IN THE MATTER OF RICARDO MORA AND KELLI KENNY, WATERFRONT DEVELOPMENT PERMIT NO. 1XXX-XX-0005.1 WFD 160001, CHALLENGED BY JAMES BODENHEIMER (DEPARTMENT OF ENVIRONMENTAL PROTECTION) ( 2019 )


Menu:
  •                              NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-3381-17T4
    IN THE MATTER OF RICARDO
    MORA AND KELLI KENNY,
    WATERFRONT DEVELOPMENT
    PERMIT NO. 1517-12-0005.1 WFD
    160001, CHALLENGED BY JAMES
    BODENHEIMER.
    _______________________________
    Argued September 25, 2019 - Decided October 30, 2019
    Before Judges Koblitz, Gooden Brown, and Mawla.
    On appeal from the New Jersey Department of
    Environmental Protection, Permit No. 1517-12-
    0005.1 WFD 160001.
    Neil Yoskin argued the cause for appellant James
    Bodenheimer (Cullen and Dykman, LLP, attorneys;
    Neil Yoskin, of counsel and on the briefs).
    Kevin J. Coakley argued the cause for respondents
    Ricardo Mora and Kelli Kenny (Connell Foley LLP,
    attorneys; Kevin J. Coakley, on the brief).
    David Andrew Tuason, Deputy Attorney General,
    argued the cause for respondent New Jersey
    Department of Environmental Protection (Gurbir S.
    Grewal, Attorney General, attorney; Jason W.
    Rockwell, Assistant Attorney General, of counsel;
    David Andrew Tuason, on the brief).
    Spector Gadon & Rosen, PC, attorneys for
    respondents Paul Rosen, Wendy Rosen, and the
    Wendy Rosen Trust (Johan Ashrafzadeh-Kian, on the
    brief).
    PER CURIAM
    James Bodenheimer appeals from the January 10, 2018 final agency
    decision of the Department of Environmental Protection (DEP), denying his
    December 1, 2016 request for an adjudicatory hearing to challenge a permit
    issued to his neighbors, Ricardo Mora and Kelli Kenny (Mora/Kenny), under
    the Waterfront Development Act (WDA), N.J.S.A. 12:5-3, and implementing
    Coastal Zone Management Rules (CZM Rules), N.J.A.C. 7:7. The permit,
    issued on October 12, 2016, approved the construction of a four-foot by 267-
    foot fixed dock on Mora/Kenny's adjacent property located on Long Beach
    Boulevard in Long Beach Township.
    On appeal, Bodenheimer raises the following points for our consideration:
    I.1 [BODENHEIMER] HAS STANDING TO BRING
    AN ADMINISTRATIVE APPEAL, AND THE
    DEPARTMENT INCORRECTLY DENIED HIS
    REQUEST FOR A HEARING AND A STAY
    PENDING THIS APPEAL.
    1
    We have eliminated the point heading describing the standard of review and
    renumbered the remaining points accordingly.
    A-3381-17T4
    2
    II. THE ISSUANCE OF THE PERMIT . . . WAS IN
    DIRECT VIOLATION OF THE DEPARTMENT'S
    OWN REGULATIONS DESIGNED TO PROTECT
    THE ENVIRONMENT AND MUST BE REVERSED.
    A. THE DEPARTMENT'S SHELLFISH
    HABITAT RULE REQUIRES THAT THE
    LOCATION AND SIZE OF THE
    PROPOSED DOCK BE ADJUSTED TO
    MINIMIZE THE AREA OF PROTECTED
    SHELLFISH HABITAT.
    B. THE DEPARTMENT'S SUBMERGED
    VEGETATION    HABITAT     RULE
    REQUIRES THAT THE LOCATION
    AND SIZE OF THE DOCK BE
    ADJUSTED TO MINIMIZE THE TOTAL
    AREA OF PROTECTED HABITAT
    COVERED BY THE STRUCTURE.
    C. THERE IS NO DE MINIMIS
    EXCEPTION      FROM        THE
    REQUIREMENT THAT THE SIZE OF
    THE PROPOSED DOCK BE MINIMIZED
    TO    PROTECT   THE    MARINE
    ENVIRONMENT.
    We affirm.
    We glean the following facts from the record.      Bodenheimer owns
    property located at lot 28, and Mora/Kenny own the adjacent lot immediately
    north of Bodenheimer's at lot 30.       Both lots front Barnegat Bay, but
    Mora/Kenny's property has 125 feet of frontage while Bodenheimer's frontage
    is significantly narrower.   In November 2015, Mora/Kenny submitted
    A-3381-17T4
    3
    applications to DEP for a waterfront development (WD) permit and a riparian
    license to construct a four-foot by 289-foot fixed dock on their property,
    projecting into Barnegat Bay. On December 3 and 12, 2015, Bodenheimer
    submitted letters to DEP, objecting to "the location and the length" of
    Mora/Kenny's proposed dock.
    In his letters, Bodenheimer explained that he did not object to a prior
    permit, granted in 2012 to Mora/Kenny's predecessor in interest, because the
    permit approved a 165-foot dock "located approximately [sixty] feet north" of
    their shared boundary. However, according to Bodenheimer, Mora/Kenny's
    application located the dock "[sixteen] feet [n]orth" of their shared property line,
    which would only provide "[thirty-two] feet" of distance between Mora/Kenny's
    proposed dock and a dock Bodenheimer anticipated constructing on his property
    in the future, rendering navigation "in close proximity" to the two docks
    "difficult and possibly unsafe."      Additionally, Bodenheimer asserted that
    Mora/Kenny's 289-foot proposed dock would "block the [n]orth/[s]outh
    channel" used by "boat owners in the neighborhood" to access "the inter-coastal
    waterway."
    A-3381-17T4
    4
    Bodenheimer's southerly neighbors, Paul and Wendy Rosen, owners of lot
    26,2 similarly objected to the location and length of Mora/Kenny's proposed
    dock, asserting that it would "exceed by over [forty] or [sixty] feet any dock on
    the coastal area of Barnegat Bay," including theirs. In letters to DEP dated
    November 25 and December 8, 2015, the Rosens objected to "the proposed
    dock's excessive length, hindrance of navigation or access to adjacent water
    areas, (which would violate N.J.A.C. 7:7-12.5), hindrance of existing
    navigational channels (which implicates N.J.A.C. 7:7-9.7), and the general loss
    of use and enjoyment that would be suffered by the inhabitants." They requested
    "a hearing to prevent the construction" of the proposed dock, and "as a nearby
    property owner within the class of persons enumerated in N.J.A.C. 7:7-
    24.3(b)(6), . . . notice of any revision, amendment, or other communication
    between the applicants and [DEP] in connection with [the] applications."
    On February 10, 2016, DEP approved the application and issued a WD
    permit to Mora/Kenny, subject to certain pre-construction conditions. The
    permit allowed "any person . . . aggrieved by [the] decision" to "request a
    hearing within [thirty] days" after publication of the decision "in the DEP
    2
    The owners of lot 26 are Paul Rosen, Wendy Rosen, and the Wendy Rosen
    Trust.
    A-3381-17T4
    5
    Bulletin."   In a March 14, 2016 e-mail, the Rosens' attorney, Johan Kian,
    communicated with Eric M. Virostek, DEP's Environmental Specialist in the
    Division of Land Use Regulation, requesting that DEP "reconsider its decision
    short of [the Rosens] filing a request for an adjudicative hearing." To support
    the request, Kian submitted a March 2, 2016 soundings plan for Mora/Kenny's
    proposed dock prepared by an engineering firm the Rosens retained.            The
    Rosens' soundings plan purportedly showed that by relocating the proposed dock
    to the northern side of the property, "a [four-foot] depth could be attained using
    a substantially shorter dock than the one requested[.]" On March 24, 2016,
    Virostek responded that after comparing the Rosens' soundings plan with the
    engineering plan submitted with Mora/Kenny's application, he agreed that "if
    the dock was relocated to the opposite side of the property, it could have been
    slightly shorter, but only by approximately [ten to fifteen feet]."
    On June 30, 2016, Mora/Kenny submitted a revised application to DEP,
    reducing the length of the proposed dock by twenty-two feet. Specifically, the
    application sought a permit for the construction of a four-foot by 267-foot dock
    with a four-foot by twenty-foot "'L' section at the waterward end."           The
    supporting engineering plan confirmed that the proposed construction complied
    with all regulations, including the Shellfish Habitat Rule, N.J.A.C. 7:7-9.2, the
    A-3381-17T4
    6
    Submerged Vegetation Rule, N.J.A.C. 7:7-9.6, and the Navigation Channels
    Rule, N.J.A.C. 7:7-9.7. The plan stated that the proposed dock would "not result
    in a loss of navigability[,]" nor "extend into a navigation channel[,]" as "[t]he
    nearest authorized navigation channel [was] approximately [500 feet] water
    ward of the end of the proposed dock."
    On October 12, 2016, DEP approved the revised application subject to
    certain pre-construction conditions, including Mora/Kenny's payment of
    $6,927.80 to "[DEP's] account for Shellfish Habitat Mitigation" in accordance
    with N.J.A.C. 7:7-9.2(d), and Mora/Kenny's receipt of "a tidelands grant, lease
    or license from the Bureau of Tidelands." As with the February 10, 2016
    approval, the WD permit allowed an appeal of an aggrieved person within thirty
    days after publication of the decision in the DEP Bulletin in accordance with
    N.J.A.C. 7:7-28.1(b).   The decision was published in the DEP Bulletin on
    November 2, 2016, and within thirty days of publication, Bodenheimer and the
    Rosens submitted separate requests for an adjudicatory hearing.
    While those requests were pending, on December 7, 2016, the Tidelands
    Resource Council (Council) conducted a hearing on Mora/Kenny's application
    A-3381-17T4
    7
    for a riparian license, pursuant to N.J.S.A. 12:3-12.1.3 At the hearing, the
    Council considered Mora/Kenny's application for "a [ten]-year revocable
    [riparian] license," required as a pre-construction condition of DEP's issuance
    of the WD permit, as well as the objections to the application interposed by
    Bodenheimer and the Rosens. Attorneys for Mora/Kenny, Bodenheimer, and
    the Rosens appeared at the hearing.
    Mora/Kenny's attorney, Allyson Kasetta, acknowledged that the Council
    was not bound by DEP's issuance of the WD permit. However, she informed
    the Council that DEP's determination indicated that all "applicable regulations
    have been met" and "should be a strong indicator" that the proposed dock "does
    not, in fact, interfere with navigation or property rights, particularly because
    [Mora/Kenny] . . . made a good-faith effort to shorten the dock to 267 feet in
    light of the objections . . . raised."       Specifically referring to the Rosens'
    soundings plan and their attorney's email exchange with Virostek, submitted as
    exhibits to the Council by the objectors, Kasetta disputed the Rosens' claim that
    relocating the dock "to the northern side of the property" could "potential[ly]
    3
    Under N.J.S.A. 12:3-12.1, the Council "is the public body responsible for the
    stewardship of the State’s riparian lands[,]" pursuant to which the Council
    "determine[s] whether applications for the lease, license, or grant of riparian
    lands are in the public interest[.]"
    A-3381-17T4
    8
    . . . shorten the dock significantly." Because the proposed dock had already been
    shortened by twenty-two feet under the revised application, Kasetta stressed
    "[t]here would be no real difference in the length if it were to be relocated " as
    the Rosens requested.
    Additionally, referring to the 2012 permit issued to Mora/Kenny's
    predecessor in interest for the construction of a 165-foot dock near the center of
    the property, according to Kasetta, even the Rosens' soundings plan showed that
    "there [was] no longer anywhere near sufficient depth at 165 feet in the center
    of the property" because of changes in "the physical circumstances." Kasetta
    also specifically refuted Bodenheimer's claim "that the location of the dock
    [was] an impediment to his property[,]" by reiterating that Mora/Kenny had
    complied with all applicable regulations governing the location, including
    ensuring that there was "a minimum of four feet from all property lines" 4 and "a
    minimum of eight feet of open water" separating docks. 5
    4
    N.J.A.C. 7:7-12.5(b)(7)(ii) requires "[c]onstruction and placement" of docks
    "a minimum of four feet from all property lines[.]"
    5
    N.J.A.C. 7:7-12.5(b)(7)(i) requires "[a] minimum of eight feet of open water
    . . . between any docks if the combined width" of any existing or proposed docks
    "over the water exceeds eight feet."
    A-3381-17T4
    9
    In turn, Bodenheimer's and the Rosens' attorneys objected to the
    application as "contrary to the public interest."      They asserted that "the
    Submerged Aquatic Vegetation Rule and the Shellfish Habitat Rule" required
    the applicant to "minimize adverse impacts to the maximum extent
    practicable[,]" which had not been done by Mora/Kenny. They also claimed the
    proposed dock would adversely affect navigability. According to the Rosens'
    attorney, if Bodenheimer built a dock on his property, crammed between the
    Rosens' and Mora/Kenny's dock, then the three docks would be "very close
    together" and would "create a lot of congestion in the area[,]" making it
    "difficult for the public to navigate in that area" and "causing conflict amongst
    the neighbors." He argued that by Mora/Kenny building their dock "a few feet
    north" and "[thirty feet] shorter[,]" these problems would be alleviated. Both
    attorneys asked the Council "to table th[e] application" until a determination was
    made by DEP on the respective hearing requests filed by both Bodenheimer and
    the Rosens.
    After confirming that the timeline for Bodenheimer's construction of a
    dock on his property was undetermined, a Council member pointed out that the
    related objection was "all conjecture" based "on what[ was] going to happen in
    the future if . . . Bodenheimer builds a dock." The Council member also stressed
    A-3381-17T4
    10
    that neither of the objectors adequately addressed whether Mora/Kenny's
    northern neighbor could lodge the same objections if the proposed dock was
    relocated to the northern side of Mora/Kenny's property as both objectors urged.
    At the conclusion of the hearing, the Council declined to table the application
    pending DEP's decision on the objectors' hearing requests, and voted
    unanimously to grant Mora/Kenny the riparian license to construct the proposed
    dock in accordance with the October 12, 2016 DEP WD permit.
    Responding to Bodenheimer's objection directed to DEP, in a December
    21, 2016 letter, Mora/Kenny opposed Bodenheimer's third-party request for a
    hearing, asserting Bodenheimer "failed to establish any statutory or
    constitutionally-protected property interest that would confer standing to pursue
    an adjudicatory hearing."      Mora/Kenny also argued that Bodenheimer's
    "substantive challenges to the issuance of the [p]ermit [were] without merit."
    On January 11, 2017, Bodenheimer reiterated his objections to DEP and
    requested a stay of the permit. On January 10, 2018, DEP Commissioner Bob
    Martin denied "Bodenheimer's requests for an adjudicatory hearing and a stay,"
    determining that Bodenheimer had no "standing" to obtain a hearing and his
    arguments opposing DEP's issuance of the WD permit to Mora/Kenny were
    A-3381-17T4
    11
    without merit.6 The Commissioner also found no "good cause" as required under
    N.J.A.C. 7:7-28.3(b) to grant a stay.
    Regarding standing, the Commissioner noted that DEP was "precluded
    from granting an administrative hearing unless Bodenheimer demonstrate[d]
    that he ha[d] either a statutory right to a hearing or a constitutionally protected
    property interest affected by the permit," neither of which was shown.
    According to the Commissioner, "the [WDA] does not provide a statutory right
    to a hearing for persons who are not applicants." Further, Bodenheimer "ha[d]
    not articulated any claim of a constitutionally protected individual property
    interest" affected by DEP's decision to issue the WD permit, "and none [was]
    apparent from a review of the hearing request."
    The Commissioner explained:
    Bodenheimer claims only that the proposed [dock] will
    hinder navigation and will negatively affect the use and
    enjoyment of his property. However, "[f]ear of damage
    to one's recreational interest or generalized property
    rights shared with other property owners is insufficient
    to demonstrate a particularized property right or other
    special interest." Spalt[ v. DEP, 
    237 N.J. Super. 206
    ,
    212 (App. Div. 1989)].          Because Bodenheimer's
    claimed interests fall into this latter category, he does
    not have a particularized property interest sufficient to
    require an adjudicatory hearing.
    6
    We were advised at oral argument that the Rosens' hearing request is still
    pending.
    A-3381-17T4
    12
    Finding that the proposed dock complied with "all applicable law and
    rules[,]" the Commissioner also rejected Bodenheimer's claim on substantive
    grounds. As to N.J.A.C. 7:7-12.5(b)(9), requiring that any "proposed structure
    not hinder navigation or access to adjacent water areas[,]" the Commissioner
    determined Mora/Kenny's application "adequately addresse[d] this criterion
    because the end of the approved [dock was] approximately 200 feet from the
    nearest authorized navigation channel used to access the neighboring docks and
    Barnegat Bay."      Therefore, contrary to Bodenheimer's assertion, the
    Commissioner concluded the proposed dock was not "a navigation hazard"
    because there was "adequate room to navigate and access adjacent water areas."
    Further, according to the Commissioner, Bodenheimer's contention that the
    approved dock would "act as an impediment to accessing his property" was
    "speculative at best" because he "[did] not currently have a [dock] on his
    property."7
    Turning to Bodenheimer's claims that the proposed dock violated N.J.A.C.
    7:7-12.5(b)(2), requiring that the dock be designed to "minimize[] adverse
    7
    The Commissioner noted that Bodenheimer's August 4, 2017 application for
    a WD permit to construct a four-foot by 234-foot dock on his property was
    approved by DEP on October 12, 2017.
    A-3381-17T4
    13
    environmental impact to the maximum extent feasible[,]"8 and N.J.A.C. 7:7-
    12.5(c) and (d), requiring compliance with the "shellfish" and "submerged
    vegetation rule[s]," respectively, the Commissioner noted that the engineering
    plan accompanying the application "demonstrate[d] that the water depths on the
    northern portion of the [p]roperty [were] not significantly greater than the d epths
    in the proposed location." This fact undermined Bodenheimer's entreaty to
    shorten and relocate the dock to the northern side of the Mora/Kenny property
    to resolve his concerns.
    When dismissing Bodenheimer's claim that the proposed dock violated
    N.J.A.C. 7:7-9.6(b)(6), requiring that the proposed dock be constructed in such
    a way as to limit "impacts to submerged vegetation habitat at the site[,]" the
    Commissioner explained that "the [p]lan depict[ed] the proposed mooring area
    at a water depth of greater than [four] feet[,]" and "a shorter [dock] would not
    satisfy th[e] rule, as the mooring piles [were] located just outward of a measured
    8
    In a related context, we explained that the phrase "to the maximum extent
    practicable[,]" qualifying the protection afforded in N.J.A.C. 7:7E-7.14 "reflects
    a balanced regulatory sensitivity to the physical, economic, and other pragmatic
    constraints that affect waterfront construction." In re Riverview Dev., LLC,
    Waterfront Dev. Permit No. 0908-05-0004.3 WFD 060001, 
    411 N.J. Super. 409
    ,
    435 (App. Div. 2010).
    A-3381-17T4
    14
    water depth of 3.6 feet."9 Thus, the Commissioner concluded that "there [was]
    no practicable or feasible way to reduce the length of the [dock] and still satisfy
    the [four]-foot depth requirement."
    Likewise, in rejecting Bodenheimer's claim that the dock violated
    N.J.A.C. 7:7-9.2(d)(3)(i)(2), requiring that the proposed dock be constructed in
    a size "to limit . . . adverse impacts" to "shellfish habitat" to the maximum
    "extent practicable[,]" the Commissioner explained:
    The area of shellfish impacted is [1436] square feet of
    documented moderate density hard clam area and
    scallop production area. The [dock] will be constructed
    of non-polluting materials and no dredging will take
    place during construction of this project. . . .10 Impact
    to shellfish habitat, including any impact that results
    because of the requirements to meet the submerged
    vegetation habitat rule, is addressed by mitigation of
    the shellfish habitat impact. Accordingly, the permit
    requires Mora/Kenny to make a monetary contribution
    to [DEP's] account for Shellfish Habitat Mitigation in
    the amount of $6,927.80 in accordance with N.J.A.C.
    7:7-17.9.[11] Thus Mora/Kenny's proposed [dock]
    9
    Under N.J.A.C. 7:7-9.6(b)(6)(vi), "[a] minimum water depth of four feet at
    mean low water must be present in the area where the boats will be moored[.]"
    10
    N.J.A.C. 7:7-9.2(d)(3)(i)(1) requires that "[t]he proposed dock" be
    "[c]onstructed of non-polluting materials[,]" and N.J.A.C. 7:7-9.2(d)(3)(v)
    prohibits "dredging . . . in conjunction with the construction or use of the
    dock[.]"
    11
    In accordance with N.J.A.C. 7:7-17.9, N.J.A.C. 9:7-9.2(m) provides that
    "mitigation for impacts to shellfish habitat and the marine ecosystem associated
    A-3381-17T4
    15
    minimizes impacts to shellfish habitat to the maximum
    extent practicable.
    Upon concluding that shortening and relocating the dock to the northern
    side of the property, as urged by Bodenheimer, would not minimize impacts to
    submerged vegetation and shellfish habitats, the Commissioner stressed DEP
    did not direct applicants "where to site a [dock] so long as the proposed location
    otherwise complie[d] with the CZM Rules[,]" as it did here.          This appeal
    followed.
    Our role in reviewing the Commissioner's decision is limited.            We
    "review[] a final agency decision with deference," In re Freshwater Wetlands
    Gen. Permit No. 16, 
    379 N.J. Super. 331
    , 341 (App. Div. 2005), and "will not
    reverse . . . unless: (1) it was arbitrary, capricious, or unreasonable; (2) it
    violated express or implied legislative policies; (3) it offended the State or
    Federal Constitution; or (4) the findings on which it was based were not
    supported by substantial, credible evidence in the record." Univ. Cottage Club
    with the construction of a dock, . . . include . . . a monetary contribution to
    [DEP's] dedicated account for shellfish habitat mitigation." "[T]he monetary
    contribution . . . is based on the area of shellfish habitat covered by planned
    structures and mooring areas, the documented shellfish density supported by the
    local habitat, and the commercial value of the resource[,]" and "is intended to
    ensure that adverse impacts to the shellfish resource are minimized and habitat
    improvements are promoted in areas outside of the impacted area through the
    use of the mitigation funds." 
    Ibid. A-3381-17T4 16 of
    Princeton N.J. Corp. v. N.J. Dep't of Envtl. Prot., 
    191 N.J. 38
    , 48 (2007)
    (citing In re Taylor, 
    158 N.J. 644
    , 656 (1999)). "This deference is even stronger
    when the agency, like DEP . . . , 'has been delegated discretion to determine the
    specialized and technical procedures for its tasks.'" In re Freshwater Wetlands
    Gen. Permits, 
    372 N.J. Super. 578
    , 593 (App. Div. 2004) (quoting Newark v.
    Nat. Res. Council, Dep't of Envtl. Prot., 
    82 N.J. 530
    , 540 (1980)).
    "We also extend substantial deference to an agency's interpretation of its
    own regulations, reasoning that 'the agency that drafted and promulgated the
    rule should know the meaning of that rule.'" In re Orban/Square Props., LLC,
    ___ N.J. Super. ___ (App. Div. 2019), slip op at 20 (quoting Permit No. 
    16, 379 N.J. Super. at 341-42
    ). "And, too, we do not reverse an agency's determination
    'because of doubt as to its wisdom or because the record may support more than
    one result.'" In re Freshwater Wetlands Gen. 
    Permits, 372 N.J. Super. at 593
    (quoting In re N.J. Pinelands Comm'n Resolution, 
    356 N.J. Super. 363
    , 372
    (App. Div. 2003)). Thus, "[a]lthough an appellate court is 'in no way bound by
    the agency's interpretation of a statute or its determination of a strictly legal
    issue,'" In re Carter, 
    191 N.J. 474
    , 483 (2007) (quoting Mayflower Sec. Co. v.
    Bureau of Sec., 
    64 N.J. 85
    , 93 (1973)), "if substantial evidence supports the
    agency's decision, 'a court may not substitute its own judgment for the agency's
    A-3381-17T4
    17
    even though the court might have reached a different result[.]'" 
    Ibid. (quoting Greenwood v.
    State Police Training Ctr., 
    127 N.J. 500
    , 513 (1992)).
    Given these principles, we reject Bodenheimer's contention that the
    Commissioner's determination that he was not entitled to an adjudicatory
    hearing was "incorrect as a matter of law, and constitute[d] arbitrary and
    unreasonable actions." "A third-party objector's right to a formal administrative
    hearing is delineated and circumscribed by the Administrative Procedure Act
    (APA), N.J.S.A. 52:14B-1 to -25."        In re Auth. For Freshwater Wetlands
    Statewide Gen. Permit 6, Special Activity Transition Area Waiver For
    Stormwater Mgmt., Water Quality Certification, 
    433 N.J. Super. 385
    , 406 (App.
    Div. 2013). "Although 'the APA does not foreclose such third parties from
    seeking judicial review of the merits of a permit once it is issued by an agency,'"
    
    id. at 406-07
    (quoting In re Riverview Dev., LLC, 
    411 N.J. Super. 409
    , 425
    (App. Div. 2010),
    the APA expressly prohibits a state agency from
    promulgating rules or regulations entitling a third party
    to an administrative appeal as a contested case under
    the APA unless "specifically authorized to do so by
    federal law or State statute," or unless a person "has [a]
    particularized interest sufficient to require a hearing on
    constitutional or statutory grounds."
    [Id. at 407 (quoting N.J.S.A. 52:14B-3.1(d), -3.2(c), -3.3).]
    A-3381-17T4
    18
    Thus, "[t]he rule is firmly settled that a trial-type adjudicatory hearing is
    not allowed in such matters except to an applicant who can show a statutory
    right or a constitutionally protected property interest." In re Waterfront Dev.
    Permit No. WD88-0443-1, Lincoln Harbor Final Dev., Weehawken, Hudson
    Cty., 
    244 N.J. Super. 426
    , 436 (App. Div. 1990). Here, Bodenheimer agrees
    that no provision of the WDA statute affords him any statutory right to a hearing.
    See 
    Spalt, 237 N.J. Super. at 212
    . "Without a statutory right to a trial-type
    hearing, . . . objectors must show that they have a 'particularized property
    interest sufficient to require a hearing on constitutional . . . grounds. '" Gen.
    Permits, 
    185 N.J. 452
    , 463-64 (2006) (quoting N.J.S.A. 52:14B-3.1, -3.2).
    However, in Spalt, we held that "[f]ear of damage to one's recreational interest
    or generalized property rights shared with other property owners is insufficient
    to demonstrate a particularized property right or other special interest." 237 N.J.
    Super. at 212.
    There, DEP refused to grant a hearing to shell fishermen who had a one-
    year leasehold in shellfish beds or to neighboring property owners challenging
    DEP's issuance of a Coastal Area Facility Review Act (CAFRA) permit to a
    corporate entity redeveloping a Barnegat Bay marina. 
    Id. at 208-11.
    As to the
    neighboring property owners, we held that "simply because some of the
    A-3381-17T4
    19
    plaintiffs reside close to the proposed [marina] site and are fearful of resultant
    injury to their property, does not mean they are entitled to an adjudicatory
    hearing." 
    Id. at 212.
    Further, because the shell fishermen could not show that
    any damage would result to them before the expiration of their shellfish bed
    leases, we concluded they did not possess a sufficient property interest to
    warrant an adjudicatory hearing. 
    Id. at 212-13.
    Similarly, in In re Amico/Tunnel Carwash, 
    371 N.J. Super. 199
    , 204 (App.
    Div. 2004), we held that adjacent landowners objecting to the construction of a
    car wash lacked a "particularized property interest" that triggered the right to a
    hearing before the Office of Administrative Law (OAL). There, a Secaucus
    service station owner applied to the New Jersey Meadowlands Commission
    (NJMC) for three bulk variances needed to construct a car wash on his property.
    
    Ibid. Adjacent landowners, a
    married couple who had participated in a hearing
    on the variances and had submitted expert reports opining that construction of
    the car wash would "create unsafe traffic conditions and have an adverse impact
    on the surrounding neighborhood[,]" appealed NJMC's approval of t he variance
    application. 
    Id. at 205-06.
    Finding that any increased traffic congestion in front of their property was
    "similar to the impacts commonly experienced by owners of property in the
    A-3381-17T4
    20
    vicinity of any proposed new development[,]" we held that the adjacent
    landowners did not have "a particularized property interest in [the service station
    owner's] development plan that entitle[d] them to [an adjudicatory] hearing."
    
    Id. at 212.
    See also Riverview 
    Dev., 411 N.J. Super. at 411
    (App. Div. 2010)
    (affirming DEP's denial of an adjudicatory hearing to townhouse residents
    challenging DEP's issuance of a WD permit to a high-rise developer on the
    ground that the residents, who complained that the proposed project would
    obstruct their views of the Hudson River and New York City skyline and worsen
    traffic near their dwellings, lacked a particularized property interest sufficient
    to require a hearing on constitutional grounds).
    In General Permits, our Supreme Court reinforced these principles in
    upholding DEP's determination that neighboring property owners "had no
    statutory or constitutional right" to "a trial-type hearing" before the OAL "as
    part of the administrative permitting 
    process." 185 N.J. at 456
    .      There,
    Maramark Builders, LLC "intend[ed] to build single-family residences" on a
    seven-acre "undeveloped piece of property in Livingston Township . . . ." 
    Id. at 455.
      "While seeking subdivision approval from the Livingston Township
    Planning Board, Maramark applied to [DEP] for a freshwater wetlands permit
    to fill a portion of 'isolated' wetlands on that property, pursuant to the Freshwater
    A-3381-17T4
    21
    Wetlands Protection Act (FWPA), N.J.S.A. 13:9B-1 to -30." Gen. 
    Permits, 185 N.J. at 455
    . "[P]roperty owners and a community organization" objected "to the
    issuance of the permit on the ground that the wetlands [were] not 'isolated' and
    that filling them [would] exacerbate flooding conditions on their adjoining
    properties." 
    Id. at 455-56.
    After "extensively examin[ing] the wetlands issue over a two -year
    period[,]" DEP "issued Maramark a freshwater wetlands permit[,]" and rejected
    the neighbors' demand for an adjudicatory hearing. 
    Id. at 456.
    On the neighbors'
    appeal, the Court applied the three-factor test enunciated in Mathews v.
    Eldridge, 
    424 U.S. 319
    , 334-35 (1976) in order to assess the constitutionality of
    the administrative procedure and determine whether the third-party objectors
    lacked the particularized property interest entitling them to an adjudicatory
    hearing. In re Freshwater Wetlands Statewide Gen. 
    Permits, 185 N.J. at 467
    .
    The Court explained:
    The first Mathews factor is "the private interest that will
    be affected by the official action;" the second is "the
    risk of an erroneous deprivation of such interest
    through the procedures used, and the probable value, if
    any, of additional or substitute procedural safeguards;"
    and the last is "the Government's interest, including the
    function involved and the fiscal and administrative
    burdens that the additional or substitute procedural
    requirement would entail."
    A-3381-17T4
    22
    [Ibid. (quoting 
    Mathews, 424 U.S. at 335
    ).]
    The Court concluded that "DEP's administrative review procedures for the
    issuance of a freshwater wetlands permit satisfied traditional notions of due
    process." 
    Id. at 456.
    Applying the Mathews factors, the Court "recognize[d]
    that the issuance of the freshwater wetlands permit was a preliminary stage of
    the approval process for the Maramark development[,]" and "[e]ven if [its]
    issuance . . . , by itself, would mean a greater run-off of water from the
    Maramark property, the adequacy of the drainage system" which "controlled
    whether there would be any additional flooding onto the neighbors' properties "
    was "primarily a matter for the Planning Board." 
    Id. at 473.
    Further, "no
    additional procedural safeguards in the DEP's decision-making process were
    constitutionally required, particularly when measured against . . . 'the fiscal and
    administrative burdens that the additional or substitute procedural requirement
    would entail.'" 
    Ibid. "Last, because the
    threat to the objectors' properties by the issuance of
    [the] permit [was] speculative, the objectors did not possess the type of
    'particularized property interest' that entitled them to a trial-type hearing . . . ."
    
    Ibid. See also Permit
    6, 433 N.J. Super. at 406-08 
    (affirming DEP's denial of
    neighboring property owners' request for an adjudicatory hearing to challenge
    A-3381-17T4
    23
    DEP's issuance of a freshwater wetlands permit in connection with Care One,
    Inc.'s expansion of its assisted living facility, which challenge was "premised on
    CareOne's project posing a threat of increased stormwater discharge to their
    properties" and failed to demonstrate "a particularized property right" giving
    "rise to a constitutional basis for granting a hearing").
    Likewise, here, we agree with the Commissioner that Bodenheimer's
    claims that the proposed dock will hinder navigation and negatively affect the
    use and enjoyment of his property are the type of "generalized property rights
    shared with other property owners" that are "insufficient to demonstrate a
    particularized property right or other special interest."   See Spalt, 237 N.J.
    Super. at 212. Further, DEP's decision-making process ensured compliance with
    the specific CZM Rules Bodenheimer asserts were violated.           Additionally,
    because the threat to Bodenheimer's property would only potentially emerge
    upon his future construction of a dock on his property, we also agree with the
    Commissioner that the threat to Bodenheimer's property by the issuance of the
    WD permit was "speculative[.]" In re Freshwater Wetlands Statewide Gen.
    
    Permits, 185 N.J. at 473
    .
    As the Court noted in In re Freshwater Wetlands Statewide Gen. Permits,
    "the administrative process provided . . . cannot be viewed in isolation[,]" but
    A-3381-17T4
    24
    should be considered "[i]n the totality of the circumstances . . . ." 
    Id. at 471-72.
    Short of a trial-type OAL hearing, "[t]he Legislature has maintained significant
    avenues for third-party objectors to present their concerns about proposed
    permits to agency decision-makers before they reach a final determination on a
    permit application." Riverview 
    Dev., 411 N.J. Super. at 425
    . Specifically,
    under N.J.S.A. 52:14B-3.1(a), "all interested persons are afforded reasonable
    opportunity to submit data, views or arguments, orally or in writing, during any
    proceedings involving a permit decision[.]" While "such oral presentations and
    written submissions are less formal than a contested case tried before an
    Administrative Law Judge," they still "provide an effective and efficient means
    for third-party objectors to voice their concerns with the State officials who will
    make the ultimate permitting decision." Riverview 
    Dev., 411 N.J. Super. at 425
    .
    Here, Bodenheimer availed himself of that opportunity in his written
    submissions to DEP objecting to Mora/Kenny's application before the
    permitting decision was made. Bodenheimer also participated in the hearing
    before the Council, which, while applying admittedly different substantive
    standards, considered his specific objections before determining whether the
    issuance of a riparian license required as a pre-condition to construction under
    the WD permit was "in the public interest[.]" N.J.S.A. 12:3-12.1. Thus, the
    A-3381-17T4
    25
    issuance of the WD permit to Mora/Kenny "was but one step in a larger
    permitting process" before Mora/Kenny could begin constructing the dock.
    Gen. 
    Permits, 185 N.J. at 472
    . 12
    We also affirm the rejection of Bodenheimer's contentions that "[DEP]
    failed to adhere to the CZM Rules" by not requiring the construction of "a
    shorter dock" at an "alternative location" in order to "minimiz[e] impacts to
    Shellfish and Submerged Vegetation Habitat" for the reasons expressed in the
    Commissioner's comprehensive January 10, 2018 decision. We add only that
    our thorough review of the record convinces us that the Commissioner's decision
    was not "arbitrary, capricious, or unreasonable" and was "supported by
    substantial, credible evidence in the record." Univ. Cottage Club of 
    Princeton, 191 N.J. at 48
    .
    Affirmed.
    12
    Indeed, to satisfy additional pre-conditions to construction of the dock under
    the WD permit, on October 23, 2017, Mora/Kenny's application to the Army
    Corps of Engineers, the federal authority charged with issuing permits for
    construction activities affecting waters of the United States, was granted, and on
    February 23, 2017, Mora/Kenny granted an easement to DEP to comply with the
    Shellfish Habitat Rule.
    A-3381-17T4
    26