STATE OF NEW JERSEY VS. MICHAEL S. HETZEL (14-05-1100, ATLANTIC COUNTY AND STATEWIDE) ( 2017 )


Menu:
  •                    NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0347-10T1
    MICHAEL A. WALTER BUILDERS, INC.,
    Plaintiff-Respondent,
    v.
    BARBARA BEDNAR,
    Defendant-Appellant.
    _______________________________
    Telephonically argued June 3, 2011 –
    Decided September 23, 2011
    Before Judges    R.    B.    Coleman,   Lihotz      and
    J. N. Harris.
    On appeal from the Superior Court of New
    Jersey, Law Division, Cape May County,
    Docket No. L-553-04.
    Keith A. Bonchi argued the cause for
    appellant   (Goldenberg,   Mackler, Sayegh,
    Mintz, Pfeffer, Bonchi & Gill, attorneys;
    Mr. Bonchi, of counsel and on the briefs;
    Rosann Allen, on the briefs).
    Stephen W. Barry argued the cause for
    respondent (Barry, Corrado, Grassi & Gibson,
    P.C., attorneys; Mr. Barry, on the brief).
    PER CURIAM
    Defendant    Barbara   Bednar      appeals   from    a   final   judgment
    granting relief to plaintiff Michael A. Walter Builders, Inc.
    following    a    bench   trial,     and     an   order       dismissing   her
    counterclaim.          On appeal, defendant argues the trial court's
    factual findings are not supported by the record and certain
    legal    conclusions         supporting      the       relief    ordered    in    favor    of
    plaintiff and in dismissing her counterclaim were reached in
    error.     We affirm.
    These facts are contained in the trial record.                               Defendant
    owned    the    Heritage       Inn    Motel       in    Cape    May.       Defendant      had
    obtained architectural and mechanical drawings for the motel's
    proposed    modifications           that    were       prepared    by    architect     Blane
    Steinman, mechanical engineer John Schade, P.E., and structural
    engineer       Tom    Shepard.             After       reviewing       these     materials,
    plaintiff's principal, Michael A. Walter, drafted estimates for
    completion      of     the    job     and    submitted          his     "Proposal"     dated
    November 20, 2003, which was accepted by defendant.                                  In the
    contract,       plaintiff,        designated            as     "the     Builder,"      would
    construct a third-floor addition to the motel and perform other
    renovations1 for defendant, designated as "the Customer," for the
    agreed sum of $1,037,300.
    Certain         provisions      of     the    proposal       as    accepted     by   the
    parties as their contract are relevant to our review.                                First,
    1
    Plaintiff had drafted three proposals for defendant, the
    last of which was executed by the parties bearing the date of
    November 20, 2003 but actually signed sometime in late January
    2004.
    2                                     A-0347-10T1
    the   proposal     expressly       incorporated         Steinman's       architectural
    plans   that      utilized       Schade's       mechanical      specifications         for
    thirty-three      Mitsubishi       "heat        pump    systems     at    14,500       BTUs
    cooling."2      Also, the plans required each room to be equipped
    with condenser and air handling units from the same manufacturer
    with the same energy output of 14,500 BTUs.
    Second,     the   agreement      included          a    payment     schedule       to
    provide fourteen draws.            Each draw was in a stated amount and
    was due upon completion of various stages of the project.
    Third,      all   renovations         and    the       addition     were    to    be
    completed      within      six     months        from    the     date     construction
    commenced, or by May 20, 2004.                  The agreement allowed a thirty-
    day extension for weather-related delays.
    Fourth,     additional       general       provisions:      (1)    mandated      any
    changes were not effective "unless in writing, signed by both
    Builder and Customer"; (2) required builders' risk insurance be
    "provided    by    [the]     Builder   to       [the]    Customer       for   [the]    new
    2
    A BTU, short for British Thermal Unit, is a basic measure
    of thermal energy.   One BTU is the amount of energy needed to
    heat one pound of water one degree Fahrenheit, measured at its
    heaviest point.   When speaking of cooling power, the BTU works
    in reverse. The air-cooling power of an air conditioning system
    refers to the amount of thermal energy removed from an area.
    The higher the BTU output, the more powerful the heating or
    cooling.    http://www.eia.gov/emeu/consumptionbriefs/cbecs/
    pbawebsite/office/office_refbtu.htm (last visited August 30,
    2011).
    3                                    A-0347-10T1
    addition" and the Customer would provide home-owner's insurance
    "for    [the]    existing   hotel";   (3)     provided   the    "Builder     will
    guarantee all workmanship of [the B]uilder and all of [the]
    Builder's       Subcontractors,   for       one   year   from    the   day     of
    settlement."
    Two additional provisions listed under "Additional Clauses"
    must also be mentioned.           Subsection (F) stated, in pertinent
    part:
    Additional work may be performed on hotel.
    Cost for work will be priced by Builder and
    accepted by Customer.      A spreadsheet for
    additional   items   will   be   provided   and
    updated by Builder periodically. . . .
    Payments   for   work   shall   be   made   the
    beginning     of     each     month,     during
    construction.    Ongoing cost for additional
    work shall not exceed 2% of the total house
    [sic] construction cost, as stated [i]n this
    [c]ontract.
    Additional work performed will affect the
    time of [a]ddition/renovation completion.
    . . .
    and subsection (J) provided:
    Failure to insist upon strict compliance
    with   any   of   the   terms,   covenants or
    conditions hereof shall not be deemed a
    waiver of such term, covenant or condition,
    nor shall any waiver or relinquishment of
    any right or power hereunder at any one or
    more   times    be    deemed   a   waiver  or
    relinquishment of such right or power at any
    other time.
    4                              A-0347-10T1
    The construction did not proceed smoothly.              We will discuss
    the dilemmas which bear on the parties' claims in litigation.
    As the details of the agreement were ironed out, plaintiff
    commenced demolition on November 20, 2003.              The first step was
    to remove the second floor ceilings, erect scaffolding,                   and
    construct the third-floor "block walls" atop the second floor.
    Plaintiff used subcontractors for this job.             It was decided the
    second floor roofing would be removed and the block for the
    third-floor wall would be laid in a piecemeal fashion because of
    "weather concerns."        Walter explained:
    [Y]ou just can't build a wall straight
    up and then build the back wall and
    then another side wall . . . [i]t has
    to be done simultaneously with another
    room. . . . Because a block wall might
    be up six feet, another block wall
    might be up four foot, another one up
    two foot.    So, it wasn't on a level
    plane where we could put boards across
    and tarp [the open roof] . . . .
    To   protect     the    property    from   water   damage   during   this
    process, plaintiff placed a tarp over the block walls and laid
    wooden planks on the tarps to hold them in place.               Also, a rope
    was woven through the eyelets of the tarps and tied to the sides
    of the building.
    During November and December 2003, before the new roof was
    shingled,    three   rainstorms        occurred.       Notwithstanding    the
    protective measures employed, "[w]hen the storms came through,
    5                           A-0347-10T1
    there [were] heavy winds that ripped the tarps off and water got
    into the [m]otel."       After the first storm in November, plaintiff
    added ropes and tarps, but "still the storm[water]                     got in[,]"
    damaging the sheetrock ceilings of the first floor, the first
    and second-floor carpeting, and some of the furniture stored in
    the first-floor rooms.
    Upon   discovering     the     extent     of    the    damage,     plaintiff
    suggested    the    parties'     submit    claims       to   their     respective
    insurance carriers.        Plaintiff hired subcontractors to restore
    the   existing     structure.       This   work      included    installing     new
    sheetrock    on    the   ceilings    and   walls;      removing    the    old   and
    installing   new    carpeting;      repairing     bathroom      tile   damage   and
    "put[ting] new trim [], new doors, and paint" on the walls.                      At
    the same time, plaintiff continued construction of the third
    floor, believing "the insurance companies would take care of the
    cost[s]" which the parties would "sort[] out later."
    Because of these construction delays, the parties agreed
    the new third-floor guest rooms would be finished for the summer
    and the meeting room, exercise room, and owner's quarters could
    be completed in the fall.          Although the third-floor rental rooms
    were completed on May 26, 2004, restoration of the first and
    second floor rooms was not completed until immediately prior to
    the July Fourth weekend.
    6                                  A-0347-10T1
    Another problem resulted regarding the heating, ventilation
    and air conditioning (HVAC) installation.                               First, plaintiff and
    the      architect          agreed          to       deviate         from      the        contract
    specifications,            and    installed            the        condenser       units     on     a
    fiberglass          deck   located       on      the     roof.           Consequently,        some
    condensers          were   closer      to     some      rooms,       "both    vertically         and
    horizontally[,]" than originally designed.                                 Second, plaintiff
    learned the Mitsubishi 14,500 BTU condenser and air handling
    units    specified         by    the     mechanical              engineer's    drawings       were
    unavailable as "[t]here was no such thing."                                  Walter consulted
    with defendant and outlined the attempts to find a comparable
    unit.     Defendant expressed concern regarding the efficiency of
    any    proposed       units.        On      April      7,    2004,      plaintiff     presented
    defendant with three options, set forth in a written "additional
    work authorization."             On May 4, 2004, defendant chose the second
    alternative listed, requesting the proposed units be upgraded to
    larger units.          She told Walter she desired plaintiff install a
    17,000        BTU     condenser          and      Arcoaire           air      handling       units
    manufactured by Bryant.                  Walter inserted this information into
    the additional work authorization, which he signed that day.
    In July or August 2004, defendant expressed concern that
    the air conditioning units were "getting cool too fast and some
    mold    was    being       created"      in      some       of    the    rooms.      At    trial,
    7                                        A-0347-10T1
    defendant    asserted       she    never       experienced         a   mold      or     mildew
    problem in any motel rooms prior to hiring plaintiff.                                Further,
    she    expressed     that   for        the   first     time    she     began      receiving
    complaints    from     guests      about       dampness       in   rooms.         Plaintiff
    observed mold growth which was confined to the first floor and
    attributed it to leaky pipes that "weren't pitched properly" in
    a     downstairs     crawlspace.             Defendant        retained      a     different
    contractor to remove and replace the HVAC units at a cost of
    $117,895.98.
    The last payment defendant provided to plaintiff -- the
    eleventh draw -- was in May 2004.                    On June 24, 2004, plaintiff
    requested     the     twelfth      draw.            After     plaintiff         made     three
    additional requests for payment, defendant allegedly responded,
    stating she had no more money.
    Plaintiff filed its two count complaint, alleging breach of
    contract and misrepresentation.                    Specifically, plaintiff sought
    payment     under    the    contract         for     services      rendered          totaling
    $148,100,    expenditures         for    storm      damage     repairs      amounting        to
    $120,000    and     "extras"      of    $60,694.        Additionally,           it     alleged
    defendant fraudulently induced plaintiff to provide services for
    which she had no intention of paying.
    Defendant denied an obligation to plaintiff and filed a
    five-count    counterclaim.              She       asserted    breach     of      contract,
    8                                      A-0347-10T1
    consumer fraud, breach of express and implied warranties, common
    law fraud, and negligence.                Defendant sought rescission of the
    contract and return of the $971,705 she had paid plaintiff along
    with compensatory damages resulting from plaintiff's failure to
    follow the contract's specifications, lost profits, interest,
    costs, and attorney's fees.3
    The seven day bench trial began on December 2, 2008.                             In
    addition to the parties' testimony concerning the contract and
    construction,       they     each    presented    fact     and   expert    witnesses.
    With regard to the HVAC units, plaintiff offered Jim Berry, the
    principal of the HVAC subcontractor, who testified the installed
    units were marketed at approximately 17,000 BTUs but as a result
    of installation, specifically the length of the refrigerant line
    between    the     condenser        and   air   handler,    a    loss   of     capacity
    resulted     in     an     average    effective     BTU     capacity      of   14,960.
    Defendant's expert, Frank A. Vinciguerra, inspected the motel in
    December, noting the rooms "were humid, very humid, and many
    areas had mold growth within them."                He concluded the units were
    oversized,        caused    short-cycling,        and    had     an   "inability      to
    dehumidify spaces."            He countered Berry's assertions, opining
    3
    Defendant later amended her pleadings to include a third-
    party complaint against nineteen additional parties, including
    the subcontractors and their respective insurers. Each of these
    parties settled the claims or were dismissed prior to trial.
    9                                  A-0347-10T1
    the reduction in capacity caused by the length of the lines was
    irrelevant since "the ability to control humidity" is not the
    same as effective cooling.
    Defendant       also   offered         expert        testimony    of     Sander     J.
    Greenberg, who quantified her lost revenue between $140,000 and
    $240,000.     This was rebutted by plaintiff's accountant, James A.
    Stavros, who maintained Greenberg's methodology did not "follow
    the standards set forth by the [American Institute of Certified
    Public     Accountants]"   for       the        calculation     of    lost     profits,
    because he failed to specify a "period of loss" and exaggerated
    potential lost profits of the motel by including business loses
    of another entity owned by defendant.
    In a written opinion, the trial judge found defendant, not
    plaintiff,    unilaterally      breached         the     contract    by    ceasing     the
    scheduled payments for completed work.                    The judge considered the
    parties'    testimony.     He    rejected,          as    incredible,      defendant's
    assertions plaintiff assumed full responsibility to pay for the
    storm damage repair costs and that plaintiff never asked for the
    twelfth draw.      Conversely, the judge noted plaintiff's principal
    was "straightforward and believable," and "kept meticulous notes
    and records that record[ed] the dates he requested the next
    draw."       The   trial   court      described           the   uncompleted         items
    discussed    by    defendant    at    trial       as     last-minute       "punch     list
    10                                  A-0347-10T1
    items,"     which     would     have     been      completed           by    plaintiff          had
    defendant     not     terminated       the    agreement          and        found    defendant
    failed to mitigate her lost revenue damages by her six month
    delay in accepting her contractor's proposal to rectify the HVAC
    problems.
    On   the    complaint,      the     court         entered       an     order    awarding
    plaintiff damages of $221,752.57, plus prejudgment interest and
    costs of $42,377.58.           With respect to defendant's counterclaim,
    the   court      considered      only        whether          plaintiff       breached          the
    parties'      contract.          He     found       no        evidence        of     fraud       or
    misrepresentation        by    plaintiff,          rather       the     court       determined
    plaintiff "met the standard of good faith, honesty in fact and
    observance     of     fair    dealing."           The    court     declined          to     credit
    Greenberg's expert opinion as to any claimed economic damages,
    concluding "the delays were caused by a number of factors which
    Greenberg did not take into account."                     The trial judge dismissed
    Defendant's counterclaim with prejudice.
    On   appeal,      defendant       argues          the    trial        court    erred       in
    concluding plaintiff had no liability as a result of the faulty
    performance      of    the     HVAC     subcontractor            and       for     failing       to
    properly     secure     the     property          from        storms       while     work       was
    progressing.          Finally,        defendant         argues     plaintiff          was       not
    11                                           A-0347-10T1
    entitled to the twelfth draw under the contract.                        We turn to our
    review of these issues.
    The scope of our review of a non-jury case is limited.
    Seidman v. Clifton Sav. Bank, S.L.A., 
    205 N.J. 150
    , 169 (2011).
    The findings on which a trial court bases its decision will "not
    be   disturbed      unless    they     are    so     wholly     insupportable      as    to
    result    in   a    denial      of    justice[.]"          Rova    Farms     Resort      v.
    Investors      Ins.    Co.,     
    65 N.J. 474
    ,   483-84    (1974)    (internal
    citations and quotations omitted).                   On the other hand, although
    a trial court's factual findings will not be overturned absent
    an abuse of discretion, questions of law are subject to de novo
    review.     Balsamides v. Protameen Chems., Inc., 
    160 N.J. 352
    , 372
    (1999).
    Defendant first argues the trial court erred as a matter of
    law in concluding the engagement of a subcontractor to install
    the HVAC units shielded plaintiff as the general contractor from
    liability for alleged resultant damage in failing to follow the
    contract    specifications           and   instead       installing      nonconforming
    HVAC units.        We reject defendant's characterization of the trial
    court's legal conclusions.
    Defendant       focuses    on    one    portion      of     the   trial    judge's
    opinion,    which     mentions       defendant's         claim    resulted      from    her
    dissatisfaction with the performance of the HVAC subcontractor,
    12                                  A-0347-10T1
    Berry.    In the discussion, the judge commented that if the HVAC
    did not work properly, "it would be the responsibility of Berry
    or the manufacturer of the product; and not [plaintiff.]"                  This
    comment related to the causation question; that is, whether the
    mold resulted from the efficiency of the units.                It was not the
    basis of the court's conclusion regarding plaintiff's liability,
    as defendant now suggests.
    "Disputes between contractors and owner[s] as to extra work
    and changes on building or working contracts are as old as the
    practice of contracting for such work and are a fertile cause of
    litigation."       Headley v. Cavileer, 
    82 N.J.L. 635
    , 637 (E & A
    1912).    The "fundamental difficulty" encountered in this field
    of    litigation   is   that   "there   is   no   statute   requiring      such
    contracts . . . to be in writing[.]"           
    Id. at 637-38.
            No matter
    how "'solemn in form'" the original agreement, parties are free
    to renounce or modify it in any way they see fit.                 
    Id. at 638
    (quoting Cooper v. Hawley, 
    60 N.J.L. 560
    , 563 (E & A 1897)).
    Therefore, a "writing requirement may be expressly or impliedly
    waived by the clear conduct or agreement of the parties or their
    duly authorized representatives."            Home Owners Constr. Co. v.
    Glen Rock, 
    34 N.J. 305
    , 316 (1961).                 See also Salvatore v.
    Trace, 
    109 N.J. Super. 83
    , 103 (App. Div. 1969), aff'd, 
    55 N.J. 362
      (1970)   (observing      that   contracting    parties    can    waive    a
    13                               A-0347-10T1
    writing       requirement         through     their        conduct).           These      aged
    pronouncements reflect little has changed over time and aptly
    describe what occurred in this matter.
    The judge thoroughly detailed his findings regarding who
    made the decision to alter the specified HVAC units once those
    identified in the specifications were unavailable.                             In doing so,
    he specifically rejected defendant's claims that the decision
    was unilaterally made by plaintiff.                        Further, the trial judge
    found    defendant's         suggestion       that       she    was     ignorant    of     the
    problem       was    not   believable       and     he     credited      the    painstaking
    testimony, supported by documentation, presented by plaintiff
    and Berry.          The court determined defendant knew of the problem
    because plaintiff had discussed the "HVAC issues" with her on
    "at least [six] occasions[,]" she selected the chosen unit and
    authorized the change.               Moreover, plaintiff delayed her decision
    for almost a month, giving her ample opportunity to consult with
    Shade    or    Steinman,       the     architect      and      engineer      who   drew    the
    original plans.            Finally, the court found no evidence submitted
    by    defendant      showing      plaintiff        breached      the    amended    proposal
    regarding the installation of the HVAC units.
    These        findings      by    the        trial       judge,       including      the
    credibility determinations leading to his conclusion plaintiff
    had    not    breached      the      parties'      agreement,         are   "supported      by
    14                                    A-0347-10T1
    adequate,    substantial       and     credible     evidence."         Rova    
    Farms, supra
    , 65 N.J. at 483-84.             The court's findings and conclusion
    will not be disturbed.
    Defendant next maintains plaintiff breached the contract's
    implied covenant of good workmanship by failing to adequately
    protect the property from storm damage.                  Defendant asserts she
    relied     upon    plaintiff's        express     expertise,     but     the     means
    employed by plaintiff to secure the motel from storm damage
    after removing the roof were performed improperly and not in a
    workmanlike       manner.       Defendant       argues   the     court    erred      in
    requiring her to pay plaintiff to correct the damage caused by
    its breach and maintains she is entitled to recover judgment
    against    plaintiff      on   this     issue.      We   find    these    arguments
    unavailing.
    Absent an express guarantee of good workmanship, "the law
    implies a covenant that the contract will be performed in a
    reasonably good and workmanlike manner."                     Ramapo Brae Condo.
    Ass'n, Inc. v. Bergen Cnty. Hous. Auth., 
    328 N.J. Super. 561
    ,
    576-77 (App. Div. 2000), aff'd, 
    167 N.J. 155
    (2001); see also
    McDonald v. Mianecki, 
    79 N.J. 275
    , 293 (1979).
    In the first count of her counterclaim, defendant includes
    a claim of breach of contract.             The bases stated for the breach
    include:    the    work     performed    and     materials     used    were    not    in
    15                                   A-0347-10T1
    compliance with the plans and the work was not in compliance
    with applicable construction codes and regulations.                   The court
    found defendant's proofs on each of these issues was lacking and
    denied relief, concluding defendant, not plaintiff breached the
    contract.
    The third count of the counterclaim asserts "breach of UCC
    warranties."    The trial judge specifically found: "The Uniform
    Commercial     Code    claim       in    the    [t]hird    [c]ount      of     the
    [c]ounterclaim was not pursued at trial and deemed abandoned by
    the [c]ourt.    The [t]hird [c]ount is dismissed with prejudice."
    The     fifth   count     of   the   counterclaim     is   the   only    claim
    directed to plaintiff's alleged failure "to protect the interior
    of the structure from [] exposure to the elements."                   The claim
    asserts plaintiff was negligent.               As to this issue, the trial
    judge   correctly     noted    defendant       released   plaintiff    and     his
    subcontractor when she settled the matter with the insurance
    carrier.
    The release is limited to the negligence claims in count
    five of the counterclaim and specifically reserves all other
    claims between plaintiff and defendant.             The question is whether
    a claim of breach of the implied covenant of good workmanship
    was pled and proven.        We find it was not.
    16                             A-0347-10T1
    In    support   of   this   issue,     defendant   suggests      plaintiff
    could have proceeded by removing smaller sections of the roof at
    any given time.     Additionally, she notes the use of tarps, wood
    and ropes did not allay the wind gusts of the storms and the
    property was damaged.         From these facts, defendant concludes
    that because the tarps did not hold, plaintiff's workmanship was
    improper.
    At trial, defendant's evidence regarding plaintiff's breach
    of the contract was directed to its summer 2004 construction
    stoppage and the alleged mold formulation from the flawed HVAC
    installation.     Defendant did not offer expert testimony opining
    that the methods chosen to protect the property in the event of
    a storm evinced a defect in workmanship (or merely was a result
    of exceptional storm circumstances, as suggested by plaintiff).
    In fact, there was no evidence offered to prove plaintiff's
    workmanship in choosing the manner of roof removal, undertaking
    piecemeal      construction     of       the    third-floor        rooms    and
    weatherproofing the structure during construction, was improper.
    Defendant's     final     argument    urges   reversal    of    the    trial
    court's     conclusion   that    she,     not   plaintiff,    breached      the
    contract when she failed to release the twelfth draw payment.
    Before the trial court, defendant argued plaintiff never asked
    her for the twelfth draw.        This contention was soundly rejected
    17                               A-0347-10T1
    by the trial judge, who found plaintiff's evidence credible.                          On
    appeal, defendant now argues the completion of certain work,
    which was not performed, was a precondition for the release of
    the draw.        Thus, her obligation to pay was not triggered.                       We
    decline to consider this assertion, which was not raised before
    the trial judge.
    It is well-settled we "decline to consider questions or
    issues    not    properly    presented        to    the   trial    court    when       an
    opportunity for such a presentation is available 'unless the
    questions so raised on appeal go to the jurisdiction of the
    trial    court    or    concern   matters      of    great   public      interest.'"
    Nieder    v.    Royal    Indem.   Ins.   Co.,       
    62 N.J. 229
    ,   234     (1973)
    (quoting Reynolds Offset Co., Inc. v. Summer, 
    58 N.J. Super. 542
    , 548 (App. Div. 1959), certif. denied, 
    31 N.J. 554
    (1960)).
    See also Spinks v. Twp. of Clinton, 
    402 N.J. Super. 465
    , 479
    (App. Div. 2008), certif. denied, 
    197 N.J. 476
    (2009).
    Affirmed.
    18                                    A-0347-10T1