WALLACE BROS., INC. VS. EAST BRUNSWICK BOARD OF EDUCATION (L-1605-14, MIDDLESEX COUNTY AND STATEWIDE) ( 2017 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-1432-15T3
    WALLACE BROS., INC.,
    Plaintiff-Respondent,
    v.
    EAST BRUNSWICK BOARD OF
    EDUCATION,
    Defendant-Appellant.
    ______________________________
    Argued October 11, 2017 – Decided November 9, 2017
    Before Judges Fuentes, Koblitz and Manahan.
    On appeal from Superior Court of New Jersey,
    Law Division, Middlesex County, Docket No. L-
    1605-14.
    Anthony P. Seijas argued the cause for
    appellant (Cleary Giacobbe Alfieri Jacobs,
    LLC, attorneys; Mr. Seijas, of counsel;
    Jessica V. Henry, on the briefs).
    Gerard J. Onorata argued the cause for
    respondent (Peckar & Abramson, PC, attorneys;
    Mr. Onorata and Patrick T. Murray on the
    brief).
    PER CURIAM
    Defendant East Brunswick Board of Education appeals from the
    April 24, 2015 order granting summary judgment on the unpaid
    portion of a Contract to plaintiff Wallace Bros. Inc.1          The Board
    contracted with Wallace to provide general construction at the New
    Memorial School in East Brunswick (project).          The total value of
    the   contract   was   $18,233,000,   plus   any   additional   costs   for
    unanticipated     work.    The   Board    paid   Wallace   $19,713,664.11.
    Although the school had been in use for two years, the Board did
    not make the last payment of $366,130.26.            Wallace claimed the
    Board did not deliver a "final" punch list indicating additional
    work to be done until after the litigation ensued.              The Board
    claims several punch lists were provided going as far back as
    April 2013.      The parties dispute whether these punch lists were
    provided to Wallace.
    The trial judge determined that the Board waited too long to
    register dissatisfaction with the completion of the project, and
    then belatedly provided a final punch list that was maintenance-
    related and substantively separate from the contract.           We reverse
    the grant of summary judgment because material facts are in dispute
    and the Board is entitled to a trial on the issue of whether the
    1
    Although the Board's appeal originally sought review of two
    orders, the appeal of the October 23, 2015 order granting delay
    damages was resolved by way of a stipulation of dismissal.
    2                           A-1432-15T3
    contract was fully completed and the last payment due in its
    entirety.2
    The Board's architect signed two Certificates of Substantial
    Completion, one on November 9, 2012 and the second on October 3,
    2013, both of which struck out the following language:
    A list of items to be completed or corrected
    is attached hereto.   The failure to include
    any items on such list does not alter the
    responsibility of the Contractor to complete
    all   Work   in  accordance   with  Contract
    Documents.
    The meaning of the striking of this language is not clear.
    The   architect     certified   that   "the   stricken     language    merely
    indicated, in my opinion, that the punch lists were not attached
    thereto."      Wallace contends the architect's signature on the
    documents    with    the   language    stricken   speaks    for   itself      in
    indicating the project was completed.
    The Board argues that the project was not completed in light
    of further punch lists.      The Board contends that it served Wallace
    2
    Wallace argues that we should not consider the Board's arguments
    not raised before the motion court.      To the extent that these
    arguments constitute "issues" not raised below, we choose to
    consider them in the interest of justice, given that public funds
    are at stake. See Nieder v. Royal Indemn. Ins. Co., 
    62 N.J. 229
    ,
    234 (1973) (noting that although appellate courts ordinarily
    should not reach issues that were not presented below, an exception
    applies where the issues significantly affect the public
    interest).
    3                              A-1432-15T3
    a punch list in April 2013, well before litigation ensued in March
    2014.   The Board solicited price proposals from other contractors
    to repair and complete Wallace's work.            Further, the Board's
    opposition to the last payment reflected about $56,000 of back
    charges3 and approximately $170,000 in liens on the project.            The
    contract requires Wallace to refund the lien amounts to the Board.
    Although    the   evidence   was   conflicting,   the   motion   judge
    determined that the Board did not submit a "final punch list" to
    Wallace until January 2015, and "[f]airness dictates that this
    punch list should be rejected as it was not submitted with the
    Certificates of Substantial Completion and the Project has been
    occupied for two years."     The contract provides in paragraph 9.9.3
    that "Partial occupancy or use of a portion or portions of the
    Work shall not constitute acceptance of Work not complying with
    the requirements of the Contract Documents."
    We review a grant of summary judgment de novo, applying the
    same standard governing the trial court under Rule 4:46-2(c).
    Liberty Surplus Ins. Corp. v. Nowell Amoroso, P.A., 
    189 N.J. 436
    ,
    445-46 (2007).    Generally, the court must "consider whether the
    3
    A back charge is a "charge against a contract in the form of a
    credit change order to a contractor for the cost of having others
    perform   portions    of   their   contract."      Back   charge,
    DictionaryofConstruction.com,
    http://www.dictionaryofconstruction.com/definition/backcharge.ht
    ml (last visited Oct. 24, 2017).
    4                             A-1432-15T3
    competent evidential materials presented, when viewed in the light
    most favorable to the non-moving party, are sufficient to permit
    a rational factfinder to resolve the alleged disputed issue in
    favor of the non-moving party."         Brill v. Guardian Life Ins. Co.
    of Am., 
    142 N.J. 520
    , 540 (1995); see also R. 4:46-2(c).
    The Board argues that the motion judge disregarded material
    disputes of fact.      First, it argues that required "closeout
    documentation" remains missing, despite a contractual obligation
    to provide these documents prior to payment on the contract
    balance.   The Board describes these documents as the proof of
    payment of all vendors, proof of insurance, subcontractor waivers,
    recorded   drawings,   proof   of   tests   and   inspections,   and    the
    maintenance package containing manufacturers' warranties.
    The motion judge, referring to the Board, stated:
    When you let so much time go by and you're
    holding up their money and then you say, oh
    you got to do all these things and there's no
    way of telling – most of them look like
    maintenance things that would occur in the
    ordinary course of using the premises, but
    basically it sounds like you're holding their
    money hostage to make them come and do repairs
    that they would not have been called upon to
    do.
    A "punch list status report" dated April 2013 lists close to
    three hundred items that had yet to be completed.                The list
    reflects that it was revised in August 2013, October 2014 and
    November 2014, when some of the items were crossed off.                 The
    5                             A-1432-15T3
    architect refers to this list as the "Final Punch List."               Examples
    from the list that were not crossed off include: caulking all
    exposed steel, removing "stub conduit," touching up paint on a
    door frame, repairing a damaged wall, installing the vinyl base
    at    a    casework    counter,    removing   paint   from   an   entry     frame,
    installing a "backer rod," patching bolts at a side-court basket,
    sanding and painting "hose bibbs," replacing crumbling grout, and
    installing concrete floor sealer.
    According to the November 2014 punch list, $163,890 worth of
    work remained.         Also still outstanding was the Board architect's
    issuance of a "final Certificate for Payment stating that . . .
    the Work has been completed in accordance with . . . the Contract
    [and] the entire balance . . . is due and payable" as required in
    paragraph 9.10.1 of the contract.             The contract requires "strict
    and entire conformity" by Wallace.
    A trial court's legal interpretation of the meaning of a
    contract is subject to de novo appellate review.                  Fastenberg v.
    Prudential Ins. Co. of Am., 
    309 N.J. Super. 415
    , 420 (App. Div.
    1998).       In Dunkin' Donuts of Am., Inc. v. Middleton Donut Corp.,
    
    100 N.J. 166
     (1985), the trial court "fashioned its own remedy on
    the       basis   of   equitable   considerations,"     believing     that      the
    contract would result in an "inappropriate windfall."                Ibid.
    6                                 A-1432-15T3
    Our   Supreme   Court   reversed,   stating:   "Equitable     relief
    cannot be claimed because a contract is oppressive, improvident,
    or unprofitable, or because it produces hardship."         Id. at 183-
    84.   The contract does not require that the last payment be made
    within a set period of time.        Material factual disputes remain
    regarding whether Wallace fully completed the contract.
    Reversed and remanded for further proceedings.         We do not
    retain jurisdiction.
    7                             A-1432-15T3
    

Document Info

Docket Number: A-1432-15T3

Filed Date: 11/9/2017

Precedential Status: Non-Precedential

Modified Date: 11/9/2017