IN THE MATTER OF THE PETITION OF NEW JERSEY NATURAL GAS COMPANY FOR A DETERMINATION CONCERNING THE SOUTHERN RELIABILITY LINK PURSUANT TO N.J.S.A. 40:55D-19 AND N.J.S.A. 48:9-25.4 (NEW JERSEY BOARD OF PUBLIC UTILITIES) (CONSOLIDATED) ( 2021 )


Menu:
  •                             NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NOS. A-3666-15
    A-3752-15
    IN THE MATTER OF THE
    PETITION OF NEW JERSEY
    NATURAL GAS COMPANY FOR
    A DETERMINATION
    CONCERNING THE SOUTHERN
    RELIABILITY LINK PURSUANT
    TO N.J.S.A. 40:55D-19 AND
    N.J.S.A. 48:9-25.4.
    ______________________________
    Argued January 20, 2021 – Decided April 29, 2021
    Before Judges Yannotti, Haas and Natali.
    On appeal from the New Jersey Board of Public
    Utilities, No. GO15040403.
    Paul Leodori argued the cause for appellant Pinelands
    Preservation Alliance (Paul Leodori, PC, attorney;
    Todd M. Parisi, on the brief).
    Daniel A. Greenhouse argued the cause for appellant
    Sierra Club (Eastern Environmental Law Center,
    attorneys; Aaron Kleinbaum, of counsel; Raghu
    Murthy, on the briefs).
    Geoffrey R. Gersten, Deputy Attorney General, argued
    the cause for respondent New Jersey Board of Public
    Utilities (Gurbir S. Grewal, Attorney General, attorney;
    Melissa H. Raksa, Assistant Attorney General, of
    counsel; Andrew M. Kuntz, Deputy Attorney General,
    and Geoffrey R. Gersten, on the briefs).
    James C. Meyer argued the cause for respondent New
    Jersey Natural Gas Company (Riker Danzig Scherer
    Hyland & Perretti, LLP, attorneys; Kevin H. Marino
    and John A. Boyle, on the briefs).
    Maura A. Caroselli, Assistant Deputy Rate Counsel,
    argued the cause for respondent New Jersey Division of
    Rate Counsel (Stephanie A. Brand, Director, attorney;
    Maura A. Caroselli, on the briefs).
    PER CURIAM
    These two appeals, argued back-to-back and consolidated for purposes of
    this opinion, arise from a proposal by respondent New Jersey Natural Gas
    Company (NJNG) to construct a natural gas pipeline through several
    municipalities and a portion of the Pinelands Area. On March 18, 2016, the
    Board of Public Utilities (Board) granted a petition by NJNG pursuant to
    N.J.S.A. 40:55D-19, and determined that the Municipal Land Use Law (MLUL),
    N.J.S.A. 40:55D-1 to -163, and any local governmental development regulations
    adopted pursuant to the MLUL, would not apply to the construction of the
    pipeline.1
    1
    We will refer to this petition as the MLUL petition.
    A-3666-15
    2
    Appellants Pinelands Preservation Alliance (PPA) and Sierra Club (SC)
    appeal from the Board's decision. Having reviewed appellants' contentions in
    light of the record and applicable law, we affirm.
    I.
    The procedural history and facts of this matter are fully set forth in the
    Board's thorough written opinion and, therefore, we need only summarize the
    most salient facts here. NJNG is a New Jersey public utility engaged in the
    business of purchasing, distributing, transporting, and selling natural gas to
    approximately 510,000 customers in Morris, Middlesex, Monmouth, and Ocean
    Counties, and the most southeastern portion of Burlington County.         While
    NJNG's northern service area was connected to five interstate transmission
    feeds, three of which could independently supply that entire region, NJNG's
    central and southern service areas were connected to the Texas Eastern
    Transmission (TETCO) gas pipeline, a single interstate feed located outside of
    NJNG's franchise area in Middlesex County.
    On April 2, 2015, NJNG filed the MLUL petition 2 with the Board
    proposing the construction and operation of an interstate natural gas
    2
    In addition to the MLUL petition, NJNG filed a "safety petition" seeking,
    among other things, the Board's approval to install the pipeline "within 100 feet
    A-3666-15
    3
    transmission pipeline to be known as the Southern Reliability Link (SRL). As
    explained in its MLUL petition, NJNG designed the SRL "to maintain system
    integrity and reliability by creating a new, redundant major feed of natural gas
    supplies from a second interstate transmission system." The SRL would connect
    NJNG's existing natural gas system to a new interstate supply point located in
    Chesterfield and operated by the Transcontinental Pipe Line Company
    (Transco). The SRL would run from that supply point through six townships:
    Chesterfield, North Hanover, Upper Freehold, Plumsted, Jackson, and
    Manchester. A 12.1 mile portion in Ocean County, which included right-of-way
    (ROW) areas located within and alongside the Joint Base McGuire-Dix-
    Lakehurst (Joint Base), would cross the State-designated Pinelands Preservation
    Area, N.J.S.A. 13:18A-2, -9, and -11(b). NJNG filed an amended petition
    incorporating a new route through Upper Freehold Township on June 5, 2015.
    In its MLUL petition, NJNG asked the Board to: (1) determine that the
    project was reasonably necessary for the service, convenience, and welfare of
    the public; (2) designate the pipeline's route through North Hanover and
    of any building intended for human occupancy." The Board granted the safety
    petition. PPA filed a separate appeal challenging the Board's approval of the
    safety petition. Docket No. A-2876-15. In an opinion filed on this date in that
    appeal, we affirm the Board's decision granting the safety petition.
    A-3666-15
    4
    Chesterfield; and (3) determine that all of the zoning and local land ordinance s
    and regulations promulgated under the MLUL by Burlington, Monmouth and
    Ocean Counties, and Chesterfield, North Hanover, Upper Freehold, Plumsted,
    Jackson, and Manchester Townships would not apply to the project. The Board
    retained the MLUL petition for hearing and designated Commissioner Dianne
    Solomon to conduct the case.
    Commissioner Solomon denied PPA's motion to intervene in the hearing,
    but granted its motion to participate in the proceeding, "limited to the right to
    argue orally and file a statement or brief as set out in N.J.A.C. 1:1-16.6(c)(1)
    and (2)." SC did not seek to intervene or participate in the matter. However,
    Commissioner Solomon conducted three public hearings on the petition and both
    PPA and SC presented testimony opposing the SRL project at the public hearing
    held on July 28, 2015.
    Commissioner Solomon conducted an evidentiary hearing on December
    5, 2015. NJNG and the affected local municipalities presented pre-filed and live
    testimony. Craig A. Lynch, NJNG's Senior Vice President of Energy Delivery,
    testified that he had thirty years of experience designing and operating NJNG's
    system. Lynch stated that the SRL project was needed to support the reliability
    and integrity of NJNG's intrastate transmission system by providing a redundant
    A-3666-15
    5
    major transmission feed to its Central and Ocean Divisions, which serve its
    customers in Ocean, Burlington, and Monmouth Counties.
    Lynch explained that over 85% of NJNG's winter peak-day gas supply for
    its Central and Ocean Divisions was provided by a single interstate connection
    operated by TETCO. The remaining 15% of NJNG's winter peak-day gas supply
    was provided by two smaller connections.       Thus, unlike NJNG's Northern
    Division with its five major interstate feeds, NJNG's customers in its Central
    and Ocean Divisions were most vulnerable to a TETCO supply chain failure.
    The SRL project would provide "a major supply of natural gas from a second
    interstate supply (Transco), reducing dependency on a single primary source
    (TETCO)." According to Lynch, "[t]he aspirational goal of NJNG [was] to be
    able to maintain service to the entire Monmouth/Ocean/Burlington region
    should one of these sources of supply be interrupted, or experience a prolonged
    loss of use of existing NJNG transmission facility along its internal backbone
    system."
    Lynch explained that Superstorm Sandy had revealed NJNG's critical need
    for system redundancy in its Central and Ocean Divisions, especially after
    31,000 of its customers had gas service curtailed during and after the stor m.
    Lynch stated that these service curtailments were related to NJNG's decision to
    A-3666-15
    6
    depressurize the local transmission system for safety reasons, and not to a total
    interruption of the interstate supply.        Nevertheless, this storm event
    demonstrated to NJNG the tremendous cost of a potential widespread intrastate
    curtailment, together with "other implications like making customer homes
    inhabitable due to a lack of heat and hot water." Lynch stated that "each location
    damaged [by the storm] also had substantial areas downstream that were viable,"
    so "[i]f additional feeds were available to those systems, the outages could have
    been minimized because [NJNG] would have isolated the damaged areas and
    kept gas flowing to the undamaged areas."
    Lynch then identified the significant difficulties, costs, and delays that
    would arise in connection with restoring service after a widespread interruption
    in the absence of a redundant feed:
    [T]he pipeline would need to be brought back into
    service either by repair or replacement. Once the
    pipeline was restored, each affected distribution system
    would need to be restored, and each customer's service
    would need to be individually restored. After the
    curtailment, technicians would have to visit every
    customer, door to door, multiple times (to turn off,
    reenergize, and turn on appliances) to restore service.
    For example, after Superstorm Sandy, it took two
    months to restore service to approximately 31,000
    customers on Long Beach Island and the Seaside
    Peninsula area of NJNG's service territory. Restoring
    service to a larger population of customers could take
    much longer.
    A-3666-15
    7
    Lynch also described two events involving TETCO's interstate feed during
    which the SRL would have affected NJNG's transmission and distribution
    system and demonstrated the need for the SRL.                   First, TETCO's
    Entriken/Chambersburg compressor stations had reduced the capacity of gas
    flowing to NJNG due to a system failure that lasted from January 7 to January
    15, 2015. "TETCO declared the outages a force majeure event," and NJNG
    estimated that a similar outage would affect approximately 350,000 to 400,000
    of its customers, cost between $170 million to $190 million, and take a minimum
    of four months to restore service once adequate supply became available.
    Second, during the 2014 Polar Vortex, an unplanned outage at TETCO's
    Delmont compressor station decreased the availability of natural gas to NJNG.
    This resulted in decreased line pressure and required NJNG to run its liquified
    natural gas (LNG) plants for thirty-six hours to maintain system integrity and
    replace lost supply. Lynch stated that a lengthier or more intense TETCO outage
    "could have resulted in significant customer interruptions because LNG supply
    and send[-]out capacities are limited." He explained that LNG plants cannot
    replace a lost supply of more than 160,000 dekatherms 3 per day (Dth/day).
    3
    A "dekatherm" is a unit of energy used primarily to measure natural gas.
    A-3666-15
    8
    Lynch asserted that with the SRL in place, there would have been no risk
    to customer interruptions during either of these events since gas service would
    have been provided via the SRL's connection to Transco.            Because NJNG
    currently relied on a single interstate feed for nearly all of its gas supply to its
    Central and Ocean Divisions, Lynch testified it would be "bad planning and
    irresponsible" for NJNG to wait for a catastrophic event resulting in widespread
    service loss before taking steps to avoid or mitigate such an event.
    Lynch also testified that the New Jersey Reinvestment in System
    Enhancement (NJ RISE) Program, approved by the Board in 2014, would not
    render the SRL unnecessary. NJ RISE was "the name of a group of six NJNG
    projects approved by the [Board] in 2014 providing system enhancements that
    improve NJNG's distribution system through storm hardening investments."
    Lynch explained that because four of those projects served as secondary feeds
    to large single-feed distribution systems along the coast, the NJ RISE project
    would not render the SRL unnecessary.
    Lynch testified that the SRL project was intended exclusively for
    reliability and not expansion or addition of services. "[T]he planning and design
    of this [p]roject [was] exclusively a reliability project, providing an alternate
    source of natural gas for our customers." However, he agreed that expansion or
    A-3666-15
    9
    addition of services was "not out of the question," and that more customers
    would increase NJNG's profits.
    Respondent Division of Rate Counsel presented the testimony of Edward
    A. McGee of McGee Consulting, LLC. McGee believed that only a portion of
    the cost of the proposed line should be borne by ratepayers, since the proposed
    pipeline was oversized for the current contract that NJNG had negotiated with
    the interstate pipeline transporting gas to the SRL. He explained that since the
    entire amount of gas set forth in the contract could be supplied to NJNG's system
    through a smaller-diameter line, only the cost of a smaller-diameter line should
    be borne by ratepayers. However, McGee made clear that he did not mean to
    suggest that NJNG should install a twenty-four-inch pipeline instead of its
    planned thirty-inch pipeline. Instead, he explained that while NJNG could
    choose the size of the line, ratepayers should not be expected to pay the cost of
    an oversized line.
    In response, Lynch testified it would be a mistake to equate the diameter
    of the pipeline with the contract NJNG had signed for the gas supply, and to
    conclude this volume was best delivered only with a twenty-four-inch pipe.
    According to Lynch, contract volume did not equal reliability requirements.
    That is, contract volume was limited by the infrastructure of the interstate
    A-3666-15
    10
    pipelines and did not reflect NJNG's full reliability requirement.          Lynch
    explained that "NJNG's primary existing backbone is [thirty]-inch pipeline" and
    a similarly-sized pipeline for the SRL project was "required to feed the entire
    system once upgrades are made to [the] backbone to provide for a fully looped
    system."
    Lynch stated that without a "looped backbone," the SRL could not provide
    gas to the entire southern portion of NJNG's service area. In the event there was
    a reduction of supply from TETCO, the SRL's design would ensure transmission
    system integrity. Also, in the absence of a thirty-inch pipeline, the additional
    capacity transacted for in the event of an interruption could not flow prop erly
    without an unacceptable pressure drop.
    NJNG also presented the testimony of Barry A. Baker, manager of the
    Impact Assessment and Permitting Department at AECOM Technology Corp.,
    who testified as an expert on siting utility transmission facilities. NJNG retained
    AECOM and Baker to assist in the evaluation and development of an alternate
    routes study in order to select a route for the SRL that would best minimize
    impacts to local communities and the natural environment while maintaining
    constructability.
    A-3666-15
    11
    Baker's alternatives analysis consisted of four fundamental phases: define
    the project study area, generate alternative routes, evaluate the alternatives, and
    determine the selected route using a quantitative and qualitative assessment. In
    the first phase, Baker found that a new service feed was required to accomplish
    NJNG's project objectives of developing an independent gate station capable of
    delivering large volumes of gas, supporting the southern end of NJNG's
    transmission system, and not needing supply from TETCO.
    Baker next split the proposed pipeline into two geographical sections
    because the eastern portion of the study area was located within the Pinelands
    and any route through that area would need to combine the impacts to the built
    and natural environments while maintaining a feasible engineering design.
    Section One began in Chesterfield at the Transco compressor station connector
    point and extended easterly to the Pinelands Area boundary. Section Two
    bordered the western edge of the Pinelands Area and extended eastward to
    NJNG's existing facilities in Manchester Township.
    Baker then employed a detailed siting analysis to determine the different
    alternative routes that would best balance social, environmental, engineering,
    and economic considerations. He also considered siting the SRL within or
    parallel to existing pipeline and utility ROWs, and crossing undeveloped land.
    A-3666-15
    12
    Baker identified five alternative routes for Section One, and four
    alternatives for Section Two. Baker explained the methodology used to generate
    each of the alternative routes:
    The goal of the [a]lternatives [a]nalysis was to
    identify a route that minimizes the impact to the built
    and natural environments to the maximum extent
    practicable, while still maintaining the technical and
    economic viability of the [p]roject. The [a]lternatives
    [a]nalysis was used to determine the most suitable route
    for a 30-inch underground transmission main
    connecting the Transco compressor station in
    Chesterfield Township and transmission system in
    Manchester Township.
    Baker's alternatives analysis considered potential impacts of each
    alternative route from three perspectives:        (1) protection of the built
    environment, which addressed human and cultural resources, including
    residential neighborhoods, other community-valued buildings, and historic sites;
    (2) protection of the natural environment, which addressed plants, animals,
    aquatic resources, ecological resources, and natural habitat; and (3) engineering
    considerations, which addressed maximizing co-location and minimizing cost
    and schedule challenges for the SRL by seeking the shortest path or using
    existing ROWs, while also avoiding areas that posed significant construction
    obstacles.
    A-3666-15
    13
    Baker then evaluated the alternative routes based on quantitative and
    qualitative assessments, and determined the advantages and disadvantages of
    each. Following this analysis, Baker stated that various alternative routes were
    not selected because of "their relative lengths through sections of the Pinelands
    Management areas where such development [was] not considered a permissible
    use." He explained that two of these routes were too close in proximity to the
    highest number of schools and churches.
    Two other proposed alternative routes, one that followed the Jersey
    Central Power and Light ROW (JCP&L ROW) and one that entered and crossed
    through the Joint Base were also not feasible. The JCP&L ROW route passed
    through preserved farmland parcels where pipeline development was prohibited,
    and that route had cumulative environmental impacts higher than any other
    alternative. The route that entered and crossed through the operational areas and
    firing ranges on the Joint Base was not selected because it would present various
    undesirable impacts, such as the dangers inherent in crossing a military range
    and possibly encountering unexploded ordnance.
    Ultimately, Baker and AECOM selected Route B for Section One, and
    Route D for Section Two. Section One, Route B was approximately 16.7 miles,
    and would require the acquisition of approximately 1.1 miles of easements on
    A-3666-15
    14
    private property and would run underneath approximately 15.6 miles of roads.
    Section Two, Route D was approximately 11.7 miles, and would require the
    acquisition of 1.0 mile of private easements outside of the Joint Base, and the
    following easements within the Joint Base: 3.8 miles along the fence line of a
    side road; 3.8 miles under other Joint Base roads; 1.5 miles adjacent to an unused
    runway; and 1.4 miles along the side of other roads or undeveloped areas. 4
    Baker concluded that these two routes would result in the least combined
    impacts to the built environment and natural environment while still offering a
    feasible engineering design and practicable construction.
    John B. Wyckoff, P.E., NJNG's Director of Engineering, testified that the
    SRL pipeline would consist of approximately twenty-eight miles of a new thirty-
    inch diameter, one-half inch wall thickness, transmission line.             Each
    construction site would be approximately one-quarter mile long, and horizontal
    directional drilling would be used to pass under most creeks or streams. Traffic
    control, road closings, detour routes, and the need for night work would be
    coordinated with local officials.
    4
    Baker also cited to a letter from the Joint Base Commander to Assemblyman
    Ronald Dancer on November 6, 2015, which stated that Route D had been
    "developed in close coordination with Air Force engineering, environmental,
    and legal experts and remains the best available on-base route."
    A-3666-15
    15
    Wyckoff further stated that the SRL was expected to provide 180,000
    Dth/day, or more than 25% of NJNG's winter design day capacity. In NJNG's
    responses to discovery requests, it explained that on its "Peak Day" in winter of
    February 2015, "a volume of 180,000 Dth would represent approximately 33%
    of [NJNG's] pipeline supply into Monmouth/Ocean county service territory, and
    32% of total customer demand including LNG production," while during the
    Polar Vortex, "a volume of 180,000 Dth would represent approximately 43% of
    [NJNG's] pipeline supply into Monmouth/Ocean county service territory, and
    31% of total customer demand including LNG production."
    Based upon the evidence presented at the hearing and at the three public
    hearings, the Board rendered a unanimous written decision and order approving
    NJNG's MLUL petition. As to the public's need for the SRL project, the Board
    concluded that NJNG "ha[d] met its burden of proof, and ha[d] shown that the
    Project 'is reasonably necessary for the service, convenience or welfare of the
    public' pursuant to N.J.S.A. 40:55D-19." Reviewing that evidence, the Board
    explained that NJNG's current transmission system unnecessarily left customers
    in its southern territory vulnerable, since those customers in parts of Ocean,
    Burlington, and Monmouth Counties were most defenseless to an interruption
    of supply from TETCO.
    A-3666-15
    16
    The Board found:
    In the event of a disruption in TETCO['s] supply, it is
    evident that NJNG's existing two remaining
    interconnections with Transco, which are also at the
    northern end of NJNG's transmission system servicing
    the Counties, lack the ability to maintain adequate
    pressure at the southern end of the system. These two
    Transco interconnections have an approximate capacity
    of 76,500 and 124,500 Dth/day and are [sic] their
    expansion is limited by the existing Transco
    transportation capacity available.       NJNG's LNG
    facilities can also be utilized to help maintain system
    pressures.     However, the LNG facilities have a
    maximum send-out of 170,000 Dth/day. At maximum
    send-out with a full tank, current LNG supplies will last
    approximately seven (7) to ten (10) days.
    Any supply disruption that outstrips the capacity of the
    existing Transco interconnection and LNG's ability to
    maintain adequate system pressure will result in the
    loss of service to customers in the southern portion of
    the [c]ompany's service territory. Should this happen,
    NJNG would need to isolate portions of the distribution
    system by shutting line valves and go house-to-house
    in the isolated areas to shut valves at each meter. The
    extent of the areas isolated depends on the extent of the
    supply interruption. Once supply issues are resolved,
    the isolated sections would need to be reenergized and
    each individual customer would need to be turned back
    on and their appliances re-lit.
    Thus, the Board concluded that NJNG's current interconnection with TETCO's
    Texas Eastern Transmission Pipeline, which was located at the northern end of
    NJNG's transmission system servicing the counties, equated to "a single point
    A-3666-15
    17
    of failure," and that the SRL's design and the fact that it would provide an
    alternate interstate supply source to the southern portion of NJNG's transmission
    system would mitigate the potential impact of this failure point.
    The Board further found that NJNG had considered alternatives to its SRL
    project, but had correctly rejected them because they did not meet the three
    criteria required for NJNG to reinforce its current transmission system: (1)
    "there must be an independent gate station capable of delivering large volu mes
    of gas"; (2) this gate station "must support the southern end of NJNG's
    transmission system"; and (3) "it must not provide supply from TETCO."
    The Board also rejected McGee's testimony on behalf of the Rate Counsel
    that the full capacity of a thirty-inch pipeline was not necessary for redundancy
    purposes. Relying on Lynch's testimony, the Board agreed that the 180,000
    Dth/day contract was not an appropriate tool to determine the correct size of the
    pipe for the project.
    The Board further concluded that the SRL project would serve the goals
    of the State’s 2011 Energy Master Plan (EMP) because the pipeline would "add
    a significant, diverse source of natural gas, while also increasing overall system
    reliability and reinforcement in NJNG’s service area." The Board explained:
    The EMP was released in 2011 and sets forth the
    strategic vision for the use, management and
    A-3666-15
    18
    development of energy in New Jersey, with the
    overarching goal of saving money while stimulating the
    economy and protecting the environment. One of the
    five (5) major goals of the EMP is to expand in-state
    electricity resources by promoting the "expansion of
    the existing [natural gas] pipeline network that serves
    gas utilities and power plants throughout New Jersey."
    An [u]pdate to the EMP ("EMP Update") was released
    in 2015. The EMP Update recommended no changes to
    the goals stated in the 2011 EMP and further
    recommended the continued advocacy "for enhanced
    intrastate [pipeline] capacity at local levels." The
    actions, decisions, determinations and rulings of State
    government entities with respect to energy "shall to the
    maximum extent practicable and reasonable and
    feasible conform" with the provisions of the EMP.
    N.J.S.A. 52:27F-15(b). In implementing its regulatory
    powers and its responsibilities, the Board considers the
    directives of the EMP.
    Thus, pursuant to N.J.S.A. 40:55D-19, the Board concluded that NJNG
    had "demonstrated the need to address its risk of a supply interruption to its gas
    transmission system." The Board explained that "the pipeline was selected to
    provide appropriate flows, in the case of curtailments in excess of 180,000
    Dth/day," and that the "SRL will provide a significant, diverse feed to NJNG's
    transmission system and support the integrity of such, while minimizing the risk
    of an interstate supply interruption."
    The Board next found that the evidence supported NJNG's review and
    analysis of the alternative intrastate routes for its project, and that its chosen
    A-3666-15
    19
    route for the SRL "[was] the most appropriate, primarily because NJNG and
    AECOM have demonstrated that its alignment minimizes the overall potential
    impacts to the environment and the community."           The Board, therefore,
    concluded there was "no reasonable practicable alternative which would have
    less adverse impact upon the environment or upon the land use and zoning
    ordinances of the respective counties and municipalities."
    The Board rejected the objectors' claims that there were more feasible
    alternatives for routing the SRL than NJNG's preferred route, such as routes that
    traversed through the Joint Base or followed the JCP&L ROW. With respect to
    the Joint Base, the Board found the evidence supported NJNG's assertion that
    this alternative "would present undesirable operational impacts" since crossing
    a military range complex and other operational areas would result in the
    possibility of encountering unexploded ordnance. The Board also noted that the
    Base Commander concurred that NJNG’s proposed route was "developed in
    close coordination with Air Force engineering, environmental, and legal experts
    and remains the best available on-base route."
    Rejecting the JCP&L ROW route, the Board found the evidence supported
    NJNG's assertion that this alternative would require the pipeline to cross
    preserved farmland, which was prohibited by the New Jersey Farmland
    A-3666-15
    20
    Preservation Program, known as the Agriculture Retention and Development
    Act (ARDA). N.J.S.A. 4:1C-11 to -48, and the State Agricultural Development
    Committee (SADC) regulations, N.J.A.C. 2:76-1.1 to -27.10. The Board also
    explained that this alternate route posed great environmental risks:
    [T]he utilization of the JCP&L ROW would require
    extensive clearing and cross environmentally sensitive
    areas containing extensive wetlands as well as
    threatened and endangered species, resulting in a higher
    overall impact to the interests being balanced in the
    alternatives analysis. As reflected in the [a]lternatives
    [a]nalysis, AECOM found that Route D crossed the
    most streams, most wetlands, most floodplains and the
    most landscape-identified threatened and endangered
    ("T&E") species habitat areas. Route D was also
    assigned the highest special permit value (five (5))
    because this alignment would cross the most streams,
    most wetlands, most floodplains and the most
    landscape-identified T&E species habitat areas.
    Therefore, the Board concluded that the route involving the utilization of
    the JCP&L ROW not only had the greatest environmental concerns, but also
    required NJNG to cross preserved farmland in contravention of state law.
    Accordingly, the Board found that a proposed route other than the one NJNG
    selected was "not feasible."
    The Board further found that the cost estimates reflected in the record for
    the SRL project ranged from approximately $150 million to $180 million.
    However, in determining whether the SRL project was "reasonably necessary
    A-3666-15
    21
    for the service, convenience or welfare of the public" under N.J.S.A. 40:55D -
    19, the Board also considered "the cost that New Jersey electricity customers
    [would] bear in connection with the Project."
    Consequently, the Board examined NJNG's review of alternative project
    proposals, that is, ones that extended interstate pipelines from multiple interstate
    suppliers through New Jersey to NJNG's service territory. According to NJNG's
    review, construction of an interstate pipeline extension to its service territory
    would cost approximately $10 million per mile. Based on this cost and the
    estimated rates of return authorized by the Federal Energy Regulatory
    Commission, NJNG found, and the Board agreed, that it would be more costly
    to pursue an interstate pipeline extension. "Since the Project is thirty (30) miles
    long, the costs of an interstate pipeline would be approximately $300 million,
    compared with the current intrastate pipeline estimate of $150-180 million."
    But the Board determined from the evidence that a number of other factors
    could influence and add to NJNG's proposed cost of an intrastate pipeline, such
    as overall length, road restoration, easement acquisition, site clearing,
    environmental mitigation, site access, and requirements to cross wetlands and
    streams. Thus, the Board found that, at the very least, the cost of a pipeline
    A-3666-15
    22
    alignment following the various alternative routes evaluated in NJNG's analysis
    could be considered comparable.
    Nevertheless, the Board took a further step in its analysis based on the fact
    that the SRL was reasonably necessary since a single interstate supply from
    TETCO currently provided the majority of gas for NJNG's territory in question.
    That is, from the evidence presented, the Board reasoned:
    If the [c]ompany experiences a loss of this TETCO
    supply, this would ultimately result in interruptions to
    approximately 350,000 to 400,000 customers during
    peak send-out periods in winter. Restoration of service
    to these customers would take a minimum of four (4)
    months and result in direct expenses to the company
    ranging from approximately $170 to $190 million, not
    including losses related to the loss of social services or
    economic activity.
    Thus, the Board found: (1) "the cost of building an intrastate pipeline,
    owned and operated by NJNG and supplied by Transco, [was] reasonable as
    compared to the alternative of building a pipeline owned and operated by an
    interstate supplier"; (2) there was "sufficient evidence in the record to conclude
    that the estimated cost of the line [was] reasonable to prevent the loss of service
    to NJNG customers and as compared to intrastate and interstate route
    alternatives"; and (3) the SRL project was "reasonably necessary for the service,
    convenience or welfare of the public" pursuant to N.J.S.A. 40:55D-19. Further,
    A-3666-15
    23
    because this matter was not a rate proceeding, the Board stated it did not have
    to "determine the recoverability of the cost of this Project, including the
    incremental cost difference between a twenty-four (24) and thirty (30) inch
    pipeline."
    In sum, the Board determined in accordance with N.J.S.A. 40:55D-19 that:
    (1) the SRL project was "reasonably necessary for the service, convenience, or
    welfare of the public" to enable NJNG to continue to provide safe, adequate, and
    reliable service to its customers; (2) NJNG should be able to construct and begin
    operation of the pipeline as proposed; and (3) the local land use and zoning
    ordinances, and any other ordinance, rule or regulation promulgated under the
    auspices of the MLUL would not apply to the construction, installation, and
    operation of the project.
    Accordingly, the Board ordered that "neither N.J.S.A. 40:55D-1 et seq.,
    nor any other government ordinances or regulations, permits or license
    requirements made under the authority of N.J.S.A. 40:55D-1 et seq. shall apply
    to the siting, installation, construction, or operation of the [p]roject." The Board
    expressly made its order "subject to the approval of any pending road opening
    permits from the affected municipalities and the New Jersey Department of
    Transportation, all other pending permits and approvals, if any, and the pressure
    A-3666-15
    24
    testing requirements of N.J.A.C. 14:7-1.14 prior to placing the Pipeline in
    operation." (emphasis added).
    These appeals followed.
    II.
    PPA argues that the SRL project violates the Pinelands Protection Act
    (Pinelands Act), N.J.S.A. 13:18A-1 to -29, the Pinelands Comprehensive
    Management Plan (CMP), and local municipal Pinelands ordinances. It also
    claims that the Pinelands Commission's (Commission's) Certificate of Filing
    (COF) did not constitute a proper review of the merits of the project through the
    Pinelands.
    In addition, PPA asserts that the SRL project is not "associated with the
    function" of the Joint Base "as required by the CMP." PPA further asserts that
    the Board should have concluded that the project violated the remediation
    process of natural restoration previously approved by the United States
    Environmental Protection Agency (USEPA) and other environmental standards
    established by the New Jersey Department of Environmental Protection
    (NJDEP). These contentions all lack merit because none of these issues were
    before the Board in this MLUL petition matter and, therefore, could only be
    considered by the agencies having jurisdiction over them.
    A-3666-15
    25
    "Generally speaking, the [Board]'s power to regulate utilities is broad." In
    re Centex Homes, LLC, 
    411 N.J. Super. 244
    , 254 (App. Div. 2009). The
    Legislature vested the Board with the "general supervision and regulation of and
    jurisdiction and control over, all public utilities . . . and their property, property
    rights, equipment, facilities and franchises so far as may be necessary for the
    purpose of carrying out the provisions of [Title 48]." N.J.S.A. 48:2-13(a).
    N.J.S.A. 48:2-23 empowers the Board to ensure that regulated public utilities
    provide safe, adequate and proper service to the citizens of New Jersey. In re
    Public Service Electric & Gas Co. (PSE&G), 
    35 N.J. 358
    , 371 (1961). N.J.S.A.
    48:2-19 states that the Board may "[i]nvestigate, upon its own initiative or upon
    complaint in writing any matter concerning any public utility."                Those
    provisions must be construed liberally. Twp. of Deptford v. Woodbury Terrace
    Sewerage Corp., 
    54 N.J. 418
    , 424 (1969); PSE&G, 
    35 N.J. at 371
    .
    The specific standard applied by the Board when considering a petition
    filed by a utility company is reflected in N.J.S.A. 40:55D-19, which states in
    part:
    This act [(the MLUL)] or any ordinance or
    regulation made under authority thereof, shall not apply
    to a development proposed by a public utility for
    installation in more than one municipality for the
    furnishing of service, if upon a petition of the public
    utility, the Board of Public Utilities shall after hearing,
    A-3666-15
    26
    of which any municipalities affected shall have notice,
    decide the proposed installation of the development in
    question is reasonably necessary for the service,
    convenience or welfare of the public.
    Nothing in this act shall be construed to restrict
    the right of any interested party to obtain a review of
    the action of the municipal agency or of the Board of
    Public Utilities by any court of competent jurisdiction
    according to law.
    [(emphasis added).]
    N.J.S.A. 48:9-25.4 further permits the Board to designate "a practicable
    route" for a public utility transmitting natural gas service if the local
    municipality fails or refuses to make such a designation or designates an
    impracticable route. That statute provides:
    Any gas company organized under the laws of
    this State in addition to but not in limitation of the
    powers conferred by the laws under which it was
    organized may construct, lay, maintain and use
    facilities, conductors, mains and pipes, with the
    appurtenances thereto, in, through and beyond any
    municipality or municipalities, for the purpose of
    transmitting through the same natural gas or any
    mixture of gas or gases of any other type or types for
    use in its business; provided, that in each case such
    corporation shall first have obtained a designation by
    the governing body or official having control thereof,
    of the public street, road, highway or place, which may
    be occupied by such corporation for such purpose. If
    any governing body or official having control of any
    public street, road, highway or place, after having
    received from such corporation a request to designate
    A-3666-15
    27
    such public street, road, highway or place, for
    occupancy by such corporation for such purpose, shall
    fail or refuse to make such designation or to designate
    a practicable route, the Board of Public Utility
    Commissioners, upon application by the corporation,
    and after hearing on notice to such governing body or
    official, shall make such designation.
    [N.J.S.A. 48:9-25.4 (emphasis added).]
    These two statutes do not invalidate the specific laws governing the
    Pinelands, wetlands, or Superfund sites. An agency cannot issue or deny a
    permit "absent satisfaction of the applicable statutory criteria."         In re
    Authorization for Freshwater Wetlands Gen. Permits, 
    372 N.J. Super. 578
    , 596
    n.8 (App. Div. 2004).
    However, "[w]hile the [Board] was 'intended by the Legislature to have
    the widest range of regulatory power over public utilities,' that power has never
    been cast in environmental terms." Centex Homes, 
    411 N.J. Super. at 265-66
    (citation omitted). The language of N.J.S.A. 48:2-23 does not give the Board
    power to decide a public utility's compliance with environmental or land use
    requirements, or give those issues "overriding consideration" in its decision to
    extend service. 
    Id. at 264
    .
    Thus, the Board had no statutory authority to review NJNG's proposed
    construction for compliance with the Pinelands Act, the CMP Rules, the
    A-3666-15
    28
    USEPA's or NJDEP's decisions or orders, or with any other environmental
    statutory scheme. Indeed, as we recently held in another case involving the
    approval of a natural gas pipeline, only the Commission has the expertise and
    exclusive legislative authority to decide whether a pipeline project compli es
    with the Pinelands Act and CMP Rules in the coordinated permitting process.
    In re Petition of S. Jersey Gas Co. (SJG), 
    447 N.J. Super. 459
    , 482 (App. Div.
    2016).
    In SJG, this court addressed the Board's grant of a petition under N.J.S.A.
    40:55D-19 for South Jersey Gas's proposed construction of a similar natural gas
    pipeline within the Pinelands. 
    Id. at 471-72
    . We noted that a provision of the
    Pinelands Act, N.J.S.A. 13:18A-10(c), stated that "no State . . . permit . . . for
    the construction of any structure or the disturbance of any land within [the
    Pinelands] shall be granted unless such approval or grant conforms to the
    provisions of [the CMP]." 
    Id. at 478
    . (alteration in original). However, we made
    clear that the decision as to whether the project conformed to the CMP had to
    be made by the full Commission and not by the Board. We stated:
    [I]n deciding whether to grant a petition brought under
    N.J.S.A. 40:55D-19, the Board determines whether the
    MLUL and local regulations adopted pursuant to the
    MLUL should be waived. The Board's approval of any
    MLUL petition must be consistent with the minimum
    A-3666-15
    29
    standards of the CMP, but the Board is not empowered
    to make that determination in the first instance. In this
    matter, that decision must be made by the Commission,
    pursuant to its authority under the Pinelands Act and
    the CMP.
    [Ibid. (emphasis added).]
    Therefore, we reject PPA's argument that the Board's decision was
    arbitrary or unreasonable because the Board did not make determinations on
    environmental issues that were within the jurisdiction of the Commission and
    other State and federal agencies.
    PPA also argues that the COF prepared by the Commission's Executive
    Director was insufficient to demonstrate that the SRL project met the standards
    of the CMP. In SJG, this court held that only the full Commission could make
    this determination and, because it did not, we remanded the matter to the
    Commission so that it could review the Executive Director's action. 
    Id.
     at 478-
    79. PPA suggests that a similar remand is warranted here. We disagree.
    First, the Board specifically stated in its final decision that its approval of
    NJNG's petition was "subject to . . . all other pending permits and approvals."
    This language sufficiently accounts for the need for prior approval by the
    Commission. Moreover, our Supreme Court has emphasized the importance of
    "comity and deference to sibling agencies" where the government oversees
    A-3666-15
    30
    "complex and manifold activities that are also the appropriate statutory concern
    of other governmental bodies." Hinfey v. Matawan Reg'l Bd. of Educ., 
    77 N.J. 514
    , 531 (1978). Thus, there is no merit to PPA's contention that the Board
    waived compliance with the Pinelands Act and the CMP Rules, or with the
    USEPA's orders or NJDEP's requirements by stating that its approval of the
    MLUL petition was subject to action by its sibling agencies on other pending
    permit applications.
    Perhaps more importantly, the Commission adopted a resolution on
    September 14, 2017 approving NJNG's application to construct the pipeline in
    the Pinelands.5 Therefore, NJNG has satisfied the requirements for Commission
    approval set forth in N.J.S.A. 13:18A-10(c) and no remand is necessary.
    III.
    In a related issue, SC argues that the Board lacked the authority under
    N.J.S.A. 40:55D-19 to waive compliance with Pinelands protection ordinances
    adopted by municipalities allegedly under the authority of the Pinelands Act
    rather than the MLUL.     Because we considered and rejected this identical
    5
    PPA and SC have filed separate appeals challenging the Commission's
    approval of this application. Docket Nos. A-925-17 and A-1004-17. In an
    opinion also filed on this date, we affirm the Commission's approval of the
    application.
    A-3666-15
    31
    argument by SC in SJG, we discern no basis for reaching a different conclusion
    here.
    In SJG, SC argued
    that the Board's decision waiving municipal approvals
    was wrong as a matter of law. [SC] contends that
    N.J.S.A. 40:55D-19 does not apply to Pinelands-based
    reviews and ordinances, and that the Board had no
    authority to override any local approval that is
    otherwise required by the Pinelands Act and any
    ordinances authorized and adopted under that Act.
    [447 N.J. Super. at 483.]
    In explaining why we were "not persuaded by this argument[,]" we stated:
    By its plain language, N.J.S.A. 40:55D-19 gives the
    Board the authority to waive the MLUL and any local
    ordinance or regulation adopted pursuant to the MLUL.
    The Board's authority under N.J.S.A. 40:55D-19
    necessarily includes the power to waive any MLUL
    review of approvals by municipalities in the Pinelands.
    The Pinelands Act does not limit the exercise of this
    power. However, as the Board recognized in its final
    decision, any development project for which local
    MLUL regulation is waived pursuant to N.J.S.A.
    40:55D-19 remains subject to the Pinelands Act and the
    minimum standards of the CMP.
    [Ibid.]
    Thus, the Board clearly had the authority to waive compliance with the
    MLUL and any local ordinance or regulation adopted pursuant to the MLUL
    A-3666-15
    32
    whether or not those ordinances were enacted by municipalities in the Pinelands
    Preservation Area.
    SC contends that some of the municipal ordinances involved in this case
    were enacted pursuant to authority granted to the municipalities by the Pinelands
    Act rather than by the MLUL. However, SC does not identify any ordinances
    that meet this description. SC also argues that municipal ordinances adopted
    pursuant to the MLUL which impose standards that exceed those established
    under the Pinelands Act or the CMP should not be waivable under N.J.S.A.
    40:55D-19. However, as we squarely held in SJG, "[t]he Board's authority under
    N.J.S.A. 40:55D-19 necessarily includes the power to waive any MLUL review
    of approvals by municipalities in the Pinelands."      Ibid. (emphasis added).
    Therefore, we reject SC's contention on this point.
    IV.
    As noted above, the Board granted PPA the opportunity to participate in
    the MLUL petition proceeding by filing a post-hearing brief and presenting oral
    argument.   However, when PPA submitted its brief, it attached seventeen
    exhibits that had not been presented at either the evidentiary hearing or the
    public hearings. These exhibits included documents that had been filed with the
    Commission concerning the pipeline, several emails, the transcript of an October
    A-3666-15
    33
    2013 analyst meeting hosted by NJNG's parent, New Jersey Resources, a
    memorandum criticizing NJNG's proposal prepared by a consultant "in the
    mergers and acquisition arena with numerous clients within the energy
    industry," and various environmental studies and economic analyses of the Joint
    Base and of New Jersey Superfund Sites from 1999 to 2014. In presenting these
    exhibits, PPA failed to submit an affidavit or certification authenticating the
    documents or verifying the facts contained in them.
    As a result, the Board declined to consider the seventeen exhibits as
    evidence.   The Board explained that although N.J.A.C. 1:1-15.2 allows an
    agency to take official notice of its own documents and the existence of
    documents issued by a sister agency, the exhibits that PPA offered with its brief
    had no accompanying formal certifications and were never subject to a review
    process by the Board or by the other parties. Thus, the Board concluded that
    PPA was "attempting to import new evidence into the record, when the authoring
    witnesses ha[d] not been qualified to testify nor been subject to cross-
    examination." Nevertheless, the Board advised PPA that it would consider its
    new submissions as public comments rather than as evidence.
    PPA now argues that the Board erred by failing to consider the documents
    as evidence. Again, we disagree.
    A-3666-15
    34
    PPA was not a party to the MLUL petition proceeding and, as a
    participant, it only had the right to file a brief and present oral argument.
    N.J.A.C. 1:1-16.6(c). Thus, PPA did not have the right to submit evidence
    during the evidentiary hearing or in a post-hearing brief.
    Moreover, PPA improperly attached the exhibits to its brief without
    providing the required affidavit or certification authenticating the exhibits or
    attesting to the accuracy of the facts contained in the documents. As we stated
    almost thirty-five years ago,
    [t]he function of [a] brief is a written presentation of
    legal argument. Facts intended to be relied on which
    do not already appear of record and which are not
    judicially noticeable are required to be submitted to the
    [trier of fact] by way of affidavit or testimony. See R.
    1:6-6 . . . . These are not merely formal requirements.
    They go to the heart of procedural due process.
    [Celino v. Gen. Accident Ins., 
    211 N.J. Super. 538
    , 544
    (App. Div. 1986).]
    As noted, the Board stated it would consider PPA's submissions as public
    comment along with all of the other non-evidentiary public comments it received
    from other participants.    Under these circumstances, there is no basis for
    disturbing the Board's decision on this issue.
    V.
    A-3666-15
    35
    In the remaining points of their briefs, PPA and SC argue that the Board's
    decision to grant NJNG's MLUL petition was arbitrary and capricious because
    the pipeline was not necessary to solve the "single point of failure" catastrophic
    scenario, which they assert could be better addressed with alternative routes that
    would avoid the Pinelands. They also allege that NJNG intends to use the SRL
    to maximize its profits rather than the reliability of its natural gas delivery
    system. These arguments lack merit.
    Our scope of review of an administrative agency's decision is limited. In
    re Carter, 
    191 N.J. 474
    , 482 (2007). "An appellate court may reverse an agency
    decision if it is arbitrary, capricious, or unreasonable." In re Proposed Quest
    Acad. Charter Sch. of Montclair Founders Grp., 
    216 N.J. 370
    , 385 (2013). As
    the Supreme Court has explained:
    Although sometimes phrased in terms of a search for
    arbitrary or unreasonable agency action, the judicial
    role [in reviewing an agency action] is generally
    restricted to three inquiries: (1) whether the agency's
    action violates express or implied legislative policies,
    that is, did the agency follow the law; (2) whether the
    record contains substantial evidence to support the
    findings on which the agency based its action; and
    (3) whether in applying the legislative policies to the
    facts, the agency clearly erred in reaching a conclusion
    that could not reasonably have been made on a showing
    of the relevant factors.
    A-3666-15
    36
    [Id. at 385-86 (quoting Mazza v. Bd. of Trs., 
    143 N.J. 22
    , 25 (1995)).]
    Our review of Board decisions is further limited by N.J.S.A. 48:2-46,
    which states in pertinent part that the Appellate Division has "jurisdiction to
    review any order of the [B]oard [of Public Utilities] and to set aside such order
    in whole or in part when it clearly appears that there was no evidence before the
    board to support the same reasonably . . . ." (emphasis added). This statute
    follows the general principle that our courts will not reverse an agency decision
    just "'because of doubts as to its wisdom or because the record may support more
    than one result,' but [are] 'obliged to give due deference to the view of those
    charged with the responsibility of implementing legislative programs.'" In re
    Adoption of Amendments to N.E., Upper Raritan, Sussex Cnty. & Upper Del.
    Water Quality Mgmt. Plans, 
    435 N.J. Super. 571
    , 583-84 (App. Div. 2014)
    (alteration in original) (quoting In re N.J. Pinelands Comm'n Resol. PC4-00-89,
    
    356 N.J. Super. 363
    , 372 (App. Div. 2003)).
    A reviewing court "will not weigh the evidence, determine the credibility
    of witnesses, draw inferences and conclusions from the evidence, or resolve
    conflicts therein." De Vitis v. N.J. Racing Comm'n, 
    202 N.J. Super. 484
    , 489-
    90 (App. Div. 1985). "[W]here there is substantial evidence in the record to
    support more than one regulatory conclusion, it is the agency's choice which
    A-3666-15
    37
    governs." Adoption of Amendments, 435 N.J. Super. at 583 (quoting Murray v.
    State Health Benefits Comm'n, 
    337 N.J. Super. 435
    , 442 (App. Div. 2001)
    (citation and internal quotation marks omitted)).
    "[J]udicial deference to administrative agencies stems from the
    recognition that agencies have the specialized expertise necessary to . . . deal[]
    with technical matters that are 'particularly well equipped to read and understand
    the massive documents and to evaluate the factual and technical issues. . . .'"
    
    Ibid.
     (quoting N.J. State League of Muns. v. Dep't of Cmty. Affs., 
    158 N.J. 211
    ,
    222 (1999)) (alteration in original). The burden of demonstrating that the
    agency's action is reversible "rests upon the [party] challenging the
    administrative action." 
    Ibid.
     (alteration in original).
    Applying these well-established principles, we discern no basis for
    disturbing the Board's decision to grant NJNG's MLUL petition because it was
    reasonably necessary for the service, convenience, or welfare of the public and
    there was "no reasonable practicable alternative which would have less adverse
    impact upon the environment or upon the land use and zoning ordinances of the
    respective counties and municipalities."        We therefore reject appellants'
    arguments on this point substantially for the reasons set forth by the Board in its
    comprehensive opinion and add the following comments.
    A-3666-15
    38
    In order to be successful on its petition for an exemption from all MLUL
    provisions and all local regulations and ordinances made pursuant to the
    MLUL's authority, NJNG had to demonstrate that its SRL project was
    "reasonably necessary for the service, convenience or welfare of the public,"
    N.J.S.A. 40:55D-19, and that the route designated was "practicable," N.J.S.A.
    48:9-25.4.
    Construing the language in N.J.S.A. 40:55-50, the predecessor to N.J.S.A.
    40:55D-19, the Supreme Court stated:
    1. The statutory phrase, "for the service,
    convenience and welfare of the public" refers to the
    whole "public" served by the utility and not the limited
    local group benefited by the zoning ordinance.
    2. The utility must show that the proposed use is
    reasonably, not absolutely or indispensably, necessary
    for public service, convenience and welfare at some
    location.
    3. It is the "situation", i.e., the particular site or
    location . . . which must be found "reasonably
    necessary," so the Board must consider the community
    zone plan and zoning ordinance, as well as the physical
    characteristics of the plot involved and the surrounding
    neighborhood, and the effect of the proposed use
    thereon.
    4. Alternative sites or methods and their
    comparative advantages and disadvantages to all
    interests involved, including cost, must be considered
    in determining such reasonable necessity.
    A-3666-15
    39
    5. The Board's obligation is to weigh all interests
    and factors in the light of the entire factual picture and
    adjudicate the existence or non-existence of reasonable
    necessity therefrom. If the balance is equal, the utility
    is entitled to the preference, because the legislative
    intent is clear that the broad public interest to be served
    is greater than local considerations.
    [PSE&G, 
    35 N.J. at
    376-77 (citing In re Application of
    Hackensack Water Co., 
    41 N.J. Super. 408
    , 425 (App.
    Div. 1956)).]
    The Court explained:
    This exemption section expresses a legislative intent
    that, in the zoning field, at least some power over a
    utility is reserved to a municipality, subject to the
    supervising authority of the Board to declare the local
    regulation inapplicable if it determines "the situation of
    the building or structure in question is reasonably
    necessary for the service, convenience or welfare of the
    public."
    [Id. at 373-74.]
    In New Jersey Nat. Gas Co. v. Borough of Red Bank, 
    438 N.J. Super. 164
    ,
    184 (App. Div. 2014), we observed that "[i]t is evident that the Legislature's
    enactment of N.J.S.A. 40:55D-19 actually increased control over a public
    utility's use of land within a municipality's borders."       These requirements
    reinforce the Court's recognition that the regulation of public utilities requires a
    regional approach. Overlook Terrace Mgmt. Corp. v. Rent Control Bd. of Town
    A-3666-15
    40
    of W. N.Y., 
    71 N.J. 451
    , 474 (1976); S. Ocean Landfill, Inc. v. Mayor & Council
    of Twp. of Ocean, 
    64 N.J. 190
    , 195 (1974).           Viewed through this prism,
    appellants' arguments opposing the Board's grant of the MLUL petition must be
    rejected.
    PPA and SC first contend that NJNG did not demonstrate a need for a
    redundant pipeline system because it has never sustained a catastrophic system
    or supply power failure and could not quantify the likelihood of such an event
    occurring in the future. Appellants also criticize NJNG because it relied upon
    Lynch's testimony, rather than that of an independent expert, to show the need
    for a redundant transmission line. We disagree.
    To support a MLUL petition under N.J.S.A. 40:55D-19, an applicant has
    the burden of showing that "the proposed use is reasonably, not absolutely or
    indispensably, necessary for public service, convenience and welfare at some
    location." PSE&G, 
    35 N.J. at 376-77
    . The term "public" is expansive, i.e.,
    regional, and does not mean only the local citizenry. 
    Id. at 376
    . Further, the
    Board must weigh all of the interests and factors to adjudicate the existence or
    non-existence of reasonable necessity. 
    Id. at 377
    .
    Lynch, who had over thirty years of experience designing and operating
    NJNG's system, stated that it would be "irresponsible" planning for NJNG to
    A-3666-15
    41
    wait for a catastrophic event resulting in widespread loss of service before taking
    steps to avoid or mitigate such an event. It was especially ill-advised to wait
    since NJNG relied on a single interstate feed for nearly all of its gas supply to
    its customers in the Central and Ocean Divisions.
    Lynch also established that there had already been two service
    interruptions in TETCO's interstate delivery system:               the Entriken/
    Chambersburg compressor station failures in January 2015, and the Delmont
    compressor station failure during a 2014 polar vortex. Superstorm Sandy also
    contributed to Lynch's conclusion that gas-feed redundancy was necessary to
    avoid potentially devastating effects of a wide-scale supply interruption. Lynch
    testified that, with a redundant gas feed in place, NJNG could have significantly
    reduced, or avoided, service interruptions after the storm, since there were
    significant portions of NJNG's territory "downstream" from storm-damaged
    areas of the distribution system that were still "viable" and could have remained
    in operation if there had been an available gas supply.        Thus, contrary to
    appellants' assertions, there was ample evidence in the record to support the
    Board's conclusion that there was a need for the project.
    Appellants argue that the Board should have rejected Lynch's reasoning,
    explaining that NJNG, during each of TETCO's supply failures, was able to
    A-3666-15
    42
    continue to provide service without a significant interruption. They also claim
    that Superstorm Sandy does not support the need for the SRL because that storm
    did not damage transmissions systems and did not interrupt the interstate supply.
    However, it was not arbitrary or unreasonable for the Board to find that simply
    because NJNG was able to avoid TETCO's service disruptions, this should
    prevent it from preparing for a more severe disturbance or showing that the SRL
    was "reasonably necessary for the service, convenience or welfare of the public"
    pursuant to N.J.S.A. 40:55D-19. Also, Superstorm Sandy clearly demonstrated
    the impact and cost that an extensive curtailment of service can have on a public
    utility's customers.
    PPA and SC further claim that the SRL is not necessary because NJNG
    had previously undertaken six other infrastructure projects known as NJ RISE.
    However, Lynch testified that the SRL was intended to complement, and not
    replace, NJ RISE. He explained that NJ RISE was "the name of a group of six
    NJNG projects approved by the [Board] in 2014 providing system enhancements
    that improve NJNG's distribution system through storm hardening investments"
    and "was submitted to the BPU in response to its January 23, 2013 Order inviting
    regulated utilities to submit 'detailed proposals for infrastructure upgrades
    designed to protect the State's utility Infrastructure from future Major Storm
    A-3666-15
    43
    Events.'" Because four of those projects were secondary feeds to large single
    feed distribution systems along the coast, the record supports the Board's finding
    that the NJ RISE project did not render the SRL unnecessary.
    Appellants also argue that because NJNG did not conduct an analysis
    related to real-world failure scenarios, it could not quantify their likelihood, and
    thus failed to demonstrate the need for the SRL as a redundant gas feed.
    However, N.J.S.A. 40:55D-19 only requires NJNG to show that the SRL "is
    reasonably necessary for the service, convenience or welfare of the public," not
    that it is likely to experience a major large-scale supply interruption in the near
    future. (emphasis added). The utility need not show that the proposed project
    is "absolutely or indispensably" necessary. PSE&G, 
    35 N.J. at 377
    . Also,
    contrary to PPA's assertion, nothing in NJNG's Distribution Integrity
    Management Plan, the governing statutes, or applicable case law required NJNG
    to seek an independent analysis to demonstrate that there was a likelihood of a
    major supply system interruption to establish the need for the SRL. Therefore,
    the Board appropriately relied upon Lynch's detailed testimony.
    As explained above, we will not reverse an agency decision because of
    doubts as to its wisdom or because the record may support more than one result.
    Adoption of Amendments, 435 N.J. Super. at 583-84. We do not weigh the
    A-3666-15
    44
    evidence, draw inferences and conclusions from the evidence, or resolve
    conflicts therein. De Vitis, 
    202 N.J. Super. at 489-90
    . N.J.S.A. 48:2-46 states
    that the Appellate Division can set aside the Board's order only "when it clearly
    appears that there was no evidence before the board to support the same
    reasonably." In light of these standards, we are satisfied that the Board did not
    err by concluding that the SRL was reasonably necessary as a redundant gas feed
    pursuant to N.J.S.A. 40:55D-19.
    Appellants next argue that NJNG failed to adequately consider alternative
    routes for the proposed pipeline and, therefore, the Board should have denied its
    MLUL petition. Again, we disagree.
    To support a MLUL petition under N.J.S.A. 40:55D-19, an applicant has
    the burden of showing that no alternative route has less impact on the
    environment or on the community. PSE&G, 
    35 N.J. at 368
    . Objectors to the
    petition have the burden of showing the existence of a feasible alternative site.
    Hackensack Water Co., 
    41 N.J. Super. at 425-26
    . Furthermore, under N.J.S.A.
    48:9-25.4, the Board can designate the locations to be used for a pipeline
    transmitting natural gas service if that route is "practicable."
    At the evidentiary hearing, NJNG presented an expert report prepared by
    AECOM and testimony by Baker on alternative routes for the pipeline. The
    A-3666-15
    45
    report examined five alternate routes for the first section of the pipeline and four
    alternate routes for the pipeline's second section. As previously discussed,
    AECOM evaluated these routes using numerous quantitative factors: (1) built
    environment (i.e., historical properties within 150 feet, school churches and
    properties within 150 feet, residences within 150 feet, number of parcels
    crossed, commercial and industrial buildings within 150 feet, and length within
    state, county or agricultural preserved lands); (2) natural environment (i.e., land -
    use/land-cover forests, stream crossings, land-use/land-cover wetlands, flood
    zones and proximity to threatened and endangered species habitat); and
    (3) engineering variables (i.e., miles within existing ROWs, miles paralleling
    existing transmission line ROWs, number of bridge crossings, number of major
    utility crossings, and length of pipeline in acidic soils).
    The report also considered qualitative factors, including: visual concerns;
    community concerns; special permit issues; construction/ maintenance
    accessibility; and schedule delay risks. After weighing the importance of each
    of those factors, AECOM determined that the route NJNG selected for the SRL
    was the most feasible.
    PPA asserts that the methodology AECOM used to compare the various
    alternative routes was intentionally biased so as to make the JCP&L ROW Route
    A-3666-15
    46
    appear more unattractive. The JCP&L ROW Route, however, was included as
    part of one of the original batch of alternatives and, therefore, AECOM had
    already devised its methodology prior to any proposal made by the
    municipalities to use that route. Thus, there was no bias.
    PPA further argues that the Board failed to consider the alternative route
    proposed by the municipalities, Section One, Route D. However, Route D was
    not a feasible or practicable alternative because the pipeline would cross
    preserved farmland and environmentally sensitive lands.
    Under the ARDA, pipeline construction on preserved farmland is
    prohibited.    The ARDA coordinates the development of county farmland
    preservation programs within certain areas where agriculture is presumed the
    first priority land use. N.J.S.A. 4:1C-12(c); Twp. of S. Brunswick v. State
    Agric. Dev. Comm., 
    352 N.J. Super. 361
    , 364-65 (App. Div. 2002). In N.J.S.A.
    4:1C-12, the Legislature found:
    a. The strengthening of the agricultural industry
    and the preservation of farmland are important to the
    present and future economy of the State and the welfare
    of the citizens of the State, and that the Legislature and
    the people have demonstrated recognition of this fact
    through their approval of the "Farmland Preservation
    Bond Act of 1981," . . . ;
    A-3666-15
    47
    b. All State departments and agencies thereof
    should encourage the maintenance of agricultural
    production and a positive agricultural business climate;
    c. It is necessary to authorize the establishment
    of State and county organizations to coordinate the
    development of farmland preservation programs within
    identified areas where agriculture will be presumed the
    first priority use of the land and where certain financial,
    administrative and regulatory benefits will be made
    available to those landowners who choose to
    participate, all as hereinafter provided.
    Landowners may petition the County Agricultural Board and/or the
    municipality for the creation of a farmland preservation program or municipally -
    approved program.      N.J.S.A. 4:1C-20 to -21.       Owners of land within a
    "municipally approved program or other farmland preservation program" may
    enter into an agreement with the County Agricultural Development Board and,
    if necessary, the municipality "to retain the land in agricultural production," as
    part of the sale of a development easement to the county or a non-profit
    organization. N.J.S.A 4:1C-24(a)(1); N.J.S.A. 4:1C-31. That development
    easement runs with the land and is "binding upon the landowner and every
    successor in interest." N.J.S.A. 4:1C-32. Consequently, land preserved for
    agricultural development cannot be used to develop non-agricultural public
    utility infrastructure, nor can a public utility acquire an interest in property,
    A-3666-15
    48
    preserved pursuant to ARDA, for a non-agricultural purpose such as
    constructing a natural gas transmission line.
    Furthermore, a public utility cannot exercise its power of eminent domain
    to acquire an interest in preserved land under N.J.S.A. 4:1C-25, which states:
    The provisions of any law to the contrary
    notwithstanding, no public body shall exercise the
    power of eminent domain for the acquisition of land in
    a municipally approved program or from which a
    development easement has been conveyed pursuant to
    section 17 of P.L.1983, c. 32 (C.4:1C-24), nor shall any
    public body advance a grant, loan, interest subsidy or
    other funds within a municipally approved program, or
    with regard to land from which a development easement
    has been conveyed pursuant to section 17 of P.L.1983,
    c. 32 (C.4:1C-24), for the construction of dwellings,
    commercial facilities, transportation facilities, or water
    or sewer facilities to serve nonfarm structures unless
    the Governor declares that the action is necessary for
    the public health, safety and welfare and that there is no
    immediately apparent feasible alternative. If the
    Governor so declares, the provisions of section 12 of
    P.L.1983, c. 32 (C.4:1C-19) shall apply.
    Moreover, Section One, Route D required the pipeline to cross the most
    streams, wetlands, and lands with threatened and endangered species habitats.
    In his report, Baker assigned Route D a high value with respect to special
    permits because it crossed a considerable length of preserved farmlands
    restricted to agricultural use and environmentally sensitive lands. Thus, the
    Board did not err by concluding that Route D was not feasible.
    A-3666-15
    49
    Therefore, we are satisfied that the evidence supported the Board's
    determination that NJNG met its burden to show that "its proposed routing [was]
    reasonable, and that no alternative route is less intrusive to the environment or
    community."
    Finally, appellants assert that NJNG intends to use the SRL only for
    profitability and not for reliability, which they claim proves that the Board's
    conclusions are arbitrary and capricious because the SRL link is not "necessary
    to maintain reliable . . . natural gas supply service for the general public," or
    "necessary for the service, convenience or welfare of the public." PPA and SC
    further assert that the size of the proposed SRL is larger in capacity than NJNG
    needs to provide any redundant service to its existing customers, which supports
    the company's intent only to grow its business. These contentions lack merit.
    There is nothing in N.J.S.A. 40:55D-19 or in PSE&G, 
    35 N.J. at 376-77
    ,
    that prevents a gas transmission company from making a profit or from
    attracting new customers by installing a new transmission line. As we stated
    previously, NJNG must show only that the SRL link is "reasonably, not
    absolutely or indispensably, necessary for public service, convenience and
    welfare." PSE&G, 
    35 N.J. at 377
    .
    A-3666-15
    50
    Moreover, NJNG offered sufficient evidence justifying its decision to
    install a thirty-inch, rather than a twenty-four-inch, transmission pipeline. First,
    NJNG demonstrated that a thirty-inch diameter line was necessary to meet its
    peak demand by presenting "iterative flow modeling," showing various
    hypothetical demand and supply situations modeled on its current system with
    the SRL in place.
    Second, a thirty-inch diameter pipeline was equal to NJNG's existing
    system connector with TETCO's interstate pipeline in Middlesex County and
    other recently installed segments.     Third, NJNG showed that a thirty-inch
    diameter pipeline would allow greater capacity from new interstate suppliers in
    the future. Based on this evidence, it was certainly within the Board's discretion
    and expertise in reviewing the construction and development of natural gas
    transmission lines to find, contrary to appellants' claims, that a 180,000 Dth/day
    contract was not an appropriate tool to determine the correct size of the pipe for
    the project. Thus, the Board did not err by finding that the proposed thirty -inch
    SRL was reasonably necessary as a redundant gas feed pursuant to N.J.S.A.
    40:55D-19.
    The Division of Rate Counsel argues that because a smaller diameter line
    would be sufficient to transport the amount of gas set forth in the NJNG contract,
    A-3666-15
    51
    only the cost of a twenty-four-inch line should be borne by ratepayers. However,
    as Rate Counsel concedes in its brief, "this matter is not a base rate proceeding"
    and, therefore, there is no need to address this contention further here.
    VI.
    All other arguments raised in this appeal, to the extent we have not
    addressed them, are without sufficient merit to be discussed. R. 2:11-3(e)(1)(E).
    VII.
    In sum, we affirm the Board's March 18, 2016 decision and order granting
    NJNG's MLUL petition.        The Board's decision is supported by sufficient
    credible evidence in the record and is neither arbitrary, capricious, nor
    unreasonable.
    Affirmed.
    A-3666-15
    52