dr-humayun-akhtar-and-yosaria-akhtar-v-jdn-properties-at-florham-park ( 2015 )


Menu:
  •                    NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2327-12T3
    DR. HUMAYUN AKHTAR and                  APPROVED FOR PUBLICATION
    YOSARIA AKHTAR,
    February 24, 2015
    Plaintiffs-Appellants,           APPELLATE DIVISION
    v.
    JDN PROPERTIES AT FLORHAM PARK, L.L.C.,
    JDN PROPERTIES, L.L.C., JOSEPH NATALE,
    RANDY DELUCA, DELTRUS, L.L.C., and
    CASEY & KELLER, INC.,
    Defendants-Respondents.
    ________________________________________________________________
    Argued January 6, 2015 – Decided February 24, 2015
    Before Judges Koblitz, Haas and Higbee.
    On appeal from Superior Court of New Jersey,
    Law Division, Morris County, Docket No.
    Docket No. L-1701-07.
    Jay J. Rice argued the cause for appellants
    (Nagel Rice, L.L.P., attorneys; Mr. Rice, of
    counsel and on the brief; Randee M. Matloff,
    on the brief).
    Andrew S. Cimino argued the cause for
    respondent Casey & Keller (Marshall Dennehey
    Warner Coleman & Goggin, attorneys; Mr.
    Cimino, of counsel and on the brief).
    The opinion of the court was delivered by
    KOBLITZ, J.A.D.
    Plaintiffs,    Dr.       Humayun    Akhtar   and     his    wife,    Yosaria,
    appeal from a jury verdict dismissing their malpractice claims
    against defendant,1 engineering firm Casey & Keller, Inc.                             A
    judge     initially      awarded      plaintiffs         summary     judgment       on
    liability, but a second judge reconsidered and vacated the grant
    of summary judgment.            A third judge held a full trial, which
    yielded a no-cause jury verdict.                Plaintiffs maintain that they
    were entitled to summary judgment as a matter of law, or at
    least a new trial, because their expert's opinion was unrebutted
    by defendant's expert.           In light of plaintiffs' burden of proof
    and the conflicting evidence as to the factual predicates for
    their expert's opinion, we affirm.
    I
    As developer JDN Properties at Florham Park, L.L.C., (JDN
    FP),    was   planning      a    ten-lot       project    on   a   set     of     steep
    properties, its manager, Randy DeLuca, engaged engineer Michael
    Lanzafama's firm, Casey & Keller, Inc.                   Lanzafama's firm was to
    perform    title,     topographic,        and    utilities     surveys,         prepare
    designs for a road and other infrastructure for the project, and
    1
    "Defendant" refers only to Casey & Keller.       The complaint
    against JDN FP, JDN Properties, and Joseph Natale, the principal
    of both entities, as well as on site-manager Randy DeLuca and
    his company Deltrus (collectively, the JDN defendants) is the
    subject of a separate consolidated appeal under docket numbers
    A-5907-11 and A-6064-11.
    2                                A-2327-12T3
    submit      those   documents      for   approval     from    the     appropriate
    government agencies.             In the course of that work, Lanzafama
    drafted an individual lot grading plan for what would become
    plaintiffs' property, depicting two semi-circular Allan Block
    retaining       walls       and     incorporating       the      manufacturer's
    specifications.         The       grading     plan    was     filed    with    the
    municipality in conjunction with the property's site plan and
    approved by borough engineer Robert Kirkpatrick in April 2005.
    Plaintiffs contracted with JDN FP to purchase the lot and
    have a home constructed, with certain modifications, such as one
    to accommodate a full walk-out basement, which ultimately drove
    the price up to just over $1.56 million.              Akhtar, who frequently
    visited the site during construction, testified at trial that
    shortly before the closing, he was surprised to find that the
    builder had deviated from Lanzafama's design by constructing a
    much longer, higher retaining wall along the eastern side of the
    property than originally designed.               He acknowledged, however,
    that he had requested that the wall be raised by at least one
    foot   to    accommodate     a    backyard    pool,   and    DeLuca    introduced
    testimony suggesting that plaintiffs' requests for modifications
    required a more level backyard and consequently, expansion of
    the    retaining    wall.         Lanzafama   claimed   at     trial    that   his
    personnel had no knowledge of the modification until their site
    3                               A-2327-12T3
    visit for a final survey, but confirmed that his design provided
    sufficient        information       for     building       the       wall     ultimately
    constructed.
    Nonetheless, the modification was undertaken without prior
    municipal approval, and JDN FP had apparently never obtained a
    permit for the wall in the first place.                        On one of his site
    visits, borough engineer Kirkpatrick noticed the change, along
    with   other      unauthorized      work.       Because    the       municipality       had
    never inspected the retaining wall's construction, he requested
    a letter assuring that the wall had been built according to the
    manufacturer's specifications.                  Lanzafama wrote the letter at
    DeLuca's request.
    At   trial     Lanzafama     testified      that,      before    doing     so,   he
    discussed      with    DeLuca       the   methods      that      had   been      used   to
    construct the wall and inspected the wall himself, albeit after
    its    completion.          He   explained      that   while        investigating,       he
    observed     geogrid       fabric   protruding      from      the    wall   at    various
    points, confirming that the three appropriately spaced layers of
    geogrid     had     been    placed.       He    also   observed        drainage     pipes
    extending from the wall, suggesting that the required toe drain
    had been installed at the crushed stone's base to evacuate any
    water that might build up within or alongside the wall.                                 His
    field crew took measurements of the wall to confirm its location
    4                                    A-2327-12T3
    and elevation, and he himself examined soil immediately behind
    the     wall    to    confirm    its    stability.            He    further       reviewed
    photographs his crew had taken on site visits, which he believed
    showed that the blocks, gravel, and geogrid were appropriately
    placed and that the correct compaction tools had been used.
    Moreover,      he    recalled    his    own     prior   site       visits    at    various
    stages of the wall's construction, albeit undertaken for other
    reasons, where he nonetheless saw the wall being built with
    appropriate materials and equipment.                    He concluded from those
    observations that the wall had been appropriately built and felt
    comfortable writing the letter.
    Borough        building    inspector       Stephen      Jones     testified        at
    deposition that the letter had not specifically been requested
    in    connection        with    the    review     of    any    application         for     a
    certificate of occupancy.              It was, in any event, submitted in
    connection       with    such    an    application.      The       borough     issued      a
    temporary certificate of occupancy for the property on June 1,
    2006.     Pursuant to the contract, JDN FP then remitted a "time of
    the essence letter" to plaintiffs and set a closing date for
    June 9.        Akhtar performed a walk-through of the property prior
    to closing and requested repair of certain defects.                           Plaintiffs
    first became aware of serious problems with the property when
    5                                      A-2327-12T3
    they learned from a plumber not long after closing that the
    house was "sliding."           They have never moved in.
    Subsequent investigations by engineering firm LAN, hired by
    JDN FP, revealed cracking in the foundation under a substantial
    portion   of    the    eastern    side    of    the       house   due   to   improperly
    compacted soil.        Plaintiffs, meanwhile, retained Henry Naughton,
    an engineering consultant, who concluded that the cracks in the
    foundation      were     attributable         to     the     soil's     poor    bearing
    capacity.      He further concluded that the eastern retaining wall,
    which   Lanzafama      had     vouched   for,       had    questionable      long    term
    stability that, because of transport of soil through the wall,
    would undermine structures supported on the soil.                        He testified
    that failure of the retaining wall was one of the causes of the
    movement of the house.           LAN recommended installing helical piles
    to   bolster    the     foundation       and       arrest    its    settlement,          but
    plaintiffs and JDN FP were never able to agree on an appropriate
    remedy.
    At trial, plaintiffs claimed Lanzafama's certification that
    the wall had been built correctly caused the certificate of
    occupancy      to     issue,     requiring         plaintiffs      to   close       on    a
    deficiently built house with a failing retaining wall.                          To that
    end, they introduced Naughton, who testified that no engineer
    should issue a certification without conducting an investigation
    6                                     A-2327-12T3
    sufficient     to     make     the   engineer      reasonably      certain      of     its
    accuracy.        He     set     forth   numerous       investigatory           steps     a
    reasonable engineer might take to reach an appropriate level of
    certainty and how Lanzafama's course of conduct fell short.                             He
    recounted      that,     although     Lanzafama      had    never       overseen       the
    construction or inspected the wall as it was built, he should at
    least have discussed with the contractor how each aspect of the
    manufacturer's specifications had been met, that the soil had
    been appropriately compacted, and that the appropriate lengths
    of   geogrid    had     been    installed.          Moreover,      he    should      have
    requested    compaction        and   soil    density   test     results      from      the
    contractor     and     performed     independent     tests    if    the    contractor
    made none available.
    Naughton         acknowledged         that    Lanzafama       had        reviewed
    photographs depicting the progress of construction of the wall,
    but disagreed that anything meaningful could be learned from
    them.   He asserted, moreover, that, had Lanzafama conducted a
    proper investigation before issuing the letter, particularly had
    he performed any soil testing, it would have set off "bells and
    whistles" undermining any confidence he could have as to the
    retaining wall's construction.
    Plaintiffs        also     introduced        Martin    Grant,       an     expert
    surveyor.      Grant took a series of measurements at several points
    7                                   A-2327-12T3
    on the wall on eight occasions from October 2007 to June 2012,
    and concluded from them that the wall had moved approximately
    one to three inches, well in excess of what the manufacturer's
    specifications contemplate.            All movement, moreover, had been in
    a consistent easterly direction.
    Defendant introduced engineering expert Robert Simpson, who
    testified that the damage to the house had been caused by the
    improperly-compacted           fill    beneath      the      foundation,    not    the
    retaining wall.         As to the issue of breach, he summarized his
    understanding of what Lanzafama had done before preparing the
    letter, but never offered an opinion as to whether issuing the
    letter constituted a deviation from any accepted standard of
    care.     He candidly acknowledged that he would not have written
    the letter under those circumstances, but elaborated that that
    was because his firm "insist[s] upon full-time inspections for
    all     certifications"        and    that       defendant     might   simply      have
    different standards.
    Moreover, Simpson believed the evidence inconclusive as to
    whether    the   wall    had    been    properly      constructed.         There    was
    strong evidence from testing and measurements by the parties'
    experts that the wall was stable.                    He concluded from his own
    observations and other experts' data that the wall had shown
    little movement and was not failing, and that, even if it were,
    8                               A-2327-12T3
    it was too far from the house for that failure to have caused
    the damage the house sustained.
    Defendant     also    conducted      its     own     investigation   of    the
    wall's      movement,     taking    measurements      approximately      every    six
    months between November 2007 and August 2012.                   Such measurements
    revealed that the wall had moved no more than a fraction of an
    inch     within    that     time,    consistent       with    the    manufacturer's
    representation of the wall's flexibility.                     Lanzafama explained
    that Allan Block retaining walls were "basically soil masses
    that act as giant gravity walls," which acquire their stability
    from geogrid fabric installed "at various levels within the soil
    mass."      Soil between each pair of geogrid layers is compacted to
    form    a   single   unit    that    acts       together.      The   manufacturer's
    specifications show that the walls are designed to be flexible
    and "move with stresses, yet not yield."
    Finally, defendant presented Wayne Sanclimenti of Ron-Jon
    Construction, the subcontractor that built the eastern retaining
    wall.       Sanclimenti testified to his experience as a certified
    Allan Block builder for at least fifteen years, explained the
    wall's construction process with reference to photographs taken
    during that construction, and stated that the wall had been
    built according to the manufacturer's specifications.
    9                               A-2327-12T3
    The jury voted five to one that defendant did not breach
    its standard of care. Therefore, the jury did not proceed to
    consider proximate cause or damages.           The trial judge denied
    plaintiffs' motion for a new trial.
    II
    Plaintiffs    first        challenge     the     second       judge's
    reconsideration of the first judge's grant of partial summary
    judgment in favor of plaintiffs as to liability.                A court may
    grant summary judgment as to an issue only if "the pleadings,
    depositions, answers to interrogatories and admissions on file,
    together with affidavits, if any, show that there is no genuine
    issue as to any material fact challenged and that the moving
    party is entitled to a judgment or order as a matter of law."
    R.   4:46-2(c).    The   facts    must   be   viewed   in   a   light   most
    favorable to the non-moving party.        Polzo v. Cnty. of Essex, 
    209 N.J. 51
    , 56 n.1 (2012) (citing Brill v. Guardian Life Ins. Co.
    of Am., 
    142 N.J. 520
    , 523 (1995)).        The slightest doubt as to an
    issue of material fact must be reserved for the factfinder, and
    precludes a grant of judgment as a matter of law.                Saldana v.
    DiMedio, 
    275 N.J. Super. 488
    , 494 (App. Div. 1994).
    Any issues of credibility must be left to the finder of
    fact.   Conrad v. Michelle & John, Inc., 
    394 N.J. Super. 1
    , 13
    10                              A-2327-12T3
    (App. Div. 2007).        That is so even where a witness's testimony
    is uncontradicted, D'Amato by McPherson v. D'Amato, 305 N.J.
    Super. 109, 115 (App. Div. 1997), as long as, when considering
    the testimony in the context of the record, persons "of reason
    and fairness may entertain differing views as to [its] truth
    [.]"     Sons of Thunder, Inc. v. Borden, Inc., 
    148 N.J. 396
    , 415
    (1997) (quoting Ferdinand v. Agric. Ins. Co. of Watertown, N.Y.,
    
    22 N.J. 482
    , 494 (1956)).                Summary judgment should be denied
    unless "the right thereto appears so clearly as to leave no room
    for controversy."       
    Saldana, supra
    , 275 N.J. Super. at 495.                   Our
    review of a ruling on summary judgment is de novo, applying the
    same legal standard as the trial court.                    Nicholas v. Mynster,
    
    213 N.J. 463
    , 478 (2013).
    Once   made,   such    an    interlocutory        order     may   always   be
    reconsidered,    on    good     cause     shown    and    in   the   interests    of
    justice, prior to entry of final judgment.                     Johnson v. Cyklop
    Strapping Corp., 
    220 N.J. Super. 250
    , 257, 263-64 (App. Div.
    1987),    certif.     denied,      
    110 N.J. 196
       (1988).     Nonetheless,
    relitigation of an interlocutory order before successive judges
    of coordinate jurisdiction is generally disfavored, Cineas v.
    Mammone, 
    270 N.J. Super. 200
    , 207-08 (App. Div. 1994), and the
    "law of the case" doctrine invests the court with discretion to
    decline relitigation of any legal decision made earlier by an
    11                               A-2327-12T3
    equal court in the same case, Lombardi v. Masso, 
    207 N.J. 517
    ,
    538-39   (2011).     The     doctrine    is   not   inflexible,   however,
    Southport Dev. Group v. Twp. of Wall, 
    295 N.J. Super. 421
    , 430
    (Law Div. 1996), aff'd, 
    310 N.J. Super. 548
    (App. Div. 1998),
    certif. denied, 
    156 N.J. 384
    (1998), and a court maintains the
    discretion   to    revisit    the   earlier     ruling   whenever      those
    "'factors that bear on the pursuit of justice and, particularly,
    the search for truth'" outweigh "the value of judicial deference
    for the rulings of [the] coordinate judge."              Hart v. City of
    Jersey City, 
    308 N.J. Super. 487
    , 498 (App. Div. 1998) (quoting
    State v. Reldan, 
    100 N.J. 187
    , 205 (1985)).              Such may be the
    case, for example, where a court recognizes clear error in the
    earlier decision.    Sisler v. Gannett Co., Inc., 
    222 N.J. Super. 153
    , 159 (App. Div. 1987), certif. denied, 
    110 N.J. 304
    (1988).
    In Lombardi, our Supreme Court emphasized that:
    [A]lthough a party who obtains summary
    judgment may believe he is absolutely free
    of the litigation, it is a contradiction in
    terms to say that an interlocutory decree
    should be a finality.        The policy that
    litigation   must   have   an    end  is   not
    threatened   in   such    a    case,   because
    litigation has not yet terminated. In other
    words, a party's sense of finality upon
    summary judgment is just that – a feeling
    unsupported by the notion of what is, in
    fact, interlocutory.     Interlocutory orders
    are always subject to revision in the
    interests of justice.
    12                              A-2327-12T3
    
    [Lombardi, supra
    ,  207  N.J.  at  535-36
    (internal citations and quotation marks
    omitted).]
    The first motion judge granted partial summary judgment to
    plaintiffs     on    liability       exclusively        because         defendant    had
    introduced no expert testimony disputing Naughton's conclusion
    that defendant had deviated from the accepted standard of care.
    The second motion judge, relying on 
    Lombardi, supra
    , 207 N.J. at
    534-40,     concluded      that     the    order    granting       partial     summary
    judgment to plaintiffs should be vacated and a trial had on
    liability     as    well    as     damages.        He   noted      that     deposition
    testimony from the building inspector, Jones, put into dispute
    whether issuance of the certificate of occupancy was conditioned
    on   defendant's     letter,       and    that   data   as   to    movement    of    the
    retaining wall did not inexorably compel the conclusion that the
    wall was moving.        Yet plaintiffs' expert Naughton had relied on
    those factual circumstances to conclude that defendant's alleged
    breach of the accepted standard of care was a proximate cause of
    plaintiffs' damages.             Resolution of either factual dispute in
    defendant's    favor       would    call    into   question       the    integrity    of
    Naughton's opinion.          Moreover, there remained a factual dispute
    as to whether the wall had, in fact, been built according to
    specifications.
    13                                 A-2327-12T3
    The summary judgment standard takes into account who has
    the burden of proof on a matter.                          CPC Int'l, Inc. v. Hartford
    Accident     &    Indem.     Co.,    316    N.J.          Super.    351,    375   (App.     Div.
    1998), certif. denied, 
    158 N.J. 73
    (1999).                               We have explained
    that, where "'the movant is also the party bearing the burden of
    persuasion with regard to a claim, its initial summary judgment
    burden is somewhat higher in that it must show that the record
    contains evidence satisfying the burden of persuasion and that
    the evidence is so powerful that no reasonable jury would be
    free    to   disbelieve           it.'"         
    Ibid. (quoting Moore's Federal
    Practice, § 56.13(1), at 56-138 (3d ed. 1997)).                               Consequently,
    where the plaintiff's case hinges on the testimony of a witness,
    whose    credibility         is     subject          to    question      considering          that
    testimony        in   the    context       of    the       record,       there    may    be    no
    "'single, unavoidable resolution'" of disputed questions of fact
    so as to warrant summary judgment.                        
    Ibid. (quoting Brill, supra
    ,
    
    142 N.J. at 540).              Naughton's report was not so "clear and
    convincing [or] . . . [un]contradicted in any way by witnesses
    or circumstances, [or] so plain and complete that disbelief of
    the story could not reasonably arise in the rational process of
    an   ordinarily       intelligent         mind       .    .    .   ."      Cameco,      Inc.   v.
    Gedicke,     299      N.J.   Super.        203,       213      (1997)      (emphasis     added)
    (quoting 
    Ferdinand, supra
    , 22 N.J. at 494), aff’d as modified,
    14                                      A-2327-12T3
    
    157 N.J. 504
    (1999).              His report was not so eminently credible
    in the context of this record, even if unopposed formally by a
    defense expert, as to demand judgment as a matter of law in
    light of plaintiffs' burden of proof.
    Moreover,      the    factual      predicates      for   Naughton's      opinion
    remained      subject       to    legitimate       dispute.     The     value    of    an
    expert's opinion is in elucidating evidence in the record and
    explaining to lay factfinders the significance of that evidence
    in light of the expert's training and experience.                            State v.
    Odom, 
    116 N.J. 65
    , 76 (1989).                 Naked opinions have no probative
    value in themselves and, indeed, are inadmissible to the extent
    they bear no connection to the factual record.                      Pomerantz Paper
    Corp. v. New Cmty. Corp., 
    207 N.J. 344
    , 372 (2011).                          The first
    motion judge stated that Naughton asserted that defendant had
    breached the accepted standard of care, specifically because it
    had "issued [its] certification with no attempt to verify how
    the    retaining      walls       at    the   subject    property     were     actually
    constructed."        (Emphasis added).
    A finder of fact could certainly conclude otherwise on the
    record available at summary judgment.                     There was evidence that
    at    least   some     investigation          occurred,    including     Lanzafama's
    observations     during          site   visits,    discussion    with    DeLuca,      and
    examination      of     photographs           of   the    retaining     wall     during
    15                                A-2327-12T3
    construction.        The fact-sensitive inquiry as to whether that
    investigation was adequate to meet the standard of care Naughton
    outlined was one for the jury, which would remain free to reject
    Naughton's credibility in whole or in part, or to resolve any
    disputed    issue       as    to    the       factual     predicate    for    Naughton's
    opinion in defendant's favor.                  See Suarez v. E. Int'l Coll., 
    428 N.J. Super. 10
    , 27 (App. Div. 2012) (cautioning that a court
    must not invade a jury's exclusive role as factfinder), certif.
    denied, 
    213 N.J. 57
    (2013).                    Defendant's failure to introduce
    any expert to address the issue of breach, in other words, did
    not in itself warrant summary judgment for plaintiffs.                                  The
    factual record on which Naughton's opinion relied was simply not
    so one-sided as to warrant that relief.                       Gilhooley v. Cnty. of
    Union, 
    164 N.J. 533
    , 545 (2000).
    The second motion judge did not abuse his discretion in
    reconsidering the first motion judge's ruling, and after our de
    novo   review,     we    agree      that       plaintiffs    were     not    entitled    to
    summary judgment on liability.
    III
    Plaintiffs also contend that the trial judge should have
    granted    their    motion         for    a    directed    verdict.         The   standard
    applicable to a motion for a directed verdict is equivalent to
    that    applicable       to    one       for    summary     judgment.         Frugis      v.
    16                                 A-2327-12T3
    Bracigliano, 
    177 N.J. 250
    , 269-70 (2003).                         The trial court must
    accept as true all evidence that supports the non-moving party's
    position and all favorable legitimate inferences therefrom to
    determine whether the moving party is entitled to judgment as a
    matter of law.        Dolson v. Anastasia, 
    55 N.J. 2
    , 5 (1969).                          The
    court must deny the motion so long as "reasonable minds could
    differ,"   Johnson       v.    Salem       Corp.,    
    97 N.J. 78
    ,   92   (1984),    to
    ensure that any legitimate dispute of material fact be left to
    the jury, Lewis v. Am. Cyanamid Co., 
    155 N.J. 544
    , 567 (1998).
    The same standard applies on appeal.                       Estate of Roach v. TRW,
    Inc., 
    164 N.J. 598
    , 612 (2000).
    The trial judge concluded after reviewing the evidence that
    judgment as a matter of law was unwarranted as to the issues of
    both breach and proximate cause.                    Plaintiffs' challenge to this
    decision      rests   on      the    notion       that,     because       Simpson    never
    directly      rebutted     Naughton's        opinion       that     defendant    deviated
    from the accepted standard of care, plaintiffs are entitled to
    judgment as a matter of law.                     However, as already discussed,
    plaintiffs were not entitled to such relief in light of their
    burden of proof, so long as Naughton's credibility could be
    reasonably subject to question, see CPC 
    Int'l, supra
    , 316 N.J.
    Super.   at    375,   or      so    long    as    the     factual    predicate      to   his
    17                                   A-2327-12T3
    opinion remained subject to reasonable dispute on this record,
    see 
    Suarez, supra
    , 428 N.J. Super. at 27.
    [At the direction of the court, Parts IV, V
    and VI are omitted from the published
    version. See R. 1:36-2(d).]
    Affirmed.
    18                      A-2327-12T3