IN THE MATTER OF THE CERTIFICATE OF THE DEPARTMENT OF ENVIRONMENTAL PROTECTION GRANTING PARTIAL RELEASE OFCONSERVATION RESTRICTIONS(DEPARTMENT OF ENVIRONMENTAL PROTECTION, AND THE STATEHOUSE COMMISSION) ( 2017 )


Menu:
  •                      NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R.1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2316-10T2
    IN THE MATTER OF THE
    CERTIFICATE OF THE DEPARTMENT
    OF ENVIRONMENTAL PROTECTION
    GRANTING PARTIAL RELEASE OF
    CONSERVATION RESTRICTIONS.
    ______________________________
    Argued March 22, 2017 – Decided July 31, 2017
    Before Judges Simonelli, Carroll and Gooden
    Brown.
    On appeal from the New Jersey Department of
    Environmental Protection and the State House
    Commission, Docket No. SHC 1531003 (Amended).
    Renée   Steinhagen   argued  the   cause   for
    appellants Pinelands Preservation Alliance,
    New Jersey Conservation Foundation and New
    Jersey     Environmental    Lobby     (Eastern
    Environmental Law Center, and New Jersey
    Appleseed PILC, attorneys; Aaron Kleinbaum and
    Ms. Steinhagen, of counsel and on the briefs).
    Joan M. Scatton, Deputy Attorney General,
    argued the cause for respondents New Jersey
    Department of Environmental Protection and
    State   House  Commission   (Christopher  S.
    Porrino, Attorney General, attorney; Melissa
    Dutton Schaffer, Assistant Attorney General,
    of counsel; Ms. Scatton, on the brief).
    PER CURIAM
    In this matter, appellants Pinelands Preservation Alliance,
    New Jersey Conservation Foundation, and New Jersey Environmental
    Lobby     (collectively,       appellants)         opposed         the     proposed
    redevelopment of a closed and capped former landfill located in
    the Township of Stafford (Stafford) into a solar energy facility.
    There is a recorded conservation restriction on the property under
    the     Conservation     Restrictions        and       Historic        Preservation
    Restriction Act (Preservation Act), N.J.S.A. 13:8B-1 to -9.                          The
    Preservation Act prohibits the release of a recorded conservation
    restriction, in whole or in part, without approval and certificates
    issued   by   the   Commissioner     of    the   New    Jersey     Department        of
    Environmental Protection (DEP).            N.J.S.A. 13:8B-6.
    There are also restrictions on the property under the New
    Jersey Green Acres Land Acquisition and Recreation Opportunities
    Act (Green Acres Act), N.J.S.A. 13:8A-35 to -55, and Garden State
    Preservation Trust Act (GSPTA), N.J.S.A. 13:8C-1 to -42.                   Both the
    Green    Acres   Act   and   the   GSPTA    prohibit        property     held   by    a
    municipality     for   conservation       purposes     to    be   disposed      of   or
    diverted to another purpose without approvals by the Commissioner
    and   State   House    Commission    (SHC).        N.J.S.A.       13:8A-47(b)(1);
    N.J.S.A. 13:8C-32(b)(1).
    The GSPTA also prohibits the property from being conveyed for
    a use other than conservation purposes without the Commissioner's
    and the SHC's approvals.           N.J.S.A. 13:8C-32(b)(1).               The GSPTA
    further prohibits granting the approvals unless the municipality
    2                                     A-2316-10T2
    agrees to replace the property "with lands of equal or greater
    fair market value and of reasonably equivalent size, quality,
    location, and usefulness for . . . conservation purposes, as
    approved by the [C]ommissioner," or "pay an amount equal to or
    greater than the fair market value of the lands, as determined by
    the [SHC]."    Ibid.
    This appeal concerns the SHC's October 23, 2014 approval of
    Stafford's amended diversion application to lease a portion of the
    landfill   site    to   a   redeveloper   to   install   renewable    energy
    facilities, and DEP's December 1, 2015 approval and issuance of
    an   amended      certificate    granting      partial   release     of   the
    conservation restrictions to accommodate the project.                For the
    reasons that follow, we affirm.
    I.
    Stafford's Redevelopment Plan
    for the Stafford Business Park
    In 2005, Stafford adopted a redevelopment plan pursuant to
    the Local Redevelopment and Housing Law, N.J.S.A. 40A:12A-1 to -
    49, to construct the Stafford Business Park (Business Park), an
    approximately 370-acre mixed-use brownfield redevelopment project
    located within the Pinelands Regional Growth Area of the Pinelands
    National Reserve in Ocean County.         Stafford proposed commercial,
    residential, and government component uses on the site.
    3                               A-2316-10T2
    Two abandoned municipal landfills occupied portions of the
    site.     The Old Stafford Township Landfill (Old Landfill), which
    operated from 1958 to 1970, was located on approximately twenty-
    five acres on the eastern side of the proposed Business Park.
    Relevant here is the Stafford Township Landfill (Landfill), which
    operated from 1970 to 1983, and was located on approximately fifty-
    five acres on the western side of the proposed Business Park.
    In    2005,    both    landfills    were   still    leaching   hazardous
    chemicals into the surface waters and groundwater.             Pursuant to a
    redevelopment plan, Stafford proposed closing both landfills in
    accordance with the regulations governing landfill closure and
    post-closure       care    in   the   Pinelands,   N.J.A.C.   7:26-2A.9    and
    N.J.A.C. 7:50-6.75.         Specifically, Stafford proposed excavating
    and remediating all buried waste at the Old Landfill, reusing any
    non-hazardous waste to close the Landfill, and constructing an
    impermeable cap over the Landfill.
    Stafford engaged a redeveloper for the project, Walters Group
    (Walters), and submitted a redevelopment plan to the New Jersey
    Pinelands Commission (Pinelands Commission) for compliance review
    and approval under the Pinelands Comprehensive Management Plan
    (Pinelands CMP), N.J.A.C. 7:50-1.1 to -10.35.                 The Pinelands
    Commission     determined        that   Stafford's      landfill    plan   was
    inconsistent with the Pinelands CMP's minimum requirements for
    4                            A-2316-10T2
    wetland buffers (which are not at issue here), and threatened and
    endangered (T&E) plants and animal species, including the Northern
    Pine Snake (which are at issue here).
    To bring Stafford's plan into compliance with the Pinelands
    CMP, in 2006, the Pinelands Commission, Stafford, and Ocean County
    entered into a memorandum of agreement (the 2006 MOA).                 Section
    VI(A)(15)    required    Stafford    to:    (1)    execute    a   conservation
    restriction against future development so that the Landfill site
    of 59.593 acres and other open space areas remain undeveloped open
    space in perpetuity; (2) incorporate low impact design measures
    and green building design features and techniques throughout the
    Business Park; and (3) submit a species management plan designed
    and implemented to protect T&E species during the project and
    reestablish them afterwards on or near the site or at other
    appropriate   areas     designated   by    the    Pinelands   Commission    and
    NJDEP.
    In addition, in order to provide an equivalent level of
    protection of the Pinelands resources, Section VI(A)(14) required
    Stafford
    to purchase and deed restrict against future
    development at least 570 acres of land (at
    least three times the forested lands to be
    disturbed as a result of the implementation
    of the [c]losure and [r]edevelopment [p]lans)
    in the [f]orest [a]rea [of the Pinelands], a
    portion of which will be located within the
    5                                A-2316-10T2
    Mill Creek drainage area to offset for
    wetlands impacts, and the remainder of which
    will constitute suitable [Northern Pine Snake]
    habitat.
    The 2006 MOA also required Ocean County to purchase seventy-five
    acres of land that constituted suitable habitat for the Northern
    Pine Snake as part of its open space acquisition program.       The
    2006 MOA did not mention solar or any other renewable energy
    facilities or services.
    The Conservation Restriction
    As required by the 2006 MOA, on December 11, 2006, Stafford
    recorded a Declaration of Covenants and Restrictions, placing a
    conservation restriction on the portion of the Business Park that
    included the Landfill (the conservation restriction).   The stated
    purposes of the conservation restriction were:
    a.   that the [r]estricted [a]rea . . . be
    protected in its natural, scenic, open and
    existing state, in perpetuity, subject only
    to the specific rights reserved to [Stafford]
    herein;
    b.   that   the  natural features  of  the
    [r]estricted [a]rea shall be respected and
    preserved to the maximum extent consistent
    with [Stafford's] exercise of the rights
    expressly reserved to [Stafford] . . .
    [herein]; and
    c.   that the [r]estricted [a]rea be forever
    protected and preserved in its natural,
    scenic, open and existing state free from all
    activities that might damage, compromise or
    interfere with the ecological diversity,
    6                          A-2316-10T2
    natural beauty or resource quality, or with
    the natural processes occurring therein[.]
    The conservation restriction provided
    that [Stafford's] [p]roperty shall be held,
    transferred, sold, conveyed, leased and
    occupied subject to the following covenants,
    conditions,   obligations  and  restrictions
    hereafter set forth:
    1.   Except as specifically set forth
    herein, the [r]estricted [a]rea may not be
    developed in any manner whatsoever and shall
    remain in its natural condition. . . .
    . . . .
    2.   Notwithstanding    the    above,    the
    [r]estricted [a]rea may be disturbed solely to
    permit    the    construction,     installation,
    maintenance and repair of the following: (i)
    stormwater basins . . . ; (ii) the landfill cap;
    (iii) access roads . . . [;] and (iv) the
    proposed [fifteen foot] wide access road to the
    compost and chipping areas all in accordance
    with the terms of the [2006] MOA, the [c]losure
    [p]lans and such other plans as [may be]
    approved by []DEP and the [Pinelands] Commission
    and subject to compliance with applicable local,
    county,   state    and   federal   law,    rules,
    regulations and ordinances. . . .            Once
    implementation of the [c]losure [p]lans is
    completed, the [r]estricted [a]rea . . . shall
    be graded and revegetated with native Pinelands
    vegetation.
    3.   [Stafford],    for     itself,    its
    successors, transferees, or assignees, agrees
    to leave the [r]estricted [a]rea unmolested and
    in [its] natural state.
    7                            A-2316-10T2
    Under the conservation restriction, the Pinelands Commission had
    the right to determine the consistency of any activity or use for
    which the restriction made no express provision.
    Sometime    after      Stafford           recorded      the    conservation
    restriction, it accepted Green Acres funding for other projects
    in the township.      As a result of accepting this funding, the
    restricted area already encumbered by the conservation restriction
    also became encumbered with Green Acres restrictions and was
    characterized as "unfunded parkland" within Stafford's recreation
    and open space inventory.1
    By 2010, Walters had removed the hazardous contents of the
    Old Landfill, filled it, and developed it into a retail shopping
    center.   Walters had also closed and capped the Landfill.                Public
    funds were not used for either project.
    In   addition,   as   required       by    the   2006   MOA,   Walters   had
    developed, in conjunction with DEP and the Pinelands Commission,
    a seven-year species management plan under which: T&E plants were
    relocated from the landfills before they were disturbed; new
    habitat for the Northern Pine Snake was constructed; an extensive
    1
    Whenever a municipality accepts Green Acres funding, all land
    it holds for recreation and conservation purposes, even if such
    properties had not been acquired or developed with those funds,
    become encumbered with Green Acres restrictions. Cedar Cove, Inc.
    v. Stanzione, 
    122 N.J. 202
    , 205 (1991).
    8                                  A-2316-10T2
    snake monitoring program was implemented; and Stafford and Ocean
    County purchased and permanently preserved 1070 acres to offset
    the impacts to both T&E habitats and wetlands.              Further, pursuant
    to a settlement agreement in an unrelated action brought by the
    Pinelands Preservation Alliance, Walters agreed to pay $1 million
    for Stafford to purchase the offset land.
    Stafford's Lease with Walters
    Early in construction of the Business Park, Walters and
    Stafford began to consider using the Landfill and its adjoining
    lands     for    the   development      of    renewable   energy   facilities,
    including installation of solar panels and wind turbines.                Walters
    had already installed solar arrays on the rooftops of the retail
    facilities in the Business Park and affordable housing rental
    apartments, and had worked on Rutgers University's two-year wind
    resource study conducted on the Landfill and its adjoining lands.
    In    the    summer   and   fall    of    2010,   Stafford    and   Walters
    approached DEP and the Pinelands Commission to discuss a renewable
    energy proposal.        Stafford proposed to lease 46.8 acres of the
    Landfill to Walters for thirty years to construct, install, and
    operate a 6.5-megawatt, 1026-panel solar array to supply energy
    to the facilities in the Business Park.             In return, Walters would
    pay Stafford annual rent ranging from $65,000 to $150,000, along
    with a sixth- and eleventh-year escalator of ten percent.                     The
    9                               A-2316-10T2
    lease would also provide for two ten-year renewals, subject to
    Stafford's approval, and would allow Walters to explore future
    installation of four 1.5-megawatt wind turbines and methane gas
    production.
    During the discussions with the agencies, Walters submitted
    an August 2010 ecological assessment report prepared by Robert T.
    Zappalorti, Executive Director of Herpetological Associates, Inc.
    After reviewing the Landfill site, Zappalorti concluded that the
    construction, installation, and on-going operation of 1026 solar
    panels would be compatible with the wildlife on site.        He also
    concluded that the solar panels would not have any direct or
    secondary adverse impacts upon the Northern Pine Snake, tree frog,
    or two rare plant species known to occur in the vicinity of the
    Business Park and Landfill.
    Zappalorti explained that the proposed 1026 solar panels
    would be erected and positioned to run from east to west for
    optimal sunlight exposure.    Each panel would be about twenty-seven
    feet wide and sixteen feet long, and would sit on two concrete
    foundations that were fourteen feet long and two feet wide, with
    twenty feet between the rows of solar panels to allow for mowing
    grasses and general maintenance.      The low end of a panel would be
    about four feet above grade, and the high end would be about twelve
    feet above grade.   All connecting wires would run above ground and
    10                           A-2316-10T2
    overhead, and there would be no excavation into the soil on the
    Landfill surface.
    DEP approved an amendment to Stafford's landfill closure plan
    to allow for the development of renewable energy facilities on the
    Landfill. On September 27, 2010, Stafford held a "scoping hearing"
    on this proposed use, at which appellants and several members of
    the public voiced their objections.2
    Three days later, Stafford filed an application with DEP and
    the   SHC,   seeking   approvals   for   a   major   diversion   from   the
    conservation restriction to lease a portion of the Landfill to
    Walters for installation of renewable energy facilities to serve
    the Business Park.       Stafford also applied to the DEP for a
    certificate to partially release the conservation restriction.            On
    October 14, 2010, Stafford held a public hearing on its diversion
    application.    Appellants and several members of the public voiced
    their objections and submitted written comments.
    On November 7, 2010, DEP approved the diversion application
    and referred the matter to the SHC. DEP considered various factors
    for preserving the site in its natural state, including the
    project's public need and public benefit, environmental impact,
    2
    N.J.A.C. 7:36-26.8 requires a municipality to conduct a "scoping
    hearing" to solicit preliminary public comment before submitting
    an application to NJDEP for a major diversion of parkland.
    11                              A-2316-10T2
    and possible alternatives.        DEP also considered the oral and
    written public comments and finding of the Pinelands Commission,
    which advised that the solar project would not require a deviation
    from the Pinelands CMP.       DEP determined that the solar project
    would provide a variety of public needs and benefits; the diversion
    would have no irreparable impact on habitats for T&E plants and
    animals; and there were no feasible alternatives.
    As to public need and benefit, DEP noted that Stafford and
    Walters had been incorporating green buildings to reduce the
    redevelopment's impacts on the Pinelands. DEP stated: "The rooftop
    solar arrays already installed by Walters provide approximately
    30% of the energy needs for the retail stores they serve and nearly
    100% of the common area power needs for the affordable housing
    residents."      In addition, various agencies, including the Board
    of Public Utilities (BPU) and other DEP divisions, had encouraged
    Stafford and Walters to explore additional renewable energy uses
    on the Landfill.      Walters estimated that approximately seventy
    percent of the Business Park's energy needs could be provided by
    developing solar and wind facilities, and that the benefits of
    reducing   the    carbon   footprint    of   development   benefitted   the
    citizens of Stafford, Ocean County, and the State.
    DEP further noted that the level of renewable energy at a
    mixed use project of this scale was unprecedented, and Walters had
    12                              A-2316-10T2
    proved that sustainable building practices can be utilized in a
    cost effective manner.      Thus, DEP concluded that the environmental
    features of the redevelopment project were a direct benefit to
    Stafford and Ocean County, and the innovative design features were
    a model for other development in the region and State.
    As to environmental impacts, DEP stated that the 2006 MOA
    required Stafford and Walters to preserve at least 570 additional
    acres for Northern Pine Snakes and other T&E species; they had
    already   acquired    and   preserved       significantly       more     than     that
    acreage; and Walters had paid $700,000 of the $1 million settlement
    with the Pinelands Preservation Alliance.              DEP further noted that
    the   Pinelands    Commission    had    agreed    to     accept       approximately
    $153,000 as recompense for amending the 2006 MOA to allow the
    proposed solar use, and had not found the project would have any
    irreparable impact on the habitat for T&E species.                       Thus, DEP
    concluded that the diversion would not have any irreparable impact
    on habitats for T&E plants or animals, and               there was no need for
    additional mitigation or compensation to offset the diversion's
    anticipated environmental impacts.
    As to other alternatives, DEP first noted that the solar
    energy generated from the project was not proposed in the abstract;
    it would be used by end users within the Business Park.                      DEP then
    concurred   with    Stafford's    findings       that:    (1)     a    "no    action"
    13                                     A-2316-10T2
    alternative was not reasonable or feasible, since it would thwart
    Stafford's goal of maximizing the production of renewable energy
    to serve the Business Park; and (2) other alternatives were not
    reasonable   or   feasible   because   Walters   had   already   maximized
    rooftop space for solar installation, and because the only other
    available land for solar installation was part of the Garden State
    Parkway or restricted by the Pinelands Commission.
    Thus, based on the project's minimal environmental impact,
    the proposed generated lease revenue, the extensive mitigation
    compensation already associated with the redevelopment project,
    and the State's efforts to promote the use of capped landfills for
    solar energy generation, DEP concluded there were no feasible
    alternatives to building the project and           locating it on the
    Landfill.    DEP explained that even though the 2006 MOA never
    mentioned solar uses, if discussions about these uses had occurred
    when the parties discussed entering into the 2006 MOA, both the
    2006 MOA and the conservation restriction would most likely have
    allowed these uses to occur without any additional compensation
    to either Stafford or the Pinelands Commission.        Lastly, DEP noted
    that the lease renewals, use of wind turbines, and methane gas
    production were not part of its approval, and those proposals had
    to be resubmitted to DEP and the SHC for future review and
    approvals, as appropriate.
    14                               A-2316-10T2
    DEP provided a list of public benefits associated with the
    overall   redevelopment   project,      including    the   closure    of   both
    landfills    without   using    public      funds,    and    the     required
    environmental   mitigation     measures    and   conditions.         DEP   also
    provided its responses to the public comments. First, DEP rejected
    comments that the solar project did not meet the thresholds of
    N.J.A.C. 7:36-26.1(d)(1), which states an applicant must show that
    the proposed diversion is for a project that either will: (1)
    "[f]ulfill a compelling public need . . . by mitigating a hazard
    to the public health, safety or welfare;" or (2) "[y]ield a
    significant public benefit . . . by improving the delivery by the
    local government unit or nonprofit, or by an agent thereof, of
    essential services to the public or to a segment of the public
    having a special need[.]"      DEP declared:
    As   a    matter   of   longstanding    agency
    interpretation,     [DEP]    has     generally
    considered utility projects such as the
    proposed diversion to fall into the "public
    benefit" category. Although most electric and
    gas projects are not constructed by a local
    government unit or nonprofit, the provision
    of energy is an essential service, and both
    public and private utility companies provide
    a commodity that local governments would
    otherwise be required to provide (such as many
    municipalities still do for water and sewer
    services.)    Therefore, the fact that the
    project is sponsored by a private, for-profit
    enterprise has not in the past disqualified
    consideration of a diversion application.
    15                                  A-2316-10T2
    Second, DEP rejected comments that the solar project did not
    meet the threshold of N.J.A.C. 7:36-26.1(d)(2), which states that
    an applicant must show "that there is no feasible, reasonable and
    available     alternative"   to    the   diversion.     After   reviewing
    Stafford's alternatives analysis, DEP concurred that it would not
    be feasible to locate another site for this project outside the
    redevelopment area given the strict regulation of the surrounding
    area under the Pinelands CMP.
    Finally, DEP rejected comments that Stafford should have
    proposed replacement land for the diversion at a four-to-one
    replacement    ratio.    Compensation     standards    for   this   project
    involving a lease are found in N.J.A.C. 7:36-26.10(c)(2), which
    states only that DEP will assess "whether the compensation that
    the applicant proposes to receive for the lease or use agreement
    is fair and appropriate[,]" and "shall require that any payments,
    rentals or other consideration received by the applicant from the
    lease or agreement be used by the applicant for its operating,
    maintenance or capital expenses related to its funded parkland or
    to its recreation program as a whole[.]"          No land compensation is
    required in that standard.        DEP declared:
    Under N.J.A.C. 7:36-26.10(d)7, []DEP does have
    the ability to require additional compensation
    to address natural resource impacts or
    mitigate other adverse impacts associated with
    a proposed diversion or disposal.     However,
    16                              A-2316-10T2
    unlike the recent Tennessee Gas Pipeline
    transaction, in which the State requested
    replacement    land    for   the    subsurface
    installation of a natural gas pipeline that
    required blasting and trenching, this project
    involves the minimally obtrusive installation
    of solar panels on the surface of a capped
    landfill. At the end of the lease, it is not
    unreasonable to assume that the panels can be
    removed and the site restored to its pre-lease
    condition.    Therefore, the []DEP has not
    required    replacement    land    for    this
    application.
    As required by N.J.A.C. 7:36-26.10(c)2ii,
    [Stafford] will use the lease proceeds for its
    operating, maintenance or capital expenses
    related to its funded parkland or to its
    recreation program as a whole.
    On November 12, 2010, the Pinelands Commission, Ocean County,
    and Stafford agreed to amend the 2006 MOA to incorporate renewable
    energy facilities and allow Stafford's execution of a Restated and
    Amended    Declaration    of    Covenants    and    Restrictions   (the     2010
    amended    MOA).    The    2010    amended    MOA    altered,   among     other
    provisions, Section VI(A)(15) of the 2006 MOA to include the
    parties'    agreement    that    renewable    energy    facilities   on      the
    Landfill were permitted, except on storm water basins, on wetlands
    and buffers, and on approximately twenty acres that the County
    already had leased for composting facilities.
    The 2010 amended MOA also provided that
    [i]n order to ensure that there continues to
    be adequate measures provided to afford, at a
    minimum, an equivalent level of protection of
    17                                 A-2316-10T2
    the resources of the Pinelands, despite the
    [p]arties agreeing to permit the development
    of [r]enewable [e]nergy [f]acilities on the
    lot comprising the . . . Landfill . . .
    [Stafford] has obligated [Walters] to make a
    monetary contribution to the [Pinelands]
    Commission in the amount of $152,900.     This
    contribution   shall   be  utilized   by   the
    [Pinelands]   Commission   to   undertake   an
    assessment of the existing landfills located
    in the Pinelands [a]rea that have not, as yet,
    been closed[.]
    On November 19, 2010, appellants notified the SHC of their
    objection to the proposed diversion.           Appellants acknowledged
    that solar energy generation is a good thing, but mainly complained
    about the lack of replacement parkland to compensate for the
    diverted land.
    At its November 22, 2010           meeting, the SHC heard public
    comments on the proposed renewable energy project.             Stafford's
    administrator    stated   that   Stafford    had   no    replacement   land
    available to compensate for the diversion.         A representative from
    DEP said that no replacement land was required for diversions
    involving leases when the surface use can be removed at the end
    of the term and the site remains parkland.              At the end of the
    meeting, the SHC unanimously voted to approve Stafford's diversion
    application.
    On December 20, 2010, DEP issued a certificate granting
    partial release of the conservation restriction.          DEP acknowledged
    18                              A-2316-10T2
    its statutory duty to consider the public interest in preserving
    land in its natural state along with any comprehensive land use
    or development plan affecting the property.                     DEP noted that the
    property was not used for recreation of any kind and was restricted
    from general public access due to security concerns associated
    with the landfill cap, but was required by the 2006 MOA to be
    planted with grasses and allowed to revert to a natural state and
    remain undeveloped.             DEP further stated that the construction
    activities associated with the project consisted primarily of the
    installation of concrete footings on the Landfill surface and
    attachment of freestanding solar panels to the concrete footings.
    DEP also found that although the project required the use of
    surface       areas,    the     remainder    of     the    property    would    remain
    undeveloped.       DEP then limited the term of the partial release to
    thirty years.       Thus, for the same reasons DEP approved Stafford's
    diversion application, it determined it was in the public interest
    to    issue    a   certificate      approving        a    partial    release   of   the
    conservation restriction to allow the solar project.
    On January 11, 2011, Stafford recorded the DEP's certificate
    and    a   Restated       and    Amended         Declaration    of    Covenants     and
    Restrictions.          On January 24, 2011, Stafford and Walters signed
    the lease agreement.            Article VIII, Sections 8.4 to 8.6, covered
    compensation offsets. Section 8.4 stated that even though Stafford
    19                                 A-2316-10T2
    and Walters contended that no offset (by way of the purchase and
    restriction of land, the payment of money or other consideration)
    was due, Walters agreed to satisfy any offset that DEP imposed on
    Stafford. Section 8.5 stated that Walters agreed to pay a separate
    offset of $152,900 required by the Pinelands Commission.                Section
    8.6 stated that Walters agreed to pay, on Stafford's behalf, any
    other offset required by government agency or ordered by court.
    In all three sections, Walters reserved the right to challenge the
    offset in appropriate legal proceedings or cancel the lease.
    Initial Notice of Appeal
    Appellants appealed from the November 7, 2010 approval of
    Stafford's      diversion   application,    and    the   December      20,   2010
    certificate      granting    partial     release    of      the   conservation
    restriction.      While the appeal was pending, appellants moved to
    supplement the record with the certification of Emile DeVito of
    the New Jersey Conservation Foundation, who certified that he had
    walked on the Landfill in May 2012, and saw new T&E bird species.
    In an email that same month, Dave Jenkins, Chief of DEP's Division
    of   Fish   &   Wildlife,   Endangered     and    Nongame    Species    Program
    (Division), said the Division would try to verify sightings of the
    Northern Pine Snake on the Landfill.             Jenkins admitted that the
    Pinelands Commission had not consulted the Division before it
    signed the 2010 amended MOA, which allowed the solar project, and
    20                                   A-2316-10T2
    DEP had not consulted the Division before approving the diversion
    application.
    We remanded for DEP and the SHC to reconsider the appropriate
    replacement land for the changed use and the project's effect on
    T&E species and habitats.
    Proceedings on Remand
    By November 2012, Walters had constructed twelve percent of
    the   solar   project,   occupying      approximately   4.4    acres    of   the
    leasehold site.      That month, DEP found that a portion of its
    decisions,     specifically      allowing    Stafford   to     retain     lease
    proceeds, was inconsistent with N.J.S.A. 13:8C-32(b)(1), which
    requires a municipality: (1) to replace diverted parkland with
    lands of equal or greater market value and of reasonably equivalent
    size,   quality,    location,     and    usefulness   for     recreation     and
    conservation purposes; or (2) to pay an amount equal to or greater
    than the fair market value of that diverted land into the Garden
    State   Preservation     Trust    for    land   acquisition.        Thus,    DEP
    determined that Stafford had to amend its diversion application
    and seek a new certificate granting the partial release of the
    conservation restriction.
    On November 22,     2012, DEP executed a remand order that
    established    a   compliance    schedule    for   Stafford    to   amend    its
    diversion application. The order also directed Stafford to submit:
    21                              A-2316-10T2
    (1) a revised compensation proposal, reflecting substitution of
    proposed replacement land for lease payments; (2) information
    about the proposed replacement land; and (3) a report analyzing
    the merits of appellants' claim concerning irreversible impacts
    to T&E species.      On December 16, 2013, the SHC approved DEP's
    remand order.
    On December 11, 2013, Stafford submitted an amended diversion
    application to DEP and the SHC, and asked for approval of a smaller
    partial    release   of   the   conservation       restriction.     Stafford
    proposed reducing the size of the solar project from 46.8 acres
    to 33.86 acres.       Stafford also proposed compensating for the
    diversion with replacement land on a one-to-one acre ratio that
    would be deed restricted for use as parkland.                  Specifically,
    Stafford offered two non-contiguous unencumbered parcels located
    near a national wildlife refuge, totaling approximately 40.85
    acres     of   undeveloped   wooded        land   containing   wetlands   and
    accessible only via a local trail system.             Stafford claimed that
    the replacement land was unlike the Landfill site, where public
    access was inaccessible due to security concerns about the cap.
    Stafford's expert, Richard E. Hall, appraised the market
    value of the diverted land at $27,000, and the market value of the
    replacement land at $114,500.          Thus, Stafford asserted that its
    proposed replacement land was approximately 1.2 times the size of
    22                             A-2316-10T2
    the proposed diversion and 4.7 times the appraised market value.
    A DEP Appraisal Section supervisor subsequently determined, after
    reviewing Hall's appraisal, that the replacement land Stafford
    proposed satisfied the lot size and dollar value requirements
    representing an equitable exchange.
    Stafford also revised the lease with Walters to make rent
    payments a percentage of the cash flow earned from any portion of
    the solar project, and provide that Walters make a one-time rental
    payment of $114,377 (the appraised value of the replacement land).
    As the remand order required, Stafford also submitted a revised
    ecological assessment report Zappalorti prepared in November 2013,
    which analyzed the merits of appellants' claims concerning impacts
    to T&E species.   Zappalorti conducted a new habitat inspection and
    evaluation of the Landfill site, and concluded that installation
    of all of the proposed 1026 solar collection panels would not have
    an irreversible adverse impact upon habitats that are critical to
    the survival of the local population of any rare plant or wildlife
    species on the Business Park.          He stated there would be no
    excavation into the soil on the Landfill surface for any reason
    whatsoever, as digging could possibly rupture the capped lining.
    Zappalorti   also   concluded    that   the   inadvertently-created
    grasslands would only be partially disturbed by the installation
    of solar panels, and there would be minimal need to access the
    23                              A-2316-10T2
    panels or disturb the grassy habitat.     He noted that rare birds
    were breeding on the Landfill because Walters had agreed, at
    appellants' request, to plant more expensive and diverse grasses
    than Ocean County's soil conservation district specialists had
    required.     Zappalorti stated that if the Landfill was not mowed
    within three to five years, it would no longer be suitable for
    grassland birds.
    As for the Northern Pine Snake, Zappalorti found that the
    Landfill site was only suitable for foraging, and noted that two
    individual snakes had been confirmed foraging there.     The site,
    however, was not suitable for winter denning due to the limited
    depth of the cap liner, or for nesting due to dense grass and
    other vegetation.
    On February 10, 2014, Stafford held a public hearing and
    accepted written comments on the amended project.       Appellants
    submitted oral and written objections.      They also submitted a
    February 18, 2014 report from Joseph Zurovchak, Ph.D., an ecologist
    specializing in ornithology, who opined that installation of a
    solar array on the Landfill site would negatively impact local
    populations of grassland birds and render the existing habitat
    unsuitable.
    On August 25, 2014, Stafford submitted a revised alternatives
    analysis to DEP.      Stafford analyzed a "no action" alternative
    24                         A-2316-10T2
    along with placing the project at other locations in and adjacent
    to the Business Park and farther. Based on that analysis, Stafford
    concluded   there   were   no   feasible,   reasonable,    or    available
    alternatives for meeting the essential purpose of the proposed
    solar project.      Stafford determined that the Landfill site was
    still the most logical and only appropriate and reasonable location
    for the planned renewable energy facilities.            Stafford further
    noted that, as a State regulatory matter, solar facilities had to
    be on-site or adjacent to their end users in order to qualify for
    financial incentives making them economically feasible.           The cost
    to extend off-site renewable energy infrastructure to the Business
    Park would be prohibitive.      Stafford also submitted a summary of
    the submitted public comments and Stafford's responses.
    Approval of the Amended Diversion Application
    and Issuance of the Amended Certificate Granting
    Partial Release of Conservation Restrictions
    On October 1, 2014, DEP approved Stafford's amended diversion
    application and referred the matter to the SHC. In an accompanying
    memorandum, Judeth Piccinini Yeany, Chief of DEP's Bureau of Legal
    Services and Stewardship, Green Acres Program, detailed DEP's
    reasons   for   recommending    approval    of   the   amended   diversion
    application.
    First, DEP found that the two wooded parcels Stafford offered
    as replacement lands were reasonably equivalent as appropriate
    25                              A-2316-10T2
    replacements for a partial diversion of the Landfill's grasslands.
    DEP determined that those parcels were in a location that would
    be accessible to the public, in close proximity to other preserved
    lands, and in an area already serving as habitat for T&E species.
    DEP acknowledged that the replacement lands did not provide the
    exact grassland characteristics that the proposed diversion area
    was alleged to possess, but concluded the proposed replacement
    lands were ecologically significant in their own right.         DEP
    believed the replacement lands provided breeding and foraging
    habitat for various birds and the Northern Pine Snake.
    DEP further explained that its use of a one-to-one land
    replacement ratio based on value and size was
    consistent with the statutory standard at
    N.J.S.A. 13:8C-32(b)(1) (which does not
    specify a replacement ratio greater than 1:1),
    the policy objectives of N.J.A.C. 7:36-
    26.10(c)(2)(ii) (which were intended to take
    into account the fact that leases of parkland
    do not involve permanent conveyances of
    property interests), and the fact that the
    parkland interest at issue in this application
    is   a    partial    interest    (conservation
    restriction) and not a full fee interest.
    Second, based on its review of Zappalorti's November 2013
    report on T&E species, the information appellants provided, and
    its own site visit, DEP concluded that impact to T&E species was
    not a reason to deny Stafford's amended diversion application.
    DEP noted that the following factors weighed against any denial:
    26                          A-2316-10T2
    (1) Walters had based the original project siting and investment
    decisions on the requirements in the 2006 MOA and 2010 amended MOA
    to protect the four known T&E species at the site; (2) Walters and
    Stafford had reduced the proposed diversion area; (3) Walters
    originally had agreed, at appellants' request, to plant more
    expensive and diverse grasses on the Landfill than were present
    and would otherwise have been required; (4) Stafford and Walters
    had a continuing obligation under the 2010 amended MOA to contact
    the Pinelands Commission and DEP if they encountered any new T&E
    species; and (5) the solar project would benefit the public.
    Although appellants allegedly had sighted T&E birds, DEP found no
    evidence that these bird species were observed during Walters'
    initial construction phase of the solar project.
    Further, DEP noted that, as part of the redevelopment project,
    Stafford, Walters, and Ocean County already had offset impacts to
    T&E    species   and   their   habitats    by:   (1)   deed   restricting
    approximately 1017 acres of land, despite only 645 being required
    by    the   Redevelopment   Project    agreement;   (2)   Walters    paying
    approximately $836,000 to the New Jersey Natural Lands Trust for
    land preservation; and (3) Walters paying $153,000 to the Pinelands
    Commission, on behalf of Stafford, to fund a study of existing
    unclosed landfills within the Pinelands Area in order to determine
    the continuing environmental impacts associated with them and the
    27                            A-2316-10T2
    appropriate means of closure to ameliorate those impacts.                  Thus,
    balancing the equities of the amended diversion application and
    exercising its discretion, DEP decided not to deny Stafford's
    application on the basis of T&E impacts.
    Prior to the SHC's meeting on October 23, 2014, Stafford and
    Walters signed a first addendum to the lease incorporating their
    revised changes.       At the meeting, Yeany explained why DEP had
    rejected the public's demand for a four-to-one compensation ratio
    of diverted land to replacement land required for a                   private
    diversion.    She declared that the solar project involved a lease,
    not a permanent fee taking, and was part of a hybrid public-private
    partnership involving a larger redevelopment project.              She stated:
    "This category of projects really then fell through the cracks and
    really     wasn't   covered     by   our   rules     [on   replacement       land
    compensation for a major diversion]."               She concluded that the
    solar project only required a one-to-one ratio for replacement
    land, pursuant to the requirements in N.J.S.A. 13:8C-32(b)(1).
    Yeany also explained that the Green Acres Program would not
    supersede    the    Pinelands    Commission's      approval   of   the     solar
    project.    The Pinelands Commission had its own endangered species
    office, and had provided for mitigation of impacts on T&E species
    in the 2006 MOA and 2010 amended MOA.              On October 23, 2014, SHC
    approved Stafford's amended diversion application.
    28                                 A-2316-10T2
    On   December   1,   2015,   DEP    issued   an   amended   certificate
    granting a partial release of the conservation restrictions.              DEP
    incorporated the analysis and findings set forth in the original
    November 7, 2010 diversion approval, and again acknowledged its
    statutory duty to consider the public interest in preserving land
    in its natural state along with any comprehensive land use or
    development plan affecting the property.               DEP also noted that
    Stafford had amended the project by reducing the diversion area
    to approximately thirty-four acres, offered approximately forty
    acres of replacement land for the diverted area, and accepted
    revised financial terms for the underlying lease. DEP also noted
    that the Pinelands Commission had approved the 2010 amended MOA,
    in exchange for additional mitigation measures, and that the SHC
    had approved Stafford's amended diversion application.
    DEP again noted that the Landfill site was not used for
    recreation of any kind, and was restricted from general public
    access due to security concerns associated with the cap, but was
    required by the 2006 MOA to be planted with grasses, allowed to
    revert to a natural state and remain undeveloped.           DEP stated that
    the construction activities associated with the solar project
    consisted primarily of the installation of concrete footings on
    the former landfill surface and the attachment of freestanding
    solar panels to the concrete footings.                 DEP also found that
    29                               A-2316-10T2
    although the project required the use of surface areas, the
    remainder of the property would remain undeveloped.             Thus, for the
    same reasons DEP had approved Stafford's original and then amended
    diversion   applications,       DEP   determined   it    was   in    the    public
    interest to issue an amended certificate approving a partial
    release    of   the    conservation   restrictions      to   allow   the     solar
    project.
    II.
    Appellants contend that DEP's decision to partially release
    the conservation restriction was not in accordance with the law
    because DEP failed to consider the public's interest and the
    decision conflicts with the requirements of the Pinelands CMP.
    Our role in reviewing an administrative agency's decision is
    limited. Pub. Serv. Elec. & Gas Co. v. N.J. Dep't of Envtl. Prot.,
    
    101 N.J. 95
    , 103 (1985). We will not reverse the agency's decision
    unless: (1) it was arbitrary, capricious, or unreasonable; (2) it
    violated express or implied legislative policies; (3) it offended
    the State or Federal Constitution; or (4) the findings on which
    it was based were not supported by substantial, credible evidence
    in the record.        Univ. Cottage Club of Princeton N.J. Corp. v. N.J.
    Dep't of Envtl. Prot., 
    191 N.J. 38
    , 48-49 (2007).
    "In reviewing an administrative agency's decision, we will
    grant considerable deference to the agency's expertise, where such
    30                                   A-2316-10T2
    expertise is a relevant factor."         In re Petition of S. Jersey Gas
    Co., 
    447 N.J. Super. 459
    , 480 (App. Div. 2016).                We "may not
    second-guess those judgments of an administrative agency which
    fall squarely within the agency's expertise."                 In re Stream
    Encroachment Permit No. 0200-04-0002.1 FHA, 
    402 N.J. Super. 587
    ,
    597 (App. Div. 2008).
    "Ordinarily, DEP is given great deference when it applies its
    considerable expertise and experience to the difficult balance
    between development and conservation." 
    Ibid.
     (citations omitted).
    "However, '[w]hile we must defer to the agency's expertise, we
    need not surrender to it.'"    Pinelands Pres. All. v. State, Dep't
    of Envtl. Prot., 
    436 N.J. Super. 510
    , 524 (App. Div.) (citation
    omitted), certif. denied, 
    220 N.J. 40
     (2014).                "The party who
    challenges DEP's decision to permit development of a certain
    location has the burden of demonstrating, not that the agencies'
    action was merely erroneous, but that it was arbitrary."              Stream
    Encroachment Permit, 
    supra,
     
    402 N.J. Super. at 597
     (citations
    omitted).
    Furthermore, although we "must give deference to the agency's
    findings of facts, and some deference to its 'interpretation of
    statutes and regulations within its implementing and enforcing
    responsibility,'   we   are   'in   no    way   bound   by    the   agency's
    interpretation of a statute or its determination of a strictly
    31                               A-2316-10T2
    legal issue.'"      Utley v. Bd. of Review, Dep't of Labor, 
    194 N.J. 534
    , 551 (2008) (citations omitted). Applying the above standards,
    we discern no reason to disturb DEP's and the SHC's decisions.
    The Public Interest
    Appellants argue that DEP violated N.J.S.A. 13:8B-5 and -6
    by   failing   to   adequately   consider   the   public's   interest    in
    preserving the Landfill in its natural state in perpetuity, which
    was one of the conditions imposed in the conservation restriction.
    Appellants aver that DEP never discussed the public's interest in
    preserving the Landfill as open space for the local plants and
    wildlife, and it was not enough to find that the Landfill would
    be a convenient location for the solar project.
    The Preservation Act generally "authorizes the assignment of
    conservation restrictions . . . to insure that the land governed
    by the restrictions will be maintained in its natural integrity."
    Vill. of Ridgewood v. Bolger Found., 
    104 N.J. 337
    , 343 (1986).
    The Preservation Act provides the only statutory mechanism for a
    conservation restriction to be released, removed, or altered:
    A conservation restriction . . . may be
    released in whole or in part, by the holder
    thereof, for such consideration, if any, as
    the holder may determine, in the same manner
    as the holder may dispose of other interests
    in land, subject to such conditions as may
    have been imposed at the time of creation of
    the restriction . . . .
    32                             A-2316-10T2
    [N.J.S.A. 13:8B-5.]
    The statute does not bar the holder of a conservation restriction
    from ever releasing it.
    In addition, N.J.S.A. 13:8B-6 provides as follows:
    The provisions of [N.J.S.A. 13:8B-5]
    notwithstanding, no conservation restriction
    acquired pursuant to this act shall be
    released   without   the   approval   of   the
    Commissioner of [DEP]. Approval of releases
    shall be evidenced by certificates of the
    Commissioner of [DEP] and shall be recorded
    in the same manner as the restriction itself.
    In determining whether the release should be
    approved, the Commissioner of [DEP] shall take
    into consideration the public interest in
    preserving these lands in their natural state,
    and any State, regional or local program in
    furtherance thereof, as well as any State,
    regional or local comprehensive land use or
    development plan affecting such property.
    It is clear from the plain language in the statute that the
    Legislature intended to establish a process for allowing recorded
    conservation restrictions, even those to be held in perpetuity,
    to be released or modified after their creation.            Thus, DEP did
    not   violate   the   Preservation   Act   by   partially   releasing   the
    conservation restriction, even though the restriction was created
    with the intention of preserving the Landfill in its natural state
    in perpetuity.
    In evaluating and determining whether to approve a diversion
    application, as part of its analysis, DEP must weigh the competing
    33                            A-2316-10T2
    public   interests   presented   by   the   proposed   diversion   against
    preservation of the parkland in its natural state.          See N.J.S.A.
    13:8B-6; N.J.A.C. 7:36-26.1(d)(1).
    Here, DEP considered the public's interests in preserving the
    Landfill as open space when it balanced the public benefits and
    needs for a solar project to power the Business Park's facilities
    against the fact that most of the leased area would remain in its
    natural state.   DEP explained how the solar project would yield
    significant public benefit in the form of renewable energy for a
    public redevelopment project.         The solar project will generate
    approximately 6.5 megawatts of new solar energy on the now-capped
    surface of the Landfill, increasing renewable energy to a mixed
    use brownfield redevelopment site that includes residential and
    retail development, as well as public administration buildings.
    As DEP explained in its approval of Stafford's original diversion
    application, approximately 70% of the energy needs for the entire
    redevelopment project can be provided through renewable energy if
    the proposed diversion and the future wind phase were approved.
    We are satisfied that DEP amply considered the public's interest
    in granting the partial release of the conservation restriction.
    The DEP acted well within its authority and appropriately applied
    its expertise in determining that the solar project yields a
    34                               A-2316-10T2
    significant      public     benefit    through      provision       of    essential
    services.
    The Pinelands CMP
    Appellants     argue     that    DEP   violated    N.J.S.A.         13:8B-6    by
    failing     to   properly     consider      the    expected     effect      on     the
    comprehensive land use protections of the Pinelands CMP and the
    T&E plant and animal species disrupted by development of the
    Business Park.       Appellants also argue that DEP's approval and
    amended     certificate      partially       releasing    the        conservation
    restrictions were based on the Pinelands Commission's illegal
    decision to accept $153,000 from Walters, as required by the 2010
    amended MOA, without requiring mitigation involving replacement
    property    in   return,    as   mandated    by    N.J.A.C.    7:50-4.52(c)(2).
    Appellants posit that Walters' monetary payments to the Pinelands
    Commission did not satisfy the Pinelands CMP's minimum standards,
    as   it    did   nothing    to   address     the    habitat     loss      from     the
    redevelopment      plan,     which    had    justified        the    conservation
    restriction in the first place.              Appellants also aver that on
    remand, DEP erred by not revisiting its choice to rely on the 2010
    amended MOA and the Pinelands Commission's finding that the solar
    project would not irreparably harm the Pinelands and T&E species.
    N.J.A.C. 7:50-4.52(c)(2) authorizes the Pinelands Commission
    to enter into an intergovernmental memoranda of agreement provided
    35                                    A-2316-10T2
    that any variation from the minimum Pinelands CMP standards "is
    accompanied      by    measures   that      will,    at   a   minimum,    afford    an
    equivalent level of protection of the resources of the Pinelands
    than would be provided through strict application of the [Pinelands
    CMP]   standards[.]"        There     are     no    measures    specified    in    the
    regulation.
    Here, DEP's choice to rely on the Pinelands Commission's
    decisions and the resulting 2006 MOA and 2010 amended MOA allowing
    renewable energy development projects on the Landfill was not
    arbitrary, capricious, or unreasonable.                   No one challenged the
    validity of the Pinelands Commission's decisions or the two MOAs,
    and the time to appeal them has long passed.
    In any event, neither the GSPTA nor DEP's regulations preclude
    DEP from approving a diversion due to the presence of, or potential
    impact on, T&E habitat.           DEP's regulations authorize, but do not
    require, the denial of a diversion application due to T&E species
    concerns.   See N.J.A.C. 7:36-26.1(e).              In the initial application,
    DEP appropriately relied on the Pineland Commission's findings
    about the solar project and ultimate agreement to amend the 2006
    MOA.     DEP's    reliance      was   appropriate         because   the   Pinelands
    Commission is charged with ensuring that the minimum standards,
    goals, and objectives of the Pinelands CMP are implemented and
    enforced,   and       because   DEP   and     the   Pinelands    Commission       have
    36                                  A-2316-10T2
    concurrent authority with respect to T&E species protection within
    the Pinelands.    See N.J.S.A. 13:18A-4; In re N.J. Pinelands Comm'n
    Resolution PC 4-00-89, 
    356 N.J. Super. 363
    , 377 (App. Div.),
    certif. denied, 
    176 N.J. 281
     (2003).
    The record shows that before DEP's initial decision to approve
    Stafford's     diversion    application,      the   Pinelands     Commission
    reviewed the proposed solar project with regard to its conformance
    with   the   requirements    of   the   Pinelands   CMP.    The   Pinelands
    Commission concluded that the solar project was consistent with
    the Pinelands CMP and agreed to amend the 2006 MOA to allow the
    project to proceed.        DEP appropriately considered the Pinelands
    Commission's    analysis    and   similarly   concluded    that   the   solar
    project would not have any irreparable impact on T&E species.             The
    DEP's decision to partially release the conservation restriction
    complied with the law, is supported by ample credible evidence in
    the record, and is not arbitrary, capricious, or unreasonable.
    III.
    Appellants argue that DEP's diversion decision subverts the
    requirements of the Green Acres Act and the GSPTA because DEP
    failed to prevent the net loss of parkland, as required by N.J.S.A.
    13:8C-32(b) (GSPTA), and N.J.A.C. 7:36-26.10(b) (Green Acres).
    Appellants also argue that DEP subverted the requirements of
    N.J.A.C. 7:36-26.1 and N.J.A.C. 7:36-26.10 and the GSPTA by failing
    37                               A-2316-10T2
    to require replacement lands on a four-to-one ratio, and require
    reasonably equivalent replacement property.                   Appellants further
    argue that DEP's finding of "ecologically significant" as it
    related to the two parcels Stafford proposed as replacement land
    does not satisfy N.J.A.C. 7:36-26.10(d).3
    Replacement Land Ratio
    Appellants argue that N.J.S.A. 13:8C-32(b)(1) applies to
    property     that    will   be    "convey[ed]"     to   a    use   for     other   than
    conservation purposes, and the term "convey" is defined in N.J.A.C.
    7:36-2.1 to mean "sell, donate, exchange, transfer, or lease for
    a   term     of     [twenty-five]        years    or    more."        Because       the
    Stafford/Walters lease term was thirty years, appellants posit
    that   the    four-to-one        ratio   applicable     to    a    major    diversion
    involving a fee simple conveyance of parkland in Table 1 of
    N.J.A.C. 7:36-26.10(g) also applies to Stafford's lease.                     In other
    words, they argue that a thirty-year lease is not a temporary
    conveyance, but a major diversion.               Appellants further claim that
    3
    We decline to address appellants' additional argument relating
    to Stafford's use of Walters' lease payments based on a purported
    October 14, 2014 memorandum of understanding between Stafford and
    Walters.   The document is not listed in the statement of items
    comprising the record on appeal, and there is no indication that
    DEP or the SHC considered it. R. 2:5-4; see also N.J. Div. of
    Youth & Family Servs. v. M.M., 
    189 N.J. 261
    , 278 (2007) (holding
    that we will not consider documents included in the appendix that
    were not presented below).
    38                                  A-2316-10T2
    Stafford's solar project is a private commercial endeavor that is
    paid for, constructed by, and therefore sponsored by, Walters.
    Accordingly, they conclude that even if the lease was considered
    only as a surface easement over parkland, a four-to-one ratio of
    replacement land would be required.
    Both the Green Acres Act, N.J.S.A. 13:8A-47(b)(1), and the
    GSPTA, N.J.S.A. 13:8C-32(b)(1), provide that property held for
    recreation and conservation purposes cannot be diverted to another
    use without DEP's and the SHC's approval.    The Green Acres Act,
    N.J.S.A. 13:8A-47, does not require any replacement lands to offset
    diverted parkland.   However, the GSPTA provides as follows:
    Approval of the commissioner and the [SHC]
    shall not be given unless the local government
    unit agrees to (a) replace the lands with
    lands of equal or greater fair market value
    and of reasonably equivalent size, quality,
    location, and usefulness for recreation and
    conservation purposes, as approved by the
    commissioner, or (b) pay an amount equal to
    or greater than the fair market value of the
    lands, as determined by the commission, into
    the Garden State Green Acres Preservation
    Trust Fund.
    [N.J.S.A. 13:8C-32(b)(1) (emphasis added).]
    Thus, N.J.S.A. 13:8C-32(b)(1) establishes a minimum one-to-one
    ratio for replacement lands.
    The Green Acres regulations set forth the standards and
    procedures for DEP's and the SHC's approval of the disposal or
    39                           A-2316-10T2
    diversion       of   funded   or   unfunded   parkland.      N.J.A.C.     7:36-
    26.1(d)(3) states that an "applicant shall compensate for the
    disposal or diversion of funded or unfunded parkland with eligible
    replacement land . . . in accordance with . . . N.J.A.C. 7:36-
    26.10[.]"
    N.J.A.C. 7:36-26.10(g) contains a table showing the minimum
    ratio of replacement land for diversions (Table 1).                   Table 1
    establishes different replacement ratios for different types of
    major diversions, i.e., easements versus full fee interests, and
    for different types of project sponsors, i.e., public project
    sponsors versus private project sponsors.           For example, diversions
    involving public project sponsors require a two-to-one ratio of
    replacement land, whereas diversions involving private project
    sponsors require a four-to-one ratio.            When the diversion involves
    only a surface easement over parkland, public project sponsors
    require    a    one-to-one    ratio,   whereas    private   project   sponsors
    require a four-to-one ratio.           The term "sponsor" is not defined.
    However,
    the term "public" used in reference to a
    diversion or disposal denotes that the project
    for which the diversion or disposal is
    proposed is constructed by or sponsored by a
    public entity; and the term "private" used in
    reference to a diversion or disposal denotes
    that the project for which the diversion or
    disposal is proposed is not constructed by or
    sponsored   by   a   public   entity.      The
    40                               A-2316-10T2
    classification of a diversion or disposal as
    public or private shall be determined by Green
    Acres based on the pre-application information
    provided by the applicant.
    [N.J.A.C. 7:36-26.10(h).]
    Because the solar project was in the form of a lease, the
    amount of replacement land was not subject to any minimum acreage
    requirements     in   Table    1.     Thus,   only     the   GSPTA's      statutory
    requirement in N.J.S.A. 13:8C-32(b)(1), that replacement lands
    should be of equal value and of reasonably equivalent size to the
    diverted land, applied to the solar project.                     Further, N.J.A.C.
    7:36-26.10(c)(2)(ii), which covers leases of encumbered parkland,
    does not require any amount of replacement land as compensation
    for these temporary conveyances.
    Accordingly, the DEP's decision to require a one-to-one ratio
    was consistent with N.J.S.A. 13:8C-32(b)(1); the policy objectives
    of N.J.A.C. 7:36-26.10(c)(2)(ii); and the fact that the parkland
    interest    at   issue    in   the    Stafford/Walters       lease    would   be    a
    temporary, partial leasehold, and not a full fee interest.                       The
    lease arose from the larger redevelopment project, making the
    parties' relationship "a hybrid" of public and private sponsors.
    Further,     Table    1   does    not   set   any    ratio     for   temporary
    easements    over     parkland   diverted     to   a     solar    project   from    a
    conservation restriction, and N.J.A.C. 7:36-26.10 is silent on
    41                                  A-2316-10T2
    using replacement land for "a diversion of parkland that entails
    a lease or use agreement[.]"              Thus, we rely on N.J.S.A. 13:8C-
    32(b)(1), which allows replacement lands "of reasonably equivalent
    size" to offset a diversion.               The statute does not require a
    replacement ratio greater that one-to-one.
    Reasonably Equivalent Replacement Property
    Appellants     argue     that       DEP's   finding   of   "ecologically
    significant" as it related to the two parcels Stafford proposed
    as   replacement    land     does   not    satisfy   N.J.A.C.    7:36-26.10(d).
    Appellants posit that the replacement and diverted lands have
    fundamentally different habitat types and cannot compensate for
    the loss of habitat and species from the proposed major diversion.
    N.J.S.A. 13:8C-32(b)(1) provides that replacement lands shall
    be "lands of equal or greater fair market value and of reasonably
    equivalent size, quality, location, and usefulness for . . .
    conservation purposes[.]"             N.J.A.C. 7:36-26.10(d) provides as
    follows, in pertinent part:
    Replacement   land   proposed    by   the
    applicant as compensation for a major disposal
    or diversion of parkland shall meet the
    following requirements:
    . . . .
    5.   For  applications   proposing
    replacement land as the only form of
    compensation, the proposed replacement
    land shall have a market value that is
    42                            A-2316-10T2
    equal to or greater than the parkland
    proposed for disposal or diversion;
    6.   The proposed replacement land
    shall be of reasonably equivalent or
    superior quality to the parkland proposed
    for disposal or diversion, including, but
    not limited to, location, accessibility,
    usefulness for recreation purposes, and
    value for ecological, natural resource
    and conservation purposes. . . ;
    7.   If the proposed replacement
    land is inadequate to meet the criteria
    in (d)5 and 6 above, the Department shall
    require the applicant to supplement its
    proposal with additional compensation in
    excess of that which would otherwise be
    required under Table 1 at (g) below.
    Such additional compensation may consist
    of either additional replacement land or
    monetary compensation, or both, and the
    amount of such compensation must be
    sufficient to compensate in full for any
    shortfalls in the market value or quality
    of the proposed replacement land[.]
    Even   if   Stafford's   proposed   replacement   lands   do   not
    precisely meet the standards in N.J.A.C. 7:36-26.10(d)(6) because
    they are wooded and not grasslands, DEP found that the replacement
    lands would provide breeding and foraging habitat for various T&E
    birds and the Northern Pine Snake.       Accordingly, DEP concluded,
    correctly, that the proposed replacement lands were reasonably
    equivalent to the lands proposed for diversion in terms of value
    for ecological, natural resource, and conservation purposes.        DEP
    also found that those parcels were already serving as habitat for
    43                            A-2316-10T2
    T&E species, and there was no evidence to support the claim that
    those   parcels    would    not   support    the    additional    T&E   species
    appellants found on the Landfill during the remand.               Furthermore,
    market value of the replacement lands was appraised approximately
    4.7 times higher than the market value of the diverted land. Thus,
    there is sufficient evidence that Stafford's replacement lands met
    the requirements in N.J.A.C. 7:36-26.10(d)(7).              Deferring to DEP's
    expertise, we do not find its assessment arbitrary, capricious,
    or unreasonable.
    IV.
    Appellants contend the DEP's failure to comply with its own
    diversion rules renders its decision arbitrary, capricious, and
    unreasonable      because   there   was     no     evidence    supporting    its
    conclusions on: (1) public benefits and needs for a solar energy
    facility; (2) the lack of irreparable harm to T&E species on the
    Landfill; and (3) no available feasible alternatives.
    Public Benefits and Needs
    Appellants     argue   there   was     no   evidence     supporting    DEP's
    conclusion that the solar project would fulfill a compelling public
    need or yield a significant public benefit by improving Stafford's
    delivery of essential services to the public or to any segment of
    the public having a special need, as required by N.J.A.C. 7:36-
    26.1.   Appellants claim that Stafford provides no electricity to
    44                                 A-2316-10T2
    its residents and that its receipt of Walters' lease payments is
    no indication that any of the essential services it already
    provides will be improved.    Appellants also aver there is no
    evidence to support DEP's assertion that a solar panel facility
    will reduce the carbon footprint of the Business Park.
    N.J.A.C. 7:36-26.1 provides as follows:
    (a) It is the Department's policy to strongly
    discourage the disposal or diversion of both
    funded and unfunded parkland.      The use of
    parkland for other than recreation and
    conservation purposes should be a last resort,
    and should only be considered by a local
    government unit or nonprofit when the proposed
    disposal or diversion is necessary for a
    project that would satisfy a compelling public
    need or yield a significant public benefit as
    defined at (d)1 below.
    . . . .
    (d) No application for the disposal or
    diversion of parkland under this subchapter
    shall be approved by the Commissioner and the
    State House Commission unless the applicant
    . . . meets the following minimum substantive
    criteria:
    1.   The . . . diversion of funded or
    unfunded parkland is for a project that will:
    i.   Fulfill a compelling public
    need, as demonstrated by the applicant
    . . . by mitigating a hazard to the public
    health, safety or welfare; [or]
    ii. Yield a significant public
    benefit, as demonstrated by the applicant
    . . . by improving the delivery by the
    local government unit . . . or by an agent
    45                           A-2316-10T2
    thereof, of essential services to the
    public or to a segment of the public
    having a special need[.]
    [(Emphasis added).]
    Even though "[i]t is [DEP's] policy to strongly discourage
    the disposal or diversion of both funded and unfunded parkland[,]"
    N.J.A.C. 7:36-26.1(a), neither the GSPTA nor the Green Acres Act
    place   an    absolute     ban   on    diverting       land   encumbered         by     a
    conservation or Green Acres restriction to a use other than
    recreation     or   conservation.           Furthermore,      nothing     in     those
    statutory or regulatory schemes prohibits DEP or the SHC from
    approving a diversion of encumbered parkland for solar energy
    purposes.     In fact, N.J.A.C. 7:50-5.36(a) of the Pinelands CMP
    states that "[a] municipality may include in its master plan and
    land use ordinance provisions . . . solar energy facilities as a
    principal use in any Pinelands management area[.]"
    The Legislature has defined "essential services" to mean the
    adequate supply of "heat, water, hot water, electricity, gas, and
    telephone service."        See, e.g., N.J.S.A. 52:27D-224.2 (defining
    essential     services   in    the    context    of    multiple    dwellings          and
    requiring notification when essential services are disrupted).
    Here,   DEP    concluded      that    the    solar    project     would   yield         a
    significant public benefit in the form of renewable energy for the
    commercial,     residential,     and    public       buildings    in    its     public
    46                                     A-2316-10T2
    redevelopment project, and solar energy was already being produced
    at the Business Park.          DEP's findings are entitled to considerable
    deference given its expertise in environmental matters.
    T&E Species
    Appellants      argue     that    DEP    erred    by    only    relying      on
    Zappalorti's reports and not consulting with DEP's Endangered and
    Nongame Species Program before approving the diversion, and by not
    obtaining a redetermination by the Pinelands Commission after
    Stafford revised its diversion application.                   Appellants further
    object to Yeany's weighing of the impact to T&E species, instead
    of having the Green Acres Program directly apply the Pinelands
    CMP's T&E regulatory standards to the changed circumstances on the
    Landfill site, and the new T&E species living there.
    Because we afford DEP's considerable expertise and experience
    great    deference     when     balancing      development     and    conservation
    determinations, we reject appellants' arguments.                   Furthermore, as
    we have previously stated, the Pinelands Commission bears the
    ultimate    responsibility        for    enforcing      the   provisions     of   the
    Pinelands Act and the CMP requirements.               Petition of S. Jersey Gas
    Co.,    supra,   447   N.J.     Super.   at    476.      Because     the   Pinelands
    Commission had approved the 2006 MOA to allow a larger project
    proposing renewable energy facilities on the capped Landfill, it
    47                                  A-2316-10T2
    is doubtful the Pinelands Commission would not have approved a
    project proposing the use of less acreage of the capped Landfill.
    Lastly, the evidence amply supports a finding that new T&E
    bird species had already arrived on the Landfill due to the
    enhanced   grasses   Walters   planted.       Since    Walters   also   had
    constructed   twelve   percent   of    the   solar    project,   occupying
    approximately 4.4 acres of the Landfill, the evidence supports
    DEP's conclusion that there would be no irreparable harm from the
    solar project to the T&E species on the Landfill.           Furthermore,
    the evidence supports a finding that those species would leave
    within three to five years if the grasslands were not maintained
    and mowed, as would happen if the diversion for the solar project
    was not approved.
    Feasible Alternatives
    Appellants argue that Stafford never reviewed making the
    project even smaller, and never provided a description of the
    methods it used to identify alternatives to the proposed diversion.
    Appellants also reject Stafford's finding that no feasible areas
    adjacent to or in proximity to the Landfill site were available
    because they were either occupied by the Garden State Parkway or
    were preserved areas of the Pinelands.
    No application for a major diversion of parkland shall be
    approved by DEP and the SHC unless
    48                               A-2316-10T2
    the   applicant   has    demonstrated    to   the
    Department's    satisfaction,     through     the
    alternatives analysis required by N.J.A.C.
    7:36-26.9(d)2, that there is no feasible,
    reasonable and available alternative to the
    disposal or diversion of funded or unfunded
    parkland.    It shall be the Department's
    presumption   that    there   is   a    feasible,
    reasonable and available alternative not
    involving parkland for the project for which
    an applicant seeks to divert or dispose of
    parkland.    The applicant must rebut this
    presumption through the alternatives analysis
    in order to obtain the approval of the
    Commissioner   and    the   [SHC]    under   this
    subchapter. If the applicant is not able to
    rebut this presumption, the Commissioner and
    the [SHC] may, in their discretion, approve
    an application for a major disposal or
    diversion of parkland based on the exceptional
    recreation and/or conservation benefit to be
    provided by the applicant[.]
    [N.J.A.C. 7:36-26.1(d)(2).]
    The alternatives analysis must identify each alternative course
    of action that could be taken to yield the significant public
    benefit to be derived from the project, including all alternatives
    presented at the scoping hearing and submitted by the public, and
    the alternative of locating the applicant's project on the proposed
    replacement land.    N.J.A.C. 7:36-26.9(d)(2).
    Here,   the   purpose   of   the   solar   project   was   to   provide
    renewable energy to a public redevelopment project.                  For its
    original and amended diversion applications, Stafford explained
    49                                A-2316-10T2
    in detail how the alternatives to the proposed solar project were
    not feasible, reasonable, or available.
    For purposes of an alternatives analysis, "an alternative may
    be considered not feasible" if it "would bring about unresolvable
    logistical problems[.]"     N.J.A.C. 7:36-26.9(e)(1).     In addition,
    an alternative may be considered "not reasonable" if it "[w]ould
    result in the essential project purpose . . . not being met[.]"
    N.J.A.C. 7:36-26.9(e)(2).      The evidence supported DEP's finding
    that taking no action would not yield the significant public
    benefit of providing renewable energy to the Business Park, and
    would not help to maximize the green building objectives of the
    redevelopment plan.      Further, constructing the solar project in
    another area of the redevelopment area would be too limiting.
    Rooftop spaces were already being used and areas farther away from
    the site presented logistical problems including increased costs
    and safety concerns.     Finally, building a solar project beyond the
    redevelopment area itself would be constrained by public utilities
    laws and would result in inadequate production.
    We conclude there was ample credible evidence in the record
    as a whole supporting DEP's and the SHC's decisions, and the
    decisions   were   not   arbitrary,    capricious,   unreasonable,    or
    contrary to law.
    Affirmed.
    50                           A-2316-10T2