Christopher Nastasi v. Ronald Brown & a. ( 2015 )


Menu:
  •                     THE STATE OF NEW HAMPSHIRE
    SUPREME COURT
    In Case No. 2014-0671, Christopher Nastasi v. Ronald
    Brown & a., the court on July 23, 2015, issued the following
    order:
    Having considered the briefs, memorandum of law, and record submitted
    on appeal, we conclude that oral argument is unnecessary in this case. See
    Sup. Ct. R. 18(1). We affirm.
    The defendants, Ronald Brown, Sweethill Investments, LLC, and Ronald
    Brown Investments, LLC, appeal the order of the Superior Court (Anderson, J.)
    after a bench trial awarding a judgment to the plaintiff, Christopher Nastasi
    d/b/a CN Building Movers, on his claims for breach of contract and
    conversion. The defendants argue that the trial court erred in failing to
    conclude that the plaintiff’s claims were barred by the statute of limitations.
    The statute of limitations is an affirmative defense, and the defendants bear the
    burden of proving that it applies to the plaintiff’s claims. Glines v. Bruk, 
    140 N.H. 180
    , 181 (1995).
    The defendants first argue that the plaintiff’s breach of contract claim
    was time-barred. To be timely, a contract claim must be brought within three
    years of when the breach occurs. Coyle v. Battles, 
    147 N.H. 98
    , 100 (2001);
    RSA 508:4, I (2010). The record shows that the defendants entered into a
    contract with the plaintiff on or about October 18, 2006, the date of the
    plaintiff’s letter setting forth the terms of the agreement, in which the plaintiff
    agreed to move the defendants’ house to a new location for $13,000. The
    contract provided that payment of $5,000 would be due when the house was
    removed from its existing foundation; a second $5,000 payment would be due
    when the house was on wheels; and a $3,000 payment would be due when the
    house was lowered onto temporary supports at the new location.
    The contract also provided that the defendants had thirty days following
    completion of the work in which to have all necessary work done to allow the
    plaintiff to remove his equipment, which consisted of steel beams and wooden
    cribs providing temporary support for the structure. The contract next
    provides, “If we are unable to remove our equipment at the end of this 30-day
    period, we shall be obliged to impose a charge of $45.00 per day thereafter for
    which our equipment must remain on the site.”
    There is no dispute that the plaintiff moved the house in October, 2006,
    and that the thirty-day period ended on or about November 15, 2006. The
    plaintiff was not able to remove his equipment after that date because there
    were no replacement supports in place. In July 2007, the plaintiff started
    sending invoices to the defendant regularly for the $45 per day rental charge
    for his equipment. On January 11, 2008, the plaintiff’s attorney sent the
    defendants a letter demanding payment “for the balance of the contract price,
    which now totals $17,730.00, and the return of the equipment supporting the
    structure.” When no response was received, the plaintiff continued sending the
    defendants invoices for the still-accruing $45 per day rental charge. On June
    25, 2011, the house was destroyed by fire. The plaintiff testified that his
    wooden cribs were destroyed, and his steel beams were damaged beyond
    repair. On July 18, 2013, the plaintiff filed suit against the defendants for
    breach of contract, conversion, and other causes of action. The defendants
    raised the statute of limitations as an affirmative defense.
    After a bench trial, the trial court ruled that the three-year statute of
    limitations in RSA 508:4 (2010) barred claims that arose prior to July 18,
    2010, the date three years prior to the date on which suit was filed. The court
    also ruled, however, that claims for rental payments from July 18, 2010
    through the date of the fire were timely because the claims did not arise until
    each day’s rent became due. See Coyle, 
    147 N.H. at 100
     (claim arises when
    breach occurs); General Theraphysical, Inc. v. Dupuis, 
    118 N.H. 277
    , 279
    (1978) (statute of limitations does not begin to run on an installment until it
    becomes due). On appeal, the defendants do not argue that the trial court
    erred in ruling that the claims for rental payments did not arise until each
    day’s rent became due. Instead, the defendants argue that the statute of
    limitations started to run on January 11, 2008, the date of the attorney’s
    demand letter, because the letter showed that the plaintiff knew by that date
    that he had been injured by the defendants’ conduct. See Wood v. Greaves,
    
    152 N.H. 228
    , 232 (2005) (declining to apply discovery rule where record
    showed that plaintiffs should have known more than three years before suit
    was filed that defendant proximately caused their injuries).
    We conclude that the defendants’ argument does not address the trial
    court’s reasoning. The plaintiff did not assert that he was unaware that he was
    injured by the defendants’ conduct, and the trial court did not rule that the
    discovery rule applies; on the contrary, the court ruled that the statute of
    limitations barred any claim that arose more than three years before the
    plaintiff filed suit. Accordingly, we conclude that the defendants have failed to
    show that the court erred in implicitly ruling that the $45 per day obligation
    was in essence an installment contract and, thus, that the claims for rental
    payments from July 18, 2010 through the date of the fire were timely. See
    Coyle, 
    147 N.H. at 100
     (on appeal, appellants have the burden to demonstrate
    error).
    2
    To the extent that the defendants argue that the January 11, 2008 letter
    from the plaintiff’s attorney effectively terminated the contract and, thus, that
    no rent accrued after that date, we note that the letter expressly states: “The
    contract continues to accrue charges at a daily rate of forty-five dollars per day
    for the use of the equipment.” Accordingly, we conclude that the trial court
    was not compelled to find that the attorney’s letter terminated the contract.
    See Behrens v. S.P. Constr. Co., 
    153 N.H. 498
    , 500-01 (2006) (We will sustain
    the trial court’s findings if they are supported by the record.).
    The defendants next argue that the trial court erred in failing to conclude
    that the plaintiff’s conversion claim was time-barred. They argue that the
    statute of limitations on this claim started to run on the date of the attorney’s
    demand letter, January 11, 2008, or shortly thereafter, because they failed to
    return the plaintiff’s equipment in response to the letter. They concede that
    nothing in the record shows that they explicitly refused to return the plaintiff’s
    equipment after receiving the letter. They assert, however, that their lack of
    response within the ten-day period set forth in the letter “constituted a refusal”
    for purposes of the statute of limitations.
    We conclude, however, that the trial court was not compelled to find that
    the defendants’ failure to return the equipment in response to the attorney’s
    demand letter constituted a conversion of the plaintiff’s property. See LFC
    Leasing & Financial Corp. v. Ashuelot Nat. Bk., 
    120 N.H. 638
    , 640 (1980)
    (noting that “not every failure to deliver upon demand will constitute a
    conversion”). Moreover, such a finding would be inconsistent with the
    defendants’ position that they repeatedly asked the plaintiff to retrieve his
    equipment, but that the plaintiff failed to do so in a timely manner. Thus, the
    trial court was not required to find that the limitations period had expired
    before the plaintiff filed suit. The trial court concluded that the defendants
    converted the plaintiff’s equipment when they failed to allow for the return of
    the property prior to the fire that damaged it beyond repair and maintained
    possession of it during the fire. We assume the trial court found that the
    conversion occurred within three years of July 18, 2013, the date the plaintiff
    filed suit, see Nordic Inn Condo. Owners’ Assoc. v. Ventullo, 
    151 N.H. 571
    , 586
    (2004) (we assume trial court made all findings necessary to support its
    decision, even if it did not do so expressly), and conclude that the record
    supports such a finding, see Behrens, 
    153 N.H. at 500-01
    .
    Affirmed.
    Dalianis, C.J., and Hicks, Conboy, Lynn, and Bassett, JJ., concurred.
    Eileen Fox,
    Clerk
    3
    

Document Info

Docket Number: 2014-0671

Filed Date: 7/23/2015

Precedential Status: Non-Precedential

Modified Date: 11/12/2024