MERRI MATTHEWS VS. BOROUGH OF BELMAR (L-1152-16, MONMOUTH COUNTY AND STATEWIDE) ( 2019 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0154-18T3
    MERRI MATTHEWS,
    Plaintiff-Appellant,
    v.
    BOROUGH OF BELMAR,
    Defendant-Respondent.
    ______________________________
    Argued August 5, 2019 – Decided August 15, 2019
    Before Judges Sabatino and Mitterhoff.
    On appeal from the Superior Court of New Jersey, Law
    Division, Monmouth County, Docket No. L-1152-16.
    Thomas M. Rogers argued the cause for appellant
    (Caruso Smith Picini, PC, attorneys; Thomas M.
    Rogers, of counsel and on the brief).
    Nicole M. Grzeskowiak argued the cause for
    respondent (Hoagland, Longo, Moran, Dunst &
    Doukas, LLP, attorneys; Nicole M. Grzeskowiak, of
    counsel and on the brief).
    PER CURIAM
    Plaintiff Merri Matthews appeals from the trial court's order of summary
    judgment dismissing her claims against defendant Borough of Belmar. Plaintiff
    fell off the east side of the Belmar boardwalk sustaining serious injuries. She
    filed suit against defendant, alleging the absence of a handrail constituted a
    dangerous condition that was a proximate cause of her fall. The trial court found
    that defendant was immunized from plaintiff's claims pursuant to the Tort
    Claims Act and that plaintiff could not establish the elements of liability under
    the statute. We affirm.
    In October 2012, a portion of defendant’s boardwalk was destroyed by
    Hurricane Sandy. During the rebuilding process, defendant applied for federal
    funding assistance, in part for the reconstruction of the destroyed boardwalk.
    This funding would reimburse defendant for ninety percent of the costs incurred
    in rebuilding the boardwalk.       Reimbursement was dependent upon the
    boardwalk being rebuilt "in kind"  as it was prior to Hurricane Sandy.
    Amenities that were not previously part of the boardwalk and were not required
    by code, such as railings, would not receive FEMA funding.
    Paul Calabrese, the Borough Engineer, coordinated with the Borough
    Administration on the construction of the boardwalk and supervised its design
    and construction.    In contemplating the reconstruction design, defendant
    A-0154-18T3
    2
    consulted engineers about a number of aspects of the boardwalk, including the
    placement of railings. Once it was confirmed that the absence of railings along
    the entire boardwalk did not violate any codes or raise any engineering concerns,
    defendant ultimately decided to forego the installation of railings other than
    those required by the American Disability Act, 42 U.S.C. §§ 12101 to 12213,
    along the nineteen access points. In December 2012, the Borough Council
    presented its plan for the reconstruction of the boardwalk to the public.
    Thereafter, Calabrese approved and signed off on the design plan. The approved
    plans did not include railings along the eastern edge of the boardwalk, including
    the eastern edge of the beach badge booth where plaintiff's accident occurred.
    Defendant thereafter invited the submission of bids, and subsequently awarded
    contracts for the reconstruction pursuant to the approved plans.
    On May 26, 2014, plaintiff arrived at the boardwalk and proceeded to a
    booth to purchase a beach badge.        The booth is located on a "bump out"
    connection to the boardwalk, which extends easterly towards the ocean and sits
    elevated above the sand. The "bump out" does not provide access to the beach;
    rather, the beach can only be accessed at select access points that have stairs and
    ramps for patrons to use to walk to the beach. After purchasing a beach badge,
    plaintiff turned and stepped away from the booth. As she did so, plaintiff
    A-0154-18T3
    3
    stepped off the east edge of the boardwalk and fell. Her face struck the edge of
    the boardwalk, and she sustained serious injuries to her face and jaw.
    On August 9, 2018, the trial judge granted summary judgment in favor of
    defendant, finding that defendant was entitled to plan or design immunity
    pursuant to N.J.S.A. 59:4-6 and discretionary immunity pursuant to N.J.S.A.
    59:2-3(a). In addition, the judge found that plaintiff failed to prove defendant's
    conduct was palpably unreasonable as required by N.J.S.A. 59:4-2. This appeal
    ensued.
    On appeal, plaintiff argues that plan or design immunity does not apply
    because defendant's decisions regarding whether to install a handrail were made
    by the Borough's mayor, business administrator, and engineer, rather than the
    full Borough Council. We disagree and affirm.1
    1
    Because we agree with the trial judge's conclusion that defendant established
    its entitlement to plan or design immunity, we find it unnecessary to address her
    alternate grounds for dismissal based on discretionary immunity pursuant to
    N.J.S.A. 59:2-3(a), or plaintiff's failure to prove defendant's conduct was
    palpably unreasonable as required by N.J.S.A. 59:4-2. Defendant's motion to
    bar plaintiff's liability expert was scheduled for the week after the summary
    judgment order under review, and was thus rendered moot.
    A-0154-18T3
    4
    Standard of Review
    We review a grant of summary judgment de novo. Conley v. Guerrero,
    
    228 N.J. 339
    , 346 (2017) (citing Templo Fuente De Vida Corp. v. Nat'l Union
    Fire Ins. Co. of Pittsburgh, 
    224 N.J. 189
    , 199 (2016)).
    [W]hen deciding a motion for summary judgment under
    Rule 4:46–2, the determination whether there exists a
    genuine issue with respect to a material fact challenged
    requires the motion judge to consider whether the
    competent evidential materials presented, when viewed
    in the light most favorable to the non-moving party in
    consideration of the applicable evidentiary standard,
    are sufficient to permit a rational factfinder to resolve
    the alleged disputed issue in favor of the non-moving
    party.
    [Brill v. Guardian Life Ins. Co. of Am., 
    142 N.J. 520
    ,
    523 (1995).]
    "[S]ummary judgment will be granted if there is no genuine issue of material
    fact and 'the moving party is entitled to a judgment or order as a matter of law.'"
    
    Conley, 228 N.J. at 346
    (citing Templo 
    Fuente, 224 N.J. at 199
    ). In reviewing
    a grant of summary judgment, appellate courts consider "whether the evidence
    presents a sufficient disagreement to require submission to a jury or whether it
    is so one-sided that one party must prevail as a matter of law." 
    Brill, 142 N.J. at 536
    (quoting Anderson v. Liberty Lobby, 
    477 U.S. 242
    , 251-52 (1986)). If
    A-0154-18T3
    5
    there is no issue of fact, appellate courts give no special deference to the trial
    court's rulings on matters of law. Templo 
    Fuente, 224 N.J. at 199
    .
    Plan or Design Immunity
    Public entity liability in New Jersey is governed by the New Jersey Tort
    Claims Act. N.J.S.A. 59:1-1 to 12-3 (the Act). The purpose of the Act is to
    "establish[] the parameters" for which recovery for tortious injury may be sought
    against public entities or public employees. Coyne v. State, 
    182 N.J. 481
    , 488
    (2005).
    Except as otherwise provided by the Act, "[t]he guiding principle . . . is
    that 'immunity from tort liability is the general rule and liability is the
    exception.'" 
    Coyne, 182 N.J. at 488
    (quoting Garrison v. Twp. of Middletown,
    
    154 N.J. 282
    , 286 (1998)). The rationale behind granting immunity is to avoid
    judicial interference with authorized State decisions. See Thompson v. Newark
    Housing Auth., 
    108 N.J. 525
    , 534 (1987).
    Plan or design immunity provided under N.J.S.A. 59:4-6 is an affirmative
    defense as to which the public entity has the burden of proof. See Birchwood
    Lakes Colony Club v. Borough of Medford Lakes, 
    90 N.J. 582
    , 599-600 (1982).
    The statute provides that
    Neither the public entity nor a public employee is liable
    under this chapter for an injury caused by the plan or
    A-0154-18T3
    6
    design of public property, either in its original
    construction or any improvement thereto, where such
    plan or design has been approved in advance of the
    construction or improvement by the Legislature or the
    governing body of a public entity or some other body
    or a public employee exercising discretionary authority
    to give such approval or where such plan or design is
    prepared in conformity with standards previously
    approved.
    [N.J.S.A. 59:4-6(a).]
    In order for plan or design immunity to attach, the public entity must
    establish that "the condition that allegedly caused the injury was 'an approved
    feature of the plan or design.'" Kain v. Gloucester City, 
    436 N.J. Super. 466
    ,
    474 (App. Div. 2014) (quoting 
    Thompson, 108 N.J. at 536
    ). The public entity
    must demonstrate that such plan or design has been approved in advance of
    construction or improvement by a body vested with the authority to give such
    approval. See Manna v. State, 
    129 N.J. 341
    , 353-54 (1992) (holding the State
    immune from liability after the State demonstrated that the bridge design was
    adequately approved in advance of its construction).
    "A public entity . . . need not show that a feature of the plans (such as the
    installation of guardrails or paving an entire intersection) 'was specifically
    considered and rejected.'" Luczak v. Twp. of Evesham, 
    311 N.J. Super. 103
    ,
    109 (App. Div. 1998) (quoting 
    Thompson, 108 N.J. at 537
    )). The public entity
    A-0154-18T3
    7
    must only provide "evidence that it had considered the general condition about
    which [the] plaintiff complains in formulating the original plan or design."
    
    Luczak, 311 N.J. Super. at 109
    (quoting 
    Manna, 129 N.J. at 358
    ). Moreover,
    entitlement to the defense "does not depend upon any showing of the
    reasonableness of the design."     Birchwood 
    Lakes, 90 N.J. at 599
    .        Once
    established, plan or design immunity is perpetual, and cannot be lost if later
    knowledge shows a design or plan to be dangerous, or later circumstances render
    it dangerous. See 
    Birchwood, 90 N.J. at 598-99
    .
    In this case, the condition complained of, the absence of handrails, was an
    approved feature of the plan or design. There is no question that defendant, in
    coordination with the Mayor and the Borough Engineer, actually considered
    whether and to what extent to include handrails in reconstructing the boardwalk.
    In formulating that decision, defendant considered the fact that FEMA would
    only provide ninety percent reimbursement for "in-kind" reconstruction. In that
    regard, prior to Hurricane Sandy, the boardwalk did not have railings except at
    designated access points. Moreover, the Borough Engineer researched whether
    the absence of railings along the entire boardwalk violated any codes or raised
    any engineering concerns. Finding no violation of any code or other engineering
    design principles, defendant made the conscious choice to forego the installation
    A-0154-18T3
    8
    of railings other than those required by the American Disability Act, 42 U.S.C.
    §§ 12101 to 12213.
    In December 2012, the Borough Council presented its plan for the
    reconstruction of the boardwalk to the public, which included a discussion of
    the plans for only limited railings. Thereafter, the Borough Engineer approved
    and signed off on the overall design plan. These decisions were all approved
    and ratified by the Borough Council prior to the reconstruction of the boardwalk.
    Accordingly, the trial court was correct in its ruling that, under these facts,
    documented by the record, defendant established its entitlement to plan or design
    immunity, and therefore summary judgment was appropriately granted.
    Affirmed.
    A-0154-18T3
    9