Eureka Co. v. State Engineer C/W 63258 ( 2015 )


Menu:
  •                                   ORDER OF REVERSAL AND REMAND
    These consolidated appeals challenge the district court's
    orders denying judicial review of the State Water Engineer's decisions
    affecting water rights. Seventh Judicial District Court, Eureka County;
    Dan L. Papez, Judge. Under NRS 533.370(2), the State Engineer "shall
    reject" an application for a proposed use of water or change of existing
    water rights where that "proposed use or change conflicts with existing
    rights." The parties ask this court to determine whether this section
    allows for the State Engineer to take into account the applicant's ability to
    mitigate the drying up of existing rights holders' water sources when
    determining if a proposed use or change will conflict with existing rights.
    However, even assuming that under NRS 533.370(2) the State Engineer
    has authority to grant an application that conflicts with existing rights
    based upon a determination that the applicant will be able to mitigate, the
    State Engineer's decision to approve the applications and issue the
    permits at issue here is not supported by sufficient evidence that
    successful mitigation efforts may be undertaken so as to dispel the threat
    to the existing rights holders. We thus reverse the district court's decision
    denying judicial review of the State Engineer's decisions and remand.
    I.
    At the heart of this appeal is the Mount Hope Mine, a large
    proposed molybdenum mine that General Moly, Inc. seeks to establish in
    Eureka County. The mine's contemplated life is 44 years, and will require
    an estimated total of 11,300 acre feet of water per year (afa). To provide
    the water for the mine, General Moly seeks to pump groundwater by well
    from the Kobeh Valley and Diamond Valley groundwater basins, basins
    that already source many existing water rights, which will cause a
    SUPREME COURT
    OF
    NEVADA
    2
    (0/ 1947A    e
    drawdown of the water table throughout the two valleys. According to a
    water resources monitoring plan created by Eureka Moly, LLC, a
    subsidiary of General Moly, the vast majority of this water for the Mount
    Hope Mine "will be consumptively used in processing activities of the
    [mining] Project (i.e.[,] no water will be returned to the aquifer)."
    General Moly created respondent Kobeh Valley Ranch, LLC
    (KVR) to hold and control the water rights for the project. Water rights
    already appropriated by a predecessor entity associated with the mining
    project were transferred to KVR, as were existing applications to
    appropriate water that the predecessor had filed in 2005. Throughout
    2006 to 2010 KVR also filed numerous applications to change the point of
    diversion, the place of use, and the manner of use of other of its existing
    water rights. Appellant Eureka County protested KVR's applications on
    numerous grounds, including that KVR's groundwater appropriations
    would conflict with existing rights under NRS 533.370(2). A number of
    holders of senior water rights sourced in Kobeh Valley and Diamond
    Valley also protested on those, and other, grounds. The State Engineer
    originally held a hearing on the applications, then pending, in 2008, after
    which he approved some of KVR's applications over these objections, but
    upon review the district court vacated the ruling and remanded the matter
    back to the State Engineer for a new hearing.
    The State Engineer held another hearing in 2010, in which he
    accepted the evidence presented at the first hearing and allowed
    additional evidence to be presented regarding specific water usage at the
    proposed mining project. The State Engineer ultimately granted all of
    KVR's applications in his Ruling Number 6127.
    SUPREME COURT
    OF
    NEVADA
    3
    (0) 1 947A    'er'
    Pertinent to this appeal, the State Engineer recognized that
    certain springs located on the Kobeh Valley floor that are in hydrologic
    connection with the underlying water table and that source existing,
    senior water rights would be "impacted" by KVR's pumping. However, the
    State Engineer found that KVR could fully mitigate any impact, and to
    that end required KVR to prepare, with the assistance of Eureka County,
    a monitoring, management, and mitigation plan (3M Plan) for approval by
    the State Engineer before KVR diverted any water. The State Engineer
    then issued KVR the various requested use and change permits requested
    by KVR.
    Eureka County, as well as appellants Kenneth F. Benson,
    Diamond Cattle Company, LLC, and Michel and Margaret Ann
    Etcheverry Family, LP, (collectively referred to as Benson-Etcheverry), all
    of whom hold existing, senior rights in the valleys, petitioned the district
    court for judicial review of Ruling 6127. The district court denied the
    petition, finding that substantial evidence supported the State Engineer's
    decision that KVR would be able to mitigate any adverse impacts to
    existing water rights. The district court further held that NRS 533.370(2)
    "does not prevent the State Engineer from granting applications that may
    impact existing rights if the existing right can be protected through
    mitigation, thus avoiding a conflict with existing rights."
    While Ruling 6127 was before the district court, KVR
    developed a 3M Plan in coordination with Eureka County. Though the
    State Engineer approved the 3M Plan, he retained ultimate authority over
    it, stating that the 3M Plan was approved with the "understanding that
    components of the Plan are subject to modification based on need, prior
    monitoring results, or changes in the approved water rights." Benson-
    SUPREME COURT
    OF
    NEVADA
    4
    (0) 1947A
    Etcheverry petitioned the district court for judicial review of this decision,
    but the district court denied that petition as well.
    Eureka County and the appellant senior right's holders appeal
    the district court's order denying judicial review of Ruling 6127. The
    appellant senior right's holders also appeal the district court's subsequent
    order denying judicial review of the State Engineer's approval of the 3M
    Plan.
    A.
    The State Engineer, who is charged with administering the
    water rights in this state, Desert Irrigation, Ltd. v. State, 
    113 Nev. 1049
    ,
    1061, 
    944 P.2d 835
    , 843 (1997), is required to approve applications to
    appropriate new water rights or to change the place, manner, or use of
    existing water rights if the applicant meets certain statutory
    requirements. NRS 533.370(1). However:
    Except as otherwise provided in subsection 10
    [which excepts applications for environmental or
    temporary permits], where there is no
    unappropriated water in the proposed source of
    supply, or where its proposed use or change
    conflicts with existing rights or with protectable
    interests in existing domestic wells as set forth in
    NRS 533.024, or threatens to prove detrimental to
    the public interest, the State Engineer shall reject
    the application and refuse to issue the requested
    permit.
    NRS 533.370(2) (emphases added).
    The State Engineer and KVR submit that the State Engineer
    may conditionally grant proposed use or change applications on the basis
    of future successful mitigation, thereby ensuring that the new or changed
    appropriation does not conflict with existing rights, in accordance with
    SUPREME COURT
    OF
    NEVADA
    5
    (U) 1,47A exo
    NRS 533.370(2). This court has never addressed whether the statute may
    be read in this manner, and we need not do so at this time. Even
    assuming that the State Engineer may grant a proposed use or change
    application on the basis of the appropriator's ability to successfully
    mitigate and bring the existing water rights back to their full beneficial
    use, substantial evidence does not support the State Engineer's decision
    that this is the case here. Town of Eureka v. Office of State Eng'r of State
    of Nev., Div. of Water Res.,    
    108 Nev. 163
    , 165, 
    826 P.2d 948
    , 949 (1992)
    ("With questions of fact, the reviewing court must limit itself to a
    determination of whether substantial evidence in the record supports the
    State Engineer's decision.").
    B.
    The State Engineer in his Ruling 6127 recognized that there
    would be extensive" drawdown of the water table in Kobeh Valley near
    KVR's main well field area due to KVR's groundwater pumping, which
    could "impact" existing "rights on springs and streams in hydrologic
    connection with the water table ... includ[ing] valley floor springs." He
    also recognized that:
    Water rights that could potentially be impacted
    are those rights on the valley floor where there is
    predicted drawdown of the water table due to
    mine pumping. The Applicant recognizes that
    certain water rights on springs in Kobeh Valley
    are likely to be impacted by the proposed
    pumping. These springs produce less than one
    gallon per minute and provide water for livestock
    purposes.
    SUPREME COURT
    OF
    NEVADA
    6
    (0) 1947A    e
    (Footnotes omitted)} But the evidence to which the State Engineer cited
    demonstrates that more than just an "impact" to these low-flow springs
    would occur. For instance, the State Engineer cited to KVR's
    hydrogeology expert Terry Katzer's testimony at the 2010 hearing that
    KVR's pumping would dry up certain springs and stock watering wells:
    Q: Okay. Will the pumping over time cause
    impacts to springs in direct stock watering wells
    in the floor of Kobeh Valley?
    A: I believe it will. And I can't name the springs
    because I am not that familiar with them. Mud
    Springs, for instance, I know where that is. I've
    been there. It will probably dry that up with time.
    And other springs that are in close proximity to
    the well field.
    Q: Stock watering wells?
    A: Stock watering wells, yes, probably.
    Flow modeling reports by KVR's hydrogeology and groundwater modeling
    expert, Dwight Smith, to which the State Engineer also cited, confirmed
    this assessment:
    Springs located in lower altitudes in the Roberts
    Mountains. . . are more likely to be impacted due
    to closer proximity to the KVCWF[ Kobeh Valley
    Central Well Field], resulting in larger predicted
    drawdown at these locations. Discharge at Mud
    Spring (Site 721) and Lone Mountain Spring (Site
    742), located near the southeast edge of the
    KVCWF near proposed well 226, are predicted to
    be impacted and will likely cease to flow based on
    'Eureka County challenges the "less than a gallon per minute"
    finding, but KVR's 2010 flow modeling report indicates that these springs
    produced less than a gallon per minute. And, while the inventory KVR
    prepared in 2011 shows an estimated less than five gallon flow for Mud
    Spring, this is not inconsistent with a less than one gallon flow finding.
    SUPREME COURT
    OF
    NEVADA
    7
    (0) 1947A    e
    predicted drawdowns of 40 to 50 feet. Both of
    these springs discharge less than approximately
    one gallon per minute.
    Smith also testified that Mud Springs and another spring called Lone
    Mountain Spring would cease to flow fairly soon after KVR begins
    pumping.
    The federal Bureau of Land Management (BLM) claims
    unadjudicated reserved rights sourced from Lone Mountain Springs. And
    respondent Etcheverry Family, LP, holds permitted existing rights in Mud
    Springs, rights consisting of 10.86 afa to use for stock watering purposes.
    Therefore, contrary to the State Engineer's, KVR's, and amici's
    assertions, 2 KVR's pumping would not merely impact existing water
    rights; the very evidence upon which the State Engineer relied
    demonstrates that KVR's appropriation would cause the complete
    depletion of the source of existing water rights. The Legislature did not
    define exactly what it meant by the phrase "conflicts with" as used in NRS
    533.370(2), but if an appropriation that would completely deplete the
    source of existing water rights does not "conflict with" those existing
    rights, then it is unclear what appropriation ever could. Furthermore,
    dictionary definitions from around the time a statute is enacted can aid
    this court in deciphering that statute's meaning, Douglas v. State, 130
    Nev., Adv. Op. 31, 
    327 P.3d 492
    , 494 (2014), and contemporaneous
    reference material with the Legislature's adoption of the "conflicts with"
    aspect of NRS 533.370(2), defines "conflict," in verb form, as "No be in
    2 This
    court authorized two amicus briefs, one filed on behalf of
    several municipal water purveyors and one filed on behalf of Nevada
    Energy.
    SUPREME COURT
    OF
    NEVADA
    8
    (0) 1947A otto
    opposition; be contrary or at variance."           See 2 THE CENTURY
    DICTIONARY AND CYCLOPEDIA, WITH A NEW ATLAS OF THE WORLD, at
    1186 (rev. enl. ed. 1911); 1913 Nev. Stat., ch. 140, § 63. To the extent that
    KVR's proposed appropriations would deplete the water available to
    satisfy existing rights at issue, they are undeniably "in opposition" thereto,
    and thus "conflict with" the existing rights under NRS 533.370(2). 3
    C.
    Considered separate and apart from any potential mitigation
    techniques, the appropriations in question are in conflict with existing
    water rights in the valleys. But the State Engineer found KVR could
    implement mitigation techniques that would ameliorate the depletion of
    Mud Springs: "The State Engineer finds that this flow loss can be
    adequately and fully mitigated by the Applicant should predicted impacts
    occur." Furthermore, because "the only way to fully ensure that existing
    water rights are protected is by closely monitoring hydrologic conditions
    while groundwater pumping occurs," the State Engineer found that "a
    monitoring, management and mitigation plan prepared with input from
    Eureka County must be approved by the State Engineer prior to pumping
    groundwater for the project." The State Engineer thus concluded that:
    "Based upon substantial evidence and testimony, and the monitoring,
    management and mitigation plan requirement, the State Engineer
    3 The State Engineer's ruling states that though the BLM originally
    protested KVR's appropriations, it withdrew its protests "after reaching a
    stipulation on monitoring, management and mitigation" with KVR. It
    seems the State Engineer assumed this was sufficient to dispense with the
    conflict under NRS 533.370(2), but this is a less than clear conclusion. In
    any event, Etcheverry Family, LP, has not withdrawn its protest of KVR's
    applications.
    SUPREME COURT
    OF
    NEVADA
    9
    10) 1047A
    concludes that the approval of the applications will not conflict with
    existing water rights . . . ."
    Nowhere in the ruling, however, does the State Engineer
    articulate what mitigation will encompass, even in the most general sense.
    And evidence of what that mitigation would entail and whether it would
    indeed fully restore the senior water rights at issue is lacking: there was
    no mitigation plan in the record before the district court or in existence
    when KVR's applications were granted. Indeed, KVR's representative
    Patrick Rogers acknowledged that he didn't "know what we [General
    Moly] would propose in a mitigation plan. A mitigation plan hasn't been
    developed yet. It would be speculative to say what we would or would not
    propose."
    The State Engineer and KVR point to KVR's experts'
    testimony as evidence that mitigation could occur and would be successful.
    But Katzer testified only that there were a variety of [mitigation]
    techniques. You could increase the well if it's being fed by a well or you
    could run a pipeline to it from part of the distribution system." Smith
    similarly testified that if predicted water table drawdown were to occur
    due to KVR's pumping, "certainly there can be mitigation measures taken,
    many of which could include shifting[] pumping around the well field as an
    easy example." While KVR's experts testified as to the existence of a few
    possible mitigation techniques, they did not specify what techniques would
    work, much less techniques that could be implemented to mitigate the
    conflict with the existing rights in this particular case. And concerns over
    precisely how KVR, or its parent company Eureka Moly, would mitigate
    these conflicts are not without cause: Martin Etcheverry testified that
    after KVR did some experimental pumping, one of his springs, Nichols
    SUPREME COURT
    OF
    NEVADA
    10
    (0) 1947A    aelip)
    Springs, was noticeably lower than before the pumping and that it had not
    yet returned to its pre-pumping levels. And according to Eureka County's
    natural resource manager, the Nichols Springs lowering was brought to
    Eureka Moly's attention multiple times, including at a meeting at the
    BLM's Battle Mountain office, but that neither KVR nor Eureka Moly had
    done anything to address the lowering of that spring.
    The State Engineer and KVR alternatively assert the existing
    rights holders conceded that mitigation could be accomplished. But the
    existing rights holders, including Martin Etcheverry, merely recognized in
    their 2010 hearing testimony that they would be satisfied if KVR could
    completely and successfully mitigate the interference with their rights.
    The State Engineer implies on appeal that KVR's mitigation
    could encompass providing substitute water to the senior rights holders by
    arguing that said holders are entitled only to the beneficial use of the
    amount of their water rights, and have no right to the historical source of
    their water rights.   See Desert Irrigation, Ltd. v. State, 
    113 Nev. 1049
    ,
    1059, 
    944 P.2d 835
    , 842 (1997) ("[E]ven those holding certificated, vested,
    or perfected water rights do not own or acquire title to water. They merely
    enjoy the right to beneficial use."). But to the extent KVR's mitigation
    would involve substitute water sources—which is not reflected in the State
    Engineer's decision or the evidence that was presented to him—there was
    no evidence before the State Engineer that KVR applied for or committed
    certain of its already obtained water rights to mitigation or where the
    substituted water would otherwise come from. And, using the State
    Engineer's numbers regarding the amount of water in the basin, there
    may not be any water left to use for mitigation after KVR's appropriation.
    The State Engineer found Kobeh Valley had 15,000 afa total. KVR's
    SUPREME COURT
    OF
    NEVADA
    11
    (0) 1947A    e
    appropriation is 11,300 afa, and the other committed rights had 1,100 afa,
    which left 2,600 afa for future appropriation. However, there is 5,530 afa
    in nonadjudicated claims to vested or reserved rights on file in the State
    Engineer's office.
    This is setting aside the further, specious assumption that
    water from a different source would be a sufficient replacement. Take, for
    example, the testimony given by an existing rights holder before the State
    Engineer that he had seen problems before with piping in water for
    animals because the pipes can freeze and interfere with the flow in the
    extreme winter cold. Given these, seemingly supported, concerns over
    such potential problems, it is therefore unclear that substitution water, if
    available, would be sufficient.   See, e.g., Weibert v. Rothe Bros., Inc.,   
    618 P.2d 1367
    , 1373 (Colo. 1980) ("In order to determine the adequacy of the
    [augmentation] plan to accomplish its intended purpose, it is necessary to
    consider the adequacy of the replacement water rights."); see also Rocky
    Ford Irrigation Co. v. Kents Lake Reservoir Co., 
    135 P.2d 108
    , 114 (Utah
    1943) (examining whether the exchange of water deteriorates water
    quality or quantity to such a degree as to "materially impair[ ] the use.").
    Added to this, a surface water rights holder may be found to
    have abandoned its right if it no longer delivers the water or maintains
    the source of diversion. NRS 533.060(4)(a)-(d). Requiring that existing
    right holders use water other than from the source that they currently
    have rights in might mean the existing right holder would need to obtain a
    new permit to appropriate that new water.         See NRS 533.060(5) ("Any
    such right to appropriate any of the water must be initiated by applying to
    the State Engineer for a permit to appropriate the water as provided in
    this chapter."). KVR did not address before the State Engineer this
    SUPREME COURT
    OF
    NEVADA
    12
    (0) 1947A    e
    potential obstacle to providing water from an alternate source to mitigate,
    and neither did the State Engineer's ruling.
    Finally, KVR asserts that the State Engineer's determination
    that "it is readily feasible to avoid conflicts when mitigating impacts to
    water sources that produce relatively minor amounts of water" merely
    reflects the State Engineer's "experience and common sense." But this is
    precisely the problem with the State Engineer's ruling: though the State
    Engineer certainly may use his experience to inform his decision making,
    his decisions must be supported by substantial evidence in the record
    before him, which is not the case here.   Town of Eureka, 108 Nev. at 165,
    
    826 P.2d at 949
    .
    D.
    Essentially, and with all other arguments aside, the State
    Engineer and KVR's position is that the State Engineer may leave for a
    later day, namely the day the 3M Plan is put before him, the
    determination of exactly what KVR's mitigation would entail. But the
    State Engineer's decision to grant an application, which requires a
    determination that the proposed use or change would not conflict with
    existing rights, NRS 533.370(2), must be made upon presently known
    substantial evidence, rather than information to be determined in the
    future, for important reasons.
    First, those who protest an application to appropriate or
    change existing water rights must have a full opportunity to be heard, a
    right that includes the ability to challenge the evidenceS upon which the
    State Engineer's decision may be based. Revert v. Ray, 
    95 Nev. 782
    , 787,
    
    603 P.2d 262
    , 264 (1979); see also NRS 533.365(5) ("Each applicant and
    each protestant shall. . . provide to the State Engineer and to each
    protestant and each applicant information required by the State Engineer
    SUPREME COURT
    OF
    NEVADA
    13
    (0) 1947A    e
    relating to the application or protest.").   Cf. Bowman Transp., Inc. v.
    Arkansas-Best Freight Sys., Inc., 
    419 U.S. 281
    , 288 n.4 (1974) ("[T]he Due
    Process Clause forbids an agency to use evidence in a way that forecloses
    an opportunity to offer a contrary presentation."). This necessarily means
    that the opportunity to challenge the• evidence must be given before the
    State Engineer grants proposed use or change applications. Those who
    protest an application's grant cannot be forced to wait and challenge a
    future 3M Plan because, as Benson-Etcheverry note: "The appeal as to
    Ruling No. 6127 can result in vacating the Ruling, among other remedies.
    However, appeal of the 3M Plan can only result in vacating the Plan." In
    other words, challenging the sufficiency of a later developed mitigation
    plan cannot undo a decision to grant applications for a proposed use or
    change that may have been erroneous. And allowing the State Engineer
    to grant applications conditioned upon development of a future 3M Plan
    when the resulting appropriations would otherwise conflict with existing
    rights, could potentially violate protestants' rights to a full and fair
    hearing on the matter, a rule rooted in due process.    Revert, 95 Nev. at
    787, 
    603 P.2d at 264
    .
    Furthermore, the State Engineer's decision to grant an
    application must be sufficiently explained and supported to allow for
    judicial review. Revert, 95 Nev. at 787, 
    603 P.2d at 265
    ; see also Port of
    Jacksonville Mar. Ad Hoc Comm., Inc. v. U.S. Coast Guard, 
    788 F.2d 705
    ,
    708 (11th Cir. 1986) (even under deferential substantial evidence review,
    courts must not merely "rubber stamp" agency action: they must
    determine that the 'agency articulated a rational connection between the
    facts presented" and the decision) (citation omitted). The State Engineer
    thus may not defer the determination of what mitigation would encompass
    SUPREME COURT
    OF
    NEVADA
    14
    (0) 1947A .
    to a later date: even if he may grant applications where the resulting
    appropriations would conflict with existing rights based upon the finding
    that the applicant would be able to successfully mitigate that deleterious
    effect, an assumption we do not adopt today, the finding must be based
    upon evidence in the record to support that mitigation would be successful
    and adequate to fully protect those existing rights.   See City of Reno v.
    Citizens for Cold Springs, 126 Nev., Adv. Op. 27, 
    236 P.3d 10
    , 18-19 (2010)
    (law requiring local governments to make a finding about plans for
    adequate services and infrastructure prior to amending a master plan to
    allow further development "require[d] something more than the deferral of
    the issue or broad, evasive conclusions about how officials can build or
    expand utilities if necessary").
    In sum, substantial evidence does not support the State
    Engineer's finding that KVR would be able to "adequately and fully"
    mitigate the fact that its groundwater appropriations will cause Kobeh
    Valley springs that sources existing rights to cease to flow. The State
    Engineer's decision to grant KVR's applications, when the result of the
    appropriations would conflict with existing rights, and based upon
    unsupported findings that mitigation would be sufficient to rectify the
    conflict, violates the Legislature's directive that the State Engineer must
    deny use or change applications when the use or change would conflict
    with existing rights. NRS 533.370(2). As appellants have met their
    burden to show the State Engineer's decision was incorrect, NRS
    533.450(10), the State Engineer's decision to grant KVR's applications
    cannot stand. Therefore, we
    SUPREME COURT
    OF
    NEVADA
    15
    (0) 1947A    ea
    REVERSE AND REMAND this matter to the district court for
    proceedings consistent with this order. 4 Because we reverse and remand
    on this basis, we do not reach the remaining issues raised in these
    consolidated appeals.
    ,   CA.
    Hardesty
    Qia°4C6sa
    Parraguirre       r
    J.
    J.
    Cherry
    Sa
    J.
    Gibbons
    °                               J.
    Pickering     \
    From the record and Ruling 6127, it is unclear which of KVR's
    4
    applications for proposed use or change in Kobeh Valley, if it can be
    pinpointed, is the appropriation that will cause the springs to dry up.
    Therefore, we must overturn the entire decision.
    SUPREME COURT
    OF
    NEVADA
    16
    (0) 1947A    (7a49)
    cc: Seventh Judicial District Court Dept. 2
    William E. Nork, Settlement Judge
    Allison, MacKenzie, Ltd.
    Schroeder Law Offices, P.C.
    Eureka County District Attorney
    Attorney General/Carson City
    Parsons Behle & Latimer/Salt Lake City
    Parsons Behle & Latimer/Reno
    Las Vegas City Attorney
    Brownstein Hyatt Farber Schreck, LLP/Las Vegas
    Dana R. Walsh
    Lewis Roca Rothgerber LLP/Las Vegas
    McDonald Carano Wilson LLP/Reno
    Dyer, Lawrence, Penrose, Flaherty, Donaldson & Prunty
    Gregory J. Walch
    Carson City District Attorney
    Henderson City Attorney
    Rowe Hales Yturbide, LLP
    Taggart & Taggart, Ltd.
    Eureka County Clerk
    SUPREME COURT
    OF
    NEVADA
    17
    (   0) 1947A    e