HAUL ROAD HOLDINGS, INC. VS. TOWNSHIP OF WAYNE (L-1866-13, PASSAIC COUNTY AND STATEWIDE) ( 2018 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2659-15T4
    HAUL ROAD HOLDINGS, INC.,
    and POLYMERIC RESOURCES
    CORP.,
    Plaintiffs-Appellants,
    v.
    TOWNSHIP OF WAYNE,
    Defendant-Respondent.
    ____________________________
    Argued telephonically October             18,   2017    –
    Decided August 13, 2018
    Before Judges Simonelli and Gooden Brown.
    On appeal from Superior Court of New Jersey,
    Law Division, Passaic County, Docket No.
    L-1866-13.
    Norman I. Klein argued the cause for
    appellants (Carlet, Garrison, Klein & Zaretsky,
    LLP, attorneys; Norman I. Klein and Virginia
    T. Shea, on the briefs).
    Matthew J. Giacobbe, Township Attorney, argued
    the cause for respondent (Matthew J. Giacobbe,
    attorney; Lisa M. Scorsolini, Assistant
    Township Attorney, on the brief).
    PER CURIAM
    Plaintiffs Polymeric Resources Corp. (PRC) and Haul Road
    Holdings, Inc. (HRH) sued defendant Township of Wayne (Township),
    alleging that from 1996 to 2013, the Township overcharged them for
    water and sewer usage fees.                  Plaintiffs sought recovery of the
    overcharges.            Following a two-day bench trial, the trial court
    entered judgment in favor of the Township.                  Plaintiffs now appeal
    that judgment entered on November 16, 2015, and the January 19,
    2016 order denying their motion for reconsideration.                     We affirm.
    We glean the following facts from the bench trial conducted
    on July 27, and 29, 2015, during which two witnesses testified for
    plaintiffs, Sol Schlesinger,1 PRC's president, and Arthur Quint,
    PRC's Vice President and Chief Financial Officer.                      Heather Vitz-
    Del Rio, the Township's Director of Public Works and Superintendent
    of Water and Sewer for the Township since 2002, testified for the
    Township.
    PRC,      a    compounder     of    thermal     plastics,     rented   property
    located   at       55    Haul   Road    in   Wayne   from   HRH,   a   wholly   owned
    subsidiary of PRC.          The property included a well approximately 500
    feet deep, a sump pit into which water from the well was pumped
    and flowed through a pipe connecting the well and the sump pit,
    1
    Sol Schlesinger alternately appears as Saul Slessinger in the
    record.
    2                              A-2659-15T4
    machinery to process the materials, twenty-five to fifty feet vats
    with heated water2 to melt the thermal plastics, warehouse space,
    a   shipping   and   receiving   area,   and   administrative   offices.
    According to Schlesinger, the company employed about fifty people
    during the day and twenty people during the night shift.
    Generally, to operate, PRC used water from its well for
    production and water supplied by the Township for domestic use.
    PRC also utilized the Township's sewer system for any water
    discharged back into the sewer system.           Pursuant to Township
    Ordinance No. 17-2006, the Township based water service charges
    on gallons consumed, which rates increased every year from 2006
    through 2010, after which they remained the same throughout the
    time period in question.    Under the Ordinance, the Township billed
    customers for the first 12,000 gallons of water supplied at a flat
    fee based on the size of the meter.      The water rates then increased
    according to three tiers of use in excess of 12,000 gallons as
    follows: 12,000 to 30,000 gallons, 30,000 to 80,000 gallons, and
    80,000 gallons and above.    At each tier, a different rate applied
    for every thousand gallons supplied.      For example, in 2010, at the
    first tier, the Township charged $5.53 per one thousand gallons;
    2
    Schlesinger estimated that the vats held about 200 gallons of
    water.
    3                            A-2659-15T4
    at the second tier, $5.60 per one thousand gallons; and at the
    third tier, $5.67 per one thousand gallons.
    Additionally, the Township charged commercial and industrial
    properties, like PRC, sewer service fees based on actual water
    usage.   Every quarter, the Township charged the property a flat
    fee of $99 in addition to $4.20 for every one thousand gallons
    above 23,700 gallons used each quarter.   If the water supplied did
    not flow back through the sewer system, the Township calculated
    its sewer service fees by deducting that amount of water from the
    recorded consumption total.    A sewer deduct meter measured the
    amount of water supplied by the Township to the facility that did
    not flow back through the sewer system. The water supply generally
    flowed in one direction but could flow backwards through the sewer
    system if a backflow preventer, licensed by the State and inspected
    by the Township, was not installed on the line.        PRC had no
    backflow preventer.
    In order to measure water and sewer charges, the Township
    installed three separate meters at the PRC facility.   A main flow
    meter, located in an exterior pit, recorded the amount of water
    the Township supplied to PRC through a two-inch line.     Once the
    water entered the facility, it dispersed into three different
    directions.   One line supplied water to the boiler room, where
    water was used for heat and air conditioning.       This line was
    4                          A-2659-15T4
    metered with a 5/8 inch sewer deduct meter. A second line supplied
    water to the production area for use in the cooling towers and had
    a two-inch sewer deduct meter.       A valve controlled the flow of
    water to this line, which remained locked with a chain unless a
    manager manually opened it to allow the flow of Township water to
    PRC's production process.    When that occurred, the purpose of the
    deduct meter was to subtract that amount of water from the water
    coming in on the main flow meter.    A third line provided water for
    general domestic use, such as water for the restrooms, kitchen
    sinks, laboratory sinks, and emergency showers.    That line was not
    separately metered.
    In a drawing identified as P-5 in evidence, Schlesinger
    described the water system as it flowed through the PRC facility.
    According to Schlesinger, PRC primarily used water from its well
    in its production process.     The well produced about 125 gallons
    of water per minute.    However, the well had no meter or other
    device attached to it to measure the amount of water supplied.
    PRC used water in the cooling towers in its production process to
    cool the plastic extruders.3    Water was recirculated through the
    3
    Schlesinger described an extruder as "basically a long spiral
    screw about [twenty] to [twenty-five] feet long . . . with a barrel
    around it, made of . . . hardened steel . . . with heater bands,
    which brings the temperature up to about 600 degrees."          The
    extruder "melts the product and then . . . pumps it out to a series
    5                           A-2659-15T4
    cooling towers and then either recycled in the cooling towers or
    lost through evaporation.     Depending on the time of year and
    temperature, some percentage of water was inevitably lost due to
    evaporation and replaced by well water or, on some occasions, by
    Township water.   PRC had no methodology for measuring evaporation.
    According to Schlesinger, in the past thirty years, PRC had
    to use Township water in its production process on only three or
    four occasions to compensate for a water shortage from the well.
    Those occasions occurred when there were problems with the well,
    including instances where the well collapsed, the pump broke and
    needed to be replaced, or a drought caused a low water table.    For
    example, in February 2015, the well was shut down for approximately
    two weeks because a pump and pipe had to be replaced, resulting
    in PRC relying exclusively on Township water.
    When PRC used Township water in its production process to
    replace or supplement water normally supplied by its well, the
    water eventually evaporated or overflowed onto the ground, but did
    not travel back through the sewer system.    Schlesinger testified
    that from 2000 to the present, he was unaware of any broken water
    of holes and dye[,]" which are then "taken into water bath[s]
    where [they] get solidified and from the water bath . . . to a
    pelletizer, which basically chops it into little pebbles" which
    are then dried, packaged and shipped to customers for use as
    "injection molding[.]"
    6                          A-2659-15T4
    lines, other than a minor leak in one of the hydra lines that was
    repaired on the same day.
    Prior to 1996, PRC's quarterly billings for water usage ranged
    from roughly $2300 to $6000.           However, from 1996 until the last
    quarter of 2012, the bills increased substantially with the 2012
    fourth quarter bill totaling over $22,000.4 Over that time period,
    PRC amassed a delinquent account of over $200,000.              In early 2013,
    PRC began the process of refinancing its debt and was required to
    pay    the   delinquent    water    bill    in    order   to   facilitate      the
    refinancing.       Prior   to   paying,     PRC   representatives      met    with
    Township officials to question the billings, claiming that they
    were billed based on estimates rather than "actual" meter readings.
    After investigating the meters and verifying the meter readings,
    the Township maintained the billings were accurate.
    According to Vitz-Del Rio, the Township billed PRC quarterly
    for water and sewer charges based on meter readings.                  Initially,
    Township     employees    physically    entered    the    property,    read    the
    meters directly from the dial, and manually entered the reading
    into a book.      Later, the meter readings were upgraded to "the ARB
    system[,]" which meant the meter readers had to physically touch
    every    remote   to   obtain   a   meter   reading.       Thereafter,       radio
    4
    The first quarter bill for 2013 reverted to approximately $4600.
    7                                 A-2659-15T4
    frequency remotes were installed, allowing meter readers to pick
    up readings from a remote device connected to the meters and wired
    to a radio frequency located on the outside of the PRC building.
    Meter readers then used a hand-held wand-like device to record the
    reading on the meters without having to physically touch the meters
    or access the buildings.
    After the meter readers collected the readings in their hand-
    held units, the data was downloaded onto a computer, after which
    it was transferred to the Township's billing software.    Bills for
    properties with more than two meters, like PRC, were produced
    manually from the Township's billing software because the software
    could only bill for two meters per account.      The meter reading
    report used to produce the bills specified the meter reading,
    water usage, any usage in excess of 12,000 gallons and the type
    of reading for each quarter.   The number in the water usage column
    was calculated by deducting the previous quarter’s reading from
    the current quarter’s reading.    If an estimate was used, it was
    designated with an "E" in the column titled "Est Flag."
    According to Vitz-Del Rio, none of the bills for any of the
    meters at the PRC facility were estimates but were, in fact, actual
    readings.   She also testified that the installation of the radio
    frequency remotes did not affect the functionality of the meters.
    In upgrading to the new system, the Township had to change only
    8                          A-2659-15T4
    the dial on the top of one of the meters at the PRC facility, but
    the other two meters remained unaltered.     Vitz-Del Rio confirmed
    that from 2008 to 2015, PRC's meters were not changed or repaired
    by the Township and she was unaware of any malfunction.          She
    explained that ordinarily, the water consumption registered on the
    sewer deduct meters should not exceed the consumption registered
    on the main in-flow meter, but attributed such an occurrence to
    "something else . . . being introduced" into the system.
    Nonetheless, PRC claimed that from 1996 to 2013, the Township
    overcharged them for water and sewer usage fees, and, after it
    complained, the Township repaired the defective meters, resulting
    in subsequent bills reflecting accurate charges.     To support its
    claim, in P-3 in evidence, Quint calculated PRC's domestic water
    usage by subtracting the meter reading on the meter measuring the
    amount of water the Township supplied from the readings on the
    sewer deduct meters measuring the amount of water flowing from the
    production and boiler lines.     According to Quint, prior to 2013,
    the Township billed PRC for approximately one to two million
    gallons of water each quarter.    However, after 2013, the domestic
    water usage noted in Quint’s calculations reflected that the
    Township billed PRC for approximately 98,000 to 481,000 gallons
    of water for domestic use.     The amount of water supplied to the
    boiler line also decreased significantly.
    9                         A-2659-15T4
    Based on the change in domestic and boiler water usage
    reflected in the billings before and after 2013, in May 2013, PRC
    filed a complaint against the Township, which was later amended,
    alleging breach of contract, breach of the covenant of good faith
    and fair dealing, unjust enrichment, and negligence.   PRC claimed
    that since 1996, the Township had overcharged it for water service
    charges and sewer fees by allowing the sewer deduct meters located
    on the property to either malfunction or remain in a state of
    disrepair or by failing to read the meters correctly.      It also
    claimed the water and sewer bills issued by the Township were
    estimates, rather than actual readings of their water and sewer
    usage consumption.    The Township filed a contesting answer and
    affirmative defenses, including failure to state a claim for which
    relief can be granted.
    At trial, Quint calculated PRC's damages in a chart identified
    as P-1 in evidence.   For each bill, Quint divided the gallons of
    water the Township supplied and billed PRC by PRC's production,
    in pounds, for that quarter.   He then divided the gallons of water
    the Township billed PRC for water flowing through the sewer system
    by PRC's production, in pounds, for that quarter.   The production
    numbers he used reflected production that was completed using both
    the Township's water and PRC's well water.      For each quarter,
    10                          A-2659-15T4
    Quint added those two ratios (water consumed/production + water
    in sewer system/production) together.
    For the contested billing period from 1995 to the first
    quarter of 2013, he averaged the total ratios he had calculated
    for each quarter.      He did the same for the non-contested billing
    period from the second quarter of 2013 to the first quarter of
    2015.   To calculate the damages, he multiplied the difference of
    those two averages by the total water and sewer charges the
    Township billed PRC during the contested time period, amounting
    to $361,107 in damages.        This analysis did not include missing
    bills or the bill from the first quarter of 2015 during which time
    PRC admittedly relied exclusively on the Township's water supply
    in its production process because its well was in disrepair. 5             It
    also did not account for the amount of water PRC used from its
    well, evaporation rates or increasing billing rates.
    Following the bench trial, in a November 16, 2015 written
    decision and accompanying order, the trial judge awarded final
    judgment in favor of the Township and dismissed the complaint with
    prejudice.   Preliminarily, the judge noted that he "considered the
    evidence   presented    by   the   parties   including   trial   testimony,
    5
    Notably, the billing for this quarter reflected water
    consumption totaling 2,240,000 gallons, which was approximately
    the same amount as the challenged quarters.
    11                             A-2659-15T4
    exhibits, proposed findings of facts, conclusions of law and
    arguments of counsel."
    In rejecting plaintiffs' claim that the Township breached the
    implied   covenant     of    good   faith      and   fair    dealing,   the     judge
    determined that plaintiffs produced "no evidence that the Township
    has acted in bad faith or with improper motive."                   Further, citing
    Callano v. Oakwood Park Homes Corporation, 
    91 N.J. Super. 105
    (App.   Div.    1996),      the   judge    determined       that   "[p]laintiffs'
    assertion of breach of contract based on a valid contractual
    relationship with the Township preclude[d] an equitable claim for
    unjust enrichment."          Regarding the negligence claim, the judge
    concluded      that   plaintiffs     "produced       no     evidence,   expert       or
    otherwise, to support a claim sounding in negligence."                   The judge
    rejected plaintiffs' "argument that [res ipsa loquitur] applie[d]"
    because "the meters in question were not under exclusive possession
    and control of the Township."
    Turning to the breach of contract claim, the judge noted
    there was no "dispute that a contractual relationship existed
    between [the parties,]" in that "[t]he Township provided water and
    sewer services and the [p]laintiffs paid for those [services]
    based on the Township's billing."              The judge also acknowledged the
    existence of an implied contract between the parties for the
    Township to provide and bill for sewer services "in accordance
    12                                  A-2659-15T4
    with [Wayne, N.J., Code § 159-18 (2013)]." According to the judge,
    "[§] 159-18 requires that 'the user . . . supply the necessary
    metering devices to measure the flow that enters the Township
    system.'"    Further, under Section 159-18B, "[w]here the water is
    taken from a source other than the Township water system, such
    source shall be metered by the user, and the quarterly sewer
    [charge] will be based on the reading of that meter."
    The judge continued that
    [b]ased on Code 159-18, the [p]laintiffs as
    "users" are obligated to supply the metering
    devices on their premises. They are further
    obligated to meter their well as a second
    source of water on their premises.
    Thus, [p]laintiffs' claims that the
    Township breached its contract by supplying
    defective   or   malfunctioning   meters   to
    [p]laintiffs fails based upon Code 159-18
    alone. It was not the Township's obligation
    to supply the meters.      More importantly,
    however, is this [c]ourt's finding that
    [p]laintiffs have produced absolutely no
    evidence to show that any of the meters
    malfunctioned or were defective in any way.
    This [c]ourt was presented with no proof
    of actual repairs or replacement of any of the
    meters. Thus, what is left for the [c]ourt
    to consider is whether the Township breached
    its    contract    by    improperly    billing
    [p]laintiffs for the water and sewer services
    provided.
    Initially, the judge determined that based on Vitz-Del Rio's
    testimony, it was undisputed that the Township billings were based
    13                          A-2659-15T4
    on   "actual   readings   and    not     estimates."        The    judge     also
    acknowledged   that   "PRC's    domestic    use   of   water      has   remained
    relatively constant over the years."        The judge noted further that
    plaintiffs' alleged breach of contract claim was "based entirely
    on the actual bills and reports prepared by the Township" and the
    billing analysis presented in P-1, which included seventy-six
    quarterly   bills   dating   back   to    1995,   seventy    of    which     were
    challenged by plaintiffs.       The judge pointed out that plaintiffs
    did not challenge the remaining six bills from April 6, 2013, to
    January 13, 2015.
    In addressing alleged billing inconsistencies, the judge
    recounted Schlesinger's and Quint's testimony "alleg[ing] mistakes
    in the billing."
    For example, both reviewed an actual bill
    generated for the fourth quarter of 2012
    . . . . That bill listed the water consumption
    at 2,325,000 gallons.    When compared to the
    Township's account report . . . , there was a
    discrepancy since [the report] listed water
    consumption at 200,000 gallons for the same
    period. It is clear that these two documents
    are inconsistent.   However, it is not clear
    that the actual bill . . . was incorrect. It
    is certainly possible that the Township's
    account report was incorrect.     In fact, the
    evidence produced in this case seems to
    support   the   billing    number   (2,325,000
    gallons).
    Similarly, turning to the sewer charges, the judge explained:
    14                                   A-2659-15T4
    A review of P-1 . . . shows that the
    $7,795.00 billed that quarter for sewer
    charges was not inconsistent with the sewer
    bills for previous quarters and in fact was
    less than the sewer charges for five of the
    previous   eight   quarters   (10/15/2000   to
    7/13/2012). Further the $12,984 billed that
    same quarter for water was less than the water
    charges for six of the previous eight
    quarters.
    Based on this analysis, the judge was "simply unable to conclude
    from the highlighted billing inconsistencies that the plaintiffs[]
    were in fact overcharged."   Thus, the judge found that plaintiffs
    "failed to establish a breach of contract by a preponderance of
    the evidence submitted."
    The judge continued that even if plaintiffs had proven a
    cause of action, the claim would still fail because "[p]laintiffs
    failed to adequately prove damages."     According to the judge,
    "[p]laintiffs produced no expert analysis regarding damages" but
    instead, submitted Quint's "calculation of damages [using] a ratio
    that he created using [plaintiffs'] own production numbers[,]"
    which analysis admittedly omitted "the rate increases" prescribed
    by the Township Ordinance and omitted plaintiffs' unmetered "well
    water usage[.]"   The judge found "Quint's analysis to be nothing
    more than mere speculation" and concluded that "[t]he proofs [did]
    not adequately explain how that ratio was developed" or "support
    15                         A-2659-15T4
    his alleged correlation between production and [plaintiffs'] use
    of Township water."
    Additionally, the judge determined that "the damages sought
    by [p]laintiffs would be significantly limited by the applicable
    statute of limitations to those damages sustained after May 23,
    2007[,]   which   [was]    six       years    prior   to   the   filing   of     the
    [c]omplaint. . . ."       According to the judge, because "damages for
    a period beyond the six[-]year statute of limitations were not
    presented 'on the face of the complaint,' . . . the Township's
    failure to specifically assert a statute of limitations bar as a
    defense [did] not act as a waiver at the time of trial" because
    the Township pled "'failure to state a claim upon which relief can
    be granted' as an affirmative defense."               Finally, the judge noted
    that plaintiffs' September 30, 2015 motion in limine "seeking an
    order   permitting   the    .    .   .   admission     into   evidence    [of]    an
    affirmation of . . . Quint" with an accompanying exhibit or "[i]n
    the alternative . . . to re-open the trial[,]" was "improper as
    it was made two months after the trial ended" and plaintiffs had
    the opportunity to present the evidence at the trial.
    Plaintiffs moved for reconsideration pursuant to Rule 4:49-
    2, asserting that the court misinterpreted Section 159-18, and
    overlooked   evidence,     specifically        P-3    in   evidence,   which     was
    Quint's calculation of water for domestic use from a summary of
    16                               A-2659-15T4
    bills from July 15, 2009 to July 13, 2015, with a breakdown of
    water consumption for flow, production, boiler and domestic use.
    On   January   19,   2016,   in   an   oral   decision,   the   judge    denied
    plaintiffs' motion.      The judge determined that he did, in fact,
    review exhibit P-3, explaining,
    I did not mention P-3 in my decision. I didn’t
    mention a lot of specific documents.      I do
    mention in my opinion that I considered all
    of the evidence that was marked at trial,
    which included P-3 . . . .
    [A]lthough I didn’t mention it, . . . the
    information was reviewed, so there’s no need
    for me to reconsider under [Rule] 4:49-2 based
    upon P-3.
    The judge reiterated that plaintiffs failed to meet their
    burden of proof and again rejected plaintiffs' claim that proof
    of billing inconsistencies indicated the Township overcharged PRC.
    In addition, the judge specified that Section 159-18 had very
    little effect in and of itself on his ultimate decision. According
    to the judge:
    [W]ith regard to the inconsistencies, . . .
    [t]here were clearly some discrepancies when
    you compared the bills to the [T]ownship
    reports. . . . But . . . I . . . focused on
    what was the total bill[.] What were the bills
    for sewer and what were the bills for water
    over this period of time and it was a
    significant period of time, even if I were to
    limit   everything    to  the   [s]tatute   of
    [l]imitation time period.
    17                               A-2659-15T4
    And my decision was based upon all of
    that review. . . . [P]laintiff[s] simply
    didn't meet its burden with regard to a breach
    of contract claim. . . . But I want to be
    clear that this decision didn't turn on . . .
    my reading of that ordinance.
    [T]he ordinance . . . based upon my
    interpretation, requires a meter for the well,
    but that in and of itself really has very
    little effect on my ultimate conclusion in the
    case. Because this is about what was metered
    and whether or not there was an appropriate
    bill for those meters. . . .
    [So] . . . [t]his really was . . . a defective
    billing case . . . .
    As to damages, the judge reiterated:
    I [also] pointed out that since I didn't find
    a breach of contract[,] I didn't have to get
    to damages. But . . . even if I had found by
    a preponderance of the evidence that [there]
    was a breach, . . . I couldn't come up with a
    firm amount on the damages.
    Finally, regarding plaintiffs' in limine motion, the judge stated:
    I didn’t think [the in limine motion] was
    appropriate.     But more importantly[,] it
    didn't really change the evidence in the case.
    I had P-1. . . . [T]his extra information
    . . . that [plaintiffs' counsel] tried to
    . . . bring after the trial was completed was
    really just kind of . . . a further explanation
    . . . of some of the evidence that I already
    considered.
    This appeal followed.
    On appeal, plaintiffs raise the following points for our
    consideration:
    18                           A-2659-15T4
    POINT I6
    THE COURT’S FINDING THAT ACTUAL DOMESTIC WATER
    USAGE REMAINED CONSTANT SHOULD HAVE GENERATED
    A FINDING THAT THE TOWN OVERBILLED PRC, AS THE
    TOWNSHIP’S BILLING DATA SHOWED A MARKED
    DECLINE IN DOMESTIC [CONSUMPTION] AFTER PRC
    COMPLAINED OF OVERBILLING.
    POINT II
    THE COURT ERRED IN MISAPPLING A MUNICIPAL
    ORDINANCE.
    POINT III
    THE COURT ERRED IN FAILING TO CONSIDER PRC’S
    PROFFER OF DAMAGES.
    POINT IV
    THE COURT ERRED BELOW IN APPLYING THE STATUTE
    OF LIMITATIONS WHEN THE TOWNSHIP WAIVED SUCH
    AFFIRMATIVE DEFENSE.
    POINT V
    THE COURT ERRED BELOW IN FAILING TO CONSIDER
    PRC’S SUBMISSION REGARDING TRUNCATED DAMAGES.
    We have considered these arguments in light of the record and
    applicable legal principles.    We reject each of the points raised
    and affirm.
    Our review of a trial court's fact-finding in a non-jury case
    is limited.    Seidman v. Clifton Sav. Bank, S.L.A., 
    205 N.J. 150
    ,
    169 (2011).    "The general rule is that findings by the trial court
    6
    We have condensed the points for clarity.
    19                          A-2659-15T4
    are binding on appeal when supported by adequate, substantial,
    credible evidence." Cesare v. Cesare, 
    154 N.J. 394
    , 411-12 (1998).
    We owe "deference to those findings of the trial judge which are
    substantially influenced by [the judge's] opportunity to hear and
    see the witnesses and to have the 'feel' of the case, which a
    reviewing court cannot enjoy."       State v. Locurto, 
    157 N.J. 463
    ,
    471 (1999) (quoting State v. Johnson, 
    42 N.J. 146
    , 161 (1964)).
    We "do not disturb the factual findings and legal conclusions of
    the trial judge unless we are convinced that they are so manifestly
    unsupported by or inconsistent with the competent, relevant and
    reasonably credible evidence as to offend the interests of justice.
    . . ."   Rova Farms Resort, Inc. v. Inv'rs Ins. Co., 
    65 N.J. 474
    ,
    484 (1974) (quoting Fagliarone v. Twp. of N. Bergen, 
    78 N.J. Super. 154
    , 155 (App. Div. 1963)).
    Similarly,    our   standard        of   review   on     a    motion     for
    reconsideration is deferential.      "Motions for reconsideration are
    governed by Rule 4:49-2, which provides that the decision to grant
    or deny a motion for reconsideration rests within the sound
    discretion of the trial court."          Pitney Bowes Bank, Inc. v. ABC
    Caging Fulfillment, 
    440 N.J. Super. 378
    , 382 (App. Div. 2015).
    "Reconsideration should be used only where '1) the [c]ourt has
    expressed   its   decision   based   upon      a   palpably       incorrect    or
    irrational basis, or 2) it is obvious that the [c]ourt either did
    20                                  A-2659-15T4
    not   consider,   or   failed    to    appreciate     the   significance     of
    probative, competent evidence.'"            
    Ibid. (alterations in original)
    (quoting Capital Fin. Co. of Delaware Valley, Inc. v. Asterbadi,
    
    398 N.J. Super. 299
    , 310 (App. Div. 2008)). "Thus, a trial court's
    reconsideration   decision      will    be    left   undisturbed   unless    it
    represents a clear abuse of discretion."               
    Ibid. An abuse of
    discretion "arises when a decision is 'made without a rational
    explanation, inexplicably departed from established policies, or
    rested on an impermissible basis.'" Flagg v. Essex Cty. Prosecutor,
    
    171 N.J. 561
    , 571 (2002) (quoting Achacoso-Sanchez v. Immigration
    & Naturalization Serv., 
    779 F.2d 1260
    , 1265 (7th Cir. 1985)).
    Plaintiffs' arguments on appeal are directed at the judge's
    rejection of their breach of contract claim. In a claim for breach
    of contract,
    [o]ur law imposes on a plaintiff the burden
    to prove four elements: first, that "[t]he
    parties entered into a contract containing
    certain terms"; second, that "plaintiff[s] did
    what the contract required [them] to do";
    third, that "defendant[s] did not do what the
    contract required [them] to do[,]" defined as
    a "breach of the contract"; and fourth, that
    "defendant[s'] breach, or failure to do what
    the contract required, caused a loss to the
    plaintiff[s]."
    [Globe Motor Co. v. Igdalev, 
    225 N.J. 469
    , 482
    (2016) (alterations in original) (quoting
    Model Jury Charge (Civil), § 4.10A "The
    Contract Claim-Generally" (May 1998)).]
    21                             A-2659-15T4
    Here, plaintiffs failed to carry their burden of proof to
    establish all the elements of their cause of action.                      We are
    satisfied that the judge's factual findings and legal conclusions
    to that effect are supported by the record, and the judge's denial
    of plaintiffs' motion for reconsideration reflects an appropriate
    exercise of discretion.
    Plaintiffs    argue    the    trial    judge     did    not   "fully     and
    adequately" consider the data in P-3, which "clearly show[ed] that
    domestic water usage decreased dramatically shortly after the
    Township inspected its water meters and its billing in January
    2013."     According to plaintiffs, "[s]ince the change was not
    accounted for by PRC's usage, it had to be the result of defective
    meters or . . . billing errors."           Additionally, plaintiffs assert
    the   judge     failed      to     adequately    consider       the    multiple
    inconsistencies contained within the bills themselves.
    Viewed through the lens of the deferential standard we accord
    the judge's factual findings, we discern no basis for intervention.
    In ruling on the motion for reconsideration, the judge confirmed
    that he considered P-3. The judge also underscored that plaintiffs
    produced   no   evidence     demonstrating      that    any    of   the    meters
    malfunctioned      or    were      defective.          Additionally,         while
    acknowledging    inconsistencies       between    the    Township's       billing
    records and its internal reports, the judge was unable to conclude
    22                                  A-2659-15T4
    given    the     other        evidence    in   the    case     that     the     billing
    inconsistencies proved that the plaintiffs were overcharged.
    Next, plaintiffs argue that the judge erred in applying
    Section 159-18 "to dismiss PRC's claim that the Township supplied
    defective or malfunctioning meters."                  According to plaintiffs,
    because the Ordinance "pertains only to discharge of well water
    to   'sewers,'     and    does    not    pertain     to    water    supplied    by   the
    Township[,]" the judge either misinterpreted the Ordinance "as
    requiring a property owner to supply its own water meters" or
    "failed to appreciate the significance of the probative evidence
    that    PRC's    well    water    never    entered    the    sewer     system."        We
    disagree.
    "The established rules of statutory construction govern the
    interpretation of a municipal ordinance."                   Twp. of Pennsauken v.
    Schad, 
    160 N.J. 156
    , 170 (1999).               Therefore, courts interpret an
    ordinance to "effectuate the legislative intent in light of the
    language used and the objects sought to be achieved." 
    Ibid. (quoting Merin v.
    Maglaki, 
    126 N.J. 430
    , 435 (1992)).                            First,
    courts examine the ordinance's language.                    
    Ibid. If it is
    clear
    and unambiguous, a plain meaning reading of the ordinance governs.
    
    Ibid. If it is
       susceptible     to     at    least     two     different
    interpretations, the court must look at extrinsic evidence such
    as its purpose and legislative history and the overall statutory
    23                                    A-2659-15T4
    scheme.   
    Ibid. "Above all, the
    [c]ourt must seek to effectuate
    the 'fundamental purpose for which the legislation was enacted.'"
    
    Ibid. (quoting N.J. Builders,
    Owners & Managers Ass'n v. Blair,
    
    60 N.J. 330
    , 338 (1972)).     We review questions of law such as
    these de novo.    Allstate Ins. Co. v. Northfield Med. Ctr., P.C.,
    
    228 N.J. 596
    , 619 (2017).
    Section 159-18 governs the Township's sewer rental fees for
    commercial and industrial properties and provides that:
    The user will supply the necessary metering
    devices to measure the flow that enters the
    Township system.   Where the water is taken
    from a source other than the Township water
    system, such source shall be metered by the
    user, and the quarterly sewer charge will be
    based on the reading of that meter.
    We agree with the judge's interpretation of the Ordinance.
    Contrary to plaintiffs' assertion, the ordinance does not qualify
    "necessary metering devices" by stating that users must provide
    only discharge meters or only provide a meter if they anticipate
    water entering the sewer system.     Rather, the ordinance expressly
    states that metering devices are required to measure the flow into
    the sewer system – not if the water flows into the sewer system.
    (Emphasis added).    Otherwise, the Township would have no way to
    verify sewer rental fees other than by relying on a customer's
    claims.
    24                           A-2659-15T4
    Furthermore, the ordinance specifies that users "will supply"
    the necessary metering devices, and requires the user to supply
    the meter "[w]here the water is taken from a source other than the
    Township water system[.]"        Thus, the ordinance requires that
    plaintiffs, as the potential users of the sewer system, supply any
    meters necessary to measure the flow of water into the sewer
    system, regardless of the amount or the source.       In any event, the
    judge's finding was predominantly based on plaintiffs producing
    "no evidence to show that any of the meters malfunctioned or were
    defective in any way[,]" more so than the application of the
    ordinance.
    Plaintiffs' remaining arguments attack the judge's findings
    with respect to       damages.   However, because we conclude that
    plaintiffs   failed    to   establish   the   requisite   breach   of   the
    contract, we need not address plaintiffs' remaining arguments.
    Affirmed.
    25                              A-2659-15T4