Cumberland Farms, Inc. v. New Jersey , 447 N.J. Super. 423 ( 2016 )


Menu:
  •                  NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-4335-14T2
    CUMBERLAND FARMS, INC.,
    Plaintiff-Appellant/
    APPROVED FOR PUBLICATION
    Cross-Respondent,
    November 2, 2016
    v.
    APPELLATE DIVISION
    NEW JERSEY DEPARTMENT OF
    ENVIRONMENTAL PROTECTION and
    THE ADMINISTRATOR OF THE NEW
    JERSEY SPILL COMPENSATION
    FUND,
    Defendants-Respondents/
    Cross-Appellants.
    ___________________________________
    Argued October 17, 2016 – Decided November 2, 2016
    Before Judges Sabatino, Haas and Currier.
    On appeal from Superior Court of New Jersey,
    Law Division, Mercer County, Docket No. L-
    1368-13.
    Mark E. Tully (Goodwin Procter, LLP) of the
    Massachusetts bar, admitted pro hac vice,
    argued   the   cause   for   appellant/cross-
    respondent (Archer & Greiner, Mr. Tully and
    Chad W. Higgins (Goodwin Procter, LLP) of
    the Massachusetts bar, admitted pro hac
    vice, attorneys; Mr. Tully, Mr. Higgins, and
    Nicholas J. Lochetta, II, on the briefs).
    Leonard Z. Kaufmann argued the cause for
    respondents/cross-appellants (Christopher S.
    Porrino, Attorney General, and Cohn Lifland
    Pearlman Herrmann & Knopf, LLP, attorneys;
    Mr. Kaufmann, Barry A.                 Knopf, and Gwen
    Farley, Deputy Attorney                General, on the
    briefs).
    The opinion of the court was delivered by
    HAAS, J.A.D.
    Plaintiff Cumberland Farms, Inc. ("CFI") appeals from the
    Law Division's April 15, 2015 order dismissing its complaint
    seeking to enforce an alleged settlement with defendants New
    Jersey     Department        of      Environmental       Protection         and    the
    Administrator      of     the     New     Jersey      Spill     Compensation       Fund
    (collectively      "the      DEP")      that   purportedly       resolved    natural
    resource damage claims the DEP had asserted under the New Jersey
    Spill and Compensation Act, N.J.S.A. 58:10-23.11 to -23.50 ("the
    Spill Act").       The DEP has filed a cross-appeal from a provision
    in the same order granting judgment to CFI on its breach of the
    implied    covenant     of    good    faith    and    fair     dealing   claim,    and
    ordering CFI and DEP to continue settlement negotiations.
    Having reviewed the parties' contentions in light of the
    record and applicable law, we affirm the trial court's dismissal
    of CFI's breach of contract, specific performance, promissory
    estoppel,    and   declaratory        judgment       claims.      However,    on   the
    DEP's     cross-appeal,      we      reverse   the     trial     court's     decision
    granting judgment to CFI on its breach of the implied covenant
    of good faith and fair dealing claim.
    2                                 A-4335-14T2
    I.
    We derive the following facts and procedural history from
    the record developed during the two-day bench trial.                              Under the
    Spill Act, the DEP may seek damages against a responsible party
    for the loss of use of natural resources adversely affected by
    the party's discharge of hazardous substances.                              N.J. Dep't of
    Envtl. Prot. v. Exxon Mobil Corp., 
    393 N.J. Super. 388
    , 399-400
    (App.      Div.    2007)     (citing      N.J.S.A.        58:10-23.11f(a)(1)             and   -
    23.11q).          In an attempt to encourage responsible parties to
    voluntarily        settle     their      potential        natural        resource       damages
    ("NRD") liability, the DEP published Policy Directive 2003-07
    ("the      Directive")       in   September          2003.         
    Id. at 395.
           The
    Directive, which by its terms created "no enforceable rights,
    legal      or     equitable,      for    any        person,"   laid       out     the     DEP's
    procedures and formulae for resolving NRD claims.                               In order to
    take advantage of the settlement process, responsible parties
    had   to    notify     the     DEP      prior       to   January    2,     2004     of    their
    intention to settle any potential NRD claims.
    CFI owns numerous convenience stores and service stations
    in New Jersey.             On December 31, 2003, CFI's attorney sent a
    letter to the Commissioner of the DEP advising that "CFI would
    like to voluntarily enter into good faith discussions with the
    [DEP] concerning any potential NRD claims at this time. . . ."
    3                                    A-4335-14T2
    In   May   2004,     CFI    identified        twenty-three       of     its     sites      as
    candidates     for   settlement.         CFI     later        notified    the     DEP      of
    another fifty-five potential sites where it faced potential NRD
    liability.
    At trial, CFI called the Administrator of the DEP's Office
    of   Natural   Resource      Restoration        ("ONRR"),        John    Sacco,       as   a
    witness.     Sacco testified that he and his staff member, Vicky
    Galofre, did not have the authority to approve NRD settlements.
    Instead,     Sacco    stated    that      he     and     Galofre        only    had     the
    "authority     to    take    part   in    negotiation,          [and]     come     to      an
    understanding of terms" with the responsible party.                            Once Sacco
    knew the terms of a proposed settlement, he had to "go to [his]
    respective management teams and make a recommendation or start a
    discussion and then . . . at that point get the authority to
    finalize a document for settlement."
    According to Sacco, proposed settlements proceeded through
    "a very iterative process.          It goes back and forth quite often."
    There were repeating rounds of analysis between the ONRR, the
    DEP's management teams, and the New Jersey Division of Law,
    which   provided     legal    advice     to    the     DEP.      The    attorneys       for
    potential responsible parties engaged in a similar process with
    their clients and experts.           During this process, which normally
    took months to complete, the parties exchanged numerous drafts
    4                                      A-4335-14T2
    of the proposed settlement agreement, correspondence, and other
    documents before any enforceable agreement could be struck.
    Sacco also testified about the public notice requirement
    the   DEP    and    responsible        parties          had    to     follow    before   any
    settlement     could     be    finalized.               On     January    12,    2006,   the
    Legislature enacted L. 2005, c. 348.                           This law, which became
    effective on April 12, 2006, amended N.J.S.A. 58:10-23.11f(b) to
    provide     that   a   responsible       party          that    had    resolved    its   NRD
    liability    with      the    DEP    "shall       not    be    liable    for    claims   for
    contribution        [from      any     non-settling              responsible       parties]
    regarding matters addressed in the settlement. . . ."
    Chapter 348 also added a new provision, N.J.S.A. 58:10-
    23.11e2, which stated:
    At   least  30   days[1]  prior   to  its
    agreement    to   any     administrative    or
    judicially approved settlement . . . the
    [DEP] shall publish in the New Jersey
    Register and on the [DEP's] website the name
    of the case, the names of the parties to the
    settlement . . . , the location of the
    property on which the discharge occurred,
    and a summary of the terms of the settlement
    . . . , including the amount of any monetary
    payments made or to be made.         The [DEP]
    shall also provide written notice of the
    settlement . . . , which shall include the
    information listed above, to all other
    parties in the case and to any other
    1
    On December 2, 2015, the Legislature increased this thirty-day
    advance notification requirement to sixty days.     L. 2015, c.
    166.
    5                                    A-4335-14T2
    potentially responsible parties of whom the
    [DEP] has notice at the time of the
    publication.
    Thus, under this new provision, the DEP and a responsible party
    could not agree to a final settlement of a NRD claim until after
    public notice of the possible settlement had been provided.
    Even   prior      to   the   enactment         of    N.J.S.A.   58:10-23.11e2,
    however, the settlement agreements negotiated between the DEP
    and    responsible       parties       included        provisions      requiring      the
    publication of public notice in the New Jersey Register of a
    settlement     agreement,       even    if       it   was    already      signed.     For
    example, the first settlement agreement the DEP negotiated with
    CFI involved a site in Ridgefield.                    This agreement provided that
    the DEP reserved the right to withdraw from the settlement if
    the public comments received following the notice "indicate[d]
    to    the   [DEP]   in    its   sole    discretion,          that   the    [s]ettlement
    [a]greement is inappropriate, improper, or inadequate."                             Thus,
    the DEP retained the right to withdraw from the agreement based
    upon its review of any comments received from the public or
    other interested parties.
    Prior to the April 12, 2006 effective date of the thirty-
    day advance public notice requirement established by N.J.S.A.
    58:10-23.11e2, the DEP and CFI entered into a written settlement
    agreement for the remaining twenty-two sites CFI had originally
    6                                  A-4335-14T2
    identified as candidates for potential settlement.                             As was the
    case    with   the    Ridgefield       settlement,          the     parties     exchanged
    multiple draft agreements and correspondence before an agreement
    covering all twenty-two sites was executed.                       Like the Ridgefield
    settlement,     this     agreement      required        public         notice     of     the
    settlement, and granted the DEP the right to withdraw from the
    agreement if, after reviewing any public comments, it determined
    the agreement was "inappropriate, improper, or inadequate."
    At that point, there were fifty-five CFI sites remaining
    for consideration under the settlement program.                               The DEP had
    already initiated litigation to recover NRD damages from CFI for
    one of these sites, which was located in Berkeley Township.
    Settlement     negotiations      involving          sites    that      were    already   in
    litigation     were    handled    in    the    first        instance     by     the    DEP's
    outside litigation counsel, rather than by Sacco or Galofre.
    CFI's   attorney      testified    that       she    wanted       to   keep     the    other
    fifty-four sites out of litigation.                    The DEP agreed with this
    approach.      Therefore, the parties dealt with the Berkeley site
    separately.     Indeed, CFI's attorney testified that none of the
    correspondence CFI subsequently exchanged with DEP's litigation
    counsel concerning the Berkley property mentioned the remaining
    fifty-four sites.
    7                                       A-4335-14T2
    After going through a mediation process, CFI and the DEP's
    litigation counsel negotiated a settlement of the Berkeley site
    litigation.    On April 12, 2007, DEP's litigation counsel advised
    CFI's attorney that CFI's "proposed settlement has been approved
    and accept[ed] by the State."              The parties then began a year-
    long exchange of documents and correspondence until they agreed
    upon   the   terms    of    the   agreement.     At   that    point,   and    in
    accordance with N.J.S.A. 58:10-23.11e2, the parties arranged for
    public notice of the unsigned agreement.              The DEP "received no
    comments that disclosed facts or considerations that indicated
    to the [DEP], in its sole discretion, that the [s]ettlement
    [a]greement was inappropriate, improper, or inadequate[,]" and
    the parties consummated the agreement on April 14, 2008, when
    the final required signature was affixed to the document.
    The DEP did not issue a release to CFI concerning the NRD
    claims relating to the Berkeley site until 2013.                    At trial,
    Sacco speculated that the release for that site may have "fell
    through the cracks."
    As part of its settlement of the Berkeley site litigation,
    CFI agreed to fund the purchase of forty-three acres of land in
    Cumberland County, which would "be held in trust and for the
    benefit of the State of New Jersey to remain undeveloped and
    undisturbed   so     that   the   natural    resources   on   and   under    the
    8                               A-4335-14T2
    [p]roperty shall remain available for the use and benefit of the
    citizens of the State."        At trial, CFI's attorney asserted that
    CFI purchased additional acreage at that time that it hoped to
    use as part of any future settlement of the remaining fifty-four
    sites.     However, CFI did not provide any documentation linking
    these additional acres of land to the fifty-four sites prior to
    CFI's purchase of this property.
    The      remaining    fifty-four       sites,     which      are    located
    throughout    New   Jersey,    are   the   subject   of   this   appeal.       On
    August 3, 2006, Galofre sent an email to CFI's attorney stating,
    "Please let me know when you are available for a conference call
    to go over the [fifty-four CFI] sites."              It appears there was a
    subsequent     discussion      between     the   attorney        and    Galofre
    concerning the sites.          On October 20, 2006, Galofre sent the
    attorney     another   email    stating,    "About     two    months    ago    we
    discussed the NRD for [fifty-four CFI] properties.                     Is [CFI]
    still interested in settling these [fifty-four] sites?"                    CFI's
    attorney responded later that day, expressing continued interest
    in pursuing a settlement, but stating that CFI's environmental
    consultants needed to obtain additional information.
    When Galofre heard nothing further, she sent an email to
    CFI's attorney on January 11, 2007, advising that Sacco                       was
    considering forwarding the fifty-four sites to the DEP's outside
    9                                A-4335-14T2
    counsel for litigation.    CFI's attorney responded that same day,
    stating CFI was still interested in negotiating a settlement.
    Five months later, CFI's attorney sent Galofre an email on
    June 14, 2007, stating that CFI
    has   authorized   me  to   propose   [36.99]
    additional acres that will be purchased by
    The Nature Conservancy to satisfy CFI's
    potential NRD liability at the remaining
    sites we were discussing.     This offer is
    made without prejudice and solely in an
    attempt to resolve a bona fide dispute and
    CFI is making no admissions of fact or law.
    The next day, Galofre thanked CFI's attorney for the email
    and stated that she would "review this and will be in touch with
    you about it."   On June 20, 2007, Galofre sent the following
    email to CFI's attorney:
    I have reviewed the proposal made by CFI as
    stated in your email dated 6/14/07, below,
    and discussed this proposal with John Sacco.
    [The] ONRR is satisfied with this proposal,
    therefore attached find a draft settlement
    agreement for your review.       Please see
    Appendix B, that lists the sites, and fill
    in the missing block and lot numbers and
    program identification numbers. If you have
    comments to the draft[,] also provide them.
    However, note that [the] ONRR will not make
    changes to boilerplate language especially
    not to the definition of "Natural Resource
    Damages[.]" Thank you.
    As noted above, Sacco, Galofre, and the ONRR did not have
    the authority to approve a settlement with CFI or any other
    potential responsible party in a NRD case.    Instead, their task
    10                      A-4335-14T2
    was to flesh out the terms of any proposed agreement and then
    forward it to their management teams for review and possible
    approval.
    Mindful of the bounds of the ONRR's limited authority, the
    "draft settlement agreement" that Galofre sent to CFI's attorney
    was a template the ONRR used as the starting point for its
    negotiations.     There were numerous blank spaces, strikeouts, and
    "redlines" throughout the form.             The template listed CFI's name
    and address, and identified the fifty-four sites that were under
    discussion.      The form also included CFI's proposal to fund the
    purchase of approximately 36.99 acres of land.                    The provision
    stating    the   amount   of   money   CFI    would   pay   the   DEP   for   its
    "oversight costs" was left blank, and the dates by which certain
    steps   would    have   to   be   completed    were   not   included    in    the
    document.
    The draft agreement included a provision that stated, "This
    [s]ettlement [a]greement shall be effective upon the execution
    of this [s]ettlement [a]greement by the Department" and CFI.                   In
    addition, by operation of N.J.S.A. 58:10-23.11e2, prior to DEP's
    agreement to any settlement, the terms of the contract had to be
    published in order to give the public the opportunity to comment
    on them.
    11                               A-4335-14T2
    At trial, Sacco confirmed that, aside from the number of
    acres of land CFI proposed to purchase, the remainder of the
    draft    settlement   agreement      was    "still    a    work     in     progress."
    Sacco described the draft as "basically a template that we send
    out."       He   stated     that     other    than        the     "terms     of     the
    compensation[,] . . . the rest of it was yet to be determined
    how it would look."          CFI's trial counsel specifically asked
    Sacco,    "[W]hat     are   you     suggesting       was    still         subject    to
    negotiation?"       Sacco replied, "It would be the entirety of the
    document."
    Nevertheless,       CFI's      attorney    testified          that     after    CFI
    received the draft settlement agreement from Galofre on June 20,
    2007, "we had a deal."          During cross-examination, however, the
    DEP's    trial   counsel    read     the     following          portion     of     CFI's
    attorney's deposition testimony into evidence:
    Q.   So there is no currently existing
    document to which you would expect [the] DEP
    to affix -- defendants to affix their
    signature, correct?
    A.   Not that I've seen.
    CFI's attorney did not respond to Galofre's June 20, 2007
    email.     On July 25, 2007, Galofre sent the attorney an email
    stating, "Please email me and tell me the status of your review
    of the settlement document, attached, for the additional [fifty-
    four] sites."    CFI's attorney did not answer this email either.
    12                                     A-4335-14T2
    In August 2008, Galofre sent an email to CFI's attorney
    stating that she was leaving the ONRR and that another staff
    member, Pam Lange, would "be taking over the [CFI] matter, the
    [fifty-four] volunteer service stations[.]"              The attorney sent
    an email thanking Galofre, but provided no substantive response
    to her previous requests for a status report.
    CFI's attorney testified that she tried to call Lange on
    one occasion, but did not speak to her.                 The attorney never
    contacted Sacco to discuss the draft settlement agreement or to
    engage in negotiations.       As the months turned into years, Sacco
    testified "there was still no response from CFI to continue with
    it."     Sacco   explained   that    CFI's   attorney   was     aware   of    the
    iterative process from the "three previous deals . . . [a]nd I
    think was pretty clear of what were the next steps.               We made our
    couple of overtures and we never heard back.              And you know it
    just -- we moved on with other things."
    Sometime in 2012, the DEP added CFI as a defendant to a
    lawsuit it had filed in 2007 in the Southern District of New
    York.    In that action, the DEP sought to recover compensation
    for the public for contamination caused by the discharge of a
    chemical that was added to gasoline, Methyl Tertiary Butyl Ether
    ("MTBE"),   at   approximately      5000   sites   throughout    New    Jersey.
    With the addition of CFI, the fifty-four sites at issue in this
    13                                A-4335-14T2
    appeal were included in the contaminated sites for which the DEP
    sought compensation.                  One of the CFI properties, known as the
    Baker's Waldwick site, was designated as a "bellwether site"
    that    would          be     tried       during    the     first    phase         of    the     MTBE
    litigation.
    On September 13, 2012, CFI's attorney sent a letter to the
    DEP's trial counsel in the MTBE litigation.                                   In the letter,
    CFI's attorney claimed that it and DEP had settled the DEP's NRD
    claims for the fifty-four sites on June 20, 2007.                                      On December
    4,     2012,       DEP's       attorney       responded       with      a    letter        stating,
    "Although          I    am     aware       that    settlement        discussions           occurred
    several years ago as to a number of sites and that some were
    settled,       I       have    seen    no    documentation        that      such        discussions
    actually resulted in an enforceable settlement of the scope you
    reference."
    On   June         20,    2013,       six    years    after     Galofre           sent    CFI's
    attorney       the       draft       settlement         agreement     for     the        fifty-four
    sites, CFI filed a complaint seeking to enforce the alleged
    final    settlement.                 CFI    asserted       that   the       DEP    breached       the
    parties'       agreement             by     including       the     sites         in     the     MTBE
    litigation,             and     it        sought    specific        performance            of     the
    settlement.            CFI also claimed that the DEP breached the implied
    covenant       of       good     faith       and    fair     dealing         "by       failing     to
    14                                      A-4335-14T2
    consummate the [s]ettlement [a]greement and failing to perform
    any of [its] obligations under this [s]ettlement [a]greement."
    CFI also argued that it partially performed its obligations
    under the alleged agreement by purchasing property that could be
    used to satisfy its NRD liability for the fifty-four sites and,
    therefore, the DEP was estopped from denying the existence of an
    enforceable    contract.               Finally,        CFI    sought      a    judgment
    "[d]eclaring that the parties' agreement remains in full force
    and effect," and requiring the DEP to enter into a settlement
    agreement "as agreed to and otherwise completing the settlement
    in this matter."
    At the conclusion of testimony, the trial judge rendered an
    oral decision, rejecting CFI's claim that "the draft settlement
    agreement"    the    DEP       sent    CFI's     attorney      on    June     20,   2007
    constituted an enforceable contract.                    The judge noted that the
    draft   agreement        had     a     number     of     blanks,      redlines,      and
    strikeouts.         In    addition,       neither        party      had   signed     the
    agreement, and no public notice had been provided as required by
    N.J.S.A. 58:10-23.11e2.               The judge found that both Sacco and
    CFI's   attorney2    testified         that     "it's    an   iterative       process,"
    2
    The judge found that Sacco was "an honest witness," but stated
    he gave "greater weight" to CFI's attorney's testimony.       In
    support of this credibility finding, the judge stated that Sacco
    testified "that the [DEP] always acts in good faith. And at the
    (continued)
    15                                   A-4335-14T2
    involving the exchange of emails "and letters and going back and
    forth. . . .     They go one thing at a time going through it until
    finally -- the matter is completely resolved."
    The trial judge also found that Sacco lacked the authority
    to approve a settlement and "that it has to go through and be
    signed by certain people at DEP."          In addition, the judge noted
    that CFI's attorney acknowledged during her deposition testimony
    that the draft agreement was not in the form required for either
    party to sign it.       Because the judge found there was no valid
    settlement agreement between CFI and the DEP, he dismissed CFI's
    breach    of    contract,   specific      performance,   and   declaratory
    judgment claims.
    The     trial   judge   also   rejected   CFI's   promissory   estoppel
    argument.      The judge found that CFI had purchased property that
    it could use to satisfy part of its NRD liability for the fifty-
    four sites, but had not completed its stated plan of buying all
    of the acreage necessary to move forward.
    (continued)
    same time he also testified that in the case of the [fifty-four]
    sites[,] the application fell through the cracks."      However,
    Sacco's comment about something falling through the cracks was
    limited to the DEP's failure to send CFI a timely release in
    connection with the Berkeley settlement.     He made no similar
    comment concerning the fifty-four sites involved in this appeal.
    Therefore, the judge's finding on this point critical of Sacco
    lacks evidentiary support in the record.
    16                            A-4335-14T2
    Finally, the trial judge entered judgment in CFI's favor on
    its    breach   of    the    implied       covenant      of    good    faith    and   fair
    dealing claim.        The judge stated "that the DEP needs to resume
    its negotiations.        Whether that means that they actually wind up
    with an agreement that can be published that's subject to the
    publication contingency, I can't say.                    In the end[,] you may not
    have   a    settlement      agreement."           This    appeal      and    cross-appeal
    followed.
    II.
    On   appeal,    CFI        argues    that    the       trial   judge     erred   by
    concluding there was no enforceable settlement agreement between
    the parties.         CFI asserts it made an offer to settle its NRD
    liability for the fifty-four sites in CFI's attorney's June 14,
    2007 letter, and that Galofre's June 20, 2007 email with the
    attached "draft settlement proposal" constituted an acceptance
    of that offer.        We disagree.
    Our review of a trial court's fact-finding in a non-jury
    case is limited.        Seidman v. Clifton Sav. Bank, S.L.A., 
    205 N.J. 150
    , 169 (2011).            "The general rule is that findings by the
    trial court are binding on appeal when supported by adequate,
    substantial,      credible         evidence.             Deference      is     especially
    appropriate     when        the    evidence        is    largely      testimonial       and
    involves questions of credibility."                      
    Ibid. (quoting Cesare v.
    17                                   A-4335-14T2
    Cesare, 
    154 N.J. 394
    , 411-12 (1998)).                    We "should not disturb
    the factual findings and legal conclusions of the trial judge
    unless    [we     are]     convinced       that      they     are      so   manifestly
    unsupported by or inconsistent with the competent, relevant and
    reasonably      credible       evidence    as   to     offend    the    interests      of
    justice."    
    Ibid. (internal quotation marks
    omitted).
    However,    we      owe     no     deference      to      a     trial   court's
    interpretation of the law, and review issues of law de novo.
    State v. Parker, 
    212 N.J. 269
    , 278 (2012); Mountain Hill, L.L.C.
    v. Twp. Comm. of Middletown, 
    403 N.J. Super. 146
    , 193 (App. Div.
    2008), certif. denied, 
    199 N.J. 129
    (2009).                          We also review
    mixed questions of law and fact de novo.                    In re Malone, 381 N.J.
    Super. 344, 349 (App. Div. 2005).                      The      interpretation       and
    construction of a contract is a matter of law for the trial
    court,   subject     to    de    novo    review   on    appeal.        Fastenberg      v.
    Prudential Ins. Co. of Am., 
    309 N.J. Super. 415
    , 420 (App. Div.
    1998); see also Kaur v. Assured Lending Corp., 
    405 N.J. Super. 468
    ,   474   (App.      Div.     2009)    (reviewing     the     enforcement      of    a
    settlement agreement de novo).
    "A settlement agreement between parties to a lawsuit is a
    contract."       Nolan v. Lee Ho, 
    120 N.J. 465
    , 472 (1990).                          The
    burden of proving that the parties entered into a settlement
    18                                  A-4335-14T2
    agreement is upon the party seeking to enforce the settlement.
    Amatuzzo v. Kozmiuk, 
    305 N.J. Super. 469
    , 475 (App. Div. 1997).
    Since      the    "settlement      of    litigation           ranks    high       in    our
    public policy," Jannarone v. W.T. Co., 
    65 N.J. Super. 472
    , 476
    (App. Div.), certif. denied sub nom., Jannarone v. Calamoneri,
    
    35 N.J. 61
           (1961),    "settlement        agreements        will        be    honored
    'absent      a     demonstration          of       fraud       or     other         compelling
    circumstances.'"               
    Nolan, supra
    ,         120    N.J.    at     472       (quoting
    Pascarella        v.    Bruck,    190   N.J.       Super.      118,    125    (App.       Div.),
    certif.     denied,       
    94 N.J. 600
       (1983)).          Unless       there      is    "an
    agreement to the essential terms" by the parties, however, there
    is   no    settlement       in    the   first      instance.           Mosley       v.    Femina
    Fashions     Inc.,       356     N.J.   Super.      118,       126    (App.       Div.    2002),
    certif. denied, 
    176 N.J. 279
    (2003).
    "A contract arises from offer and acceptance, and must be
    sufficiently definite 'that the performance to be rendered by
    each      party    can    be     ascertained        with      reasonable          certainty.'"
    Weichert Co. Realtors v. Ryan, 
    128 N.J. 427
    , 435 (1992) (quoting
    West Caldwell v. Caldwell, 
    26 N.J. 9
    , 24-25 (1958)).                                "A written
    contract     is    formed        when   there      is    a    'meeting       of    the    minds'
    between      the       parties    evidenced        by     a    written       offer       and    an
    unconditional, written acceptance."                          Morton v. 4 Orchard Land
    Trust, 
    180 N.J. 118
    , 129-30 (2004) (quoting Johnson & Johnson v.
    19                                         A-4335-14T2
    Charmley Drug Co., 
    11 N.J. 526
    , 538-39 (1953)).                     Thus, "[i]t is
    requisite that there be an unqualified acceptance to conclude
    the manifestation of assent." Weichert Co. 
    Realtors, supra
    , 128
    N.J. at 435-36 (quoting Johnson & 
    Johnson, supra
    , 11 N.J. at
    539).     "In the very nature of the contract, acceptance must be
    absolute" and "unequivocally shown."               Johnson & 
    Johnson, supra
    ,
    11 N.J. at 538.
    Applying these principles in this case, we discern no basis
    for disturbing the trial judge's determination that CFI failed
    to   meet    its    burden    of    proving       there    was     an    enforceable
    settlement agreement.         The record clearly establishes that the
    DEP never agreed to do anything more than attempt to negotiate a
    final settlement through the iterative process, and that CFI
    never responded to the DEP's overtures.
    Both parties knew that Sacco, Galofre, and the ONRR did not
    have the authority to enter into a binding settlement agreement.
    Their   authority    was     limited      to   negotiating       with    a   potential
    responsible party on the terms of a possible settlement, which
    then needed to be reviewed and approved by DEP managers.                         Thus,
    Galofre     never   stated    in    her    June    20,    2007    email      that   DEP
    management    had    agreed    to   settle      the   matter.           Instead,    she
    specifically advised CFI's attorney that she was forwarding a
    "draft settlement agreement" for the attorney's review.
    20                                  A-4335-14T2
    Contrary     to   CFI's   contention,       Galofre's     email   cannot   be
    read    as    an    "unqualified";         "absolute";      or    "unequivocal[]"
    acceptance of CFI's June 14, 2007 "offer" to settle CFI's NRD
    liability for the fifty-four sites.                 Johnson & 
    Johnson, supra
    ,
    11 N.J. at 538-39.              Instead, as the trial judge found, the
    emails and the "draft settlement agreement" did not contain the
    terms   necessary        to   constitute    a    binding    settlement.       CFI's
    attorney's email only referred to the property CFI proposed to
    fund as part of the settlement.                 In turn, the draft agreement
    Galofre      sent   to    the    attorney       contained   numerous      redlines,
    strikeouts, and blanks.           As CFI's attorney conceded during her
    deposition testimony, neither party could sign the agreement in
    the condition it was in when Galofre started the negotiation
    process on June 20, 2007.
    The fact that CFI's attorney never responded to Galofre's
    July 25, 2007 email asking the attorney to advise her of the
    "status of [the attorney's] review of the [draft] settlement
    document," is also telling.            "A contracting party is bound by
    the apparent intention he or she outwardly manifests to the
    other party.        It is immaterial that he or she has a different,
    secret intention from that outwardly manifested."                        Hagrish v.
    Olson, 
    254 N.J. Super. 133
    , 138 (App. Div. 1992) (citing Looman
    21                                  A-4335-14T2
    Realty Corp. v. Broad St. Nat'l Bank of Trenton, 
    74 N.J. Super. 71
    , 82 (App. Div.), certif. denied, 
    37 N.J. 520
    (1962)).
    It   is    clear      from    Galofre's       email    that   the    DEP     did    not
    believe       there    was     a     binding        settlement   agreement.            CFI's
    attorney did nothing to question the DEP's understanding of the
    nascent     status      of     the    negotiations.           Indeed,       CFI    did     not
    communicate with the DEP concerning the fifty-four sites for
    over five years and, only then, asserted that its NRD liability
    for    these       locations          had   been        settled.            Under      these
    circumstances,          the        trial    judge       properly      rejected         CFI's
    contention that there was an enforceable settlement as of June
    20, 2007.
    The trial judge's determination is further supported by two
    additional factors.            First, the draft agreement expressly stated
    that the settlement would not be effective until it was executed
    by both parties.              As the judge observed, this provision was a
    material term of any resolution of the case.                           Because neither
    party signed the marked-up version of the agreement Galofre sent
    to    CFI's      attorney      on    June   20,       2007,   there    was    no     final,
    enforceable contract between the parties.
    Second,        under     N.J.S.A.       58:10-23.11e2,         the    DEP     and     a
    potentially responsible party may not agree to a settlement of
    NRD liability until after the DEP has published notice of the
    22                                   A-4335-14T2
    terms of the settlement.            Because the parties never arrived at
    an understanding of the terms of a final settlement, the DEP was
    never able, much less required, to publish the notice pursuant
    to the statute.         Therefore, the trial judge properly determined
    there   was    no     enforceable   agreement     between      the   DEP    and    CFI
    regarding the fifty-four sites.
    Finally on this point, CFI contends that if the parties
    agreed upon the terms that needed to be included in the notice
    required      by     N.J.S.A.    58:10-23.11e2,       this     "agreement"      would
    constitute a binding contract and the DEP would thereafter be
    powerless to withdraw from that "agreement" even if it received
    persuasive         negative    comments   about   the        proposed     settlement
    during the public comment period following the publication of
    the notice.         Because we have determined that no valid settlement
    agreement     was     forged    between   the   DEP    and    CFI,   we    need    not
    further address this contention in this opinion.                          See Indep.
    Realty Co. v. Twp. of N. Bergen, 
    376 N.J. Super. 295
    , 301 (App.
    Div. 2005) (noting that while the New Jersey Constitution does
    not confine the exercise of judicial power to actual cases and
    controversies, "it is well settled that [courts] will not render
    advisory opinions or function in the abstract").
    That having been said, however, we perceive no principled
    basis for the Legislature to have required in N.J.S.A. 58:10-
    23                                 A-4335-14T2
    23.11e2   that   public     notice      be   published        of    the    proposed
    settlement   terms     thirty    days   prior    to   DEP's    agreement      to    a
    settlement of a NRD claim if it did not intend for the DEP to be
    able to consider the public comments received during that period
    and make a determination whether to consummate, withdraw from,
    or modify the settlement.         See State v. Reynolds, 
    124 N.J. 559
    ,
    564 (1991) ("A construction of a statute that will render any
    part of a statute inoperative, superfluous, or meaningless, is
    to be avoided.").       Significantly, the parties' prior agreements
    expressly permitted the DEP to withdraw from the settlements in
    its sole discretion after it considered the public comments.
    Paragraphs six and seven of the "draft settlement agreement"
    Galofre sent to CFI's attorney also contained the template of a
    similar provision that was not finalized because the parties
    never agreed to the terms of a settlement in this case.
    The DEP's interpretation of the public comment process and
    its ability to respond to those comments in the public interest
    as evidenced by the language included in its final agreements is
    entitled to "great weight as evidence of its conformity with the
    legislative intent."      Malone v. Fender, 
    80 N.J. 129
    , 137 (1979).
    Therefore, we reject CFI's contention on this point.
    In    sum,   CFI    failed    to    prove   there   was        an   enforceable
    settlement   agreement.         Therefore,      the   trial    judge      correctly
    24                                 A-4335-14T2
    dismissed    CFI's      claims       for     breach       of   contract,       specific
    performance, and a declaratory judgment against the DEP.
    For similar reasons, the judge also properly rejected CFI's
    promissory      estoppel      argument.          "The     elements     of   promissory
    estoppel are '1) a clear and definite promise, 2) made with the
    expectation that the promisee will rely upon it, 3) reasonable
    reliance upon the promise, 4) which results in definite and
    substantial detriment.'"             East Orange Bd. Of Educ. v. N.J. Sch.
    Const. Corp., 
    405 N.J. Super. 132
    , 148 (App. Div.) (quoting
    Lobiondo v. O'Callaghan, 
    357 N.J. Super. 488
    , 499 (App. Div.),
    certif. denied, 
    177 N.J. 224
    (2003)), certif. denied, 
    199 N.J. 540
      (2009).      As    discussed         above,      there   was     no   "clear    and
    definite    promise"     by    DEP    that       it    would   enter    into   a   final
    settlement agreement with CFI.                    Thus, CFI cannot demonstrate
    that it relied upon that nonexistent "promise" in connection
    with its purchase of additional property that it hoped to use to
    resolve its NRD liability for the fifty-four sites.
    Finally, we are constrained to reverse the portion of the
    April 15, 2015 order entering judgment in CFI's favor on its
    claim that the DEP breached the implied covenant of good faith
    and fair dealing.          "[E]very contract in New Jersey contains an
    implied    covenant     of    good    faith      and    fair   dealing."       Sons    of
    Thunder, Inc. v. Borden, Inc., 
    148 N.J. 396
    , 420 (1997).                              The
    25                                 A-4335-14T2
    implied       covenant          applies       to     "both        the        performance        and
    enforcement of the contract."                        Brunswick Hills Racquet Club,
    Inc.    v.    Route       18    Shopping      Ctr.       Assocs.,       
    182 N.J. 210
    ,      224
    (2005).       Under this "implied covenant . . . 'neither party shall
    do anything which will have the effect of destroying or injuring
    the    right       of    the    other      party    to    receive       the    fruits     of    the
    contract.'"             Palisades Props., Inc. v. Brunetti, 
    44 N.J. 117
    ,
    130 (1965) (quoting 5 Williston on Contracts § 670, at 159-60
    (3d ed. 1961)).
    However,         it     is   well    established         and    CFI     concedes,       that
    "[i]n the absence of a contract, there can be no breach of an
    implied      covenant          of   good    faith    and       fair    dealing."        Noye     v.
    Hoffman-La         Roche       Inc.,    238   N.J.       Super.       430,    434   (App.      Div.
    1990).       Here, there was no contract between CFI and the DEP.
    Therefore, the judge should have also dismissed CFI's breach of
    the implied covenant of good faith and fair dealing claim.
    In sum, we affirm the trial court's dismissal of CFI's
    breach of contract, specific performance, promissory estoppel,
    and declaratory judgment claims.                         We reverse the portion of the
    April 15, 2015 order granting judgment to CFI on its breach of
    the implied covenant of good faith and fair dealing claim, and
    remand       for    the      prompt     entry       of    an    order        dismissing     CFI's
    complaint in its entirety.
    26                                      A-4335-14T2
    Affirmed in part; reversed in part; and remanded.     We do
    not retain jurisdiction.
    27                         A-4335-14T2