Byrd Underground, L.L.C. v. Angaur, L.L.C. , 2014 NV 62 ( 2014 )


Menu:
  •                                                       130 Nev., Advance Opinion 472-
    IN THE SUPREME COURT OF THE STATE OF NEVADA
    BYRD UNDERGROUND, LLC; AND                           No, 61978
    WELLS CARGO, INC.,
    Appellants,
    vs.
    FILED
    ANGAUR, LLC; BALAJI PROPERTIES                                AUG 0 7 2014
    INVESTMENT, LLC; AND US BANK
    C K cLINDEMAN
    NATIONAL ASSOCIATION,                                  CLEI   •
    Respondents.                                           BY        At E
    tirAriports::::
    11 I er
    i
    Certified questions, pursuant to NRAP 5, concerning the
    priority of mechanics' liens based on visible commencement of
    construction. United States Bankruptcy Court for the District of Nevada;
    Bruce T. Beesley, Judge.
    Questions answered in part.
    Foley & Oakes, PC, and Daniel T. Foley, Las Vegas; M. Nelson Segel, Las
    Vegas; Peel Brimley LLP and Eric B. Zimbelman and Richard L. Peel,
    Henderson,
    for Appellants.
    Fennemore Craig Jones Vargas and Craig S. Dunlap and Christopher H.
    Byrd, Las Vegas; Meier & Fine, LLC, and Glenn F. Meier, Las Vegas,
    for Respondents.
    BEFORE THE COURT EN BANC.
    OPINION
    By the Court, GIBBONS, C.J.:
    In Nevada, a mechanic's lien takes priority over other
    encumbrances on a property that are recorded after construction of a work
    SUPREME COURT
    OF
    NEVADA
    (0) 194Th ca4MAD
    of improvement visibly commences. The visible-commencement-of-
    construction requirement often gives rise to dispute, however, and the
    United States Bankruptcy Court for the District of Nevada has certified
    three questions of law to this court regarding this aspect of mechanic's lien
    priority law.'
    The first question queries whether the placement of dirt
    material on a future project site before building permits are issued and the
    'The three certified questions were presented as follows:
    1. Can a mechanic's lien claimant properly
    claim lien priority under NRS 108.225 when the
    dirt/material that is the basis of the lien on the
    project was placed on a prospective building
    project site months before the building permit was
    issued or the general contractor hired? Stated
    another way, does placing significant quantities of
    dirt/material on a prospective building project site
    months before a building permit is issued
    constitute "commencement of construction" on
    such a site pursuant to NRS [108.221121?
    2. Did the Nevada Supreme Court in J.E.
    Dunn Northwest, Inc. v. Corus Construction
    Venture, LLC, 
    249 P.3d 501
    , 509, 127 Nev. Adv.
    Op. 5 (Nev. 2011) mistakenly use the term of art
    "clearing and grading" instead of "clearing and
    grubbing" when describing preparatory work on a
    construction project?
    3. Does "grading" in the circumstances
    presented here constitute visible "commencement
    of construction" under NRS 108.22112 for
    purposes of establishing lien priority under NRS
    108.225?
    SUPREME COURT
    OF
    NEVADA
    2
    (0) 1947A tretep
    general contractor is hired can constitute commencement of construction.
    The second question asks us to clarify our decision in J.E. Dunn
    Northwest, Inc. v. Corns Construction Venture, L.L.C.,   127 Nev. 
    249 P.3d 501
    (2011), in which we stated that "clearing or grading" does not
    constitute commencement of 
    construction. 127 Nev. at 249
    P.3d at
    509. In our view, answering this question requires us to evaluate the
    appropriate precedential weight that courts should give to the passage in
    question, and we therefore rephrase the• second certified question to
    include whether this statement was dictum.      See, e.g., Boorman v. Nev.
    Mem'l Cremation Soc'y, 126 Nev. „ 
    236 P.3d 4
    , 6 (2010) (rephrasing
    certified questions under NRAP 5). We rephrase the second question as
    follows:
    Was the passage in J.E. Dunn Northwest, Inc. v.
    Corns Construction Venture, L.L.C., 127 Nev.     ,
    
    249 P.3d 501
    , 509 (2011), that states
    "preparatory work on a site, such as clearing or
    grading, does not constitute commencement of
    construction," dictum? If so, can grading work
    constitute visible commencement of construction
    under NRS 108.22112?
    Finally, the third question inquires whether the grading that took place in
    this case constituted visible commencement of construction, such that the
    mechanics' liens at issue take priority.
    Because the second question influences our analysis of the
    other questions, we address it first. We respond to the three questions as
    follows. Regarding the bankruptcy court's second question, we conclude
    that this court's use of the term "clearing or grading" was dictum, and
    thus, our holding in J.E. Dunn does not preclude a trier of fact from
    finding that grading property for a work of improvement constitutes
    visible commencement of construction. Regarding the first question, we
    SUPREME COURT
    OF
    NEVADA
    3
    (0) 1947A c(gDir
    conclude that contract dates and permit issuance dates are irrelevant to
    the visible-commencement-of-construction test, but may assist the trier of
    fact in determining the scope of the work of improvement. Finally, we
    decline to answer the third question because it would require this court to
    resolve the factual dispute as to whether the grading presented here
    constituted visible commencement of construction of the work of
    improvement.
    FACTS AND PROCEDURAL HISTORY
    The construction project
    The debtor respondents Angaur, LLC, and Balaji Properties
    Investment, LLC (collectively, the owners), jointly purchased a parcel of
    unimproved real property in Las Vegas, Nevada. No relevant activity took
    place with respect to the subject property until the spring and summer of
    2006; when two different third parties placed, and allegedly spread,
    between 200 and 300 truckloads of dirt/material on the property. 2 Both of
    the third parties were performing work on unrelated construction projects
    on neighboring parcels and roadways. The degree to which the subject
    property was covered and subsequently spread or graded is unclear given
    the record before this court.
    Meanwhile, the owners solicited bids from general contractors
    to construct a strip mall on the property. During bidding on the project,
    2 The parties could not agree what to call the substance that was
    placed on the property, so the bankruptcy court used the term
    "dirt/material." The bankruptcy court noted that it did not intend the
    term to carry any specific legal meaning. We also will use the term
    "dirt/material" to remain consistent with the bankruptcy court.
    SUPREME COURT
    OF
    NEVADA
    4
    (0) 1.947A
    appellant Byrd Underground, LLC, submitted a bid to general contractor
    Joseph's Construction to perform subcontracted grading work, but Atlas
    Construction Ltd., not Joseph's Construction, was selected as the general
    contractor. On November 2, 2006, at the request of Atlas, a representative
    of Byrd dug four to six holes on the subject property with a backhoe. Byrd
    dug these holes to determine how much dirt/material had been brought
    onto the subject property since its prior bid in order to submit a revised
    bid to Atlas incorporating the new scope of work. On November 8, 2006,
    Atlas and the owners executed the written contract for Atlas to serve as
    the general contractor on the construction project.
    On November 28, 2006, a title company conducted a site
    inspection of the subject property and concluded that the land was vacant
    and that there was no evidence of a recent work of improvement.
    Thereafter, the owners borrowed funds from PFF Bank & Trust for the
    purpose of constructing the strip mall on the subject property, 3 and on
    November 29, 2006, a deed of trust for the construction loan was recorded
    with the Clark County Recorder. Byrd had not performed any work on the
    subject property prior to November 29, 2006, other than digging the test
    holes and submitting bids to Joseph's Construction and Atlas.
    Subsequently, a dust control permit and a building permit
    were issued for the subject property. During construction, Atlas used and
    incorporated at least a portion of the dirt/materials into the construction
    project. Atlas and Byrd executed three written subcontracts—for wet
    3 PFF
    Bank eventually went into FDIC receivership and respondent
    US Bank now claims ownership of the construction loan and deed of trust.
    SUPREME COURT
    OF
    NEVADA
    5
    (0) 1947A
    utilities, dry utilities, and grading—in 2007.         Byrd and another
    subcontractor, appellant Wells Cargo, Inc. (collectively, lien claimants),
    provided services for the construction project but were not paid. As a
    result, they commenced mechanic's lien actions in state court and obtained
    judgments against Angaur, Balaji, and Atlas.
    Angaur and Balaji file bankruptcy petitions and the lien claimants'
    objections lead the bankruptcy court to certify questions to this court
    After the construction project was completed, the owners filed
    voluntary petitions for relief under Chapter 11 of the Bankruptcy Code.
    Both of the owners' schedules of creditors holding secured claims included
    (1) a "[first [m]ortgage" to US Bank, and (2) both lien claimants' judgment
    liens. The owners and US Bank entered into a forbearance agreement and
    created a disclosure statement and plan of reorganization with the
    bankruptcy court that stated that US Bank was the only "Class 1" secured
    creditor.
    The lien claimants filed an objection to the owners' disclosure
    statement and plan of reorganization, and they subsequently filed an
    adversary complaint in bankruptcy court to determine the priority of liens.
    At the close of discovery, the owners, US Bank, and the lien claimants
    filed competing motions for summary judgment.
    During briefing on the competing motions for summary
    judgment, the lien claimants requested that the bankruptcy court certify
    questions to this court in order to clarify whether this court in J.E. Dunn
    mistakenly used the term "clearing [or] grading" instead of "clearing and
    grubbing" when describing non-"construction" preparatory work on a
    construction project. The lien claimants argued that "clearing and
    grubbing" is a recognized term of art used in the construction industry,
    whereas "clearing and grading" is not. Additionally, the lien claimants
    SUPREME COURT
    OF
    NEVADA
    6
    (0) 1947A    e
    argued that evidence of the dirt/materials being spread or graded on the
    subject property creates genuine issues of material fact regarding when
    the construction visibly commenced sufficient to avoid summary judgment.
    In response, the bankruptcy court certified questions to this court.
    DISCUSSION
    Priority of mechanics' liens in Nevada
    A mechanic's lien is a "statutory creature established to help
    ensure payment for work or materials provided for construction or
    improvements on land."        In re Fontainebleau Las Vegas Holdings
    (Fontainebleau II), 128 Nev. „ 
    289 P.3d 1199
    , 1210 (2012); see also
    Hearing on S.B. 343 Before the Assembly Judiciary Comm, 73d Leg.
    (Nev., May 13, 2005) (indicating that mechanics' liens "assist people who
    have improved real property so that they can get paid for their efforts").
    Here, the parties do not dispute that the lien claimants performed lienable
    work. But "whether work is entitled to a lien pursuant to NRS 108.22184
    and whether it is entitled to priority over other encumbrances pursuant to
    NRS 108.225 are two entirely separate issues." J.E. Dunn, 127 Nev. at
    , 249 P.3d at 507.
    Relevant to the priority issue, Nevada's mechanic's lien
    priority statute, NRS 108.225, provides that mechanics' liens are entitled
    to priority over any encumbrance that attaches after construction of a
    work of improvement began:
    1. The liens provided for in NRS 108.221 to
    108.246, inclusive, are preferred to:
    (a) Any lien, mortgage or other encumbrance
    which may have attached to the property after the
    commencement of construction of a work of
    improvement.
    SUPREME COURT
    OF
    NEVADA
    7
    (0) 1947A
    2. Every mortgage or encumbrance imposed
    upon, or conveyance made of, property affected by
    the liens provided for in NRS 108.221 to 108.246,
    inclusive, after the commencement of construction
    of a work of improvement are subordinate and
    subject to the liens provided for in NRS 108.221 to
    108.246, inclusive, regardless of the date of
    recording the notices of liens.
    Thus, if construction has commenced on a "work of improvement" before a
    deed of trust is recorded, then a mechanic's lien will take a priority
    position over the deed of trust regardless of when the notice of lien is
    recorded. NRS 108.225; see J.E. Dunn, 127 Nev. at , 249 P.3d at 509;
    Fontainebleau II, 128 Nev. at , 289 P.3d at 1211. Moreover, to claim
    priority, a claimant itself need not perform before the deed of trust is
    recorded, so long as the work of improvement began before the deed's
    recordation, because "all mechanics' liens relate back to the date overall
    construction is commenced." J.E. Dunn, 127 Nev. at 
    n.2, 249 P.3d at 504
    n.2. As a result, in this case, the lien claimants are entitled to priority
    positions over the deed of trust if the work of improvement's construction
    commenced, as those terms are defined by statute, on the subject property
    before the deed of trust was recorded on November 29, 2006.
    Visibility of the work of improvement alone determines priority
    NRS 108.22112 defines "[c]ommencement of construction" as
    the date on which:
    1. Work performed; or
    2. Materials or equipment furnished in
    connection with a work of improvement,
    is visible from a reasonable inspection of the site.
    This court analyzed NRS 108.22112 in J.E. Dunn and concluded that,
    consistent with "the recognized policy interest in maintaining certainty
    SUPREME COURT
    OF
    NEVADA
    8
    (0) 1947A
    and predictability in construction financing," which would be hindered if
    lenders were forced to assume the risk associated with funding a
    construction project over which nonvisible work could grant contractors
    priority, "visibility alone determines priority." 127 Nev. at 
    249 P.3d at 508
    , 506. We then reviewed the preconstruction activities that
    Dunn—the lien claimant—had performed, in light of NRS 108.22112's
    visibility standard. In doing so, we stated, "[o]ther courts have more
    generally held, and we agree, that preparatory work on a site, such as
    clearing or grading, does not constitute commencement of construction."
    
    Id. at ,249
    P.3d at 509 (citing Clark v. Gen. Elec. Co., 
    420 S.W.2d 830
    ,
    833-34 (Ark. 1967), superseded by statute as stated in May Constr. Co. v.
    Town Creek Constr. & Dev., L.L.C., 
    383 S.W.3d 389
    , 392-95 (Ark. 2011)).
    Because placing an architect's sign at the project site and removing power
    lines was "insufficient to provide lenders notice of lienable work entitled to
    priority," we held that those preconstruction activities failed to constitute
    visible commencement of "'actual on-site construction."       
    Id. at ,
    249
    P.3d at 509 (quoting Aladdin Heating Corp. v. Trs. of Cent. States, 
    93 Nev. 257
    , 260, 
    563 P.3d 82
    , 84 (1977)).
    Regarding the second question, the lien claimants take issue
    with our statement in J.E. Dunn that listed "clearing or grading" as types
    of nonvisible preparatory work that fail to establish construction
    commencement, and they argue that the statutes require merely that
    construction be visible to a reasonable site inspection to establish lien
    priority. J.E. Dunn, 127 Nev. at , 249 P.3d at 504-05 (citing Aladdin
    
    Heating, 93 Nev. at 260
    , 563 P.2d at 84). The lien claimants argue that it
    is unnecessary to declare broad categories of construction activities per se
    "nonvisible," thereby depriving the trier of fact of the opportunity to
    SUPREME COURT
    OF
    NEVADA
    9
    (0) 1947A
    evaluate the visibility of such activities on a case-by-case basis. As
    concerns clearing and grading, we agree.
    As noted, mechanics' liens have priority over other
    encumbrances that attach to the property after "the [visible]
    commencement of construction of a work of improvement." NRS
    108.225(1)(a). NRS 108.22188 defines "[w]ork of improvement" as the
    "entire structure or scheme of improvement as a whole, including, without
    limitation, all work, materials and equipment to be used in or for the
    construction, alteration or repair of the property or any improvement
    thereon." Nothing in these provisions excludes preconstruction activities
    from the definition of work of improvement, and indeed, subsection 2 of
    NRS 108.22188 expressly recognizes that activities undertaken to prepare
    the project site can be a work of improvement. NRS 108.22188(2) (stating
    that "the improvement of the site" may be "contemplated by the contracts
    to be a separate work of improvement to be completed before the
    commencement of construction of the buildings"). Moreover, NRS
    108.22128 defines "Mmprovement," in pertinent part, as including
    buildings, irrigation systems and landscaping, removal of trees or other
    vegetation, the drilling of test holes, and grading, grubbing, filling, or
    excavating. In construing these provisions together, as we must, City of
    N. Las Vegas v. Warburton, 127 Nev. „ 
    262 P.3d 715
    , 718 (2011),
    we conclude that the trier of fact must look to the entire structure or
    scheme of improvement as a whole—the "overall construction"—rather
    than solely evaluating the activities based on whether they are
    preparatory or structural or vertical construction, in determining whether
    construction on a work of improvement has commenced.       J.E. Dunn, 127
    Nev. at 
    n.2, 249 P.3d at 504
    n.2.
    SUPREME COURT
    OF
    NEVADA
    10
    (0) 1947A
    Accordingly, grading work can be an integral part of the
    "entire structure or scheme of improvement as a whole" and part of the
    actual on-site construction. NRS 108.22188. If it is, grading may be
    sufficient to establish commencement of construction in Nevada as long as
    it is visible from a reasonable inspection of the site sufficient to provide
    lenders notice that lienable work has commenced, and we are unwilling to
    conclude, as a matter of law, that on-site grading work can never place
    lenders on notice that lienable work has begun. NRS 108.22112; see also
    May Constr. 
    Co., 383 S.W.3d at 392-94
    (construing Arkansas's mechanic's
    lien statute "just as it reads, giving the words their ordinary and usually
    accepted meaning in common language" in determining that grading can
    constitute commencement of construction).
    This holding is consistent with J.E. Dunn, in which we
    explained that the visibility requirement for determining lien priority
    applies to preconstruction activities. 127 Nev. at 
    249 P.3d at 507
    -
    08, To the extent that the examples of nonconstruction preparatory work
    in J.E. Dunn suggest otherwise, neither clearing nor grading were at issue
    in that case, and thus the examples are mere dicta.     See St. James Vill.,
    Inc. v. Cunningham, 
    125 Nev. 211
    , 216, 
    210 P.3d 190
    , 193 (2009). We take
    this opportunity to clarify that J.E. Dunn does not preclude a trier of fact
    from finding that clearing and grading work constitutes visible
    commencement of construction of a work of improvement. We thus
    answer the second question, as we have rephrased it, in the affirmative:
    our statement in J.E. Dunn, 127 Nev. at , 249 P.3d at 509, regarding
    "clearing or grading" was dictum, and grading work may constitute visible
    commencement of construction under NRS 108.22112.
    SUPREME COURT
    OF
    NEVADA
    11
    (0) 1947A    e
    Contract dates and permit issuance dates are irrelevant to the visible-
    commencement-of-construction test set forth by NRS 108.22112
    The bankruptcy court's first certified question asks whether a
    mechanic's lien claimant can properly claim lien priority under NRS
    108.225 based on work that was performed or materials that were
    delivered months before the building permit was issued and the general
    contractor was hired. The lien claimants argue that the plain language of
    MRS 108.225 and NRS 108.22112 require visibility, and that nothing in
    the statutes conditions the priority of a lien on the issuance of permitting
    or contract dates. The lien claimants argue that the timing of contracts
    and permits related to a given project is irrelevant to the issue of whether
    the delivery of materials or the performance of work had, in fact, been
    furnished prior to the date the deed of trust was recorded. We agree.
    Here, "the meaning of NRS 108.22112 is plain and requires
    visibility for work performed, including preconstruction services, in order
    for a mechanic's lien to take a priority position over a deed of trust."   J.E.
    Dunn, 127 Nev. at , 249 P.3d at 506-07; see also Aladdin 
    Heating, 93 Nev. at 260
    , 563 P.2d at 84. Thus, any subjective intent on the part of an
    owner to commence construction on a given date, based on either a
    contract or permit issuance date, is not an element of the commencement
    of construction and should therefore not be considered dispositive.        See
    May 
    Constr., 383 S.W.3d at 395
    (concluding that the district court erred
    when it failed to make factual determinations regarding objective, visible
    manifestation of activity on the property, and instead ruled that
    construction did not commence until after the mortgage was recorded
    based on the perceived intent of the lender).
    But while the date of the contract or permits does not directly
    affect priority, the contract and permits may have some bearing on the
    SUPREME COURT
    OF
    NEVADA
    12
    (0) 1947A 9404>
    issue, because the fact-finder must define the work of improvement before
    it can determine when that work of improvement visibly commenced. In
    this regard, contracts and permits may assist in determining the scope of
    the work of improvement's "structure or scheme ... as a whole." NRS
    108.22188. If the contract expressly or impliedly excludes certain work,
    then that work might not be a part of the "work of improvement."           See
    Schultz v. King, 
    68 Nev. 207
    , 212-13, 
    228 P.2d 401
    , 404 (1951) (looking to
    the contract in addressing the possible scope of a work of improvement);
    see also L Cox Constr. Co. v. CH2 Invs., L.L.C., 129 Nev. „ 
    296 P.3d 1202
    , 1205 (2013) (determining a work of improvement's scope by looking
    to the purpose, impetus, and continuity of the work, the parties'
    contemplations regarding the project, the building and operating permits,
    and the timing of the work in relation to the rest of the construction).
    Thus, we answer the first question in the affirmative, with a
    caveat: a mechanic's lien claimant may properly claim lien priority under
    NRS 108.225 when the work or material forming the basis of the lien's
    priority was placed or performed on the site "months before the building
    permit was issued or the general contractor hired," as long as there was,
    in fact, visible commencement of construction as defined by NRS
    108.22112 and as long as all of the work or material placed or performed
    on the site in the prior months was a part of the same work of
    improvement under NRS 108.22188 as the later work giving rise to the
    mechanic's lien.
    We decline to answer the third certified question because it asks this court
    to make findings of fact that should be left to the bankruptcy court
    The third certified question asks: "[d] oes 'grading' in the
    circumstances presented here constitute visible 'commencement of
    construction' under NRS 108.22112 for purposes of establishing lien
    SUPREME COURT
    OF
    NEVADA
    13
    (0) I947A •
    priority under NRS 108225?" But the visibility, scope, and duration of a
    work of improvement generally are factual questions for the trier of fact to
    decide, L Cox 
    Construction, 129 Nev. at 296
    P.3d at 1205, and this
    court recently noted that it cannot make findings of fact in responding to a
    certified question. In re Fontainebleau Las Vegas Holdings (Fontainebleau
    I), 127 Nev. „ 
    267 P.3d 786
    , 795 (2011). "The answering court's role
    is limited to answering the questions of law posed to it, and the certifying
    court retains the duty to determine the facts and to apply the law provided
    by the answering court to those facts."    
    Id. at 267
    P.3d at 794-95.
    "This approach prevents the answering court from intruding into the
    certifying court's sphere by making factual findings or resolving factual
    disputes." 
    Id. at ,
    267 P.3d at 795.
    The dispute between the parties as to whether the importing
    and spreading or grading of the dirt/material in this case constituted
    visible "commencement of construction" of one comprehensive "work of
    improvement" is, as explained above, of an intensively factual nature.
    Given these unresolved factual disputes, we decline to answer the third
    question.
    CONCLUSION
    We conclude that this court's use of the term "clearing or
    grading" in J.E. Dunn Northwest, Inc. v. Corus Construction Venture,
    L.L.C., 127 Nev. „ 
    249 P.3d 501
    , 509 (2011), was dictum and does
    not alter our ultimate holding that visibility alone determines priority.
    We therefore clarify that grading work may constitute visible
    commencement of construction of a work of improvement in some
    circumstances, as long as it is visible from a reasonable inspection of the
    site in a manner sufficient to provide notice of lienable work that may be
    entitled to priority. Additionally, we conclude that contract dates and
    SUPREME COURT
    OF
    NEVADA
    14
    (0). I.947A
    permit issuance dates are irrelevant to the visible-commencement-of-
    construction test set forth by NRS 108.22112, but may assist the trier of
    fact in determining the scope of the work of improvement. Finally, we
    decline to decide whether the circumstances presented here constitute
    visible commencement of construction under MRS 108.22112 of a
    comprehensive work of improvement under NRS 108.22188 because it
    would require this court to resolve thOactual dispute between the parties.
    Gibbons
    We concur:
    tehiL                         J.
    Pickering
    J.
    Hardesty
    J.
    Parraguirre
    J.
    ,   J.
    Saitta
    SUPREME COURT
    OF
    NEVADA
    15
    (0) I947A    (044
    7      (