Appeal of Matthew Lowrie & a. ( 2018 )


Menu:
  •                     THE STATE OF NEW HAMPSHIRE
    SUPREME COURT
    In Case No. 2017-0257, Appeal of Matthew Lowrie & a., the
    court on September 17, 2018, issued the following order:
    Having considered the briefs and oral arguments of the parties, the court
    concludes that a formal written opinion is unnecessary in this case. The
    petitioners, Matthew and Katherine Lowrie and Mark and Deborah Pasculano,
    appeal a ruling of the New Hampshire Wetlands Council (Wetlands Council or
    Council) dismissing their appeal of a wetland Restoration Plan Approval issued
    by the New Hampshire Department of Environmental Services (DES) to their
    abutting neighbors, the respondents, Bruce and Mary McCarthy, for lack of
    jurisdiction. We affirm.
    The relevant facts follow. In January 2016, DES issued a “Letter of
    Deficiency” to the respondents, after it had received complaints “relative to
    alleged turbid water . . . originating from [the respondents’] property after rain
    events and entering an adjacent stream and subsequently then entering Lake
    Sunapee in Sunapee.” In its letter, DES identified several actions the
    respondents needed to take to correct the noted deficiencies including:
    reinstalling and maintaining erosion controls on the property; retaining an
    environmental professional certified in erosion and sediment control;
    submitting monitoring reports to DES; submitting a temporary stabilization
    plan to DES by February 2016; and submitting a permanent stabilization plan
    to DES by March 2016.
    The letter stated that if compliance was not achieved within the time
    period set forth, “DES may take further action against [the respondents]
    including issuing an order requiring that the deficiencies be corrected and/or
    referring the matter to the New Hampshire Department of Justice for injunctive
    relief.” In addition, DES indicated that its personnel “may re-inspect the
    property at a later date to determine whether [the respondents] have come into,
    and are maintaining, full compliance with applicable laws and rules,” and that
    DES “reserve[d] the right to pursue monetary penalties for the deficiencies noted
    . . . as well as any deficiencies noted in subsequent inspections of the property.”
    In response, the respondents engaged an engineering firm and submitted a
    “Temporary Stabilization Plan” in February 2016. DES approved the plan in a
    letter titled “TEMPORARY STABILIZATION PLAN APPROVAL.” In April 2016, the
    respondents’ engineer submitted a permanent stabilization plan.
    Subsequently, the respondents’ engineer submitted a wetland impact
    assessment and proposed restoration plan to DES. In September 2016, DES
    approved the restoration plan in a letter titled “RESTORATION PLAN
    APPROVAL.” The approved plan contained 20 specific conditions including
    restoring approximately 9,055 square feet of wetlands and requiring the
    submission by a qualified environmental consultant of monitoring reports to
    DES over an approximately one-year period “to document the success of the
    restoration and outline a schedule for remedial actions if necessary.” The letter
    stated that the plan approval “does not relieve the [respondents] from the
    obligation to obtain other local, state or federal permits that may be required.”
    In October, the petitioners appealed to the Wetlands Council. The
    petitioners argued that DES acted unlawfully or unreasonably in approving the
    restoration plan for a variety of reasons including: “by not requiring an
    accounting of all of the destroyed wetlands”; “because [DES] did not require a
    sufficient mitigation ratio”; “by not requiring any permits” such as an alteration
    of terrain permit, a state wetlands permit, or a federal wetlands permit; by
    failing to require “hydrology calculations, water quantity/quality testing, and
    ongoing monitoring of water quantity/quality”; and by “not resolv[ing] disputes
    on existing wetlands.” (Bolding omitted.) In sum, the petitioners were not
    satisfied that the restoration plan required the respondents “to fully address
    the stormwater runoff and wetlands destruction that they have unlawfully
    caused.” The petitioners requested that the Wetlands Council “revoke the
    Approval and remand the matter to DES for further proceedings consistent
    with the Council’s findings and rulings.”
    The respondents moved to summarily dismiss the petition, arguing, among
    other assertions, that because a Restoration Plan Approval is not a “department
    permitting decision” as defined by RSA 21-O:14 (Supp. 2017), the Wetlands
    Council lacked jurisdiction to hear the appeal. The Wetlands Council agreed,
    and, accordingly, granted the respondents’ motion for summary dismissal. The
    petitioners unsuccessfully moved for reconsideration, and this appeal followed.
    The petitioners raise two issues on appeal. First, they argue that the
    Wetlands Council erred by concluding that it lacked jurisdiction to hear the
    appeal because the “Restoration Plan Approval” issued by DES is a department
    permitting decision subject to appeal to the Council. Second, they argue that
    the restoration plan approval constitutes an “after the fact” wetlands permit
    subject to appeal to the Council. (Quotation omitted.)
    Resolving these issues requires us to interpret the relevant statutory
    provisions. This court is the final arbiter of the intent of the legislature as
    expressed in the words of the statute considered as a whole. Appeal of Union
    Tel. Co., 
    160 N.H. 309
    , 317 (2010). In interpreting a statute, we first look to
    the language of the statute itself, and, if possible, construe that language
    according to its plain and ordinary meaning. 
    Id.
     Unless we find that the
    statutory language is ambiguous, we need not look to legislative intent. 
    Id.
    Furthermore, we interpret statutes in the context of the overall statutory
    2
    scheme and not in isolation. 
    Id.
     We review an agency’s statutory
    interpretation de novo. See 
    id. at 314
    .
    The Wetland Council’s jurisdiction to hear appeals is set forth in RSA 21-
    O:5-a (Supp. 2017) and RSA 21-O:14. The Council is authorized to “hear all
    administrative appeals from department decisions made under RSA 482-A
    relative to wetlands . . . and [to] decide all disputed issues of fact in such
    appeals in accordance with RSA 21-O:14.” RSA 21-O:5-a, V. A “department
    permitting decision” constitutes a “department decision” under RSA 21-O:14,
    I(c).
    The statute defines a “department permitting decision” as “the
    department’s final action to grant in whole or in part, with or without
    conditions, or to deny an application or other request for a license as defined in
    RSA 541-A:1, VIII.” RSA 21-O:14, I(a). A “license” as defined in RSA 541-A:1,
    VIII (2007) is “the whole or part of any agency permit, certificate, approval,
    registration, charter or similar form of permission as required by law.”
    The petitioners first argue that the Wetlands Council erred “by denying it
    had jurisdiction under RSA 21-O:5-a to hear the appeal.” (Bolding and
    capitalization omitted.) Their argument is as follows:
    The Wetlands Council has broad jurisdictional authority to hear
    “appeals from department decisions made under RSA 482-A
    relative to wetlands.” RSA 21-O:5-a. Department Decisions are
    defined in RSA 21-O:14 to include “Department Permitting
    Decisions” and “Department Enforcement Decisions.” RSA 21-
    O:14, I(c). Department Permitting Decisions are defined to include
    “the department’s final action to grant in whole or in part, with or
    without conditions, or to deny an application or other request for
    a license as defined in RSA 541:1, VIII.” RSA 21-O:14, I(a)
    (emphasis added). RSA 541-A:1, VIII defines a request for a license
    as “the whole or part of any agency permit, certificate, approval,
    registration, charter or similar form of permission required by law”
    (emphasis added).
    Putting this together, there is a right to appeal Department
    “Permitting Decisions,” which [are] defined to include the “approval
    or similar form of permission” to do work where permission is
    required. By statute, work in wetlands areas requires approval
    and a permit. RSA 482-A:3.
    (Ellipses omitted.)
    We disagree that the DES decision at issue is a “department permitting
    decision.” As set forth above, to qualify as a “department permitting decision,”
    3
    RSA 21-O:14, I(a) requires that such decision be the result of an “application or
    other request for a license.” However, the respondents did not make an
    application or other request to DES; rather, the restoration plan approval was
    requested by DES. The use of the word “approval” did not turn DES’s
    discretionary enforcement action into a department permitting decision.
    Accordingly, we are not persuaded that the DES restoration plan approval — a
    step taken by DES as part of its discretionary authority to investigate and
    enforce the wetlands laws under RSA chapter 482-A — constitutes a
    “department permitting decision” within the meaning intended by the
    legislature. See Appeal of Morgan, 
    144 N.H. 44
    , 48 (1999) (explaining that
    “decisions to investigate and prosecute are committed to the sound discretion
    of the agency” and that “[b]y virtue of its specialized knowledge and authority,
    the agency alone is empowered to develop that enforcement policy best
    calculated to achieve the ends contemplated by the legislature and to allocate
    its available funds and personnel in such a way as to execute its policy
    efficiently and economically” (quotation and brackets omitted)).
    The petitioners next argue that the restoration plan approval constitutes
    an “after the fact” wetlands permit subject to appeal to the Wetlands Council.
    In support, they rely upon an administrative rule providing that “[a]pplications
    received after work is completed shall be subjected to the same review as any
    other application.” N.H. Admin. R., Env-Wt 302.05. Thus, they contend, DES
    “cannot bypass the statutory requirement of a permit by simply issuing a
    document called a Restoration Plan Approval, thereby depriving [the
    petitioners] their rights of notice and appeal associated with the review and
    issuance of a wetlands permit.”
    The restoration plan approval was not an after-the-fact permit. The
    restoration plan approval was issued in response to the respondents
    voluntarily complying with the actions identified by DES in its letter of
    deficiency. To conclude that the restoration plan approval issued by DES
    constituted an after-the-fact permitting decision appealable to the Wetlands
    Council under RSA 21-O:14 requires a strained interpretation of the statutory
    language not supported by the plain meaning of the words used. See Appeal of
    Michele, 
    168 N.H. 98
    , 102 (2015) (explaining that we construe all parts of a
    statute together to effectuate its overall purpose and avoid an absurd or unjust
    result).
    Affirmed.
    HICKS, BASSETT, and HANTZ MARCONI, JJ., concurred.
    Eileen Fox,
    Clerk
    4
    

Document Info

Docket Number: 2017-0257

Filed Date: 9/17/2018

Precedential Status: Non-Precedential

Modified Date: 11/12/2024