Mentis Sciences, Inc. v. Pittsburgh Networks, LLC ( 2020 )


Menu:
  • NOTICE: This opinion is subject to motions for rehearing under Rule 22 as
    well as formal revision before publication in the New Hampshire Reports.
    Readers are requested to notify the Reporter, Supreme Court of New
    Hampshire, One Charles Doe Drive, Concord, New Hampshire 03301, of any
    editorial errors in order that corrections may be made before the opinion goes
    to press. Errors may be reported by e-mail at the following address:
    reporter@courts.state.nh.us. Opinions are available on the Internet by 9:00
    a.m. on the morning of their release. The direct address of the court’s home
    page is: http://www.courts.state.nh.us/supreme.
    THE SUPREME COURT OF NEW HAMPSHIRE
    ___________________________
    Merrimack
    No. 2019-0548
    MENTIS SCIENCES, INC.
    v.
    PITTSBURGH NETWORKS, LLC
    Argued: June 24, 2020
    Opinion Issued: September 22, 2020
    Shaheen Guerrera & O’Leary, LLC, of North Andover, Massachusetts
    (Peter G. Shaheen on the brief and orally), for the plaintiff.
    Peabody & Arnold LLP, of Boston, Massachusetts (Robert A. McCall and
    John J. O’Connor on the brief, and Mr. O’Connor orally), for the defendant.
    DONOVAN, J. The plaintiff, Mentis Sciences, Inc., appeals an order of
    the Superior Court (McNamara, J.) dismissing its claims for damages
    representing the cost of recreating lost data and lost business and negligence
    against the defendant, Pittsburgh Networks, LLC. The plaintiff argues that the
    trial court erred by: (1) concluding that the damages representing the cost of
    recreating lost data and lost business were consequential; (2) concluding that
    the limitation of liability clause in the parties’ contract is enforceable; and (3)
    dismissing its claim for negligence. We affirm because the damages sought by
    the plaintiff are consequential and the limitation of liability clause precludes
    the plaintiff from recovering consequential damages. We also conclude that the
    economic loss doctrine bars the plaintiff’s negligence claim.
    I. Facts
    We assume the following facts, as alleged in the plaintiff’s complaint, to
    be true. The plaintiff is an engineering firm that, among other things, designs,
    develops, and tests advanced composite materials for United States
    Department of Defense customers. Since entering this sector in 1996, the
    plaintiff has acquired “a vast amount of valuable data that was utilized in its
    operations.”
    In 2010, the defendant began providing the plaintiff with technological
    support or “IT” services. In 2014, the parties executed a “Service Agreement” in
    which the defendant agreed to provide the plaintiff with services including
    “monitoring of computers and network, data backup, network services,
    antivirus, and comprehensive maintenance and support for servers, PC’s and
    the network,” and the plaintiff agreed to pay the defendant an annual fee of
    $15,864. The parties’ contract included the following limitation of liability
    clause: “The Service Provider shall not be liable for any indirect, special,
    incidental, punitive or consequential damages, including but not limited to loss
    of data, business interruption, or loss of profits, arising out of the work
    performed . . . by the Service Provider.”
    In August 2014, the defendant notified the plaintiff that a drive in one of
    its servers had failed and would need to be replaced. The defendant thereafter
    provided the plaintiff a summary of the problem: a “Redundant Array of
    Independent Disks” controller malfunctioned, causing the corruption of some
    of the plaintiff’s data. The defendant attempted to recover the corrupted data;
    however, the data was permanently lost because the defendant had failed to
    properly back it up.
    The plaintiff initiated an action against the defendant, alleging breach of
    contract and negligence. In its complaint, the plaintiff alleged that the lost
    data “represents valuable intellectual property compiled over many years and is
    of daily critical use in [the plaintiff’s] business.” The plaintiff further alleged
    that, as a result of the data loss, it was required to conduct “massively
    expensive” testing in order to recreate the data and that, without the lost data,
    it was “unable to bid or participate in various projects worth potentially
    millions of dollars.” The plaintiff posited that its “actual damages,” which
    included the cost of recreating the data and lost business, were “estimated to
    be in the millions of dollars.” The defendant moved to dismiss the plaintiff’s
    complaint, arguing that the contract’s limitation of liability clause barred the
    damages sought by the plaintiff because they were consequential. It also
    argued that the plaintiff’s negligence theory was unavailable under New
    Hampshire law.
    The trial court, finding the limitation of liability clause enforceable,
    concluded that the damages sought by the plaintiff were consequential and
    2
    therefore unrecoverable because of the limitation of liability provision.
    According to the trial court, the plaintiff could only recover “what [it] expected
    to receive, the fair market value of [the defendant]’s services, which is probably
    close to . . . the contract price.” The trial court also concluded that the
    plaintiff’s negligence claim was precluded by the economic loss doctrine.
    Accordingly, the trial court dismissed the plaintiff’s damages claims for the cost
    of recreating the lost data and lost business and its negligence claim.
    Thereafter, in a ruling that is not the subject of this appeal, the trial court
    awarded the plaintiff $40,000 in direct damages. This appeal followed.
    II. Standard of Review
    In reviewing a trial court’s order on a motion to dismiss, we assume the
    plaintiff’s pleadings to be true and construe all reasonable inferences in the
    light most favorable to the plaintiff. Gen. Insulation Co. v. Eckman Constr.,
    
    159 N.H. 601
    , 611 (2010). We need not, however, assume the truth of
    statements in the plaintiff’s pleadings that are merely conclusions of law. 
    Id.
    Where, as here, the plaintiff attaches a copy of the contract to the complaint,
    we may consider the terms of the contract in reviewing the ruling on the
    motion to dismiss. See Beane v. Dana S. Beane & Co., 
    160 N.H. 708
    , 711
    (2010). A motion to dismiss should be granted if the plaintiff’s allegations are
    not reasonably susceptible of a construction that would permit recovery. See
    
    id.
     In making this inquiry, we look at the facts alleged in the complaint and
    the applicable law and determine whether the allegations provide a basis for
    legal relief. See Eckman Constr., 159 N.H. at 611. If they do not, the trial
    court properly granted the motion to dismiss. See id.
    III. Analysis
    A. Recreation of Data and Lost Business Damages
    We first address the plaintiff’s argument that its complaint seeks only
    “direct damages, and not consequential or incidental damages.” In particular,
    the plaintiff’s complaint claims damages for “man hours spent trying to
    recreate some of the data” and for its loss of business “because it could not bid
    on certain governmental contracts without the data to support its proposals.”
    The goal of money damages for a breach of contract is to place “the
    injured party ‘in as good a position as [it] would have been in had the contract
    been performed.’” Riblet Tramway Co. v. Stickney, 
    129 N.H. 140
    , 149 (1987)
    (quoting Restatement (Second) of Contracts § 347 cmt. a at 112 (1979)); see
    Hawkins v. McGee, 
    84 N.H. 114
    , 117 (1929). This principle describes the
    damages necessary to fulfill an injured party’s expectation interest. See
    Restatement (Second) of Contracts § 347(a)-(c) & cmt. a at 112 (1981). In
    arguing that the damages it seeks are direct rather than consequential, the
    plaintiff incorrectly equates its expectation interest with the measure of direct
    3
    damages. A party’s expectation interest is comprised, in part, of “the loss in
    the value to him of the other party’s performance caused by its failure or
    deficiency,” in addition to “any other loss, including incidental or consequential
    loss, caused by the breach.” Restatement (Second) of Contracts, supra §
    347(a)-(b), at 112. Thus, according to the principles we explain further below,
    a party’s expectation interest may be fulfilled by an award of both direct and
    consequential damages. See 11 Joseph M. Perillo, Corbin on Contracts § 55.3,
    at 10 (rev. ed. 2005) (“Placing a party in the same economic position as
    performance would have sometimes requires a grant of general [or direct]
    damages coupled with consequential damages.”).
    The line dividing what may be considered direct versus consequential
    damages “is not capable of exact determination.” Id. § 56.6, at 105. However,
    we find the following principles instrumental when divining the difference.
    Direct damages “are based on the value of the performance itself,” whereas
    consequential damages are based “on the value of some consequence that
    performance may produce.” Dan B. Dobbs & Caprice L. Roberts, Law of
    Remedies: Damages — Equity — Restitution § 12.4, at 811 (3d ed. 2018); see
    Restatement (Second) of Contracts, supra § 347(a)-(b), at 112; see also
    Schonfeld v. Hilliard, 
    218 F.3d 164
    , 176 (2d Cir. 2000) (describing
    consequential damages as those that “seek to compensate a plaintiff for
    additional losses (other than the value of the promised performance) that are
    incurred as a result of the defendant’s breach”). Thus, consequential damages
    “are not based on the capital or present value of the promised performance but
    upon benefits it can produce or losses that may be caused by its absence.”
    Dobbs & Roberts, supra § 12.2, at 804; see Restatement (Second) of Contracts,
    supra § 347 cmt. c at 114 (“Consequential losses include such items as injury
    to person or property resulting from defective performance.”); see also KC
    Properties v. Lowell Inv. Partners, 
    280 S.W.3d 1
    , 10 (Ark. 2008) (describing
    consequential damages as those that flow “from some of the consequences or
    results of the breach”).
    Applying these principles to the plaintiff’s claim for damages representing
    the cost of recreating the data and lost business, we conclude that such
    damages are consequential. Pursuant to the parties’ contract, the defendant
    agreed to provide services to maintain and manage the plaintiff’s network
    infrastructure. Even if we assume, as the plaintiff asserts, that the defendant
    explicitly agreed to provide data protection or backup services, we would
    conclude that the damages the plaintiff seeks are consequential. The cost of
    recreating the lost data does not represent the value of the performance of
    maintaining and managing the plaintiff’s network or data. Rather, this cost
    represents an amount necessary to repair a loss that was caused by the
    absence of the performance of those services, and, accordingly, is
    consequential in nature.
    4
    Similarly, the business and profits that the plaintiff lost because it
    cannot use the data to bid on projects do not represent the value of the
    defendant’s performance. Lost profit damages may be direct or consequential,
    depending upon the circumstances. See Atlantech Inc. v. American Panel
    Corp., 
    743 F.3d 287
    , 293 (1st Cir. 2014) (discussing when lost profit damages
    may be considered direct or consequential); see also Kerr S.S. Co. v. Radio
    Corporation of America, 
    157 N.E. 140
    , 141 (N.Y. 1927) (“[D]amage which is
    general [or direct] in relation to a contract of one kind may be classified as
    special [or consequential] in relation to another.”). Here, the claimed lost profit
    damages are not direct because the profits lost were not inherent in the
    contract; that is, the plaintiff did not stand to earn these profits as a direct
    result of its contract with the defendant. See Penncro Associates, Inc. v. Sprint
    Spectrum, L.P., 
    499 F.3d 1151
    , 1156 (10th Cir. 2007) (explaining that one
    situation in which lost profit damages are considered direct is “if a services
    contract is breached and the plaintiff anticipated a profit under the contract”);
    see also Atlantech, 743 F.3d at 293 (providing as an example of lost profits that
    are direct damages “a general contractor su[ing] for its remaining contract price
    less saved expenses”). Rather, what the plaintiff gained from the contract was
    the defendant’s services. The plaintiff’s profits were anticipated as a result of
    its bidding and participating in other “projects,” which relied upon actions and
    contingencies that would have taken place outside of its contract with the
    defendant. Accordingly, the lost profit damages the plaintiff seeks are
    consequential. See Atlantech, 743 F.3d at 293 (determining that the lost profit
    damages sought by the plaintiff were consequential because “they depend on
    contingencies beyond the terms of the contract itself”); Penncro, 
    499 F.3d at 1156
     (explaining that lost profits damages are considered consequential if the
    breach precluded the plaintiff “from performing other work . . . from which it
    expected to make a profit”).
    The cases relied upon by the plaintiff provide no support for its argument
    that the damages it seeks are direct rather than consequential. In those cases,
    the courts did not have the occasion to consider the difference between direct
    and consequential damages. See, e.g., In re: Yahoo! Inc. Customer Data
    Security Breach Litigation, 16-MD-02752-LHK, 
    2017 WL 3727318
    , at *46 (N.D.
    Cal. Aug. 30, 2017) (finding that a limitation of liability clause did not bar
    direct damages in data breach litigation, but refusing to consider which of the
    plaintiff’s claimed damages were direct as opposed to consequential because
    the issue was not properly presented by the parties); In re Anthem, Inc. Data
    Breach Litigation, 
    162 F. Supp. 3d 953
    , 982-83 (N.D. Cal. 2016) (dismissing a
    breach of contract claim because the plaintiffs failed to specify in their
    complaint which contractual provisions were breached); Marchesseault v.
    Jackson, 
    611 A.2d 95
    , 98-99 (Me. 1992) (affirming the trial court’s award of
    damages for breach of a construction contract where the distinction between
    direct and consequential damages was not at issue).
    5
    For the same reason, Emery v. Caldeonia Sand & Gravel Co., 
    117 N.H. 441
     (1977), is unavailing to the plaintiff. There, plaintiff farm operators
    brought a breach of contract action against a construction company after the
    company failed to restore the plaintiffs’ farmland according to their contract’s
    specifications. 
    Id. at 444
    . The trial court awarded the plaintiffs damages in
    the amount necessary to restore the land. 
    Id. at 445
    . We affirmed the award
    of damages, explaining that “[a] valuable income-producing asset has been
    rendered unproductive; the damages awarded constitute a reasonable means of
    bringing that asset back to life.” 
    Id. at 448
    . In reaching this conclusion, we
    applied the principle that “the goal of compensation” in a contract case is “the
    awarding of a sum which is the equivalent of performance of the bargain [by
    which the court] attempt[s] to place the plaintiff in the position he would be in
    if the contract had been fulfilled.” 
    Id. at 447
     (quotation omitted). This
    principle describes a plaintiff’s expectation interest, which, as we explained
    above, can include both direct and consequential damages. See Restatement
    (Second) of Contracts, supra § 347(a)-(b), at 112. We further observed that the
    parties’ written agreements included no damage limitation provision and, thus,
    we had no occasion to distinguish direct from consequential damages. Emery,
    
    117 N.H. at 446
    . Accordingly, the case has no bearing on the difference
    between these categories of damages.
    B. Enforceability of the Limitation of Liability Provision
    We next turn to the plaintiff’s argument that the limitation of liability
    provision in the parties’ contract is unenforceable because it prevents the
    plaintiff from obtaining a “minimum adequate remedy” and is thus contrary to
    public policy. The provision provides that the defendant is not liable for “any
    indirect, special, incidental, punitive or consequential damages.”
    Parties to a contract are generally bound by the terms of an agreement
    freely and openly entered into. Rizzo v. Allstate Ins. Co., 
    170 N.H. 708
    , 713
    (2018). Courts cannot improve the terms or conditions of an agreement that
    the parties themselves have executed or rewrite contracts merely because they
    might operate harshly or inequitably. See 
    id.
     However, we will not enforce a
    contract or contract term that contravenes public policy. 
    Id.
     We have
    explained that an agreement is against public policy “if it is injurious to the
    interests of the public, contravenes some established interest of society,
    violates some public statute, is against good morals, tends to interfere with the
    public welfare or safety, or, . . . is at war with the interests of society and is in
    conflict with the morals of the time.” 
    Id.
     (quotation omitted).
    The plaintiff does not argue that the limitation of liability provision
    violates public policy based upon any of the interests we identified in Rizzo.
    Rather, as support for its assertion that the provision here violates public
    policy, the plaintiff relies upon Orthopaedic Center of South Florida, P.A. v.
    Stryker Corporation, 08-60742-CIV-DIMITROULEAS, 
    2008 WL 11331981
     (S.D.
    6
    Fla. Sept. 16, 2008). There, the United States District Court for the Southern
    District of Florida, applying Florida law, concluded that a limitation of liability
    clause that precluded recovery of “direct, special, incidental or consequential
    damages resulting from any breach of warranty or condition, or under any
    other legal theory,” was unenforceable. Id. at *3. The court reasoned that a
    reasonable person would not understand that the clause “contract[s] away any
    meaningful remedy” for a breach and enforcing the clause “would allow the
    Defendants to breach provisions of the contract through its own negligent
    behavior, with impunity, thereby rendering specific provisions of the contract
    meaningless.” Id.
    Here, on the other hand, the limitation of liability clause does not extend
    to “direct” damages or preclude recovery for “damages resulting from any
    breach of warranty or condition, or under any legal theory.” Cf. id. Rather, the
    clause specifically states that the defendant is not liable for “indirect, special,
    incidental, punitive or consequential damages, including but not limited to loss
    of data, business interruption, or loss of profits.” Thus, the limitation of
    liability provision at issue in Stryker was significantly broader than the
    provision set forth in the parties’ contract in this case. This difference renders
    Stryker inapposite. The defendant here could not “breach provisions of the
    contract . . . with impunity,” id., but remained liable for direct damages
    stemming from any breach, and the plaintiff recovered $40,000 in direct
    damages. Furthermore, given the specificity of the clause, a reasonable person
    would have known what they were contracting away, cf. id.; nonetheless, the
    plaintiff chose to enter into the contract.
    The plaintiff also relies upon RSA 382-A:2-719 (2011), a provision of the
    New Hampshire Uniform Commercial Code (UCC), in support of its argument
    that a contract provision precluding recovery of a “minimum adequate remedy”
    is unenforceable. We find this argument unavailing. First, the UCC generally
    applies only to contracts for the sale of goods. In re Trailer and Plumbing
    Supplies, 
    133 N.H. 432
    , 435 (1990). The language of the parties’ contract
    demonstrates that it is a services contract, and, accordingly, the UCC does not
    apply. See id. at 438 (“Because the agreement is a contract for services, the
    UCC does not govern this dispute.”). Second, RSA 382-A:2-719 does not use
    the phrase “minimum adequate remedy,” but states that, in a contract for the
    sale of goods, consequential damages “may be limited or excluded unless the
    limitation or exclusion is unconscionable.” RSA 382-A:2-719(3).
    “Unconscionability has generally been recognized to include an absence of
    meaningful choice on the part of one of the parties together with contract terms
    which are unreasonably favorable to the other party.” Rizzo, 170 N.H. at 717
    (quotation omitted). Here, even if we were to consider the principles of law
    embodied in the UCC in our analysis, the plaintiff makes no argument that it
    lacked a meaningful choice or was in an unequal bargaining position with the
    defendant. See id. Accordingly, we are not persuaded by the plaintiff’s
    arguments that the limitation of liability provision is unenforceable.
    7
    In sum, we conclude that the damages representing the cost of recreating
    the data and lost profits are consequential. Because we also conclude that the
    limitation of liability clause, which precludes recovery of consequential
    damages, is enforceable, the plaintiff is unable to recover those damages.
    C. Negligence Claim
    Finally, we address the plaintiff’s argument that the economic loss
    doctrine does not bar its negligence claim. The economic loss doctrine is a
    “judicially-created remedies principle that operates generally to preclude
    contracting parties from pursuing tort recovery for purely economic or
    commercial losses associated with the contract relationship.” Plourde Sand &
    Gravel v. JGI Eastern, 
    154 N.H. 791
    , 794 (2007) (quotation omitted). The
    doctrine recognizes that contract and warranty law are better suited than tort
    law for “dealing with purely economic loss in the commercial arena.” 
    Id.
    (quotation omitted). Allowing a contracting party to sue in tort “when a
    transaction does not work out as expected” in effect allows that party to
    “rewrit[e] the agreement to obtain a benefit that was not part of the bargain.”
    
    Id.
     (quotation omitted). Accordingly, the doctrine “precludes a harmed
    contracting party from recovering in tort unless he is owed an independent
    duty of care outside the terms of the contract.” Wyle v. Lees, 
    162 N.H. 406
    ,
    410 (2011).
    In Wyle, we determined that the economic loss doctrine did not bar the
    plaintiff’s negligent misrepresentation claim because the misrepresentations
    induced the plaintiff to enter into a contract. Id. at 411-12. The plaintiff
    argues that the defendant “negligently misrepresented to [the plaintiff] that it
    was routinely backing up [the plaintiff’s] data.” However, in Wyle we endorsed
    a distinction between negligent misrepresentation claims “that center upon an
    alleged inducement to enter into a contract from those that focus upon
    performance of the contract.” Id. at 411. When a negligence claim is “based
    merely upon the breach of a contractual duty,” the claim will not lie. Id. On
    the other hand, when “the misrepresentation of present fact serves as an
    inducement for the contract,” the negligence claim is not duplicative of the
    breach of contract claim. Id. (quotation omitted).
    Here, the plaintiff’s complaint does not allege that the defendant
    negligently misrepresented facts in order to induce the plaintiff to enter into the
    contract. Cf. id. at 412 (concluding that a negligent misrepresentation claim
    was unrelated to any material terms of the contract because the claim was
    based upon the defendants’ negligent misrepresentation of facts which induced
    the plaintiff to enter into a purchase and sale agreement). Rather, the
    complaint states that the defendant “was negligent in failing to exercise a
    reasonable standard of care in performing its work by . . . failing to confirm
    that [the plaintiff’s] data was being backed up.” This claim “merely relate[s] to
    a breached promise to perform the terms of the contract” because any duty to
    8
    back up the plaintiff’s data, and thus confirm that such performance was being
    rendered, was created by the terms of the contract. Id. Accordingly, the
    negligence claim is indistinguishable from a claim that the defendant failed to
    perform under the contract and, as such, is “barred by the economic loss
    doctrine.” Id.; see Catalan v. GMAC Mortg. Corp., 
    629 F.3d 676
    , 693 (7th Cir.
    2011) (concluding that the economic loss doctrine barred plaintiffs’ negligence
    claim because the duties claimed by the plaintiffs were rooted in the contract
    itself).
    IV. Conclusion
    For the reasons stated above, we affirm the trial court’s dismissal of the
    plaintiff’s damages claims representing the cost of recreating its lost data and
    lost business and its negligence claim.
    Affirmed.
    HICKS, BASSETT, and HANTZ MARCONI, JJ., concurred.
    9