Appeal of Liberty Utilities (EnergyNorth Natural Gas) Corp., D/B/A Liberty ( 2023 )


Menu:
  • NOTICE: This opinion is subject to motions for rehearing under Rule 22 as
    well as formal revision before publication in the New Hampshire Reports.
    Readers are requested to notify the Reporter, Supreme Court of New
    Hampshire, One Charles Doe Drive, Concord, New Hampshire 03301, of any
    editorial errors in order that corrections may be made before the opinion goes
    to press. Errors may be reported by email at the following address:
    reporter@courts.state.nh.us. Opinions are available on the Internet by 9:00
    a.m. on the morning of their release. The direct address of the court’s home
    page is: https://www.courts.nh.gov/our-courts/supreme-court
    THE SUPREME COURT OF NEW HAMPSHIRE
    ___________________________
    Public Utilities Commission
    No. 2022-0146
    APPEAL OF LIBERTY UTILITIES (ENERGYNORTH NATURAL GAS) CORP.,
    D/B/A LIBERTY
    (New Hampshire Public Utilities Commission)
    Argued: February 9, 2023
    Opinion Issued: November 15, 2023
    Pastori | Krans, PLLC, of Concord (Terri L. Pastori and Ashley D. Taylor
    on the brief, and Terri L. Pastori orally), for the petitioner.
    John M. Formella, attorney general, and Anthony J. Galdieri, solicitor
    general (Christopher G. Aslin, senior assistant attorney general, on the brief
    and orally), for the New Hampshire Department of Energy.
    Donald M. Kreis, consumer advocate, on the brief, for the Office of the
    Consumer Advocate.
    HANTZ MARCONI, J. The petitioner, Liberty Utilities (EnergyNorth
    Natural Gas) Corp., d/b/a Liberty (Liberty), appeals an order of the New
    Hampshire Public Utilities Commission denying Liberty’s request to recover
    development costs related to a proposed natural gas pipeline and tank system,
    the Granite Bridge project. The respondents, the New Hampshire Department
    of Energy and the Office of the Consumer Advocate, appear in opposition to
    this appeal. We affirm.
    I
    The following facts either were stated in the Public Utilities Commission’s
    orders or are drawn from the contents of the documents in the certified record
    before us. This case arises from an unrealized construction project. Liberty is
    a utility company that provides natural gas to thousands of customers in parts
    of New Hampshire. According to Liberty, it relies solely on Tennessee Gas
    Pipeline Co., LLC (Tennessee Gas Pipeline) for its gas supply in southern and
    central New Hampshire. Liberty executives testified that Liberty sought more
    supply from Tennessee Gas Pipeline because Liberty was facing increased
    demand. Liberty and Tennessee Gas Pipeline agreed to an arrangement
    whereby Liberty would receive additional gas from a second pipeline, but
    Tennessee Gas Pipeline cancelled that arrangement. In response, Liberty
    began to explore other options, and eventually decided to construct its own
    pipeline and tank system, called the Granite Bridge project. During that time,
    however, Liberty continued to assess the viability of increasing its supply with
    Tennessee Gas Pipeline. As part of its efforts to construct Granite Bridge,
    Liberty spent approximately $9.1 million in “development costs.” Liberty
    estimated that $7.5 million of that amount consisted of engineering,
    environmental, consulting, internal labor, commission related costs, and land
    costs. Liberty executives specified that the costs included preliminary designs,
    environmental assessments, outside consulting services, and options to
    purchase land, among others. Despite those costs, according to Liberty, it
    would have been years before Liberty broke ground on Granite Bridge. Later,
    Tennessee Gas Pipeline offered Liberty more space on its pipeline at a cheaper
    rate than the projected cost of Granite Bridge. Liberty accepted that offer, and
    then cancelled the Granite Bridge project.
    After Liberty cancelled Granite Bridge, it sought to recover approximately
    $7.5 million in costs through a temporary rate increase to its customers. The
    Public Utilities Commission determined that Liberty could not recover those
    costs through its rates because they were “associated with construction work”
    that was unfinished, and thus barred by RSA 378:30-a. Liberty filed a motion
    for rehearing, which the Public Utilities Commission denied.
    This appeal followed.
    II
    RSA chapter 541 governs our review of Public Utilities Commission
    decisions. See RSA 378:31 (2009). Under RSA 541:13, we will not set aside
    the Public Utilities Commission’s order except for errors of law, unless we are
    satisfied, by a clear preponderance of the evidence, that it is unjust or
    2
    unreasonable. RSA 541:13 (2021). The Public Utilities Commission’s findings
    of fact are deemed prima facie lawful and reasonable. Id. In reviewing the
    Public Utilities Commission’s findings, our task is not to determine whether we
    would have found differently or to reweigh the evidence, but rather, to
    determine whether the findings are supported by competent evidence in the
    record. See Appeal of Malo, 
    169 N.H. 661
    , 668 (2017). We review the Public
    Utilities Commission’s rulings on issues of law de novo. See Appeal of
    Pennichuck Water Works, 
    160 N.H. 18
    , 26 (2010).
    Liberty asserts that its costs are recoverable under RSA 378:30-a
    because construction never began on Granite Bridge. See RSA 378:30-a
    (2009). Determining whether Liberty’s costs are recoverable requires
    interpreting RSA 378:30-a. We first look to the language of the statute itself,
    and, if possible, construe that language according to its plain and ordinary
    meaning. Doe v. Attorney General, 
    175 N.H. 349
    , 352 (2022). We interpret the
    statute as written and will not consider what the legislature might have said or
    add language that the legislature did not see fit to include. 
    Id.
     The legislature
    is not presumed to waste words or enact redundant provisions and, whenever
    possible, every word of a statute should be given effect. 
    Id.
     We construe all
    parts of a statute together to effectuate its overall purpose and avoid an absurd
    or unjust result. 
    Id.
     Moreover, we do not consider words and phrases in
    isolation, but rather within the context of the statute as a whole. 
    Id.
    We begin with the text of the statute to determine whether Liberty’s costs
    are recoverable:
    Public utility rates or charges shall not in any manner
    be based on the cost of construction work in progress.
    At no time shall any rates or charges be based upon any
    costs associated with construction work if said
    construction work is not completed. All costs of
    construction work in progress, including, but not
    limited to, any costs associated with constructing,
    owning, maintaining or financing construction work in
    progress, shall not be included in a utility’s rate base
    nor be allowed as an expense for rate making purposes
    until, and not before, said construction project is
    actually providing service to consumers.
    RSA 378:30-a.
    The plain language of RSA 378:30-a prohibits Liberty from recovering its
    costs for Granite Bridge through its rates. We focus on the second sentence
    because its breadth is broadest. See Appeal of Public Serv. Co. of N.H., 
    125 N.H. 46
    , 52 (1984). The second sentence prohibits recovering “any costs
    3
    associated with construction work if said construction work is not completed.”
    RSA 378:30-a. That sentence broadly restricts recovering costs because a cost
    need only be “associated with” uncompleted construction work for it to be
    unrecoverable. Id.; see Appeal of Public Serv. Co. of N.H., 
    125 N.H. at 54-55
    .
    Here, Liberty sought to recover approximately $7.5 million in costs specifically
    related to its plan to construct Granite Bridge. Executives for Liberty testified
    that these costs included engineering, environmental, and consulting costs,
    among others, and Liberty itself deemed them development costs. They
    testified that the money was spent on, among other things, preliminary
    designs, environmental assessments and compliance, cost analysis, regulatory
    approvals, and options to purchase land and acquire easements. Those costs
    were associated with Granite Bridge because they were steps in the process to
    construct its pipeline and tank system, a physical structure. See Appeal of
    Public Serv. Co. of N.H., 
    125 N.H. at 54
    .
    Liberty asserts that the Public Utilities Commission ignored the word
    “work” in the second sentence of RSA 378:30-a, improperly expanding the
    statute’s reach. By doing so, Liberty contends, the Public Utilities Commission
    barred costs without giving effect to the entirety of the statute. The statute
    bars “costs associated with construction work,” and Liberty contends no
    “construction work” occurred here. Because interpreting RSA 378:30-a is a
    legal question, we review the Public Utilities Commission’s order de novo. See
    Appeal of Pennichuck Water Works, 
    160 N.H. at 26
    . Interpreting the entirety of
    the second sentence still leads to the same conclusion, regardless of whether
    the Public Utilities Commission ignored a word in its analysis. We have
    already interpreted “construction work” to refer to a physical structure. Appeal
    of Public Serv. Co. of N.H., 
    125 N.H. at 53-54
    . Granite Bridge was to consist of
    a pipeline and tank system, a physical structure. See 
    id.
     While no physical
    structure was built, Liberty’s costs remained “associated with” one because
    Liberty incurred costs specifically related to its plan to build a physical
    structure.
    Nevertheless, Liberty contends that its costs should be recoverable
    because it incurred them as part of its statutory obligation to evaluate its
    potential least cost option. As the Department of Energy pointed out, however,
    these “costs would be capitalized if the project had been placed in service” and,
    as the Public Utilities Commission found, are not “least-cost planning costs.”
    The Public Utilities Commission found: “As pointed out by the [Office of the
    Consumer Advocate] and [the Department of] Energy, these costs were not
    routine planning to determine the least-cost course of action, but were costs
    incurred in furtherance of a specific project, Granite Bridge.” As the Public
    Utilities Commission concluded, “[t]he operative question is whether the costs
    were ‘associated with construction,’ . . . .” “Here, these costs were plainly
    associated with the construction of the Granite Bridge project.” The Granite
    Bridge project was “not completed” because it was never constructed. RSA
    4
    378:30-a. Accordingly, Liberty cannot recover its costs when it cancelled the
    project and consumers derived no benefit. See id.; Appeal of Public Serv. Co. of
    N.H., 
    125 N.H. at 54-55
    .
    Next, Liberty argues that our decision in Appeal of Public Service Co. of
    New Hampshire supports its contention that for the second sentence to bar
    recovery of costs actual construction must have begun. We disagree. In
    Appeal of Public Service Co. of New Hampshire, we determined that RSA
    378:30-a barred the utility company from recovering, through rates, its
    investment in a plant which was abandoned during construction. See Appeal
    of Public Service Co. of N.H., 
    125 N.H. at 54-55
    . The utility acquired an
    interest in a project to build a nuclear electric power generating plant and had
    invested $15,926,729 in the construction when the owners cancelled the
    project. 
    Id. at 48-49
    . When the utility sought to recover these costs through
    ratemaking, we held that RSA 378:30-a barred it from doing so. 
    Id. at 54-55
    .
    We reasoned that the company’s costs were “associated” with construction
    work because the company invested in constructing the facility. 
    Id. at 54
    . This
    decision, Liberty contends, limits the meaning of “associated with construction
    work” to projects where actual construction has begun.
    The issue in Appeal of Public Service Co. of New Hampshire, however,
    was whether costs associated with abandoned construction could be recovered
    for that part of the project that had been completed before abandonment. 
    Id. at 51
    . The nature and timing of the costs incurred were not issues in that
    case. See 
    id.
     In particular, we were not provided with a breakdown of the
    costs sought to be recovered, but assumed that the investment included the
    cost of the “actual construction and the cost of money used to pay for it.” 
    Id.
    Without a breakdown of the costs, we cannot determine whether Appeal of
    Public Service Co. of New Hampshire held that pre-construction costs were
    “associated with construction work.” See 
    id.
     Thus, we had no occasion to
    decide in that case whether pre-construction costs alone were costs “associated
    with construction work.” Without such an occasion, Appeal of Public Service
    Co. of New Hampshire did not limit “costs associated with construction work”
    to costs incurred where actual construction began. See 
    id. at 54, 55
    .
    Turning to Liberty’s argument that the first sentence of RSA 378:30-a
    does not apply, we agree because the “construction work” was not “in
    progress.” Regarding the third sentence, Liberty contends that it is
    inapplicable because it addresses “construction work in progress” and no
    “construction work in progress” occurred here. Because “construction work in
    progress” must be different from “construction work,” the examples in the third
    sentence are irrelevant to interpreting the second sentence. We also agree with
    Liberty that the third sentence does not apply, but disagree that its examples
    are irrelevant to our analysis of the second sentence. The third sentence
    states:
    5
    All costs of construction work in progress, including,
    but not limited to, any costs associated with
    constructing, owning, maintaining or financing
    construction work in progress, shall not be included in
    a utility’s rate base nor be allowed as an expense for
    rate making purposes until, and not before, said
    construction project is actually providing service to
    consumers.
    RSA 378:30-a. The third sentence describes “construction work in progress” to
    include “any costs associated with constructing, owning, maintaining or
    financing construction work in progress.” 
    Id.
     In comparison, the second
    sentence also uses the term “any costs associated” but does not delimit the
    timing of the costs incurred to while construction is “in progress.” 
    Id.
     Because
    the second sentence captures costs beyond those “in progress” in the third
    sentence, the costs in the second sentence necessarily encompass costs similar
    to those costs in the third sentence. Thus, construed together, the third
    sentence informs the nature of the costs “associated with” construction work to
    also encompass pre-construction activities, such as “owning” and “financing.”
    Because the statute is unambiguous, we decline to look to the legislative
    history of RSA 378:30-a. See Sutton v. Town of Gilford, 
    160 N.H. 43
    , 55
    (2010).
    Next, we turn to Liberty’s contention that we should look to RSA 162-
    H:2, III to determine what constitutes “construction work” in the second
    sentence of RSA 378:30-a. Liberty contends that RSA 162-H:2, III should be
    read together with RSA 378:30-a to help determine whether Liberty’s costs are
    “associated with construction work.” The Department of Energy counters that
    Liberty waived that argument by failing to include it in Liberty’s motion for
    rehearing. RSA 541:3 governs the procedure for rehearing before the Public
    Utilities Commission. RSA 541:3 (2021). It states, “[w]ithin 30 days after any
    order or decision has been made by the commission, any party to the action . .
    . , may apply for a rehearing . . . , specifying in the motion all grounds for
    rehearing.” 
    Id.
     In its motion for rehearing, Liberty did not mention RSA 162-
    H:2, III, specifically, but did argue that it had not made application for a siting
    permit, nor undertaken any pre-construction or construction activities, and
    cited RSA 162-H:5, I. It then drew the Public Utilities Commission’s attention
    to RSA 162-H:2, III by letter dated January 18, 2022, more than thirty days
    after the Public Utilities Commission October 29, 2021 order. The Public
    Utilities Commission deemed this a “new argument[]” and declined to address
    it.
    We have held however, that a party may cite new authorities so long as
    its general argument was raised in the first instance. See Chagnon Lumber Co.
    v. Stone Mill Const. Corp., 
    124 N.H. 820
    , 822 (1984); State v. Schachter, 133
    
    6 N.H. 439
    , 440 (1990) (holding that where a party raised its “general theory of
    recovery” before the trial court, it “will not lose its right to appeal on that theory
    simply because it cited for the first time on appeal a statute that it believed to
    be favorable to its position.”) Liberty argued before the Public Utilities
    Commission that the dictionary definitions of “construction” and “construct”
    provided legal support for its costs being recoverable and it pointed to its lack
    of siting permit activities pursuant to RSA chapter 162-H as further proof that
    these costs were not related to construction work. In its letter, Liberty added a
    specific reference to RSA 162-H:2, III to define what activities are considered
    “construction work.” Thus, we disagree with the Commission that the letter
    raised a new issue; rather, it raised additional legal authority to support issues
    already presented by Liberty.
    On the merits of Liberty’s additional statutory construction argument, we
    are not persuaded. Liberty contends that RSA 162-H:2, III should be read in
    conjunction with RSA 378:30-a. RSA 162-H:2, III defines “[c]ommencement of
    construction.”
    “Commencement of construction” means any clearing of
    the land, excavation or other substantial action that
    would adversely affect the natural environment of the
    site of the proposed facility, but does not include land
    surveying, optioning or acquiring land or rights in land,
    changes desirable for temporary use of the land for
    public recreational uses, or necessary borings to
    determine      foundation      conditions,     or      other
    preconstruction monitoring to establish background
    information related to the suitability of the site or to the
    protection of environmental use and values.
    RSA 162-H:2, III (2023). Liberty contends that its costs cannot be “associated
    with construction work” because they do not fall under RSA 162-H:2, III. The
    Department of Energy and the Office of the Consumer Advocate counter that
    RSA 162-H:2, III and RSA 378:30-a differ, and should not be read together. We
    agree with them.
    RSA 162-H:2, III and RSA 378:30-a are part of separate and distinct
    regulatory regimes dealing with different subject matter. See RSA 162-H:2;
    RSA 378:30-a. RSA chapter 162-H pertains to the energy facility evaluation,
    siting, construction and operation for projects. RSA ch. 162-H (2023).
    Conversely, RSA chapter 378 governs public utility rate setting. See RSA
    378:27 (Supp. 2022); RSA 378:28 (2009). RSA 162-H:2, III defines what
    constitutes “commencement of construction” before which a certificate must be
    obtained from the Site Evaluation Committee. RSA 162-H:2, III; RSA 162-H:5,
    I. RSA 378:30-a, however, restricts certain costs from being recovered through
    7
    a utility’s rates. RSA 378:30-a. Furthermore, the statutes were enacted at
    different times, rendering RSA 162-H:2, III, enacted in 1991, of little help in
    interpreting RSA 378:30-a, enacted more than a decade earlier in 1979. Laws
    1979, 101:1; Laws 1991, 295:1. Therefore, we decline to import the definition
    of “[c]ommencement of construction” in RSA 162-H:2, III into RSA 378:30-a.
    For the foregoing reasons, we affirm the order of the Public Utilities
    Commission.
    Affirmed.
    MACDONALD, C.J., and DONOVAN, J., concurred.
    8
    

Document Info

Docket Number: 2022-0146

Filed Date: 11/15/2023

Precedential Status: Precedential

Modified Date: 11/15/2023