-
Sedgwick, J. After the former judgment in this case had been reversed upon the plaintiffs’ appeal (102 Neb. 249), the plaintiffs filed an amended petition in the district court and the defendant filed an amended answer. In this answer the defendant alleged a counterclaim asking damages against the plaintiffs for an alleged failure to per
*246 form four several contracts in which the plaintiffs agreed to purchase from the defendant grain to he shipped as specified in the contracts. When the evidence was completed, each party made such requests for an instructed verdict that the court- discharged the jury and determined the case upon the pleadings and evidence. The court found that there was due from the defendant to the plaintiffs $47,934.32, and that there was due from the plaintiffs to the defendant upon its counterclaim $28,610.81, and entered judgment in favor of the plaintiffs for the difference, $19,323.51. Prom this judgment the plaintiffs have again appealed, insisting that the amount allowed upon the defendant’s counterclaim is too large.By these four contracts, upon which the counterclaim was based; the defendant sold to the plaintiffs wheat and corn as therein specified to be shipped from Omaha, the defendant’s place of business, to Baltimore. One of these contracts contained the sentence, “Shipment Jan. Feb. open port or permit by Feb. 1st.” The others contained words of similar import, and the difference in the. wording is not material perhaps to our discussion. From the evidence it appears that this provision of the contracts meant that the defendant could ship the grain any time during the months of January and February,' and that, because of conditions existing during the war, the ports for shipment were at times closed by the government, and consequently the railroads would not receive grain for shipment from Omaha to Baltimore unless the shipper first obtained a special permit for that purpose.
The defendant contends that the contracts should be construed to mean that the plaintiffs agreed, in case the port was not open, to obtain these permits at the times named in the contracts; that the plaintiffs failed to perform that part of the contracts, so that the defendant was unable to ship the grain, and in the meantime the market declined in price to the defendant’s damage. The trial court found: “That defendant’s
*247 counterclaim should be and is sustained, and that the market price of the grain involved in such counterclaim should be taken as of the day after the respective dates on which permits for the shipment of such grain were under the respective contracts to he furnished by plaintiffs to defendant.” The plaintiffs contend that the contracts should not be construed to be an absolute agreement on their part to procure and furnish the permits at the time specified; and that the court erred in finding that the price of the grain should be taken as of the day on which the permits were to be furnished, and that the price should be taken as of the day when the defendant declared the contracts canceled because of the failure to furnish the permits; and that in the meantime the market price had' advanced so that the defendant suffered no damages.It appears to be conceded that, owing to the existing conditions, it was impossible for the plaintiffs to procure the permits, and it might become a very important question whether these contracts should be construed as absolute agreements binding upon the plaintiffs to procure these permits at the times specified, so as to make them liable for any loss the defendant might suffer because of the refusal of the railroad companies to issue the permits. When, at the times 'specified for procuring these permits, it was found that they could not be obtained, the market price of grain was rapidly declining, so that it would be largely to the financial interest of the plaintiffs to delay the shipments and equally to the interests of the defendant to make as early shipments as possible, if the contracts wese to be enforced. It appears that a lively correspondence between these parties .ensued in regard to obtaining the permits. This correspondence and the conditions then existing are very much discussed in the briefs. It seems clear from this correspondence, under the existing conditions, that the defendant was insisting that the plaintiffs were bound by the contracts to furnish the permits as specified in the contracts,
*248 and that any failure to do so would make the plaintiffs liable for any loss that the defendant might suffer on that account; and the plaintiffs were as strongly insisting that, under the circumstances, the failure to procure the permits was not a breach of the contracts on the part of the plaintiffs, but was a misfortune that affected both parties alike, and that the plaintiffs were not liable for any loss that might occur to the defendant by reason of such failure. We do not find it necessary to determine the construction of these contracts upon that point. If we accept the defendant’s theory of the absolute guaranty by the plaintiffs that the permits would be procured — which is by no means clear — the question whether, in considering the defendant’s damage, the market price of the grain should be taken as of the day named in the contracts for furnishing these permits, or of the day when the defendant declared a cancelation of the contracts, becomes a very material question.. The parties have agreed and stipulated in the record the market price of the grain on each of the days named for furnishing the permits, and on the day the contracts were canceled by the defendant. The market price was so high on the last named date that, if that day is taken as the time of the alleged breach of the contracts by the plaintiffs, the defendant suffered no damage, but rather made a profit by the delay in shipments.
After the day named in the contracts for procuring the permits, the defendant continued to insist upon procuring the permits, if possible, and some permits were obtained and further shipments made by defendant under the contracts. This continued until the time for shipments made by defendant had terminated, and the defendant thereupon declared the contracts terminated. This was March 3,1917, and in May, 1918, the defendant filed in the district court the counterclaim for damages.
If the failure on the part of plaintiffs to obtain and furnish the permits on the day named in the contracts
*249 is to be regarded as a breach of the contract, it was immaterial when these permits were obtained, provided they were in time to satisfy the defendant to continue the shipments. Therefore, without waiving the procuring of the permits, the defendant might waive the time of procuring them. This was clearly done by the conduct of the defendant. On January 30, 1917, defendant wrote plaintiffs, “At the present moment the open sales that are now due are waiting for permits to ship and are past due.” Plaintiffs answered by telegraph, “Our hands are tied until railroads give more relief.” As late as February 14, 1917, defendant wired, “Have you-'anything for us to-day?” and February 19, 1917, “What prospects furnishing permit of wheat and hundred corn?” and February 20, Í917, “Can complete your last permit corn to-day if you will furnish permit balance hundred due advise immediately give us some wheat. ’ ’ And then, as the time for shipment would expire on March 1, defendant began to correspond looking to a cancelation of the contracts; and on Sunday, March 2, the defendant forr m.ally, for the first time, declared the contracts forfeited, “because of your failure to furnish railway permits” (under the contracts specifying particularly all of the contracts involved)-, “or make other disposition, we have canceled all of the above contracts.” This was followed on Monday, the 3d, by a letter confirming the cancelation. The measure of damages in such case is the difference between the price agreed upon and the price at the time of the breach of contract complained of. The precise day of furnishing the permits being of no importance, except as it delayed shipment, might be waived by offering to receive the permit at a later date, and the correspondence amounted to such offer. It follows that the breach of contract on plaintiffs’ part was in failing to furnish permits within the time that defendant offered to receive them as a comp lian:.-;: with the contracts, which was March 2, or, as that was Sunday, March 3. It follows that the*250 measure of damages would be the difference between the contract price and the market price on the 3d day of March. The market price advanced after the date named in the contracts for furnishing the permits, so that the defendant suffered no damage.The judgment is therefore reversed and the cause remanded for further proceedings.
REVERSED.
Letton and CorNish, JJ., not sitting.
Document Info
Docket Number: No. 20825
Citation Numbers: 103 Neb. 245, 171 N.W. 50, 1919 Neb. LEXIS 36
Judges: Cornish, Letton, Sedgwick
Filed Date: 3/1/1919
Precedential Status: Precedential
Modified Date: 11/12/2024