Gutschow v. Washington County , 74 Neb. 378 ( 1905 )


Menu:
  • Letton, C.

    This was an action brought by a taxpayer of the county of Washington, who was the owner of lands ad*379joining and affected by a proposed ditch improvement in said county, to enjoin the board of supervisors from letting a contract for the construction of the ditch. It appears that, after the preliminary proceedings required by the statute were had, the county board advertised for bids for the construction of the improvement, and in February, 1904, the contract therefor was awarded to Callahan Bros. & Katz, a firm of contractors. They filed the required bond, which was approved, and a contract was duly entered into between them and the county board for the construction of said ditch. The contract provided that the ditch was to be completed by the 15th of June, 1904. On June 1, 1904, on the application of the contractors, the time for completing the ditch- was extended to January 1, 1905, under certain conditions. In July, 1904, the contractors declined to further proceed with the work on account of alleged irregularities in some of the proceedings of the board, and at a meeting on July 13 the board found that the contract had not been completed, nor had the work thereunder been commenced, and the contract was declared forfeited. The board then proceeded to advertise for bids for the construction of the ditch. At the time specified for the reception of bids the board met and, the bid of R. A. Brown & Company being the only one submitted, they awarded the contract for the construction of the ditch to that firm, whereupon this action was begun to enjoin them from entering into this contract. In the district court a demurrer to the petition was sustained, and judgment rendered dismissing the action, from which judgment plaintiff appeals to this court.

    His first argument is that the only power given to the board to relet a contract for the construction of the ditch is given by section 20, article I, chapter 89, Compiled Statutes 1903 (Ann. St. 5519), which provides that “any contract not completed within the time specified, shall be reestimated and relet to the lowest responsible bidder, but not for a sum greater than the estimate, nor a second time to the same party”; that a contract which *380has never been begun is not a contract “not completed,” and that the words “not completed” imply something commenced and left unfinished. We are unable to discern the force of this argument. A contract, the work upon which has never been commenced, is certainly no nearer completion than one upon which part of the work has been performed. To adopt the construction contended for by the appellant would be to create the anomalous situation that, where a few shovelfuls of dirt had been thrown out in beginning the work of constructing a ditch, the board might relet the contract, but that, where nothing has been done at all, it was absolutely deprived of all power, and had reached an impasse. We will not lightly impute to the legislature such an intention, and we think the argument is without merit. If such were the law, the only means necessary to take to render abortive the whole proceedings would be to act as the first contractors did here — take the contract and fail to carry out its provisions.

    The next point urged is that, since there was only one bidder, the contract was not let to the “lowest responsible bidder.” State v. Board of County Commissioners, 13 Neb. 57, was a mandamus proceeding brought to compel the board of county commissioners of York county to <mter into a contract with the relator for the purchase of certain stationéry, on the ground that he was the loAvest competent bidder therefor. It appears that two bids were filed with the board, but one of the bids was filed out of time and was not in accordance with the advertisement. This left the relator the only bidder. The court held that he was the lowest competent bidder and the writ was awarded as prayed. See, also, Baum v. Sweeny, 5 Wash. 712, 32 Pac. 778. It may often happen from the character of the work to be performed, or of the supplies to be furnished, that in a given locality one person alone may have the facilities and appliances necessary to fulfill the terms of the contract. It is a matter of common knowledge that extensive, excavations, such as canals, ditches, or railway cuts, may be carried on much more cheaply and expedi*381tiously by the use of poAver machinery. A bidder equipped with such appliances may have so great an advantage over the ordinary individual as to make it useless to attempt to compete AA'ith him. Indeed, the bid of R. A. Brown & Company in the instant case recites that they had “a suitable dredge machine, now idle and ready for immediate use.” There is nothing alleged against the good faith of the bidder, nor is it averred that the price is excessive or the bidder not responsible. Apparently, neither the county board nor the bidder are to blame in any way for the failure of other persons to file bids. Some courts haAe held that, Avhere there Avas only one bidder, he could not be said to be the loAvest bidder, since he was also the highest bidder; but in the absence of fraud or collusion, or of any showing that the price is excessive or unreasonable, we see no reason for assuming this position.

    The third objection made is that the contract exceeds the estimated cost of construction, and that the bid did not comply Avith the terms of the notice Avhich called for bids for the construction of the ditch by working sections. The reestimate made under the direction of the board showed no change from the former estimate. .The estimate makes the total cost $42,705.84, the number of yards of earth to be excavated 388,344 cubic yards, and Brown’s bid at 9| cents a cubic yard makes the total $35,912.57, which is within the estimate. The petition alleges that the amount of $42,690.24 was adopted by the board of supervisors as the estimate of the cost of said improvement, after having ascertained all the expenses, compensation for land taken and damages; that the main item of cost in the estimate Avas for the excavation of the ditch, Avhieh under the bid of Callahan Bros. & Katz amounted to $32,536.78, Avliile Brown’s bid aggregated $35,912.57, Avhoreby the estimate Avould be exceeded by $3,375.79, which the board of supervisors had no authority to do. The petition, hoAvever, does not separate the items of the? estimate so. as to show Avhat was originally estimated as the cost of excavation and construction. Brown’s bid *382falls within the original estimate, and hence is not subject to the objection made by appellant.

    As to the contention that the bid did not respond to the advertisement, because it was not made by each working section, this is a mistake, since the bidder proposed to “construct, excavate and complete by working sections” at and for the price of 9|: cents a cubic yard of earth. This means at 9J cents for each working section, or the same rate per yard -for all.

    We think the judgment of the district court is correct, and recommend that it he affirmed.

    Ames and Oldham, CO., concur.

    By the Court: For the reason stated in the foregoing opinion, the judgment of the district court is

    Affirmed.

Document Info

Docket Number: No. 13,974

Citation Numbers: 74 Neb. 378, 104 N.W. 602, 1905 Neb. LEXIS 227

Judges: Ames, Letton, Oldham

Filed Date: 9/20/1905

Precedential Status: Precedential

Modified Date: 10/18/2024