HELIX ELEC. OF NEV., LLC v. APCO CONSTR., INC. C/W 80508 , 2022 NV 13 ( 2022 )


Menu:
  •                                                        138 Nev., Advance Opinion      13
    IN THE SUPREME COURT OF THE STATE OF NEVADA
    HELIX ELECTRIC OF NEVADA, LLC,                          No. 77320
    Appellant/Cross-Respondent,
    vs.
    APCO CONSTRUCTION, INC., A
    NEVADA CORPORATION,
    Respondent/Cross-Appellant.
    HELIX ELECTRIC OF NEVADA, LLC,                          No. 80508
    Appellant/Cross-Respondent,
    vs.
    APCO CONSTRUCTION, INC., A
    • •c
    NEVADA CORPORATION,
    MAR 2 4 2022
    Respondent/Cross-Appellant.
    ELI
    CLERK
    ay
    IEF DEPUTY CLERK
    Consolidated appeals and cross appeals from a district court
    judgment, certified as final pursuant to NRCP 54, and an award of attorney
    fees in a construction contract action. Eighth Judicial District Court, Clark
    County; Mark R. Denton, Judge.
    Affirmed.
    Peel Brimley LLP and Eric B. Zimbelman and Richard L. Peel, Henderson,
    for Appellant/Cross-Respondent.
    Fennemore Craig, P.C., and Christopher H. Byrd, Las Vegas; Fennemore
    Craig, P.C., and John Randall Jefferies, Phoenix, Arizona; Marquis Aurbach
    Coifing and Cody S. Mounteer, Las Vegas,
    for Respondent/Cross-Appellant.
    SUPREME COURT
    OF
    NEVADA
    (0) I 947A .)1004
    t 2 - OÝ2,V5
    BEFORE THE SUPREME COURT, PARRAGUIRRE, C.J., STIGLICH and
    SILVER, JJ.
    OPINION
    By the Court, SILVER, J.:
    Pay-if-paid provisions enable a contractor to pay the
    subcontractor only if the contractor first receives payment from the project
    developer or owner. We clarified in APCO Construction, Inc. v. Zitting
    Brothers Construction, Inc., 
    136 Nev. 569
    , 569, 
    473 P.3d 1021
    , 1024 (2020),
    that pay-if-paid provisions, while not void per se, are unenforceable if they
    run contrary to the rights and requirements established under NRS
    624.624-.630. Here, the district court correctly concluded that a subcontract
    provision conditioning the payment of funds retained from earlier progress
    payments on the contractor first being paid was unenforceable. As the court
    further concluded, however, the unenforceability of the pay-if-paid
    condition did not also invalidate the remaining conditions precedent for
    obtaining the retention payment. We also agree with the district court that,
    as the subcontract was assigned after the original contractor terminated its
    contract with the developer, the subcontractor cannot obtain the unpaid
    retention from the original contractor. Finally, for the same reason, the
    contractor is not entitled to attorney fees under the subcontract for
    defending this action. We therefore affirm.
    FACTS AND PROCEDURAL HISTORY
    Gemstone Development West, Inc., sought to construct
    condominiums (the project) and hired respondent/cross-appellant APCO
    Constniction, Inc., as its general contractor. APCO, in turn, subcontracted
    with appellant/cross-respondent Helix Electric of Nevada, LLC, at
    Gemstones direction. While working under APCO, Helix billed
    2
    $5,131,207.11 and was paid $4,626,186.11. The difference, $505,021, was
    withheld in retention. Under section 3.8 of the subcontract, the retention
    would be released only upon the occurrence of several conditions, including
    Gemstone paying APCO, Helix completing its work on the project,
    Gemstone accepting that work, and Helix delivering close-out documents
    and claim releases to APCO.
    Before the project's completion, the relationship between APCO
    and Gemstone deteriorated. Due to Gemstone's failures to issue certain
    progress payments to APCO, APCO issued stop work notices for the project
    multiple times. In so doing, APCO notified the subcontractors that while
    all work on the project was suspended due to its stop work notice, the parties
    were hoping to resolve the issues and, as the prime contract had not at that
    point been terminated, its subcontractors remained contractually bound to
    their subcontracts with APCO. Gemstone, in turn, claimed APCO was in
    breach of their agreement and threatened to terminate the prime contract
    if the breaches were not cured. Gemstone notified the subcontractors of the
    imminent termination of APCO and that it had already located a
    replacement general contractor so as to not delay the project. Soon
    thereafter, APCO notified the subcontractors that it intended to terminate
    the prime contract, explaining that when the general contractor terminates
    its contract, the subcontractors could also terminate their subcontracts.
    Ultimately, APCO left the project at the end of August, with both parties
    claiming that they had terminated the prime contract."
    'Gemstone and APCO disputed which of them terminated the prime
    contract, but ultimately, it was determined by the district court that APCO
    validly terminated the contract.
    3
    Gemstone thereafter notified the subcontractors that it had
    terminated the prime contract and that Camco Pacific Construction
    Company would act as construction manager in place of APCO. Helix did
    not terminate its subcontract with APCO but worked on the project under
    Carrico from August to September 2008. Although Helix did not sign the
    subcontract Cameo proposed, it billed Camco for its remaining fees,
    including the retention earned while Helix worked under APCO, as
    instructed by Gemstone. By December 15, 2008, however, the project
    lenders had withdrawn funding and work on the project was terminated.
    Camco paid Helix only a fraction of the amount it billed, which payment did
    not cover its retention.
    APCO, Camco, and numerous subcontractors, including Helix,
    recorded mechanics liens against the property, and the district court
    consolidated the multiple cases for purposes of discovery and trial.
    Pertinent here, the district court granted partial summary judgment in
    favor of Helix and other subcontractors, preventing APCO and Camco from
    asserting any defenses based on pay-if-paid agreements. The court relied
    on NRS 624.624 and Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.,
    
    124 Nev. 1102
    , 
    197 P.3d 1032
     (2008), which generally make pay-if-paid
    agreements unenforceable and also require higher-tiered contractors to pay
    their lower-tiered subcontractors within the time periods set forth in NRS
    624.624(1).
    At trial, the district court found that the subcontracts had been
    assigned to Gemstone under the prime contract because Gemstone
    purported to terminate the prime contract and told the subcontractors that
    their contracts would be assumed by Cameo; Carrico began directing the
    project and receiving billings from the subcontractors, including for
    SUPREME COURT
    OF
    NEVADA
    (CO 1947A    a1Mbo
    4
    retention; and Helix worked directly with Gemstone and Camco, not APCO,
    after APCO left the project. The district court dismissed Helix's claims for
    retention against APCO because section 3.8s preconditions for retention
    were not satisfied while APCO was the contractor, a fact that Helix
    admitted. Specifically, the district court faulted Helix for failing to show
    completion of the entire project and Gemstones acceptance, Gemstones
    final payment to APCO, and delivery of the close out documents and claim
    releases.
    APCO requested attorney fees pursuant to section 18.5 of the
    subcontract, but the court awarded APCO attorney fees pursuant to NRCP
    68, for less than APCO's requested amount. Helix appeals, challenging the
    denial of its claims for retention against APCO and the award of attorney
    fees under NRCP 68, and APCO cross-appeals, challenging the reduction of
    its requested attorney fees.
    DISCUSSION
    Construction contracts commonly allow the owner or developer
    of a project to withhold a percentage of funds from progress payments to the
    contractor pending completion of the work. See Pittsburg Unified Sch. Dist.
    v. S.J. Amoroso Constr. Co., 
    181 Cal. Rptr. 3d 694
    , 698-99 (Ct. App. 2014).
    Such "retainage or "retention" helps reduce the risk of nonperformance and
    ensure the work is completed per the contract's terms. 
    Id.
     In Nevada, the
    right to retain funds in this manner is governed by NRS 624.624(2)(a)(1),
    which authorizes a higher-tiered contractor, upon written notice, to
    withhold from any payment owed to the lower-tiered subcontractor "[a]
    retention amount . . . pursuant to the agreement, but the retention amount
    withheld must not exceed 5 [(formerly 10)] percent of the payment that is
    [otherwise] required."
    SUPREME COURT
    OF
    NEvaoa
    (0) 1947A astellb
    5
    In this appeal, Helix seeks its withheld retention from APCO,
    asserting that, even though the prime contract was terminated and APCO
    was required to leave the project, APCO never terminated the subcontract
    and thus owes Helix the amount withheld in retention.2 Helix argues that
    the district court incorrectly determined that the subcontract retention
    provision's preconditions and the subcontract's purported assignment to
    Gemstone/Camco precluded payment. In addressing Hethes initial
    argument—that the section 3.8 preconditions are unenforceable, we first
    address whether our holding in Zitting applies to pay-if-paid provisions
    regarding retention. More specifically here, we determine whether, under
    Zitting, NRS 624.624-.630 invalidates section 3.8 of the subcontract in its
    entirety. We thereafter address whether Helix's subcontract was assigned,
    precluding Helix's argument that the retention is owed by APCO.
    2He1ix   alternatively argues that the retention amount is due under a
    quantum meruit theory because its contract with APCO was unenforceable
    for failure to reach a meeting of the minds. But after reviewing the record,
    we conclude substantial evidence supports the district court's finding that
    the subcontract was enforceable. Cf May v. Anderson, 
    121 Nev. 668
    , 672-
    73, 
    119 P.3d 1254
    , 1257 (2005) (explaining that we will defer to the district
    court's factual findings where they are based on substantial evidence).
    Further, to the extent Helix asserts that APCO owes it "additional
    monies earned and unpaid after APCO left the [p]roject,” the same analysis
    applies.
    SUPREME COURT
    OF
    NEVADA
    10) 1447A allaNa.                                        6
    The district court correctly determined that Helix is not entitled to further
    payment from APCO under the subcontract
    The section 3.8 preconditions are valid
    Helix argues the preconditions to obtaining its retention
    payment under section 3.8 of the APCO-Helix subcontract are void and
    unenforceable under Zitting and its antecedent, Lehrer McGovern Bovis,
    because those preconditions include an invalid pay-if-paid provision and
    improperly require Helix to waive its rights under NRS 624.624-.630.
    Consequently, Helix appears to argue, the retention amount became due
    immediately upon completion of its work and is currently owed by APCO.
    We review these questions de novo. I. Cox Constr. Co. v. CH2 Invs., LLC,
    
    129 Nev. 139
    , 142, 
    296 P.3d 1202
    , 1203 (2013) (explaining that we review
    statutory interpretation questions de novo); May, 121 Nev. at 672, 
    119 P.3d at 1257
     (explaining that we review contract interpretation questions de
    novo). We will interpret a clear and unambiguous contract as written. Am.
    First Fed. Credit Union v. Soro, 131 Nev, 737, 739, 
    359 P.3d 105
    , 106 (2015).
    In Lehrer McGovern Bovis, we addressed pay-if-paid provisions,
    which predicate a subcontractor's right to payment from a general
    contractor upon the developer or owner first paying the general contractor.
    We concluded that pay-if-paid provisions violate public policy and are
    generally unenforceable. In Zitting, we clarified that, consistent with 2001
    statutory amendments and NRS 624.628(3), pay-if-paid provisions are not
    void per se but will be unenforceable if they (1) "require subcontractors to
    waive or limit rights provided under NRS 624.624-.630; (2) "relieve general
    contractors of their obligations or liabilities" under those same statutes; or
    (3) "require subcontractors to waive their rights to damages." 136 Nev. at
    569, 473 P.3d at 1024. As to the third factor, NRS 624.628(3)(c) more
    specifically provides that a condition is void if it does the following:
    7
    Requires a lower-tiered subcontractor to waive,
    release or extinguish a claim or right for damages
    or an extension of time that the lower-tiered
    subcontractor may otherwise possess or acquire as
    a result of delay, acceleration, disruption or an
    impact event that is unreasonable under the
    circumstances, that was not within the
    contemplation of the parties at the time the
    agreement was entered into, or for which the lower-
    tiered subcontractor is not responsible, is against
    public policy and is void and unenforceable.
    (Emphases added.)
    Pay-if-paid provisions "require a case-by-case analysis to
    determine whether they are permissible." Zitting, 136 Nev. at 574, 473 P.3d
    at 1027. In Zitting, which involved the claims of another subcontractor who
    worked on the project under a subcontract substantially similar to that at
    issue here, the district court determined the subcontract's pay-if-paid
    provisions were void and unenforceable. 136 Nev. at 574-75, 473 P.3d at
    1027. On appeal, we agreed, because the subcontract provisions conditioned
    Zitting's right to payment on the contractor being paid by the owner and
    thus both violated the subcontractor's right under NRS 624.624(1) to
    prompt payment for its work and restricted its recourse to a mechanics lien
    granted by statute. Id.
    For the same reasons, the precondition subjecting Heli,x's right
    to payment of the retention amount on APCO receiving payment from
    Gemstone is void. The precondition requires Helix to waive its right to
    monies earned if APCO does not receive payment, even if Helix meets its
    obligations, is not at fault for the events that led to nonpayment, and would
    otherwise have a claim for that retention.         See NRS 624.628(3)(c).
    Accordingly, we conclude that this precondition is void.
    8
    Helix contends that section 3.8s other preconditions are also
    void—first, because the pay-if-paid precondition's invalidity voids the whole
    section, and second because they limit its statutory rights by requiring it to
    satisfy conditions "entirely outside of its control." But the subcontract
    included a severability clause, and Helix does not otherwise show why the
    entire provision fails based on one unenforceable pay-if-paid precondition.
    Nor does Helix show that, under NRS 624.628(3), the preconditions to the
    retention payment require it to waive or limit its statutory or contractual
    rights and thus are invalid as a matter of law. NRS 624.624(2)(b) explicitly
    permits a contractor to condition payment of the retained funds upon the
    subcontractor supplying lien releases, and the statute does not preclude the
    contractor from imposing other completion and acceptance conditions on the
    payment. Indeed, such terms appear to go to the very purposes of
    retention—to encourage the subcontractor to complete its work on the
    project and to reserve funds to cure any default •by the subcontractor. See
    Pittsburg Unified Sch. Dist., 181 Cal. Rptr. 3d at 699 (where a contractor
    defaults on the construction contract, the owner is entitled to use the
    retention to complete the contract); see also 3 Philip L. Bruner & Patrick J.
    O'Connor, Jr., Bruner & O'Connor on Construction Law § 8:18, at 39 (2016)
    ("A common contract approach to reducing a contractee's risk that its
    contractor will fail to fully perform its contractual obligations is to withhold
    a percentage of the sums due until the work is substantially complete.").
    Helix's additional arguments for not enforcing the
    preconditions—that events subsequent to beginning work on the project,
    including the project's ultimate abandonment, rendered the preconditions
    impossible, futile, and excused—do not go to the general validity of those
    terms, but rather to the facts of this case. Thus, the district court did not
    9
    err by determining that, aside from the pay-if-paid precondition, the
    subcontract's retention payment preconditions were valid. To the extent
    Helix argues that APCO, by stopping work on the project or failing to
    terminate the subcontract, prevented it from completing the preconditions,
    such that those preconditions should be excused, the district court
    concluded that Helix's work under the subcontract continued after APCO
    left the project under assignment to Gemstone/Camco. Helix's arguments
    as to the assignment findings are discussed next.
    APCO's obligations under the subcontract were assigned
    Helix contends that APCO's obligation to pay Helix for its work
    on the project, including retention fees, was never assigned or waived and
    therefore APCO must pay Helix the retention it earned. Specifically, Helix
    argues that the prime contract allows for assignment only where Gemstone
    terminates APCO for cause and that, because APCO was the party
    ultimately found to have validly terminated the prime contract and APCO
    did not expressly terminate its subcontract with Helix, APCO remained
    obligated to pay Helix for the work it performed under the subcontract.
    "An assignment of a right is a manifestation of the assignor's
    intention to transfer it by virtue of which the assignor's right to performance
    by the obligor is extinguished in whole or in part and the assignee acquires
    a right to such performance." Restatement (Second) of Contracts § 317 (Am.
    Law Inst. 1981). "[A]n assignment does not modify the terms of the
    underlying contract. It is a separate agreement between the assignor and
    assignee which merely transfers the assignor's contract rights, leaving them
    in full force and effect as to the party charged." Easton Bus. Opportunities,
    Inc. v. Town Exec. Suites-E. Marketplace, LLC, 
    126 Nev. 119
    , 125, 
    230 P.3d 827
    , 831 (2010) (internal quotation marks omitted). Nevada law favors "the
    free assignability of rights and frowns on restrictions that would limit or
    10
    preclude assignability," and ordinarily a contractual right is assignable
    unless the assignment will materially change the contract's terms or the
    contract expressly precludes assignment.      Id. at 124, 
    230 P.3d at 830
    (internal quotation marks omitted); see also Restatement (Second) of
    Contracts § 317 (Am. Law Inst. 1981) (explaining that where neither the
    contract nor a statute precludes assignment, a contract right is assignable
    unless the assignment "would materially change the duty of the obligor, or
    materially increase the burden or risk imposed on him by his contract, or
    materially impair his chance of obtaining return performance, or materially
    reduce its value to him").
    Absent a contract provision or statute that imposes restrictions
    on assignments, "there are no prescribed formalities that must be observed
    to make an effective assignment," so long as the assignor manifests "a
    present intention to transfer its contract right to the assignee." Easton, 126
    Nev. at 127, 
    230 P.3d at 832
     (internal quotation marks omitted). Evidence
    of an assignment may include that the assignee administers the project and
    ensures it is correctly carried out, the assignee pays the subcontractors, and
    the assignee answers questions about the project and is physically present
    at the project.   Cf. J. Christopher Stuhrner, Inc. v. Centaur Sculpture
    Galleries, Ltd., 
    110 Nev. 270
    , 274-75, 
    871 P.2d 327
    , 330-31 (1994).
    Here, section 10.02 of the Gemstone-APCO prime contract
    provides in pertinent part that, for any enumerated reason, "Developer
    may.. . terminate employment of General contractor and may.. . . accept
    assignment by any Third-Party Agreements pursuant to section 10.04." In
    turn, Section 10.04 provides in pertinent part, "Each Third-Party
    Agreement for a portion of the Work is hereby assigned by General
    Contractor to Developer provided that such assignment is effective only
    11
    after termination of the Agreement by Developer for cause" and upon
    written notification in writing to the general contractor and the
    subcontractor. In August, Gemstone notified APCO that it would terminate
    the agreement for cause and, upon termination, acquire the subcontracts by
    assignment, and in September, Gemstone sent Helix a letter confirming its
    intent to continue with Helix's services, to which was attached a ratification
    agreement incorporating the APCO-Helix subcontract. Although Helix
    ultimately did not sign the ratification, it negotiated terms, continued to
    work on the project under Camco, and submitted billing statements to
    Camco. Thus, even though the district court many years later concluded
    that APCO, not Gemstone, had validly terminated the contract, it appears
    that the parties proceeded under section 10.04 as if Gemstone had
    terminated the prime contract for cause based on the information available
    to them at the time.
    Regardless, even if Gemstones purported termination did not
    trigger an assignment under the prime contract, we conclude that the
    APCO-Helix subcontract was assigned to Gemstone/Camco. Nothing in the
    prime contract prevented an assignment by other means, and neither that
    contract nor the subcontract required Helix to approve the assignment.
    Gemstone manifested an intent to assign the contract obligations to Camco
    by telling subcontractors their contracts would be assumed by Camco, and
    Camco thereafter directed the project. Helix worked directly with
    Gemstone and Camco after APCO left the project, and Helix billed Cameo
    for its payments, including for the retention. Therefore, we conclude the
    district court did not err in finding APCO's obligations under the
    subcontract were assigned after APCO left the project and Cameo became
    SUPREW COURT
    Of
    NEVADA
    12
    (0) OVA
    the general contractor.3 See Saavedra-Sandoval v. Wal-Mart Stores, Inc. ,
    
    126 Nev. 592
    , 599, 
    245 P.3d 1198
    , 1202 (2010) (holding that we will affirm
    the district court if it reaches the correct result, even if for the wrong
    reason). Accordingly, the district court did not err in concluding that Helix
    failed to prove that APCO owes it further payment for retention or other
    amounts.4
    The district court did not abuse its discretion in granting APCO attorney fees
    pursuant to NRCP 68
    Helix argues that APCO's offer of judgment was untimely,
    rendering NRCP 68 fees unavailable, because it was not made before the
    start of trial in the consolidated cases in 2012. Helix asserts that, because
    no written order bifurcated the trial and the district court recognized the
    start of one overarching "triar for purposes of NRCP 41(e), failure to serve
    the offer of judgment before the trial of matters involving parties other than
    it in 2012 necessarily rendered the offer untimely. While NRCP 68(a)
    requires parties to serve offers of judgment before trial, we explained in
    Allianz Insurance Co. v. Gagnon that an action may consist of more than
    3As we conclude that the district court properly determined the
    subcontract was assigned, we reject Helix's argument that section 9.4 of the
    subcontract, even if it applied here when the subcontract was not
    terminated for convenience, requires APCO to pay Helix's retention.
    4He1ix's   argument that the district court erred in not holding APCO
    liable for the payments owed Helix because this court, in Zitting, already
    determined that APCO is the "party legally liable" under the mechanics'
    lien statutes, see Zitting, 136 Nev. at 577, 473 P.3d at 1029, is without merit.
    In Zitting, APCO waived many of the defenses at issue here, including the
    conditions precedent and assignment arguments. Id. at 576 & n.6, 473 P.3d
    at 1028 & n.6.
    13
    one trial for NRCP 68 purposes. 
    109 Nev. 990
    , 994-95, 
    860 P.2d 720
    , 723-
    24 (1993) ("The offer of judgment is a useful settlement device which should
    be made available at every possible juncture where the rules allow.").
    Nothing in that opinion, or in the federal case it relied on, Cover v. Chicago
    Eye Shield Co., 
    136 F.2d 374
    , 375 (7th Cir. 1943), requires an order
    bifurcating trial or ties the definition of "triar for offer-of-judgment
    purposes to NRCP 41(e). See generally In re Estate of Sarge, 
    134 Nev. 866
    ,
    870-71, 
    432 P.3d 718
    , 722 (2018) ("Consolidated cases retain their separate
    identities . . . ."). Accordingly, the district court properly concluded that the
    offer of judgment, made before trial on Helix's claims began in 2018, was
    timely.
    APCO argues on cross-appeal that the district court erred by
    relying on NRCP 68 to grant APCO its attorney fees incurred following the
    offer of judgment, instead of relying on section 18.5 of the APCO-Helix
    subcontract to award APCO its fees for the entirety of the case. Attorney
    fees are not recoverable absent a statute, rule, or contractual provision.
    Albios v. Horizon Cmtys., Inc., 
    122 Nev. 409
    , 417, 
    132 P.3d 1022
    , 1028
    (2006). We review the district court's decision regarding the fees for an
    abuse of discretion. Gunderson v. D.R. Horton, Inc., 
    130 Nev. 67
    , 80, 
    319 P.3d 606
    , 615 (2014) (reviewing attorney fees for an abuse of discretion).
    "Generally an assignor retains ordy those rights which have not
    passed to the assignee by the assignment . . . ." 6A C.J.S. Assignments
    § 120 (2016). "Mollowing an assignment of a contract the assignee stands
    in the shoes of the assignor and the assignor retains no rights to enforce the
    contract at all." See 6A C.J.S. Assignments § 105 (2016); see also Lauren
    Kyle Holdings, Inc. v. Heath-Peterson Constr. Corp., 
    864 So. 2d 55
    , 58 (Fla.
    Dist. Ct. App. 2003) ("Because an assignment vests in the assignee the right
    SUPREME COURT
    OF
    NEVADA
    (0) I947A    c‘0144
    14
    to enforce the contract, an assignor retains no rights to enforce the contract
    after it has been assigned."). Because the APCO-Helix subcontract was
    assigned to Gemstone and Camco, APCO retains no right to enforce section
    18.5 of the subcontract, and the district court did not err by declining to
    award APCO attorney fees under the subcontract. Accordingly, we affirm
    the attorney fees award.
    CONCLUSION
    We clarify that Zitting applies to retention fees earned by
    subcontractors, and we conclude that section 3.8s pay-if-paid precondition
    is unenforceable under NRS 624.628(3)(c). However, Helix fails to show
    that the other preconditions in section 3.8 are invalid. We further conclude
    that the APCO-Helix subcontract was assigned under these facts and that.
    therefore, APCO was not entitled to attorney fees under section 18.5 of the
    subcontract but was properly awarded fees pursuant to NRCP 68.
    Accordingly, we affirm the district court.5
    LIZ4a.t.)
    Silver
    ur:
    C.J.
    Parraguirre
    ilp4'
    A4
    Stiglich
    5As to the parties remaining arguments, we have considered them
    and conclude they are either unnecessary to address, given this disposition,
    or without merit.
    15