7.	 Administrative Law. In the absence of anything to the contrary, language con-
    tained in a rule or regulation is to be given its plain and ordinary meaning.
    8.	 ____. For purposes of construction, a rule or order of an administrative agency is
    treated like a statute.
    9.	 Statutes: Intent. In construing a statute, a court must look to the statutory objec-
    tive to be accomplished, the evils and mischiefs sought to be remedied, and the
    purpose to be served. A court must then reasonably or liberally construe the
    statute to achieve the statute’s purpose, rather than construing it in a manner that
    defeats the statutory purpose.
    10.	 Appeal and Error. An appellate court is not obligated to engage in an analysis
    that is not necessary to adjudicate the case and controversy before it.
    (1)
    Nebraska Advance Sheets
    2	287 NEBRASKA REPORTS
    Appeal from the District Court for Adams County: Stephen
    R. Illingworth, Judge. Reversed.
    Michael O. Mead, Special City Attorney, of Whelan, Scherr,
    Glen & Mead, P.C., L.L.O., for appellant.
    Arthur R. Langvardt, of Langvardt, Valle & James, for
    appellees.
    Robert F. Bartle, Special Assistant Attorney General, of
    Bartle & Geier Law Firm, for amicus curiae Nebraska Board
    of Engineers and Architects.
    Heavican, C.J., McCormack, Miller-Lerman, and Cassel, JJ.
    Cassel, J.
    INTRODUCTION
    A municipal building inspector denied an application for
    a building permit because the construction documents were
    not prepared by a registered design professional. The city’s
    appeals board upheld the denial, but in an error proceeding
    initiated by the landowners, the district court reversed. The
    city now appeals. Because the building code mandated prepa-
    ration of the documents by a registered design professional
    “where required”1 by Nebraska statutes, our decision turns
    upon interpretation of exemptions specified in the Engineers
    and Architects Regulation Act2 (Act) and related regulations.
    We conclude that the appeals board acted within its jurisdic-
    tion and that there was sufficient relevant evidence to support
    a reasonable conclusion that the proposed renovation failed to
    qualify for statutory and regulatory exemptions to the Act. We
    therefore reverse the judgment of the district court.
    BACKGROUND
    Mike Carey and Becky Carey applied for a building permit
    for an interior renovation of a 10,800-square-foot apartment
    building located in Hastings, Nebraska. The Careys planned
    to convert the building’s 20 apartment units into 10 apartment
    1
    See 2009 International Building Code § 107.1.
    2
    Neb. Rev. Stat. § 81-3401 et seq. (Reissue 2008 & Cum. Supp. 2012).
    Nebraska Advance Sheets
    CAREY v. CITY OF HASTINGS	3
    Cite as 
    287 Neb. 1
    units and to replace the building’s electrical and plumbing sys-
    tems. They did not plan to move or alter the building’s load-
    bearing walls. The proposed renovation also entailed the instal-
    lation of fire-rated doors at the entrance of each apartment
    unit and corridor, exit signs above exit doors, and continuous
    handrails at each flight of stairs.
    The building inspector for the City of Hastings denied the
    Careys a building permit based upon his belief that the con-
    struction plans submitted by the Careys were required to be
    approved by a licensed architect. The applicable building code
    required submitted construction documents to be prepared by
    a registered design professional where required by statute.
    Specifically, § 107.1 of the 2009 International Building Code
    provided, in pertinent part: “Submittal documents consisting of
    construction documents . . . shall be submitted in two or more
    sets with each permit application. The construction documents
    shall be prepared by a registered design professional where
    required by the statutes of the jurisdiction in which the project
    is to be constructed.” (Emphasis in original.)
    Under the Act, criminal liability is attached to the unlicensed
    practice of architecture or engineering unless such practice is
    exempt.3 Section 81-3446(1) provides that the owner of any
    real property engages in the practice of architecture or engi-
    neering when he or she allows a project to be constructed
    on his or her real property unless a licensed professional is
    employed to furnish at least minimum construction phase
    services or the project is exempt from the Act.4 The building
    inspector believed that the Careys’ proposed renovation did not
    qualify under any exemption to the Act. He therefore denied
    the Careys a building permit based upon his belief that the
    applicable building code required their construction plans to be
    approved by a licensed architect.
    The Careys disputed the denial of the building permit and
    claimed that their proposed renovation came within an excep-
    tion to the Act provided by § 81-3449(5). The exception
    provides that the Act’s provisions regulating the practice of
    3
    See § 81-3442(1).
    4
    See § 81-3446(1).
    Nebraska Advance Sheets
    4	287 NEBRASKA REPORTS
    architecture do not apply to “[a]ny alteration, renovation,
    or remodeling of a building if the alteration, renovation, or
    remodeling does not affect architectural or engineering safety
    features of the building.”5 Because no load-bearing walls were
    to be moved or altered and safety features were to be added,
    the Careys contended that the renovation qualified under
    § 81-3449(5).
    The Careys also claimed that a regulation clarifying
    § 81-3449 established that their project was exempt from
    the Act. The Careys cited 110 Neb. Admin. Code, ch. 10,
    § 10.4.1.2 (2008). Section 10.4.1.2 exempts a renovation if the
    “area of renovation . . . does not adversely impact the mechani-
    cal system; the electrical system; the structural integrity; the
    means of egress; and does not change or come into conflict
    with the occupancy classification.” (An amendment in 2011
    did not change the quoted language.) The Careys contended
    that their renovation came within § 10.4.1.2 because the build-
    ing’s electrical and plumbing systems were to be replaced and
    would therefore not be adversely affected.
    The building inspector then sought an opinion from a compli-
    ance officer with Nebraska’s Board of Engineers and Architects
    (state board) whether the Careys’ proposed construction plans
    required a licensed architect’s approval. After reviewing the
    drawings submitted by the Careys, the state board sent the
    Careys a letter stating that the board believed the renovation
    was not exempt under § 81-3449(5) because the renovation
    would affect the building’s safety features. The letter further
    stated that the board believed 110 Neb. Admin. Code, ch. 10,
    § 10.4.1.2, was inapplicable because the building’s mechanical
    and electrical systems and means of egress would be adversely
    impacted. The letter explained that the state board concurred
    with the building inspector’s determination that the renovation
    required the involvement of a licensed design professional and
    recommended that the city deny a building permit until such a
    professional was retained.
    The Careys appealed the denial of the building permit to the
    City of Hastings Board of Appeals (appeals board). At the May
    5
    § 81-3449(5).
    Nebraska Advance Sheets
    CAREY v. CITY OF HASTINGS	5
    Cite as 
    287 Neb. 1
    17, 2011, meeting of the appeals board, the Careys’ attorney
    emphasized that the Careys believed their proposed renovation
    was exempt from the Act under § 81-3449(5) and 110 Neb.
    Admin. Code, ch. 10, § 10.4.1.2. The Careys’ attorney further
    asserted that the state board only had the authority to prevent
    the unauthorized practice of architecture or engineering and did
    not have the authority to determine whether a building permit
    should be issued.
    One member of the appeals board then commented that the
    plans submitted by the Careys did not clearly show the exist-
    ing structure of the building so that a determination could be
    made as to whether the renovation would have an adverse
    effect. The board member stated that a design professional
    was necessary to make that determination. The board member
    then stated that he “would like to entertain a motion that [the
    appeals board] uphold the decision from the [state board].”
    The Careys’ attorney immediately clarified that the appeals
    board was not reviewing the state board’s determination, but
    was reviewing the building inspector’s denial of the building
    permit. The building inspector also emphasized that the focus
    of the motion should be his denial of the permit. Ultimately,
    the appeals board’s proceedings show that a motion was
    made by another member of the appeals board to “deny the
    appeal.” The motion was seconded, and all members present
    voted for the motion. Thus, the Careys’ appeal was denied,
    which effectively upheld the denial of the permit by the build-
    ing inspector.
    The Careys next filed a petition in error in the district court
    for Adams County pursuant to Neb. Rev. Stat. § 25-1901 et
    seq. (Reissue 2008). After a hearing, the court entered an order
    overruling the appeals board and ordering that the Careys be
    issued a building permit without the requirement of a licensed
    architect’s involvement. The court concluded that the appeals
    board did not act within its jurisdiction and that there was
    insufficient evidence to support the permit’s denial because
    the appeals board’s decision was “totally based” upon the state
    board’s recommendation. The court further stated that it could
    find no authority granting the state board the power to make
    recommendations to local building inspectors and that nothing
    Nebraska Advance Sheets
    6	287 NEBRASKA REPORTS
    within the Act authorized the state board to give advice on
    local building projects. Finally, the court concluded that even
    if the Act applied to the Careys’ renovation, the project was
    exempt under § 81-3449(5).
    The city filed a timely notice of appeal. Pursuant to statutory
    authority, we moved the case to our docket.6
    ASSIGNMENTS OF ERROR
    The city assigns that the district court erred in (1) con-
    cluding that the appeals board did not fulfill its jurisdictional
    requirements, (2) concluding that the appeals board’s decision
    was based upon insufficient evidence, and (3) ordering the city
    to issue a building permit to the Careys without the require-
    ment that they retain a licensed architect.
    STANDARD OF REVIEW
    [1] In reviewing the decision of an administrative board on a
    petition in error, both the district court and the appellate court
    review the decision of the board to determine whether it acted
    within its jurisdiction and whether the decision of the board
    is supported by sufficient relevant evidence.7 The evidence is
    sufficient, as a matter of law, if an administrative board could
    reasonably find the facts as it did on the basis of the testimony
    and exhibits contained in the record before it.8
    [2,3] The interpretation of statutes and regulations presents
    questions of law.9 We independently review questions of law
    decided by a lower court.10
    ANALYSIS
    Our review in this case is limited to whether the appeals
    board acted within its jurisdiction and upon sufficient relevant
    evidence in affirming the denial of the building permit. We first
    6
    See Neb. Rev. Stat. § 24-1106(3) (Reissue 2008).
    7
    Campbell v. Omaha Police & Fire Ret. Sys., 
    268 Neb. 281
    , 
    682 N.W.2d 259
    (2004).
    8
    Id.
    9
    Blakely v. Lancaster County, 
    284 Neb. 659
    , 
    825 N.W.2d 149
    (2012).
    10
    
    Id. Nebraska Advance
    Sheets
    CAREY v. CITY OF HASTINGS	7
    Cite as 
    287 Neb. 1
    analyze the basis for the board’s jurisdiction and then turn to
    the sufficiency of the evidence before the board at its May 17,
    2011, meeting.
    Jurisdiction of Appeals Board
    [4,5] The parties agree that the district court’s use of the
    term “jurisdiction” is somewhat of a misnomer in the sense
    that the court was not referring to subject matter or personal
    jurisdiction. We have defined subject matter jurisdiction as
    the power of a tribunal to hear and determine a case in the
    general class or category to which the proceedings in question
    belong and to deal with the general subject matter involved.11
    The parties agree that the appeal was correctly addressed to
    the appeals board, which had the authority to review the denial
    of the building permit. Personal jurisdiction is the power of a
    tribunal to subject and bind a particular person or entity to its
    decisions.12 Clearly, the city and the Careys were present at
    the hearing on the Careys’ appeal and submitted to the appeals
    board’s jurisdiction of their appeal.
    When the district court spoke of jurisdiction, it addressed
    the appeals board’s reliance on the recommendation from the
    state board. However, this conclusion conflates the issue of
    jurisdiction with the sufficiency of the evidence. The evidence
    relied upon by the appeals board had no bearing upon its
    authority to either affirm or overrule the building inspector’s
    denial of the building permit. The Careys’ appeal of the denial
    of the building permit was properly before the appeals board,
    which had the authority to affirm or reverse the denial. The
    court therefore erred in finding that the appeals board acted
    outside its jurisdiction in affirming the permit’s denial.
    Sufficiency of R elevant Evidence
    The district court concluded that the appeals board’s deci-
    sion to affirm the denial of the building permit was “totally
    based” on the state board’s recommendation that a licensed
    design professional was required to be retained by the Careys.
    11
    Young v. Govier & Milone, 
    286 Neb. 224
    , ___ N.W.2d ___ (2013).
    12
    
    Id. Nebraska Advance
    Sheets
    8	287 NEBRASKA REPORTS
    The court therefore found that the appeals board’s decision was
    not made upon sufficient relevant evidence. The court further
    concluded that even if the Act applied, the renovation was
    exempt under § 81-3449(5).
    We disagree with the court’s conclusion that the appeals
    board did not base its decision upon sufficient relevant evi-
    dence. We emphasize that in the context of a decision made
    by an administrative board, evidence is sufficient if the board
    reasonably could find the facts as it did on the basis of the tes-
    timony and exhibits contained in the record before it.13
    First, the district court’s conclusion was based upon an
    incorrect reading of the appeals board’s proceedings. The
    court partly relied upon one member’s statement expressing
    a desire to “entertain a motion” to uphold the state board’s
    decision. But this overlooks the discussion that followed
    where the Careys’ attorney emphasized the motion should
    focus on the building inspector’s decision and the same mem-
    ber “concur[red]” in that articulation. The court also relied
    upon a snippet of the discussion where the building inspector
    appeared to admit that if the state board had disagreed with
    his conclusion, he would have reversed his ruling. But this
    was immaterial. The record makes it clear that the inspector
    had already made his decision. According to the case summary
    prepared for the appeals board, the Careys were informed in
    writing on September 14, 2010, of the requirement that the
    plans be prepared by a licensed architect. The state board’s
    action was not taken until April 22, 2011. The inspector’s
    willingness to reconsider his decision did not amount to an
    abdication of his decisionmaking authority. Thus, the court’s
    conclusion that the appeals board “totally based” its deci-
    sion on the state board’s recommendation is not supported by
    the record.
    Second, the record includes sufficient relevant evidence
    from which the appeals board could reasonably find that the
    Careys’ construction plans were required to be approved by a
    licensed architect under the applicable building code. In addi-
    tion to the state board’s recommendation, the appeals board
    13
    See Campbell, supra note 7.
    Nebraska Advance Sheets
    CAREY v. CITY OF HASTINGS	9
    Cite as 
    287 Neb. 1
    was presented with the building inspector’s independent con-
    clusion that the Careys’ renovation was not exempt from the
    Act. The building inspector told the appeals board that it was
    “pretty clear” that the Careys’ project required an architect of
    record under the Act.
    [6,7] Third, the evidence reasonably supported the appeals
    board’s conclusion that the Careys’ project did not qualify
    under the statutory or regulatory exemptions to the Act. But
    before we discuss this evidence, we must examine the statutory
    and regulatory exemptions without deference to the appeals
    board’s interpretation. In the absence of a statutory indication
    to the contrary, an appellate court gives words in a statute their
    ordinary meaning.14 Likewise, language in a rule or regulation
    is to be given its plain and ordinary meaning.15
    Contrary to the Careys’ argument, § 81-3449(5) did not
    exempt their project from the Act. Section 81-3449(5) exempts
    “[a]ny alteration, renovation, or remodeling of a building if
    the alteration, renovation, or remodeling does not affect archi-
    tectural or engineering safety features of the building.” The
    Careys argue that “no existing architectural or engineering
    safety features are affected by the remodeling involved here,
    although certain modern safety features arising in the fire
    codes are being added, under the supervision of the state fire
    marshal and the city’s building inspectors.”16 Thus, the Careys
    implicitly argue that because these safety features were gov-
    erned by fire codes, they are not “architectural” safety features.
    We disagree. The practice of architecture includes “services in
    connection with the design and . . . alteration of a building.”17
    Design, in turn, means the “preparation of schematics, layouts,
    plans, drawings, specifications, calculations, and other diag-
    nostic documents which show the features, scope, and detail
    of an architectural or engineering work to be executed.”18
    14
    Vlach v. Vlach, 
    286 Neb. 141
    , 
    835 N.W.2d 72
    (2013).
    15
    See Belle Terrace v. State, 
    274 Neb. 612
    , 
    742 N.W.2d 237
    (2007).
    16
    Brief for appellees at 13.
    17
    § 81-3420.
    18
    § 81-3409.
    Nebraska Advance Sheets
    10	287 NEBRASKA REPORTS
    Compliance with fire, building, plumbing, and similar codes
    clearly requires such layouts, plans, drawings, and specifica-
    tions to incorporate the necessary features in the design of
    a project. The design of the Careys’ renovation entailed the
    installation of fire-rated doors at the entrance of each apart-
    ment unit and corridor, exit signs above each exit door, and a
    continuous handrail at each flight of stairs. Thus, the evidence
    was sufficient to reasonably support the conclusion that the
    renovation would affect the building’s safety features and was
    thereby not exempt from the Act.
    [8,9] Similarly, the regulatory exemption did not apply.
    The exemption provided by § 10.4.1.2 applies if the “area of
    renovation . . . does not adversely impact the mechanical sys-
    tem; the electrical system; the structural integrity; the means
    of egress; and does not change or come into conflict with the
    occupancy classification.”19 In analyzing this exemption, we
    first reject the Careys’ interpretation that a renovation that
    entails the replacement of a building’s structure or systems
    cannot be said to “adversely impact” such structure or systems.
    Renovations are generally undertaken to improve the condi-
    tion of a building or its systems. Thus, to accept the Careys’
    interpretation would effectively remove all renovations from
    the requirement of oversight by a licensed design professional
    and defeat the purpose of the Act. For purposes of construc-
    tion, a rule or order of an administrative agency is treated like
    a statute.20 In construing a statute, we look to the statutory
    objective to be accomplished, the evils and mischiefs sought
    to be remedied, and the purpose to be served. A court must
    then reasonably or liberally construe the statute to achieve
    the statute’s purpose, rather than construing it in a manner
    that defeats the statutory purpose.21 We therefore interpret the
    phrase “adversely impact” as including the replacement of a
    building’s structure or systems.
    19
    See 110 Neb. Admin. Code, ch. 10, § 10.4.1.2.
    20
    Utelcom, Inc. v. Egr, 
    264 Neb. 1004
    , 
    653 N.W.2d 846
    (2002).
    21
    Blakely, supra note 9.
    Nebraska Advance Sheets
    CAREY v. CITY OF HASTINGS	11
    Cite as 
    287 Neb. 1
    Here again, the appeals board had sufficient evidence to
    reasonably support its conclusion that the renovation failed
    to qualify under § 10.4.1.2. The evidence that the building’s
    plumbing and electrical systems were to be replaced reason-
    ably supported the conclusion that the building’s mechanical
    and electrical systems would be adversely affected. The instal-
    lation of fire-rated doors at the entrance of each apartment
    unit and corridor similarly provided reasonable support for
    the conclusion that the means of egress would be adversely
    affected. Thus, the evidence reasonably supported the appeals
    board’s decision.
    We conclude that the evidence before the appeals board rea-
    sonably supported the determination that the applicable build-
    ing code required the Careys’ submitted plans to be approved
    by a licensed design professional. Because we find that the
    appeals board acted within its jurisdiction and upon sufficient
    relevant evidence, we reverse the court’s order overruling the
    permit’s denial.
    Order to Issue Building P ermit
    [10] Because we conclude that the appeals board acted
    within its jurisdiction and upon sufficient relevant evidence,
    we need not consider whether the court acted within its
    authority in ordering the city to issue a building permit with-
    out the requirement of a licensed architect’s involvement.
    An appellate court is not obligated to engage in an analysis
    that is not necessary to adjudicate the case and controversy
    before it.22
    CONCLUSION
    We reverse the district court’s order overruling the permit’s
    denial based upon our conclusion that the appeals board acted
    within its jurisdiction and upon sufficient relevant evidence in
    affirming the denial of the building permit. Notwithstanding
    the state board’s recommendation, the appeals board was pre-
    sented with sufficient evidence to conclude that the Careys’
    22
    Holdsworth v. Greenwood Farmers Co-op, 
    286 Neb. 49
    , 
    835 N.W.2d 30
          (2013).
    Nebraska Advance Sheets
    12	287 NEBRASKA REPORTS
    renovation was not exempt from the Act and that a licensed
    architect was required to approve the submitted construction
    plans under the applicable building code. We therefore reverse
    the court’s order and so need not consider the appropriateness
    of the granted relief.
    R eversed.
    Wright, J., participating on briefs.
    Connolly and Stephan, JJ., not participating.
    Justin S. Furstenfeld, appellant, v.
    Lisa B. P epin, appellee.
    ___ N.W.2d ___
    Filed December 13, 2013.      No. S-13-122.
    1.	 Judgments: Jurisdiction: Appeal and Error. A jurisdictional question which
    does not involve a factual dispute is determined by an appellate court as a matter
    of law, which requires the appellate court to reach a conclusion independent of
    the lower court’s decision.
    2.	 Jurisdiction: Appeal and Error. Before reaching the legal issues presented for
    review, it is the duty of an appellate court to determine whether it has jurisdic-
    tion over the matter before it, irrespective of whether the issue is raised by
    the parties.
    3.	 Jurisdiction: Final Orders: Appeal and Error. For an appellate court to acquire
    jurisdiction of an appeal, there must be a final order entered by the tribunal from
    which the appeal is taken.
    4.	 Final Orders: Appeal and Error. The three types of final orders which may
    be reviewed on appeal are (1) an order which affects a substantial right and
    which determines the action and prevents a judgment, (2) an order affecting a
    substantial right made during a special proceeding, and (3) an order affecting
    a substantial right made on summary application in an action after judgment
    is rendered.
    5.	 Actions: Statutes. “Special proceedings” include civil statutory remedies not
    encompassed in chapter 25 of the Nebraska Revised Statutes.
    6.	 Actions: Modification of Decree: Child Custody. Proceedings regarding modi-
    fication of a marital dissolution, which are controlled by Neb. Rev. Stat. § 42-364
    (Cum. Supp. 2012), are special proceedings, as are custody determinations, which
    are also controlled by § 42-364.
    7.	 Words and Phrases. A substantial right is an essential legal right, not a mere
    technical right.
    8.	 Final Orders: Appeal and Error. A substantial right is affected if the order
    affects the subject matter of the litigation, such as diminishing a claim or defense