Soffer v. the Bank of Nova Scotia ( 2014 )


Menu:
  •                                  ORDER AFFIRMING IN PART, REVERSING IN PART, AND
    REMANDING
    These are appeals from a district court summary judgment
    and a post-judgment order awarding costs in a contract action. Eighth
    Judicial District Court, Clark County; Allan R. Earl, Judge.
    Appellant Jeffrey Soffer is the principal of the Turnberry
    group of companies, including appellant Turnberry Development, LLC,
    that was part of a joint venture that developed the Town Square Las
    Vegas Mall. To fund the construction of Town Square, Soffer obtained a
    $470,000,000 construction loan from a group of lending institutions (the
    Senior Lending Group), which included respondent The Bank of Nova
    Scotia (BNS). As the maturity date approached, the parties sought to
    negotiate a possible new loan. They entered into a pre-negotiation
    agreement (PNA), which required any final binding agreement to be
    written. The parties then exchanged a term sheet through a series of e-
    mails as they attempted to negotiate the new loan. The term sheet
    contained a disclaimer stating that it was not a written agreement for
    purposes of the PNA. The original loan went into default in March 2009,
    but the Senior Lending Group did not foreclose and the parties continued
    to negotiate. In December 2009, the parties exchanged a version of the
    term sheet that had a column entitled "FINAL, Agreed to by All Parties."
    Following the December exchange, the parties continued to work on
    completing the term sheet requirements and to negotiate the details of the
    agreement not yet resolved. However, negotiations eventually broke down
    and no agreement was finalized A foreclosure sale was scheduled for
    February 2011.
    SUPREME COURT
    Of
    NEVADA
    2
    (0) 1947A    ADIr.
    tri
    Soffer and Turnberry Development initially filed a complaint
    against BNS wherein they sought, amongst other relief, to enjoin the
    foreclosure sale, but they ultimately abandoned that cause of action and
    the foreclosure sale was completed in March 2011. Thereafter, Soffer
    amended the complaint twice, eventually alleging the eight causes of
    action at issue in this appeal. Soffer's first five causes of action
    surrounded his allegations that BNS, as agent for the Senior Lending
    Group, breached a binding contract when it failed to conclude the new
    loan. In the three remaining causes of action, it is alleged that Turnberry
    Development, as property manager for Town Square, was entitled to
    unpaid management fees. BNS moved for summary judgment arguing
    that the agreement was unenforceable as a matter of law, and the relevant
    documents showed that it did not owe management fees to Turnberry
    Development. The district court granted the motion and dismissed the
    complaint in its entirety. BNS and respondent TSLV, Inc. then filed a
    memorandum of costs. Soffer and Turnberry Development moved to retax
    and settle costs, which the district court granted in part and denied in
    part and awarded BNS and TSLV $294,287.94 in costs. These appeals
    followed. The parties are familiar with the facts and we do not recount
    them further except as pertinent to our disposition.
    The district court did not err in dismissing Soffer's first five causes of
    action because there was no enforceable agreement as a matter of law
    "This court reviews a district court's grant of summary
    judgment de novo."    Wood v. Safeway, Inc.,   
    121 Nev. 724
    , 729, 
    121 P.3d 1026
    , 1029 (2005). Summary judgment is appropriate when "there is no
    genuine issue as to any material fact and. . . the moving party is entitled
    to a judgment as a matter of law." NRCP 56(c).
    SUPREME COURT
    OF
    NEVADA
    3
    (0) I947A    )4V4E)
    Soffer argues that the district court erred in determining that
    the parties did not enter into a binding and enforceable agreement. He
    asserts that the term sheet was an agreement that represented a meeting
    of the minds on all material terms, and any specific terms not included
    were set forth in the original loan, which the parties intended to
    incorporate. Furthermore, Soffer contends that the disclaimer language
    was accidently included in the term sheet and must be ignored because it
    conflicts directly with the offer that was accepted by the parties through
    the exchange of e-mails to form a binding contract. As an initial matter,
    we note that both parties agree that New York law applies to the
    substantive legal issues in this matter.
    "It is well settled that a contract is to be construed in
    accordance with the parties' intent, which is generally discerned from the
    four corners of the document itself."        MHR Capital Partners, LP v.
    Presstek, Inc., 
    912 N.E.2d 43
    , 47 (N.Y. 2009). A "fundamental tenet of
    contract law [is] that enforceable legal rights do not arise from contract
    negotiations until both parties consent to be bound or, in any event,
    manifest that consent to each other."      Chrysler Capital Corp. v. Se. Hotel
    Props. Ltd. P'ship, 
    697 F. Supp. 794
    , 799 (S.D.N.Y. 1988) (applying New
    York law). "[W]hen a party gives forthright, reasonable signals that it
    means to be bound only by a written agreement,' that intent is honored."
    Kowalchuk v. Stroup,     
    873 N.Y.S.2d 43
    , 47 (App. Div. 2009) (quoting
    Jordan Panel Sys., Corp. v. Turner Constr. Co., 
    841 N.Y.S.2d 561
    , 565
    (App. Div. 2007)).
    We conclude that in this case the disclaimer on the term sheet
    and the language in the PNA clearly evinced the parties' intent not to be
    bound. First, the PNA unambiguously stated that the parties were free to
    SUPREME COURT
    OF
    NEVADA
    4
    (01 1947A.    e
    withdraw from negotiations without penalty "until a written agreement is
    executed." Second, not only did each page of the term sheet, which was
    circulated amongst the parties as it was being negotiated, state that it was
    "FOR DISCUSSION PURPOSES ONLY," but the disclaimer on the first
    page explicitly stated that it was "not a 'written agreement' within the
    meaning" of the PNA. The plain and unambiguous language of the
    disclaimer cannot be ignored simply because the document's fourth
    column was titled "FINAL, Agreed to by All Parties." See RM 14 FK Corp.
    v. Bank One Trust Co., N.A., 
    831 N.Y.S.2d 120
    , 123 (App. Div. 2007)
    (stating that a contract must also be interpreted so as not to "render any
    clause meaningless.").
    Soffer also argues that the disclaimer language on the term
    sheet was irrelevant because the offer was contained within the e-mail,
    and the term sheet was merely attached to convey the agreed-upon terms.
    However, this argument fails because the language in the body of the e-
    mail itself does not indicate the intent to create a binding agreement.
    Rather, it simply asks that the attached terms be approved so the parties
    could continue to work toward a formal binding agreement. Furthermore,
    even if the e-mail's language was construed as an offer to enter into a
    binding commitment, the e-mail itself contained no essential material
    terms, but instead sought approval of the attachment, and could thus not
    stand alone as an offer. See 
    Kowalchuk, 873 N.Y.S.2d at 46
    (stating that,
    to be enforceable, an offer must include all essential terms) As such, we
    conclude that the term sheet was a necessary part of the parties' offer,
    thus making the disclaimer language relevant to that offer.
    We further reject Soffer's alternative argument that even if
    the agreement was not enforceable, BNS was still required to negotiate in
    SUPREME COURT
    OF
    NEVADA
    5
    (0) I94Th
    ArWSERIFELIPM
    good faith. Soffer bases his argument upon a distinction drawn by federal
    courts in New York between two different types of preliminary
    agreements. A Type I agreement is an agreement that is "preliminary
    only in form" as the "parties [may] desire a more elaborate formalization of
    the agreement," but the agreement is complete and enforceable.         Teachers
    Ins. & Annuity Ass'n of Am. v. Tribune Co.,        
    670 F. Supp. 491
    , 498
    (S.D.N.Y. 1987). A Type II preliminary agreement occurs when there is a
    "mutual commitment to a contract on agreed major terms," but the parties
    recognize "the existence of open terms that remain to be negotiated."       
    Id. The contract
    itself is not binding, but the parties "accept a mutual
    commitment to negotiate together in good faith in an effort to reach final
    agreement within the scope that has been settled in the preliminary
    agreement." 
    Id. To determine
    whether an agreement is a Type II preliminary
    agreement, courts consider the following factors: whether the parties
    expressed an intent to be bound; the context of the negotiations; the
    existence of open terms; whether there was partial performance; and the
    necessity of putting the agreement in final form. 
    Teachers, 670 F. Supp. at 499-503
    . In applying the factors from Teachers, federal courts have stated
    that "[t]he first factor, the language of the agreement, is 'the most
    important.' .. . Indeed, if the language of the agreement is clear that the
    parties did not intend to be bound, the Court need look no further."    Cohen
    v. Lehman Bros. Bank, FSB, 
    273 F. Supp. 2d 524
    , 528 (S.D.N.Y. 2003)
    (quoting Arcadian Phosphates, Inc. v. Arcadian Corp., 
    884 F.2d 69
    , 72 (2d
    Cir. 1989)). Here, because the plain language within the four corners of
    the term sheet contained an explicit disclaimer that the negotiations were
    non-binding, and the PNA allowed for negotiation between the parties
    SUPREME COURT
    OF
    NEVADA
    6
    U 1947A    e
    without any possibility of incurring liability, our inquiry ends. Thus, we
    conclude that the district court did not err in dismissing Soffer's and
    Turnberry Development's first five causes of action.
    The district court erred in dismissing as a matter of law the remaining
    three causes of action related to Turnberry Development's management fees
    Soffer and Turnberry Development argue that the district
    court erred in dismissing the remaining three causes of action for
    Turnberry Development's unpaid management fees. They claim that
    evidence was presented to show that the Senior Lending Group explicitly
    requested that Turnberry Development continue to manage the property
    during the time the parties were negotiating the possible new loan, and
    while the loan was in default, thus, creating an oral contract. The Senior
    Lending Group then breached that contract when it failed to pay for those
    services. BNS counters that the relevant documents show that one of the
    other Turnberry companies, Turnberry/Centra Sub, LLC, not BNS, was
    responsible for paying the management fees. Furthermore, BNS contends
    that Turnberry Development's claim of an oral agreement is barred by the
    original loan agreement and the PNA.
    The district court concluded that Turnberry Development's
    claimS of an oral agreement for the payment of Turnberry Development's
    management fees was "barred by the PNA and the Loan Agreement as a
    matter of law." The court further concluded that the property
    management agreement provided that Turnberry/Centra was obligated to
    pay Turnberry Development's management fees, not BNS. However, our
    review of the record indicates that both the PNA and the original loan
    were entered into between Turnberry/Centra and the agent on behalf of
    the Senior Lending Group. Turnberry Development is an affiliate of
    Turnberry/Centra and, under New York law, "affiliated corporations are,
    SUPREME COURT
    OF
    NEVADA
    7
    (0) 1947A
    74E4WEntila I Z412114,04(Fi                                                ffitalLaSESI
    as a rule, treated separately and independently so that one will not be
    held liable for the contractual obligations of the other absent a
    demonstration that there was an exercise of complete dominion and
    control." Sheridan Broad. Corp. v. Small, 
    798 N.Y.S.2d 45
    , 46 (App. Div.
    2005).
    In this case, BNS has not made the requisite demonstration of
    complete domination and control by Turnberry/Centra over Turnberry
    Development. As such, while the PNA and original loan governed the
    relationship between BNS and Turnberry/Centra, it has no bearing on
    Turnberry Development and its dealings with BNS. Furthermore, the fact
    that the property management agreement was between Turnberry/Centra
    and Turnberry Development would not necessarily preclude a separate
    contract between BNS and Turnberry Development. Therefore, we
    conclude that the district court erred in determining that, as a matter of
    law, these documents mandated dismissal of Soffer's and Turnberry
    Development's three remaining causes of action for Turnberry
    Development's management fees.
    Accordingly, we affirm that portion of the district court's
    judgment dismissing Soffer's and Turnberry Development's first five
    causes of action, and we reverse that portion of the district court's
    judgment dismissing the remaining three causes of action for Turnberry
    Development's management fees, and we remand this matter to the
    district court for proceedings consistent with this order.
    Based on our decision to partially reverse the district court's
    summary judgment, we conclude that the district court's order awarding
    costs to BNS and TSLV is premature. Accordingly, we reverse the district
    court's award of costs. Cf. Kahn v. Morse & Mowbray, 
    121 Nev. 464
    , 479-
    SUPREME COURT
    OF
    NEVADA
    8
    107 1947A e
    80, 
    117 P.3d 227
    , 238 (2005) (reversing an entire fee award made under
    NRS 18.010(2)(b) when summary judgment was reversed in part and
    affirmed in part on appeal).
    It is so ORDERED.
    J.
    Hardesty
    Douglas
    IL&       <
    hes-c      ,   J.
    J.
    cc:   Hon. Allan R. Earl, District Judge
    Ara H. Shirinian, Settlement Judge
    Meister Seelig & Fein LLP
    Carbajal & McNutt, LLP
    Lemons, Grundy & Eisenberg
    Katten Muchin Rosenman LLP/New York
    Katten Muchin Rosenman LLP/Los Angeles
    Ballard Spahr, LLP
    Eighth District Court Clerk
    SUPREME COURT
    OF
    NEVADA
    9
    (0) 194Th 4910))9