Lund-Ross Constructors v. Duke of Omaha , 33 Neb. Ct. App. 73 ( 2024 )


Menu:
  • Nebraska Supreme Court Online Library
    www.nebraska.gov/apps-courts-epub/
    08/06/2024 01:05 AM CDT
    - 73 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Lund-Ross Constructors, Inc., a Nebraska
    corporation, appellant, v. The Duke of
    Omaha, LLC, a Georgia limited liability
    company, et al., appellees.
    ___ N.W.3d ___
    Filed July 30, 2024.    No. A-23-660.
    1. Jurisdiction: Appeal and Error. A jurisdictional issue that does not
    involve a factual dispute presents a question of law.
    2. Arbitration and Award: Appeal and Error. In reviewing a decision
    to vacate, modify, or confirm an arbitration award, an appellate court is
    obligated to reach a conclusion independent of the trial court’s ruling as
    to questions of law.
    3. Judgments: Appeal and Error. When reviewing questions of law, an
    appellate court resolves the questions independently of the lower court’s
    conclusions. However, the trial court’s factual findings will not be set
    aside on appeal unless clearly erroneous.
    4. Arbitration and Award: Federal Acts: Motions to Vacate. Congress
    enacted the Federal Arbitration Act to provide for expedited judicial
    review to confirm, vacate, or modify arbitration awards.
    5. ____: ____: ____. The Federal Arbitration Act favors arbitration agree-
    ments, and this applies in both state and federal courts. Under the act’s
    framework, once an arbitrator comes to a decision and makes an award,
    the parties have several options. The parties can request the court to
    confirm the award pursuant to 
    9 U.S.C. § 9
     (2018), vacate the award
    under 
    9 U.S.C. § 10
     (2018), or modify the award pursuant to 
    9 U.S.C. § 11
     (2018).
    6. Arbitration and Award: Judgments. The purpose of confirming an
    arbitration award is to provide a judgment that can then be enforced
    through court proceedings.
    7. Arbitration and Award: Motions to Vacate. When arbitration has
    already occurred and a party seeks to vacate, modify, or confirm an
    - 74 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    award, an extraordinary level of deference is given to the underlying
    award itself.
    8.   Arbitration and Award: Federal Acts: Motions to Vacate. The Federal
    Arbitration Act sets forth four grounds under which a court may vacate
    an arbitration award, and in the absence of one of these grounds, the
    award must be confirmed.
    9.   Jurisdiction: Appeal and Error. Before reaching the legal issues
    presented for review, it is the power and duty of an appellate court to
    determine whether it has jurisdiction over the matter before it.
    10.   Arbitration and Award: Federal Acts: Contracts. Arbitration in
    Nebraska is governed by the Federal Arbitration Act if it arises from
    a contract involving interstate commerce; otherwise, it is governed by
    Nebraska’s Uniform Arbitration Act.
    11.   Arbitration and Award: Federal Acts: Jurisdiction: Appeal and
    Error. The determination of whether the Federal Arbitration Act or
    Nebraska’s Uniform Arbitration Act governs the arbitration merely
    establishes the framework for the jurisdictional analysis and does not
    answer whether an appellate court has jurisdiction over an appeal.
    12.   Arbitration and Award: Federal Acts: Final Orders: Appeal and
    Error. When the Federal Arbitration Act applies, Nebraska courts deter-
    mine finality for purposes of appeal by applying state procedural rules.
    13.   ____: ____: ____: ____. In order to determine whether state law gov-
    erns the finality for purposes of appeal of an order under the Federal
    Arbitration Act, courts must first apply state procedural rules to deter-
    mine if the order is final for purposes of appeal and then determine
    whether the result of that inquiry would undermine the goals and poli-
    cies of the act.
    14.   Jurisdiction: Legislature: Appeal and Error. For an appellate court
    to have jurisdiction over an appeal, the Legislature must specifically
    provide appellate jurisdiction. Unless a Nebraska statute provides for an
    appeal, such right does not exist.
    15.   Arbitration and Award: Final Orders: Appeal and Error. To deter-
    mine whether an order on an arbitration award is appealable, an appellate
    court first considers whether it is an appealable order under Nebraska’s
    Uniform Arbitration Act and, if not, whether it is a final order under
    
    Neb. Rev. Stat. § 25-1902
     (Cum. Supp. 2022).
    16.   Final Orders: Appeal and Error. Under the final order statute, the
    three types of final orders which may be reviewed on appeal are (1) an
    order affecting a substantial right in an action that, in effect, determines
    the action and prevents a judgment; (2) an order affecting a substantial
    right made during a special proceeding; and (3) an order affecting a
    - 75 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    substantial right made on summary application in an action after a judg-
    ment is rendered.
    17.   ____: ____. To determine if an order denying a motion to vacate is a
    final order, appellate courts consider whether the order affected a sub-
    stantial right. Whether an order affects a substantial right depends on
    whether it affects with finality the rights of the parties in the subject
    matter. It also depends on whether the right could otherwise effectively
    be vindicated. An order affects a substantial right when the right would
    be significantly undermined or irrevocably lost by postponing appel-
    late review.
    18.   Arbitration and Award: Motions to Vacate. The denial of a motion to
    vacate an arbitration award does not affect a substantial right because
    following the denial of the motion to vacate, the unsuccessful party’s
    recourse would then be a motion to confirm the award.
    19.   Judgments: Intent. The meaning of a court’s judgment is a question of
    law that must be determined from all parts thereof, read in its entirety,
    and must be construed as a whole so as to give effect to every word and
    part, if possible, and bring all of its parts into harmony as far as this can
    be done by fair and reasonable interpretation.
    20.   Arbitration and Award: Federal Acts: Contracts: Appeal and Error.
    When the Federal Arbitration Act applies, an appellate court must
    also determine whether the result of the appealability inquiry would
    undermine the goals and policies of the act. The purpose of the act is
    to replace judicial indisposition to arbitration with a national policy
    favoring it and placing arbitration agreements on equal footing with all
    other contracts.
    21.   Arbitration and Award: Motions to Vacate. Under Nebraska’s proce-
    dural law for arbitration under Nebraska’s Uniform Arbitration Act, a
    district court is authorized to sua sponte confirm the award following
    its denial of a motion to vacate. This procedure under the act not only
    allows the court to confirm an award without a request from the parties,
    but requires it.
    22.   Arbitration and Award: Intent. The Federal Arbitration Act contains
    no express preemptive provision, nor does it reflect a congressional
    intent to occupy the entire field of arbitration.
    23.   Arbitration and Award: Appeal and Error. Where the application of
    state appellate procedural rules produces a different outcome than would
    be provided under the Federal Arbitration Act, its goals and policies are
    not undermined if the state rules only affect the timing of the appeal.
    24.   Appeal and Error. An appellate court will not consider an argument or
    theory that is raised for the first time on appeal. Thus, when an issue
    is raised for the first time in an appellate court, it will be disregarded
    - 76 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    inasmuch as a lower court cannot commit error in resolving an issue
    never presented and submitted to it for disposition.
    25.   Arbitration and Award: Contracts: Proof: Appeal and Error. A
    party seeking relief under 
    9 U.S.C. § 10
    (a)(4) (2018) of the Federal
    Arbitration Act bears a heavy burden. It is not enough to show that the
    arbitrator committed an error, or even a serious error. Because the par-
    ties bargained for the arbitrator’s construction of their agreement, an
    arbitral decision even arguably construing or applying the contract must
    stand, regardless of a court’s view of its (de)merits. Only if the arbitra-
    tor acts outside the scope of his or her contractually delegated authority
    by issuing an award that simply reflects the arbitrator’s own notions of
    economic justice, rather than drawing its essence from the contract, may
    a court overturn the determination. Thus, the sole question on judicial
    review is whether the arbitrator interpreted the parties’ contract, not
    whether the arbitrator construed it correctly.
    26.   Arbitration and Award: Federal Acts: Motions to Vacate: Proof.
    Pursuant to 
    9 U.S.C. § 10
    (a)(3) (2018) of the Federal Arbitration Act,
    vacatur is appropriate where the arbitrator’s misbehavior prejudiced the
    rights of any party to the proceeding. Parties seeking to vacate an award
    for misconduct under this section must show that they were deprived of
    a fair hearing. While a fair hearing does not require the arbitrator to hear
    all evidence tendered by the parties, the arbitrator must give each of the
    parties to the dispute an adequate opportunity to present its evidence
    and arguments.
    27.   Arbitration and Award: Motions to Vacate. A court may vacate an
    award only if the arbitrator’s refusal to hear pertinent and material evi-
    dence prejudiced the rights of the parties to the arbitration proceedings.
    28.   Arbitration and Award. The arbitrator must provide an opportunity for
    the parties to present some evidence to support their claims and counter
    the other party’s.
    29.   ____. An invalid portion of an arbitration award may be severed from
    the remainder of the award.
    30.   Arbitration and Award: Appeal and Error. A court reviewing an
    arbitration award under the Federal Arbitration Act can confirm and/or
    vacate the award, either in whole or in part.
    Appeal from the District Court for Douglas County: Molly
    B. Keane, Judge. Affirmed in part, and in part vacated.
    Justin D. Eichmann, of Houghton, Bradford & Whitted, P.C.,
    L.L.O., for appellant.
    - 77 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Justin W. Pritchett and Steven R. Hogan, of Fraser Stryker,
    P.C., L.L.O., for appellee A Raymond Plumbing, Inc.
    Pirtle, Chief Judge, and Riedmann and Bishop, Judges.
    Pirtle, Chief Judge.
    I. INTRODUCTION
    Lund-Ross Constructors, Inc. (Lund-Ross), entered into an
    agreement with The Duke of Omaha, LLC (the Duke), to be
    the general contractor for the construction of an apartment
    complex. Lund-Ross then hired A Raymond Plumbing Inc.
    (Raymond) as a subcontractor. After the Duke withheld pay-
    ment to Lund-Ross, Lund-Ross withheld payment to Raymond.
    Pursuant to an arbitration clause in their contracts, the Duke
    and Lund-Ross proceeded to arbitration. After the arbitration
    hearing, Raymond submitted a counterclaim.
    The arbitrator entered an award finding that the Duke owed
    Lund-Ross $307,103 and that Lund-Ross owed Raymond
    $215,508.31. Citing procedural irregularities, Lund-Ross filed
    a motion to vacate or modify the award in the district court
    for Douglas County, requesting that the court enter an order
    vacating the award, or at least that portion which provided
    for any award made in favor of Raymond. The district court
    denied the motion after finding that none of the grounds for
    vacatur under the Federal Arbitration Act (FAA) were present.
    See 
    9 U.S.C. §§ 1
     through 16 (2018 & Supp. VI 2022). Lund-
    Ross now appeals the district court’s denial of its motion. For
    the following reasons, we affirm in part the award in favor
    of Lund-Ross, and we vacate in part the arbitration award in
    favor of Raymond.
    II. BACKGROUND
    On February 28, 2017, Lund-Ross entered into a contract
    with the Duke to be the general contractor for the construc-
    tion of an apartment complex in Omaha, Nebraska. This
    agreement had a binding arbitration clause where any claims
    - 78 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    between the parties would be resolved through arbitration
    governed by the FAA.
    On May 3, 2017, Lund-Ross subcontracted Raymond to
    provide the plumbing services for the apartment complex.
    As part of that agreement, Raymond agreed to arbitrate any
    claims against Lund-Ross or the Duke. Additionally, this
    contract had a “pay-if-paid” provision that stated if payment
    was withheld from Lund-Ross by the Duke, Lund-Ross would
    withhold payment to Raymond.
    After the completion of the apartment complex, the Duke
    notified Lund-Ross that it was going to withhold $952,599
    from its final payment. Accordingly, Lund-Ross withheld pay-
    ment from Raymond. Lund-Ross and Raymond both pro-
    ceeded to file construction liens for the amounts owed to
    them. Lund-Ross’ lien was for $952,599 and Raymond’s was
    for $215,508.31. Lund-Ross then filed suit against the Duke,
    and Raymond filed suit against the Duke and Lund-Ross.
    Both lawsuits were stayed pending the contractual arbitra-
    tion. However, because Raymond failed to submit a proposed
    scheduling order, its suit was eventually dismissed for lack of
    prosecution and was never refiled.
    On May 11, 2021, Lund-Ross filed a demand for arbitration
    against the Duke where it alleged breach of contract, quantum
    meruit, and unjust enrichment. As part of this demand, Lund-
    Ross included Raymond as a respondent. On June 1, the Duke
    filed a counterclaim against Lund-Ross in the arbitration pro-
    ceedings for breach of contract, breach of express warranty,
    and indemnification.
    Over the next 1½ years, the appointed arbitrator held pro-
    gression conferences and entered four scheduling orders on
    July 26 and December 13, 2021, and March 25 and September
    15, 2022. Over this period, Raymond was in contact with
    Lund-Ross’ counsel and agreed to pay a portion of the hear-
    ing fees so that its counsel could observe the hearing and
    answer any of the arbitrator’s questions about its involvement
    in the underlying controversy. Raymond did not otherwise
    - 79 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    participate in the proceedings and even acknowledged in an
    email to the other parties that it did not intend to be an active
    participant. Accordingly, leading up to the hearing, Raymond
    never provided a statement of its claim, discovery requests, a
    witness list, an exhibit list, or a prehearing brief.
    The arbitration hearing occurred from January 9 to 11, 2023.
    Other than the claims outlined by Lund-Ross and the Duke, no
    other claims or causes of action had been filed in the proceed-
    ings or were pending before the arbitrator at the hearing. While
    no record of the hearing was made, the arbitrator’s order and
    Raymond’s attorney’s affidavit state that the parties generally
    agreed Raymond’s work was satisfactory and the only reason
    Raymond was not being paid was because Lund-Ross did not
    have a contractual obligation to pay Raymond until it had been
    paid by the Duke.
    On January 11, 2023, Raymond’s principal testified at the
    hearing and attempted to assert claims against Lund-Ross.
    But upon cross-examination, the principal acknowledged that
    Raymond never filed any claims in the arbitration proceed-
    ings and never revived its lawsuit against the Duke and Lund-
    Ross. After hearing this testimony, the arbitrator stopped the
    cross-examination and determined that it did not have jurisdic-
    tion over Raymond’s claims because they were never filed.
    Raymond’s principal then left the hearing.
    On January 30, 2023, Lund-Ross and the Duke were noti-
    fied that Raymond had paid an administrative fee and the
    arbitrator had granted Raymond’s request to file a coun-
    terclaim against Lund-Ross in the arbitration proceedings.
    On February 3, Raymond filed an answer and counterclaim
    against Lund-Ross for breach of contract, breach of implied
    covenant of good faith and fair dealing, and quantum meruit/
    unjust enrichment. Within these claims, Raymond alleged
    that Lund-Ross owed it at least $215,508.31. Lund-Ross filed
    an objection to Raymond’s counterclaim, arguing that it was
    untimely, and motioned to strike it.
    - 80 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    On March 9, 2023, without responding to Lund-Ross’ objec-
    tion and motion to strike, the arbitrator entered his award that
    found the Duke owed Lund-Ross $307,103 and Lund-Ross
    owed Raymond $215,508.31. On March 29, Lund-Ross filed a
    “Motion to Modify/Correct Arbitration Award” with the arbi-
    trator requesting that Raymond’s award be removed. Raymond
    filed an objection to this motion, and on April 28, the arbitra-
    tor ultimately denied the motion.
    On May 23, 2023, Lund-Ross filed a motion to vacate
    or modify the arbitration award in the district court. In its
    motion, Lund-Ross argued the award should be vacated pur-
    suant to 
    9 U.S.C. § 10
    (a) of the FAA due to the arbitrator’s
    misconduct and misbehavior in allowing Raymond to file its
    claims after the hearing concluded and refusing to receive
    evidence in opposition to those claims. The district court
    denied Lund-Ross’ motion and, in its order, stated:
    Here, although the Court recognizes [Lund-Ross’]
    concerns regarding their ability to present and rebut
    evidence regarding [Raymond’s] claims, the Court does
    not find that one of the four grounds under which a
    court may vacate an arbitration award [outlined in 
    9 U.S.C. § 10
    (a)] is present. Therefore, the award must be
    confirmed.
    Following this order, Raymond filed a motion to clarify
    whether the district court’s order confirmed the arbitration
    award or merely indicated that it would be confirmed upon
    the subsequent filing of a motion to confirm. That motion was
    not answered before Lund-Ross appealed the district court’s
    denial of its motion to vacate.
    On December 22, 2023, Raymond motioned for this court
    to summarily dismiss Lund-Ross’ appeal. Raymond argued
    that because the district court’s order on Lund-Ross’ motion
    to vacate was not a final, appealable order, we did not have
    jurisdiction over the appeal. On January 8, 2024, we denied
    Raymond’s motion to dismiss and directed the parties to
    address the jurisdiction issue in their briefs.
    - 81 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    III. ASSIGNMENTS OF ERROR
    Lund-Ross assigns, consolidated, restated, and reordered,
    that the district court erred in (1) failing to determine Raymond
    waived its right to arbitrate its claims and (2) failing to vacate
    the arbitration award at least as to the portion providing an
    award in favor of Raymond pursuant to 
    9 U.S.C. § 10
     because
    the arbitrator (a) was guilty of misbehavior that caused it
    prejudice under § 10(a)(3) and (b) exceeded his powers or so
    imperfectly executed them that a mutual, final, and definite
    award was not made under § 10(a)(4).
    IV. STANDARD OF REVIEW
    [1] A jurisdictional issue that does not involve a factual
    dispute presents a question of law. See Cinatl v. Prososki, 
    307 Neb. 477
    , 
    949 N.W.2d 505
     (2020).
    [2] In reviewing a decision to vacate, modify, or confirm
    an arbitration award, an appellate court is obligated to reach
    a conclusion independent of the trial court’s ruling as to ques-
    tions of law. 
    Id.
    [3] When reviewing questions of law, an appellate court
    resolves the questions independently of the lower court’s con-
    clusions. See 
    id.
     However, the trial court’s factual findings
    will not be set aside on appeal unless clearly erroneous. 
    Id.
    V. ANALYSIS
    [4-6] This matter involves the parties’ arbitration under
    the FAA. Congress enacted the FAA to provide for “‘expe-
    dited judicial review to confirm, vacate, or modify arbitra-
    tion awards.’” Seldin v. Estate of Silverman, 
    305 Neb. 185
    ,
    200, 
    939 N.W.2d 768
    , 783 (2020). The FAA favors arbitra-
    tion agreements, and this applies in both state and federal
    courts. Seldin v. Estate of Silverman, 
    supra.
     Under the FAA’s
    framework, once an arbitrator comes to a decision and makes
    an award, the parties have several options. The parties can
    request the court to confirm the award pursuant to 
    9 U.S.C. § 9
    , vacate the award under 
    9 U.S.C. § 10
    , or modify the
    award pursuant to 
    9 U.S.C. § 11
    . The purpose of confirming
    - 82 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    an arbitration award is to provide a judgment that can then be
    enforced through court proceedings. Cinatl v. Prososki, 
    supra.
    [7] When arbitration has already occurred and a party seeks
    to vacate, modify, or confirm an award, “an extraordinary level
    of deference [is given] to the underlying award itself.” Seldin
    v. Estate of Silverman, 
    305 Neb. at 200
    , 939 N.W.2d at 783
    (internal quotation marks omitted). The U.S. Supreme Court
    has instructed that under the FAA, a court may vacate an arbi-
    trator’s decision “only in very unusual circumstances.” Seldin
    v. Estate of Silverman, 
    305 Neb. at 201
    , 939 N.W.2d at 783
    (internal quotation marks omitted).
    [8] The FAA sets forth four grounds under which a court
    may vacate an arbitration award, and in the absence of one of
    these grounds, the award must be confirmed. Seldin v. Estate of
    Silverman, 
    supra.
     Those grounds are as follows:
    “(1) where the award was procured by corruption,
    fraud, or undue means;
    “(2) where there was evident partiality or corruption in
    the arbitrators, or either of them;
    “(3) where the arbitrators were guilty of misconduct
    in refusing to postpone the hearing, upon sufficient cause
    shown, or in refusing to hear evidence pertinent and mate-
    rial to the controversy; or of any other misbehavior by
    which the rights of any party have been prejudiced; or
    “(4) where the arbitrators exceeded their powers, or
    so imperfectly executed them that a mutual, final, and
    definite award upon the subject matter submitted was not
    made.”
    
    Id. at 201
    , 939 N.W.2d at 783, quoting 
    9 U.S.C. § 10
    (a).
    1. Jurisdiction
    The parties first contest whether we have proper juris-
    diction over this appeal. Before evaluating the legal issues
    presented for review, it is the duty of an appellate court to
    determine whether it has jurisdiction over the matter before
    it. McPherson v. Walgreens Boot Alliance, 
    314 Neb. 875
    , 
    993 N.W.2d 679
     (2023).
    - 83 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Raymond asserts we lack jurisdiction over the appeal
    because the district court’s order was not a final, appealable
    order. Raymond contends that an order denying a motion to
    vacate an arbitration award is not an appealable order under 
    9 U.S.C. § 16
    (a) of the FAA, nor is it a final order under 
    Neb. Rev. Stat. § 25-1902
     (Cum. Supp. 2022). As to the latter argu-
    ment, Raymond asserts the appeal cannot be perfected until
    the district court rules on a motion to confirm and finalizes
    the rights of the parties. Until that occurs, it argues this is an
    interlocutory appeal for which we lack jurisdiction.
    In response, Lund-Ross essentially argues that the district
    court’s order is a final, appealable order because it both denied
    its motion to vacate and confirmed the award. And, in the
    alternative that the court’s order did not confirm the award,
    Lund-Ross cites various cases from the Eighth Circuit where
    it considered appeals from the denials of motions to vacate
    arbitration awards without questioning whether it had appellate
    jurisdiction under the FAA.
    [9-12] Before reaching the legal issues presented for review,
    it is the power and duty of an appellate court to determine
    whether it has jurisdiction over the matter before it. Seldin v.
    Estate of Silverman, 
    305 Neb. 185
    , 
    939 N.W.2d 768
     (2020).
    Arbitration in Nebraska is governed by the FAA if it arises
    from a contract involving interstate commerce; otherwise, it
    is governed by Nebraska’s Uniform Arbitration Act (UAA).
    Seldin v. Estate of Silverman, 
    supra.
     In this matter, it is
    uncontested that the arbitration involved interstate commerce
    and was governed by the FAA. However, the determination of
    whether the FAA or the UAA governs the arbitration merely
    establishes the framework for the jurisdictional analysis and
    does not answer whether we have appellate jurisdiction over
    this appeal. See McPherson v. Walgreens Boot Alliance, 
    supra.
    This is so because even when the FAA applies, Nebraska
    courts determine finality for purposes of appeal by apply-
    ing state procedural rules. McPherson v. Walgreens Boot
    Alliance, 
    supra.
    - 84 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    [13,14] As the Nebraska Supreme Court provided in Webb v.
    American Employers Group, 
    268 Neb. 473
    , 481, 
    684 N.W.2d 33
    , 41 (2004):
    [T]o determine whether state law governs the finality for
    purposes of appeal of an order . . . under the FAA, we
    must first apply our state procedural rules to determine if
    the order is final for purposes of appeal and then deter-
    mine whether the result of that inquiry would undermine
    the goals and policies of the FAA.
    For this court to have jurisdiction over an appeal, the Legislature
    must specifically provide appellate jurisdiction. McPherson
    v. Walgreens Boot Alliance, 
    supra.
     In other words, unless a
    Nebraska statute provides for an appeal, such right does not
    exist. 
    Id.
    [15] In Cinatl v. Prososki, 
    307 Neb. 477
    , 
    949 N.W.2d 505
    (2020), the Supreme Court applied state procedural rules to
    determine if it had jurisdiction over an appeal from the denial
    of a motion to vacate an arbitration award that was governed
    by the UAA. In finding that the order denying the motion to
    vacate was not a final, appealable order, the court stated, “To
    determine whether the [order is] appealable, we first consider
    whether [it is an] appealable order[] under the [UAA] and, if
    not, whether [it is a] final order[] under . . . § 25-1902.” Cinatl
    v. Prososki, 
    307 Neb. at 486
    , 949 N.W.2d at 514.
    [16] The court first decided that 
    Neb. Rev. Stat. § 25-2620
    (a)
    (Reissue 2016) of the UAA was silent as to whether denials
    of a motion to vacate were appealable. See Cinatl v. Prososki,
    
    supra.
     As such, it proceeded to evaluate its jurisdiction under
    Nebraska’s final order statute, § 25-1902. Under the final
    order statute, the three types of final orders which may be
    reviewed on appeal are (1) an order affecting a substantial
    right in an action that, in effect, determines the action and
    prevents a judgment; (2) an order affecting a substantial right
    made during a special proceeding; and (3) an order affect-
    ing a substantial right made on summary application in an
    - 85 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    action after a judgment is rendered. See Cullinane v. Beverly
    Enters. - Neb., 
    300 Neb. 210
    , 
    912 N.W.2d 774
     (2018).
    [17] To determine if the order denying the motion to vacate
    was a final order, the court considered whether the order
    affected a substantial right. Whether an order affects a sub-
    stantial right depends on whether it affects with finality the
    rights of the parties in the subject matter. Cinatl v. Prososki,
    
    supra.
     It also depends on whether the right could otherwise
    effectively be vindicated. 
    Id.
     An order affects a substantial
    right when the right would be significantly undermined or
    irrevocably lost by postponing appellate review. 
    Id.
    [18] Citing to a case from the Hawaii Supreme Court, the
    Cinatl court concluded that the denial of the motion to vacate
    did not affect a substantial right because following the denial
    of the motion to vacate, “the unsuccessful movant’s recourse
    would then be a motion to confirm the award.” 
    307 Neb. at 488
    , 949 N.W.2d at 515 (citing Salud v. Financial Sec. Ins.
    Co., Ltd., 
    69 Haw. 427
    , 
    745 P.2d 290
     (1987)). It continued to
    indicate that because a motion to confirm the award should
    occur swiftly after a denial of a motion to vacate, the unsuc-
    cessful movant would be able to perfect the appeal and obtain
    appellate review of the order confirming the award. Cinatl v.
    Prososki, 
    supra.
     Thus, the court stated, “though not immedi-
    ately appealable, an unsuccessful movant for judicial vacatur
    should not have to wait long to obtain appellate review.” 
    Id. at 489
    , 949 N.W.2d at 516.
    In the current matter, Lund-Ross maintains that the holding
    in Cinatl is inapplicable because the district court’s order in
    this case both denied its motion to vacate and confirmed the
    award. Accordingly, Lund-Ross argues that there is nothing
    left for the court to decide. Raymond opposes this conten-
    tion and asserts that the district court’s order did not confirm
    the award.
    [19] The meaning of a court’s judgment is a question of
    law that must be determined from all parts thereof, read in its
    entirety, and must be construed as a whole so as to give effect
    - 86 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    to every word and part, if possible, and bring all of its parts
    into harmony as far as this can be done by fair and reasonable
    interpretation. See Bayne v. Bayne, 
    302 Neb. 858
    , 
    925 N.W.2d 687
     (2019). We determine that because the district court con-
    cluded its order by stating, “Therefore, the award must be
    confirmed,” the court’s order confirmed the arbitration award.
    Because the court’s order confirmed the arbitration award,
    there is nothing left for the district court to decide. As such,
    we conclude the district court’s denying Lund-Ross’ motion
    to vacate and confirming the award affected a substantial right
    and was a final, appealable order.
    [20] While we have concluded that the district court’s order
    denying vacatur and confirming the award is appealable under
    Nebraska’s procedural rules, Webb v. American Employers
    Group, 
    268 Neb. 473
    , 
    684 N.W.2d 33
     (2004), instructs that
    when the FAA applies, we must also determine whether the
    result of the appealability inquiry would undermine the goals
    and policies of the FAA. See McPherson v. Walgreens Boot
    Alliance, 
    314 Neb. 875
    , 
    993 N.W.2d 679
     (2023). As articu-
    lated by the U.S. Supreme Court, the purpose of the FAA is
    to “replace judicial indisposition to arbitration with a ‘national
    policy favoring [it] and plac[ing] arbitration agreements on
    equal footing with all other contracts.’” Hall Street Associates,
    L. L. C. v. Mattel, Inc., 
    552 U.S. 576
    , 581, 
    128 S. Ct. 1396
    ,
    
    170 L. Ed. 2d 254
     (2008).
    [21] Here, we recognize that utilizing Nebraska’s state
    procedural rules may yield a different result compared to the
    application of the FAA. Applying Nebraska’s procedural law
    for arbitration under the UAA, the district court was autho-
    rized to sua sponte confirm the award following its denial of
    Lund-Ross’ motion to vacate. 
    Neb. Rev. Stat. § 25-2613
    (d)
    (Reissue 2016) of the UAA states “If the application to vacate
    is denied and no motion to modify or correct the award is
    pending, the court shall confirm the award.” In statutory
    interpretation, “shall,” generally, is considered mandatory and
    inconsistent with the idea of discretion. Prokop v. Lower
    - 87 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Loup NRD, 
    302 Neb. 10
    , 
    921 N.W.2d 375
     (2019). Therefore,
    the procedure under the UAA not only allowed the court to
    confirm the award without a request from the parties, but
    required it.
    In contrast, the FAA does not contain a similar provision
    allowing trial courts to confirm the arbitration award in the
    absence of a pending motion to vacate or modify. And federal
    courts do not all agree as to whether a court can confirm an
    arbitration award under the FAA in the absence of a specific
    motion requesting it. Several federal courts have found that
    an explicit motion to confirm is not necessary and, instead,
    treated motions to dismiss the opposing parties’ motions to
    vacate as the practical equivalents of a motion to confirm.
    See Maidman v. O’Brien, 
    473 F. Supp. 25
     (S.D.N.Y. 1979).
    See, also, Sanluis Developments v. CCP Sanluis, L.L.C., 
    556 F. Supp. 2d 329
     (S.D.N.Y. 2008); General Elec. Co. v. Anson
    Stamping Co. Inc., 
    426 F. Supp. 2d 579
     (W.D. Ky. 2006).
    Likewise, one federal court treated a motion for summary
    judgment as an implicit motion to confirm. See Andrea Doreen
    v. Building Material Local Union 282, 
    250 F. Supp. 2d 107
    (E.D.N.Y. 2003).
    However, in at least one decision, the U.S. District Court
    for the District of Nebraska has signaled that a formal motion
    to confirm is necessary to confirm an arbitration award under
    the FAA because 
    9 U.S.C. § 9
     requires a specific factual find-
    ing of “an agreement by the parties for the entry of a judg-
    ment on the award.” Riddle v. Wachovia Securities, LLC, No.
    8:05CV87, 
    2006 WL 83101
     at *2 (D. Neb. Jan. 12, 2006).
    While this case involved a different procedural posture, the
    court explained that the parties needed to file a formal motion
    to confirm and that the mere opposition to a motion to
    vacate and a footnote in an opposing brief seeking confirma-
    tion were not the functional equivalents of a motion seeking
    confirmation.
    [22,23] Despite this potential disparity in outcomes between
    Nebraska’s procedural rules and the FAA, we determine that
    - 88 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    our decision regarding the finality of the district court’s order
    does not undermine the goals and policies of the FAA. As the
    Supreme Court has stated, “‘The FAA contains no express pre-
    emptive provision, nor does it reflect a congressional intent
    to occupy the entire field of arbitration.’” Kremer v. Rural
    Community Ins. Co., 
    280 Neb. 591
    , 602, 
    788 N.W.2d 538
    , 549
    (2010) (quoting Volt Info. Sciences v. Leland Stanford Jr. U.,
    
    489 U.S. 468
    , 
    109 S. Ct. 1248
    , 
    103 L. Ed. 2d 488
     (1989)).
    Additionally, the Nebraska Supreme Court has twice indicated
    that where the application of state appellate procedural rules
    produces a different outcome than would be provided under
    the FAA, the FAA’s goals and policies are not undermined if
    the state rules only affect the timing of the appeal.
    In Kremer v. Rural Community Ins. Co., supra, the court
    found that an order compelling arbitration was appealable
    under Nebraska’s final order statute but was not appealable
    under the FAA. Although the outcomes under the FAA and
    our state procedural rules were different, Kremer held that the
    state procedures only impacted the timing of the appeal and
    did not interfere with the parties’ substantive rights to enforce
    their agreement. Because of this, the court found that allow-
    ing an immediate appeal did not undermine the goals of the
    FAA. Similarly, in McPherson v. Walgreens Boot Alliance,
    
    314 Neb. 875
    , 
    993 N.W.2d 679
     (2023), the court found that
    the FAA would allow an interlocutory appeal from an order
    staying arbitration where Nebraska’s procedural rules would
    not. Despite this incongruence, the court cited to Kremer in
    deciding that applying the state procedural rule did not under-
    mine the goals of the FAA because it only impacted the tim-
    ing of the appeal, not the substantive rights of the parties to
    enforce the agreement.
    In the matter at hand, our decision that the district court’s
    order confirmed the arbitration award and thus affected a sub-
    stantial right only affects the timing of the appeal and does
    not impact the substantive rights of the parties. Accordingly,
    we conclude that the district court’s order was a final,
    - 89 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    appealable order under Nebraska’s final order statute and that
    allowing the appeal does not undermine the goals and objec-
    tives of the FAA. Therefore, we find that we have appellate
    jurisdiction over this appeal.
    2. Waiver
    Lund-Ross assigns the district court erred in failing to find
    that Raymond waived its right to arbitrate. Lund-Ross gener-
    ally asserts that by not participating in the arbitration until
    after the hearing, Raymond acted inconsistently with its right
    and, therefore, waived its right to partake in the arbitration.
    [24] Although Lund-Ross objected to Raymond’s claims
    as untimely and prejudicial, it did not specifically claim that
    Raymond had waived its right to participate in the arbitra-
    tion; therefore, Lund-Ross did not properly raise this argument
    either in the arbitration proceeding or in its motion to vacate
    filed in the district court. An appellate court will not consider
    an argument or theory that is raised for the first time on appeal.
    Eletech, Inc. v. Conveyance Consulting Group, 
    308 Neb. 733
    ,
    
    956 N.W.2d 692
     (2021). Thus, when an issue is raised for the
    first time in an appellate court, it will be disregarded inasmuch
    as a lower court cannot commit error in resolving an issue
    never presented and submitted to it for disposition. 
    Id.
     Because
    Lund-Ross did not raise the issue of waiver in its motion to
    vacate, the argument was never presented to the district court.
    Without a ruling from the district court, we are unable to find
    that it committed error. Therefore, we conclude that Lund-
    Ross’ assignment of error pertaining to the alleged waiver of
    Raymond’s right to arbitration fails.
    3. Failure to Vacate Arbitration Award
    Lund-Ross assigns the district court erred in failing to vacate
    the arbitration award under 
    9 U.S.C. § 10
     because the arbitrator
    exceeded his powers and/or imperfectly executed them under
    § 10(a)(4) and was guilty of misbehavior that prejudiced its
    rights under § 10(a)(3).
    - 90 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    (a) Exceeded Powers or
    Imperfectly Executed Them
    Lund-Ross argues the award should be vacated under 
    9 U.S.C. § 10
    (a)(4) of the FAA because the arbitrator exceeded
    his powers and/or so imperfectly executed them that a mutual,
    final, and definite award was not made.
    [25] A party seeking relief under 
    9 U.S.C. § 10
    (a)(4) bears
    a heavy burden. Oxford Health Plans LLC v. Sutter, 
    569 U.S. 564
    , 
    133 S. Ct. 2064
    , 
    186 L. Ed. 2d 113
     (2013). It is not
    enough to show that the arbitrator committed an error, or even
    a serious error. 
    Id.
     Because the parties bargained for the arbi-
    trator’s construction of their agreement, an arbitral decision
    even arguably construing or applying the contract must stand,
    regardless of a court’s view of its “(de)merits.” 
    Id.,
     
    569 U.S. at 569
    . Only if the arbitrator acts outside the scope of his or
    her contractually delegated authority by issuing an award that
    simply reflects the arbitrator’s own notions of economic jus-
    tice, rather than drawing its essence from the contract, may a
    court overturn the determination. 
    Id.
     Thus, the sole question
    on judicial review is whether the arbitrator interpreted the par-
    ties’ contract, not whether the arbitrator construed it correctly.
    
    Id.
     See, also, City of Omaha v. Professional Firefighters Assn.,
    
    309 Neb. 918
    , 
    963 N.W.2d 1
     (2021) (stating that same stan-
    dard of judicial review applies under the UAA).
    We determine that Lund-Ross is not entitled to relief under
    
    9 U.S.C. § 10
    (a)(4) because the record demonstrates the
    arbitrator interpreted the contract between the parties. In his
    award, the arbitrator stated:
    There was no testimony by Lund-Ross or The Duke that
    . . . Raymond failed to meet any of its obligations under
    the subcontract between the parties. There was testimony
    that Lund[-]Ross withheld from [Raymond] the amount
    of $215,508.31, based on the “pay-if[-]paid” provision
    under its subcontract with Lund-Ross based on the with-
    holding of The Duke from Lund-Ross in the amount
    of $952,599. This arbitration resolved the withholding
    - 91 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    issue and I find that [Raymond] is now entitled to pay-
    ment of the amount withheld.
    This language shows the arbitrator’s award was based on his
    interpretation of the agreement between the parties and the
    evidence presented to him. Although we acknowledge Lund-
    Ross’ assertions that it was prevented from presenting certain
    evidence, our task here is limited to deciding whether the arbi-
    trator was arguably adhering to contract interpretation when
    he made the award. We determine that he was. Therefore, we
    conclude the district court did not err in not vacating the arbi-
    tration award under 
    9 U.S.C. § 10
    (a)(4).
    (b) Misbehavior That Prejudiced
    Lund-Ross’ Rights
    Lund-Ross argues the award should be vacated under 
    9 U.S.C. § 10
    (a)(3) of the FAA because the arbitrator was guilty
    of misbehavior that prejudiced its rights. Lund-Ross con-
    tends the arbitrator misbehaved by preventing the full cross-
    examination of Raymond’s principal, not providing any notice
    of Raymond’s counterclaims until after the hearing, and not
    allowing Lund-Ross the opportunity to present evidence in
    opposition to Raymond’s counterclaims.
    Raymond contends this assignment of error should fail
    because this is the first time that Lund-Ross has argued the
    arbitration should be vacated under 
    9 U.S.C. § 10
    (a)(3).
    When an issue is raised for the first time in an appellate
    court, it will be disregarded inasmuch as a lower court can-
    not commit error in resolving an issue never presented and
    submitted to it for disposition. Eletech, Inc. v. Conveyance
    Consulting Group, 
    308 Neb. 733
    , 
    956 N.W.2d 692
     (2021).
    Lund-Ross’ motion to vacate did not specifically state that
    it sought vacation under this section of the FAA. However,
    its motion claimed the arbitrator’s actions were “extremely
    prejudicial” and laid out factual allegations claiming that the
    arbitrator allowed Raymond to file counterclaims without
    notifying Lund-Ross and did not allow Lund-Ross to present
    - 92 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    evidence in opposition to those claims. Seemingly because of
    the wide breadth of these allegations, the district court found
    it necessary to analyze whether vacatur was proper under
    each of the four grounds provided within 
    9 U.S.C. § 10
     of
    the FAA. Therefore, because Lund-Ross’ motion to vacate
    contained factual allegations encompassing § 10(a)(3) and the
    district court did, in fact, decide that vacation was improper
    under that section, we conclude that this assignment of error
    is properly before us.
    [26,27] Pursuant to 
    9 U.S.C. § 10
    (a)(3) of the FAA, vacatur
    is appropriate where the arbitrator’s misbehavior prejudiced
    the rights of any party to the proceeding. See Seldin v. Estate
    of Silverman, 
    305 Neb. 185
    , 
    939 N.W.2d 768
     (2020). Parties
    seeking to vacate an award for misconduct under this sec-
    tion must show that they were deprived of a fair hearing. 
    Id.
    While a fair hearing does not require the arbitrator to hear all
    evidence tendered by the parties, the arbitrator must give each
    of the parties to the dispute an adequate opportunity to pre­
    sent its evidence and arguments. Hoteles Condado Beach Etc.
    v. Union De Etc., 
    763 F.2d 34
     (1st Cir. 1985); Global Gold
    Min., LLC v. Ayvazian, 
    612 Fed. Appx. 11
     (2d Cir. 2015). In
    other words, a court may vacate an award only if the arbitra-
    tor’s refusal to hear pertinent and material evidence prejudiced
    the rights of the parties to the arbitration proceedings. Three
    S Delaware v. DataQuick Information Systems, 
    492 F.3d 520
    (4th Cir. 2007); Mical v. Glick, 
    581 Fed. Appx. 568
     (7th Cir.
    2014); Aviles v. Charles Schwab & Co., Inc., 
    435 Fed. Appx. 824
     (11th Cir. 2011).
    Three frequently cited and persuasive decisions by the First,
    Second, and Fifth Circuits illustrate the kinds of refusals to
    consider evidence that have run afoul of 
    9 U.S.C. § 10
    (a)(3).
    The first is Hoteles Condado Beach Etc. v. Union De Etc.,
    supra, where an employee was fired and criminally charged
    for exposing himself to a guest. In the employment arbitra-
    tion that followed, the guest refused to testify without her
    husband present. The arbitrator denied her request, so in lieu
    - 93 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    of the woman’s live testimony, the arbitrator permitted the
    hotel to introduce a transcript of the couple’s testimony during
    the criminal case. But the arbitrator then refused to give the
    transcript any weight and found in the employee’s favor. The
    First Circuit found that this constituted misconduct because
    the “testimony was unquestionably relevant” and no other evi-
    dence was available to substantiate or to refute the company’s
    charges. Id. at 40.
    The second case is Tempo Shain Corp. v. Bertek, Inc., 
    120 F.3d 16
    , 17 (2d Cir. 1997), where the Second Circuit found
    that an arbitration panel’s refusal to wait for a witness with
    “crucial testimony” constituted misconduct under 
    9 U.S.C. § 10
    (a)(3). The witness was temporarily unavailable due to a
    family medical problem, but because the panel deemed that
    his testimony would be cumulative to other evidence, it did
    not continue the hearing. The Second Circuit found that there
    was no reasonable basis to think the testimony was cumulative
    and that therefore, the arbitrator committed misbehavior that
    prejudiced one of the parties by excluding evidence “plainly
    ‘pertinent and material to the controversy.’” Tempo Shain
    Corp. v. Bertek, Inc., 
    120 F.3d at 20
    .
    Lastly, in Gulf Coast Indus. Workers Union v. Exxon Co.,
    USA, 
    70 F.3d 847
     (5th Cir. 1995), an employer hired an
    investigator to search for drugs in its refinery. After the inves-
    tigator found marijuana in one of the employee’s vehicles,
    the employee refused to take a drug test and was fired. In
    the ensuing arbitration, the company attempted to introduce
    test results to prove the discovered substance was marijuana.
    However, the arbitrator said that was unnecessary because
    the test results were already in evidence. After the hearings
    were complete, the arbitrator ordered the employee to be
    reinstated because the employer had not proved the substance
    was marijuana.
    In its finding that this constituted misconduct, the Fifth
    Circuit stated, “not only did the arbitrator refuse to con-
    sider evidence of the positive drug test, he prevented [the
    - 94 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    company] from presenting additional evidence by misleading
    it into believing that [the test results] had been admitted as a
    business record.” Id. at 850. The court continued to explain
    that the arbitrator’s use of the company’s failure to present
    evidence, which he told them not to present, as a predicate
    for ignoring the test results was misconduct that fell squarely
    within the scope of 
    9 U.S.C. § 10
    (a)(3).
    Although these cases are not perfectly analogous to the
    current matter, the present case is an example of a similarly
    inexplicable refusal to hear “evidence pertinent and material
    to the controversy.” See 
    9 U.S.C. § 10
    (a)(3). The arbitra-
    tor not only cut short Lund-Ross’ ability to cross-examine
    Raymond’s principal at the hearing, but he fully denied its
    ability to offer any evidence in response to Raymond’s coun-
    terclaims. While the arbitrator and Raymond state there was
    no complaint with the quality of Raymond’s work product, an
    issue existed as to whether Raymond’s delay on the project
    contributed to the liquidated damages assessed against Lund-
    Ross. If it did, this issue was certainly pertinent and material
    to the controversy.
    [28] While the case law from various jurisdictions unani-
    mously supports the proposition that an arbitrator does not
    need to consider every piece of relevant evidence presented
    to them, the arbitrator must provide an opportunity for the
    parties to present some evidence to support their claims and
    counter the other party’s evidence. See Global Gold Min., LLC
    v. Ayvazian, 
    612 Fed. Appx. 11
    , 14 (2d Cir. 2015) (“[f]airness
    requires arbitrators to give a party an ‘adequate opportunity to
    present its evidence and argument’”). We do not believe that
    the arbitrator’s limiting the cross-examination of Raymond’s
    principal, allowing Raymond to file its counterclaims after
    the hearing had already concluded over Lund-Ross’ objection,
    refusing to consider evidence in opposition to those counter-
    claims, and proceeding to award Raymond the exact amount it
    sought are indica of a fundamentally fair hearing.
    - 95 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Therefore, we determine that by allowing Raymond to file
    its counterclaim after the hearing and then subsequently refus-
    ing to consider Lund-Ross’ evidence in opposition to the
    counterclaim, the arbitrator was guilty of misconduct and
    misbehavior that prejudiced Lund-Ross’ rights. See Cong. of
    Holy Family Cath. Ch. v. Mickey Const., 
    500 So. 2d 802
     (La.
    App. 1986) (court found allowing untimely counterclaim to be
    filed and accepting evidence on it at arbitration hearing sup-
    ported vacatur of award on basis that arbitrators were guilty
    of any other misbehavior by which rights of any party have
    been prejudiced). Accordingly, we conclude that the district
    court erred in not vacating the arbitration award in favor of
    Raymond pursuant to 
    9 U.S.C. § 10
    (a)(3) of the FAA. This
    would leave the award in favor of Lund-Ross undisturbed. The
    question then becomes whether partial vacatur of an award is
    allowed under the FAA and Nebraska law.
    [29] Neither party provided authority on this particular
    issue, nor did we locate any Nebraska or Eighth Circuit
    cases on point. However, Connecticut has a long history of
    allowing arbitration awards to be severed. The Connecticut
    Supreme Court has routinely found that “an invalid portion
    of an arbitration award may be severed from the remainder of
    the award.” Blondeau v. Baltierra, 
    337 Conn. 127
    , 174, 
    252 A.3d 317
    , 348 (2020). The court has stated that (1) “‘[when]
    specific questions have been submitted to the arbitrators, we
    have held that the portion of the arbitrators’ award that was
    entirely outside the submission was void’”; (2) “‘when an
    arbitrator exceeds his authority, the award is void only to the
    extent that he does so, if the part [that] is void can be sepa-
    rated from the rest without injustice and without affecting the
    merits of the part of the award [that] is within the submis-
    sion’”; and (3) “‘[i]f several distinct matters are submitted
    [to arbitration], the award as to some of them may be good
    while it is void as to the residue.’” 
    Id. at 174
    , 252 A.3d at
    348-49. See, also, Bodner v. United Services Auto. Ass’n, 
    222 Conn. 480
    , 
    610 A.2d 1212
     (1992); Local 63, Textile Workers
    - 96 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    Union v. Cheney Brothers, 
    141 Conn. 606
    , 
    109 A.2d 240
    (1954); Parmelee v. Allen, 
    32 Conn. 115
     (1864), overruled
    on other grounds, Alexson v. Foss, 
    276 Conn. 599
    , 
    887 A.2d 872
     (2006).
    [30] The Second Circuit has similar case law that directly
    references 
    9 U.S.C. § 10
     of the FAA. “A court reviewing an
    arbitration award under the FAA ‘can confirm and/or vacate the
    award, either in whole or in part.’” Scandinavian Reinsurance
    v. Saint Paul, 
    668 F.3d 60
    , 71 (2d Cir. 2012). While that opin-
    ion does not provide any further discussion regarding the issue,
    it cited a prior Second Circuit opinion that did. See D.H. Blair
    & Co., Inc. v. Gottdiener, 
    462 F.3d 95
     (2d Cir. 2006). In that
    prior opinion, the court stated:
    Because “[a]rbitration awards are not self-enforcing,”
    they must be given force and effect by being converted
    to judicial orders by courts; these orders can confirm
    and/or vacate the award, either in whole or in part. . . .
    Here, [the party] petitioned the court to confirm in part
    and vacate in part the arbitration award. That request
    simply sought to give effect to the arbitration award. The
    partial vacatur of the award sought . . . does not alter
    the nature of the action, which we believe is properly
    considered to involve “enforcing” the arbitration award.
    
    Id. at 104
    . The court ultimately reversed the decision of the
    district court, but did not take issue with the proposed proce-
    dure of only partially vacating the award.
    Based upon the authority cited above, we believe the proper
    result here is to affirm the award in favor of Lund-Ross’
    claim against the Duke, but to vacate the award in favor of
    Raymond’s claim against Lund-Ross.
    VI. CONCLUSION
    We conclude that we have jurisdiction over this appeal
    under our state procedural rules and that Raymond did not
    waive its right to arbitration. We further conclude that the
    district court did not err in refusing to vacate the arbitration
    - 97 -
    Nebraska Court of Appeals Advance Sheets
    33 Nebraska Appellate Reports
    LUND-ROSS CONSTRUCTORS V. DUKE OF OMAHA
    Cite as 
    33 Neb. App. 73
    award under 
    9 U.S.C. § 10
    (a)(4), but did err in not vacat-
    ing the award under § 10(a)(3) as to Raymond. We therefore
    affirm that part of the district court’s decision in favor of
    Lund-Ross and against the Duke, and we vacate that part of
    the decision of the district court in favor of Raymond and
    against Lund-Ross.
    Affirmed in part, and in part vacated.
    

Document Info

Docket Number: A-23-660

Citation Numbers: 33 Neb. Ct. App. 73

Filed Date: 7/30/2024

Precedential Status: Precedential

Modified Date: 8/6/2024