IN THE MATTER OF LACEY TOWNSHIP CAFRA PERMIT (DEPARTMENT OF ENVIRONMENTAL PROTECTION) ( 2019 )


Menu:
  •                             NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon an y court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-3173-16T3
    IN THE MATTER OF LACEY
    TOWNSHIP CAFRA PERMIT.
    ___________________________
    Argued December 10, 2018 – Decided April 26, 2019
    Before Judges Sabatino and Haas.
    On appeal from the New Jersey Department of
    Environmental Protection.
    Aaron Kleinbaum argued the cause for appellant Save
    Barnegat Bay (Eastern Environmental Law Center,
    attorneys; Aaron Kleinbaum, of counsel; Raghu
    Murthy, on the briefs).
    Lauren R. Staiger argued the cause for respondent
    Township of Lacey (Gilmore & Monahan, PA,
    attorneys; Lauren R. Staiger, on the brief).
    Jason Brandon Kane, Deputy Attorney General, argued
    the cause for respondent New Jersey Department of
    Environmental Protection (Gurbir S. Grewal, Attorney
    General, attorney; Melissa H. Raksa, Assistant
    Attorney General, of counsel; Jason Brandon Kane, on
    the brief).
    PER CURIAM
    Appellant Save Barnegat Bay appeals from a decision by the Department
    of Environmental Protection (DEP) to issue a Coastal Area Facility Review Act,
    N.J.S.A. 13:19-1 to -21, (CAFRA) permit to the Township of Lacey (Township)
    to restore and reconstruct Bayfront Park, a Township-owned site that was
    destroyed by Superstorm Sandy. We affirm.
    I.
    Bayfront Park (Park) is located on Beach Boulevard in the Township. The
    Park covers approximately 5.5 acres, and is bordered by Barnegat Bay (Bay) to
    the east, Forked River to the north, a private beach to the south, and private
    residential properties to the west. Prior to Superstorm Sandy making landfall in
    New Jersey on October 29, 2012, the Park was mainly sand. As a result of
    frequent high-wave action on the shore of the Park, the natural sandy beach
    eroded over time, sometimes at the rate of three feet per year. In an effort to
    stem the tide of this erosion, the Township installed "rip-rap"1 along the
    perimeter of the shoreline. Residents wishing to access the Bay were able to do
    so by walking over the rip-rap, or by simply entering the water at either end of
    the rip-rap.
    1
    "Rip-rap" is a shore protection structure composed of loose stones and
    boulders.
    A-3173-16T3
    2
    Superstorm Sandy dislodged the rip-rap, destroyed a small gazebo, and
    caused other significant damage to the Park. As a result, the Township applied
    for, and received, a $1,239,196.75 Community Development Block Grant for
    Disaster Relief from the New Jersey Economic Development Authority. With
    these funds, the Township planned to restore the Park so it could again be
    enjoyed by the public. In order to protect the beach in the future, the Township
    decided to build a "gabion" 2 wall along the shoreline, and add stormwater
    management basins at the site. The Township also sought to provide amenities
    to the public by providing a gazebo, a walking path, a playground area, and an
    observation deck overlooking the Bay.3
    In November 2015, the Township applied for a CAFRA Individual Permit
    for permission to take these shore protection measures and make the
    improvements described above. During the thirty-day public comment period
    that followed, DEP received nine written comments, including a nine-page letter
    2
    A "gabion" is a "shore protection structure that is comprised of wire mesh
    basket(s) or mattress(es) filled with rock and used in multiples as a structural
    unit installed to withstand the forces of waves and currents." N.J.A.C. 7:7 -1.5.
    3
    The Township also proposed providing twenty-six paved parking spaces for
    Park visitors.
    A-3173-16T3
    3
    from appellant.4 Appellant primarily objected to the installation of the gabion
    wall in lieu of a "living shoreline" that would not include any structural measu res
    to prevent the erosion of the shoreline. Appellant also noted that the beach
    provided habitat for terrapins, birds, and other species. After submitting this
    letter, appellant took no further action regarding the Township's permit
    application while DEP was reviewing it.
    Another commenter, Dr. John Wnek, the Research Coordinator of Project
    Terrapin at the Marine Academy of Technology and Environmental Science,
    Ocean County Vocational Technical School, recommended that the Township
    include a "turtle garden"5 at the site to enhance the nesting habitat for terrapins,
    and plant sand-tolerant, native vegetation to stabilize the nesting area and
    protect any terrapin hatchlings. Unlike appellant, Dr. Wnek continued to work
    with the Township and DEP as the application proceeded through the review
    process.
    4
    Appellant attached two photographs of a diamondback terrapin to the letter.
    5
    A "turtle garden" is a patch of sandy soil above the high water line that
    provides a nesting habitat for diamondback terrapins.
    A-3173-16T3
    4
    Other commenters included homeowners who lived near the Park, as well
    as a few other area residents.6 One homeowner voiced her concerns with the
    proposed development in front of adjacent homes, but emphasized that "the
    recreational plan for the northern section of the [B]ayfront [P]ark is well -
    planned and will be an asset to the community." This individual was the only
    commenter besides Dr. Wnek to express continued interest in the project during
    the time between the expiration of the public comment period and DEP's final
    decision on the permit.
    At the end of the public comment period, DEP issued a deficiency letter
    to the Township, citing the application's shortcomings in demonstrating
    compliance with some CAFRA and stormwater regulations. On April 15, 2016,
    the Township submitted a revised application addressing each of DEP's
    concerns.
    In the ninety days 7 that followed, DEP staff consulted with Dr. Wnek, the
    interested Township resident, and the Township's engineering consultants. As
    6
    The Sierra Club of Ocean County submitted a short e-mail to DEP, and noted
    that a gabion wall might "cut off" the terrapins' access to the Park beach.
    7
    Upon submission of a revised CAFRA individual permit application after
    public comments are received, DEP has ninety days to issue a decision on the
    revised application. N.J.A.C. 7:7-26.6(d).
    A-3173-16T3
    5
    a result, the Township agreed to build a turtle garden in the Park, with thirty-six
    "turtle transit tunnels" along the entire length of the gabion wall. These tunnels
    would permit the terrapins to continue to access and nest along the beach and
    waterfront.
    On July 13, 2016, DEP staff issued a thorough written report,
    recommending approval of the Township's permit application. For the reasons
    set forth in this report, the staff found that the project complied with all of DEP's
    applicable regulations, including those governing coastal engineering, N.J.A.C.
    7:7-15.11; coastal high hazard areas, N.J.A.C. 7:7-9.18; beaches, N.J.A.C. 7:7-
    9.22; riparian zones, N.J.A.C. 7:7-9.26; endangered or threatened wildlife or
    vegetation species habitat, N.J.A.C. 7:7-9.36; and critical wildlife habitats,
    N.J.A.C. 7:7-9.37. On that same date, DEP approved the permit.
    N.J.A.C. 7:7-26.6(g) states that DEP "shall provide notice of the decision
    on an application for authorization under a . . . CAFRA individual permit in the
    DEP Bulletin[8 (Bulletin)] and to any person who specifically requested notice
    of the decision on a particular application." Unfortunately, DEP did not publish
    notice of its approval of the Township's application in the Bulletin until February
    8
    DEP publishes the Bulletin on a semi-monthly basis and it contains a list of
    environmental and construction permit applications recently filed or acted upon
    by DEP.
    A-3173-16T3
    6
    15, 2017. DEP states in its appellate brief that the delay in publishing the notice
    was due to an inadvertent oversight.
    Although there was a delay in publishing this notice, the permit
    specifically stated that "any person who is aggrieved by this decision or any of
    the conditions of this permit may request a hearing within 30 days after notice
    of the decision is published in the . . . Bulletin." In spite of this, appellant did
    not request a hearing. Although it thereafter filed a timely notice of appeal,
    appellant also did not seek a stay of the construction of the shoreline and terrapin
    protection project, or the Park amenities, from either DEP or this court. Thus,
    the entire project has already been completed, and the Park reopened to the
    public in August 2017.
    II.
    On appeal, appellant argues that DEP improperly granted the permit
    because: (1) it should have required the Township to employ a "non-structural"
    means of protecting the shoreline; (2) the Township's project would "devastate
    a diamondback terrapin nesting habitat"; (3) the project threatened the habitat
    of other endangered wildlife; (4) DEP violated the public trust doctrine; and (5)
    DEP deprived appellant of "due process" by delaying the publication of the
    permit's approval in the Bulletin. All of these contentions lack merit.
    A-3173-16T3
    7
    "Established precedents guide our task on appeal. Our scope of review of
    an administrative agency's final determination is limited." Capital Health Sys.
    v. N.J. Dep't of Banking & Ins., 
    445 N.J. Super. 522
    , 535 (App. Div. 2016),
    (citing In re Stallworth, 
    208 N.J. 182
    , 194 (2011)). We decide only whether the
    findings made could reasonably have been reached on sufficient credible
    evidence present in the record, considering the proofs as a whole. In re Taylor,
    
    158 N.J. 644
    , 656 (1999). We will not upset the ultimate determination of an
    agency unless it is shown it was arbitrary, capricious, or unreasonable, or that it
    violated legislative policies expressed or implied in the statutes governing the
    agency. Seigel v. N.J. Dep't of Envtl. Prot., 
    395 N.J. Super. 604
    , 613 (App. Div.
    2007).
    "In reviewing agency action, the fundamental consideration is that a court
    may not substitute its judgment for the expertise of an agency 'so long as that
    action is statutorily authorized and not otherwise defective because arbitrary or
    unreasonable.'" Williams v. Dep't of Human Servs., 
    116 N.J. 102
    , 107 (1989)
    (quoting Dougherty v. Dep't of Human Servs., 
    91 N.J. 1
    , 12 (1982)). Thus, our
    appellate review does not encompass whether the agency's decision was wise,
    only whether it was lawful.
    "[J]udicial deference to administrative agencies
    stems from the recognition that agencies have the
    A-3173-16T3
    8
    specialized expertise necessary to . . . deal[] with
    technical matters and are 'particularly well equipped to
    read and understand the massive documents and to
    evaluate the factual and technical issues . . . .'"
    "'[W]here there is substantial evidence in the record to
    support more than one regulatory conclusion, it is the
    agency's choice which governs.'" . . . The court "may
    not vacate an agency determination because of doubts
    as to its wisdom or because the record may support
    more than one result," but is "obliged to give due
    deference to the view of those charged with the
    responsibility of implementing legislative programs."
    [In re Adoption of Amendments to Water Quality
    Management Plans, 
    435 N.J. Super. 571
    , 583-84 (App.
    Div. 2014) (alterations in original) (citations omitted).]
    Where an agency's expertise is a factor, we will defer to that expertise,
    particularly in cases involving technical matters within the agency's special
    competence. In re Freshwater Wetlands Prot. Act Rules, 
    180 N.J. 478
    , 489
    (2004). This deference is even stronger when the agency, like DEP, "has been
    delegated discretion to determine the specialized and technical procedures for
    its tasks." City of Newark v. Natural Res. Council, 
    82 N.J. 530
    , 540 (1980).
    Moreover,
    [w]hen an administrative agency interprets and applies
    a statute it is charged with administering in a manner
    that is reasonable, not arbitrary or capricious, and not
    contrary to the evident purpose of the statute, that
    interpretation should be upheld, irrespective of how the
    forum court would interpret the same statute in the
    absence of regulatory history.
    A-3173-16T3
    9
    [Reck v. Dir., Div. of Taxation, 
    345 N.J. Super. 443
    ,
    448 (App. Div. 2001) (quoting Blecker v. State, 
    323 N.J. Super. 434
    , 442 (App. Div. 1999)), aff’d o.b., 
    175 N.J. 54
     (2002).]
    Applying these principles, we discern no reason to disturb DEP's decision
    to grant the permit to the Township.
    A.
    Contrary to appellant's first contention, DEP did not violate its Coastal
    Engineering Rule, N.J.A.C. 7:7-15.11, by permitting the Township to use a
    gabion wall to protect the shoreline. As appellant correctly points out, this
    regulation establishes a hierarchy in shore protection and storm damage
    reduction projects. In this hierarchy, DEP prefers that the permit applicant first
    consider the use of non-structural means of protecting the shore. N.J.A.C. 7:7-
    15.11(b)(1).
    However, if non-structural measures are "not feasible or practicable[,]"
    the agency's next preference is that the permittee employ a "hybrid" combination
    of structural and non-structural elements, such as the gabion wall and vegetation
    A-3173-16T3
    10
    measures DEP approved in the present case. N.J.A.C. 7:7-15.11(b)(2). 9 In
    evaluating whether hybrid shore protection measures may be used instead of
    entirely non-structural measures, DEP evaluates "the type of waterway on which
    the site is located, the distance to the navigation channel, the width of waterway,
    water depth at the toe of bank, the bank orientation, shoreline slope, fetch, [10]
    erosion rate, the amount of sunlight the site receives, substrate composition, and
    presence of shellfish habitat." 
    Ibid.
    In its revised application, the Township's engineers explained that
    [i]n order to best protect the park with the least
    amount of disturbance area, the low gabion wall was
    selected. This methodology provides the best means of
    wave attenuation, especially towards the narrow,
    southerly end of the park, closest to the houses. An
    earthen berm would need to be elevated above the
    Flood Hazard Area Elevation to be effective. A berm
    built below the Flood Hazard Elevation would erode in
    flood events. A berm built above the Flood Hazard
    Elevation would have roughly a 65 foot wide footprint
    and be aesthetically unpleasing. A 25 foot wide berm
    would be required with 5:1 side slopes resulting in a 65
    foot footprint. It would also encroach upon the
    residential properties adjacent to the site since the area
    9
    If a hybrid combination is neither feasible or practicable, the permittee may
    exclusively use structural measures to protect the shoreline. N.J.A.C. 7:7 -
    15.11(b)(3).
    10
    A "fetch" is the "distance across water that wind blows unimpeded. The
    greater the fetch, the greater the wind and wave forces." Hatt 65, LLC v.
    Kreitzberg, 
    658 F.3d 1243
    , 1245 n.3 (11th Cir. 2011).
    A-3173-16T3
    11
    in between the property lines and edge of rip-rap varies
    from 25 feet to 60 feet. Also, there is no berm to tie
    into on adjacent properties which would cause erosion
    and washouts at the ends of the berm.
    After considering the Township's expert's findings, DEP reasonably
    concluded that the non-structural measures, such as the living shoreline now
    advocated by appellant, were neither feasible nor practicable under N.J.A.C.
    7:7-15.11(b)(2). In its comprehensive report, DEP staff noted that the Park was
    "experiencing significant erosion."         Although the staff recognized that
    "vegetative methods of shoreline stabilization are the preferred methods over
    structural solutions" under N.J.A.C. 7:7-15.11(b)(1), a hybrid solution was
    necessary because "[b]ased on information submitted by the [Township's
    engineers], given the limited beach width, open fetch from the west and
    recurrent tidal erosional forces, this area is a high energy zone and is subject to
    highly erosive forces."    Moreover, DEP staff found that the Park "has no
    developed dune system and/or any form of structural protective structure. The
    lack of protection has led to flooding and damage in past storm events."
    Based upon the uncontradicted expert engineering evidence submitted by
    the Township, and DEP's recognized expertise in this esoteric area, we discern
    no basis for disturbing DEP's conclusion that the use of solely non-structural
    A-3173-16T3
    12
    shore protection measures was not feasible, and that the hybrid methods chosen
    by the Township were both appropriate and necessary.
    B.
    Appellant's argument that the project would "devastate" a terrapin nesting
    habitat also lacks merit. Pursuant to N.J.A.C. 7:7-9.37(b),
    development that would directly or through secondary
    impacts on the relevant site or in the surrounding region
    adversely affect critical wildlife habitats is
    discouraged,[11] unless: (1) [m]inimal feasible
    interference with the habitat can be demonstrated; (2)
    [t]here is no prudent or feasible alternative location for
    the development; and (3) [t]he proposal includes
    appropriate mitigation measures.
    Here, the Township's project clearly includes appropriate mitigation measures
    to offset any interference with the terrapin habitat at the Park.
    By working with Dr. Wnek, the Township was able to modify the gabion
    wall design to provide the terrapins better access to nesting sites by adding
    thirty-six "turtle transit tunnels" through the wall. These tunnels enable the
    terrapins to travel from the shoreline to the Park. The Township also included
    11
    "Discouraged" is defined in N.J.A.C. 7:7-1.5 to mean that the proposed
    project is "likely to be rejected or denied" unless "mitigating or compensating
    measures can be taken so that there is a net gain in quality and quantity of the
    coastal resource of concern" and the proposed use is in the public interest.
    A-3173-16T3
    13
    a "turtle garden" away from the playground and other amenities for the terrapins.
    To further protect this habitat, DEP imposed seasonal restrictions on any work
    involving construction equipment along the waterfront, and required the
    Township to maintain the vegetation in the turtle garden. 12 In addition, Dr.
    Wnek agreed to consult with the Township throughout the completion of the
    project.
    With these modifications to the Township's original proposal, we are
    satisfied that DEP properly found that the requirements of N.J.A.C. 7:7-9.37
    were met. Therefore, we reject appellant's contrary contention.
    C.
    Appellant next claims that DEP violated the Endangered or Threatened
    Species Habitat regulation, N.J.A.C. 7:7-9.36, by allowing development in a
    12
    On October 15, 2018, we granted appellant's motion to supplement the record
    on appeal to include information that the Township had mowed some of the
    vegetation at the Park after June 1, 2018 in violation of the seasonal work
    restrictions set forth in its permit. On July 26, 2018, DEP issued a notice of
    violation to the Township for violating this condition. This post-permit
    violation is not relevant to the present appeal, which involves the question of
    whether DEP properly issued the permit to restore and protect the Park. DEP
    addressed the violation appellant brought to our attention and, if appellant was
    dissatisfied with that resolution, it could have taken action to challenge it.
    Appellant did not do so.
    A-3173-16T3
    14
    habitat "essential for survival" of six endangered and threatened bird species.
    We disagree.
    Pursuant to N.J.A.C. 7:7-9.36,
    [d]evelopment of endangered or threatened wildlife or
    plant species habitat is prohibited unless it can be
    demonstrated, through an endangered or threatened
    wildlife or plant species impact assessment, . . . that
    endangered or threatened wildlife or plant species
    habitat would not directly or through secondary impacts
    on the relevant site or in the surrounding area be
    adversely affected.
    During its review of the Township's application, DEP staff determined that the
    State's Landscape Maps13 identified six endangered and threatened species
    which may live in Ocean County, including the Bald Eagle, Northern Harrier,
    Osprey, Black Skimmer, Roseate Tern, and Black-Crowned Night Heron.
    However, after reviewing these maps, and documentation submitted by
    the Township, DEP staff found that the "proposed work locations do not feature
    suitable State- or Federally-listed threatened or endangered species habitat." In
    addition, the staff concluded that "no adverse impact to suitable open water
    habitat that occurs for protected avian species foraging along Barnegat Bay is
    13
    The New Jersey Division of Fish and Wildlife's Endangered and Nongame
    Species Program is responsible for documenting imperiled species and their
    habitats in New Jersey by preparing these Landscape Maps.
    A-3173-16T3
    15
    anticipated through the proposed project."         DEP staff's findings are fully
    supported by the record developed during the permit review process. Therefore,
    we discern no principled basis on this record for disturbing DEP's determination
    that the application complied with N.J.A.C. 7:7-9.36.
    D.
    We also disagree with appellant's contention that DEP violated the "public
    trust doctrine" by permitting the Township to "cut off" the public's access to the
    Bay by building a gabion wall to protect the Park's shoreline from erosion. The
    public trust doctrine "derives from the ancient principle of English law that land
    covered by tidal waters belonged to the sovereign, but for the common use of
    all the people." Borough of Neptune City v. Borough of Avon-By-The-Sea, 
    61 N.J. 296
    , 303 (1972); see also Matthews v. Bay Head Improvement Ass'n, 
    95 N.J. 306
    , 312 (1984) (noting that "[t]he public trust doctrine acknowledges that
    the ownership, dominion and sovereignty over land flowed by tidal waters,
    which extend to the mean high water mark, is vested in the State in trust fo r the
    people").
    DEP codified these principles in N.J.A.C. 7:7-16.9(a) which, in pertinent
    part, states:
    [p]ublic access to the waterfront is the ability of the
    public to pass physically and visually to, from, and
    A-3173-16T3
    16
    along tidal waterways and their shores and to use such
    shores, waterfronts and waters for activities such as
    navigation, fishing, and recreational activities
    including, but not limited to, swimming, sunbathing,
    surfing, sport diving, bird watching, walking, and
    boating.
    However, "no public access is required if there is no existing public access
    onsite[,]" but "[a]ny existing public access shall be maintained or equivalent
    onsite public access shall be provided." N.J.A.C. 7:7-16.9(k)(3)(i).
    Contrary to appellant's contention, DEP's approval of the gabion wall did
    not violate the public trust doctrine or N.J.A.C. 7:7-16.9. Before Superstorm
    Sandy destroyed the Park, it was mainly sand, with rip-rap imperfectly
    protecting the shore. The Township did not fund any specific access route to
    the Bay, but residents could walk over the rip-rap to get into the water.
    The construction of the gabion wall did not deprive the public of access
    to the Bay any more than the rip-rap previously had. Indeed, the public can walk
    on top of the gabion wall along the shoreline, and step off of it into the Bay at
    any point because the top of the wall is no more than two feet above the surface
    of the water. Because the public has the same access to the Bay that it had before
    A-3173-16T3
    17
    Superstorm Sandy,14 we conclude that DEP fully complied with the public trust
    regulation, N.J.A.C. 7:7-16.9.
    It is also important to note that the restored Park now provides increased
    public access to the Bay through the addition of a walking path, recreational
    activities, a playground, and a small parking lot. The shoreline is also better
    protected. Thus, the present factual circumstances are plainly distinguishable
    from the cases appellant relies upon to claim that the construction of a gabion
    wall, which citizens can walk along as they access the Bay, violates the public
    trust doctrine. See Van Ness v. Borough of Deal, 
    78 N.J. 174
    , 180 (1978)
    (barring a municipality from roping off an area of beach in front of a casino and
    reserving it for the use of casino members only); Borough of Neptune City, 
    61 N.J. at 298, 310
     (striking a financial barrier to public water access); Matthews,
    238 N.J. Super. at 312, 332 (voiding a regulation prohibiting public water
    access).
    14
    In addition, the public continues to have the option, as it did while there was
    only rip-rap at the shoreline, of accessing the Bay by walking around the wall
    and rip-rap to the northern and southern boundaries of the Park to enter the
    water.
    A-3173-16T3
    18
    E.
    Finally, appellant argues that DEP "violated its constitutional due process
    obligations" by failing to publish notice of its July 13, 2016 approval of the
    Township's permit until February 15, 2017, when it appeared in the Bulletin.
    Again, we disagree.
    The record does not disclose a specific explanation for the delayed
    publication of the approval of the permit, although DEP has stated that it was
    caused by an inadvertent oversight. 15 Regardless of the reason for the delay,
    however, it is clear that appellant suffered absolutely no prejudice as a result of
    it.
    DEP published notice of the filing of the Township's application in the
    Bulletin, and thereafter provided a thirty-day public comment period. During
    the comment period, appellant submitted a letter in opposition to the proposed
    project. Unlike several other commenters, appellant then took no further action
    prior to the permit's approval. When it was issued, the permit specifically stated
    that "any person who is aggrieved by this decision or any of the conditions of
    15
    In its appellate brief, appellant speculates that DEP may have delayed
    publishing notice of the approval of the permit so the public would lose interest
    in it, thereby ensuring there would be less opposition to any d ecision to grant
    the permit. However, nothing in the record supports this assertion.
    A-3173-16T3
    19
    this permit may request a hearing within 30 days after notice of the decision is
    published in the DEP Bulletin."       Thus, appellant had thirty days after the
    publication of the February 15, 2017 Bulletin to request a hearing. It did not do
    so.16
    Because DEP provided notice to appellant of the filing of the application,
    allowed appellant to submit written comments addressing the application, and
    afforded appellant the right to request a hearing, DEP provided appellant with
    all of the process due it under the circumstances of this case.
    F.
    In sum, we conclude that DEP's decision to approve the Township's
    application for a CAFRA permit to restore and protect the Park for the public's
    use was neither arbitrary, capricious, or unreasonable. DEP followed all of the
    governing regulatory policies, and its findings supporting its approval of the
    project are fully supported by the administrative record.
    Affirmed.
    16
    As previously noted, appellant also had the opportunity to seek a stay of
    construction pending appeal from DEP and this court. However, it did not
    pursue this remedy.
    A-3173-16T3
    20