EPIC MANAGEMENT, INC. VS. NEW JERSEY SCHOOLS DEVELOPMENT AUTHORITY (NEW JERSEY SCHOOLS DEVELOPMENT AUTHORITY) ( 2018 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-3818-16T3
    EPIC MANAGEMENT, INC.,
    Appellant,
    v.
    NEW JERSEY SCHOOLS
    DEVELOPMENT AUTHORITY, and
    HALL CONSTRUCTION CO., INC., and
    ERNEST BOCK & SONS, INC.,
    Respondents.
    Argued July 2, 2018 – Decided July 18, 2018
    Before Judges Carroll and Rose.
    On appeal from the             New   Jersey     Schools
    Development Authority.
    Patrick T. Murray argued the cause for
    appellant (Peckar & Abramson, PC, attorneys;
    Gerard J. Onorata and Patrick T. Murray, on
    the brief).
    William Harla argued the cause for respondent
    New Jersey Schools Development Authority
    (DeCotiis, FitzPatrick, Cole & Giblin, LLP,
    attorneys; William Harla and Thomas A. Abbate,
    of counsel; Gregory J. Hazley, on the brief).
    Robert T. Lawless argued the cause for
    respondent   Hall   Construction   Co.,   Inc.
    (Hedinger & Lawless, LLC, attorneys; Robert
    T. Lawless, on the brief).
    PER CURIAM
    Appellant Epic Management, Inc. (Epic), the second-ranked
    bidder, appeals from the April 27, 2017 final agency decision of
    the New Jersey Schools Development Authority (SDA) awarding a
    contract to Hall Construction Co., Inc. (Hall), the first-ranked
    bidder,     for    the   design       and   construction        of    an   addition   and
    renovations to Millville Senior High School (the Project).                        In its
    decision, the SDA rejected bid protests filed by Epic and Ernest
    Bock & Sons, Inc. (Bock),1 the third-ranked bidder.
    The SDA concluded that Hall's chosen electrical contractor,
    R.    Palmieri     Electrical      Contractors,         Inc.    (Palmieri),     did   not
    exceed its aggregate rating limit set by the Treasury Division of
    Property Management and Construction (DPMC).                         The SDA also found
    Hall's alleged failure to indicate it would be self-performing
    electrical work on the Project not to be a material defect that
    warranted     rejection       of   its      bid   because       Hall's     purchase     of
    electrical        equipment     did    not    constitute        the     performance     of
    electrical work.
    On   appeal,      Epic      contends       the     SDA    violated      its    own
    administrative        regulations,          and   that    its    final     decision     is
    1
    Bock is not involved in this appeal.
    2                                   A-3818-16T3
    arbitrary, capricious, and unreasonable.                  We conclude otherwise,
    and affirm substantially for the reasons expressed by the SDA in
    its April 27, 2017 decision.
    I.
    The record establishes that on September 30, 2016, the SDA
    solicited bids for the Project.                  The SDA received five price
    proposals, which were publicly opened on March 2, 2017.                   Price and
    non-price scores were then weighted and tabulated to arrive at a
    final ranking of the bidders.           Hall was ranked first, while Epic
    and Bock were ranked second and third, respectively.
    As required by N.J.S.A. 52:18A-243(b) and the SDA's bid
    specifications,      each     bidder    was        required      to   identify     any
    subcontractors     it   intended       to    use    for    the    plumbing,      HVAC,
    electrical, and structural steel work components of the Project.
    Section 1.3 of the bid specifications further required a design
    builder to indicate whether it intended to self-perform any of
    those four component services.
    Hall's bid designated Palmieri as its electrical contractor.
    Hall   did   not   identify    itself       as   self-performing       any    of   the
    electrical work.
    3                                     A-3818-16T3
    Palmieri was DPMC classified and SDA prequalified for an
    aggregate contract limit of $15 million.2       As part of Hall's bid,
    Palmieri submitted a DPMC Form 701 certifying that its unfinished
    work   totaled   $5,420,508.    Palmieri's     quote    to    Hall   for   the
    electrical subcontract work was $9,168,000.        Together, Palmieri's
    subcontract quote and the value of its unfinished work fell within
    its $15 million aggregate limit.
    On March 17, 2017, Epic lodged a formal protest with the SDA
    seeking a rejection of Hall's bid.        Epic argued that Hall's bid
    was    materially   defective   because   it    named        an   unqualified
    subcontractor.      Specifically, Epic contended the value of the
    electrical work on the Project exceeded the approximately $9.5
    million Palmieri had remaining under its aggregate limit and hence
    Palmieri was ineligible to perform the Project's electrical work.
    Hall subsequently explained that it intended to directly
    purchase certain electrical supplies, and therefore Palmieri's
    pre-bid proposal to Hall excluded some of the required electrical
    equipment and materials for the Project.          In turn, Epic argued
    that Hall's bid was defective because Hall failed to disclose its
    2
    This meant that the amount of any subcontract to Palmieri, plus
    the value of Palmieri's unfinished work on other projects, public
    and private, could not exceed $15 million.
    4                                  A-3818-16T3
    decision to purchase materials and equipment as self-performing
    work.
    The   SDA   received   extensive   written   submissions    from   the
    parties and addressed in detail each of the issues they raised in
    its thorough April 27, 2017 decision.      Initially, the SDA rejected
    Epic's contention that Hall was precluded from purchasing the
    materials used in the electrical phase of the Project.          Citing the
    statutory language of N.J.S.A. 52:18A-243, the SDA explained:
    A plain reading of these provisions
    reveals that the work and materials for
    [school] facilities construction projects may
    be performed by a single contracting party.
    In other words, these provisions expressly
    authorize one contractor to provide all of the
    work and materials. However, these provisions
    also require that, to the extent another
    subcontractor will be used to provide "any"
    of the work and materials in the plumbing,
    HVAC, electrical or structural branches, then
    that subcontractor must be identified.
    Accordingly, there is nothing in the
    cited statute that precludes Hall from
    performing any of the work in the various
    branches or from obtaining any of the
    materials for that work.     N.J.S.A. 52:18A-
    243(b) merely requires Hall to identify any
    of the subcontractors to whom it will
    subcontract for the furnishing of "any of the
    work and materials" for the applicable
    branches. Here, Hall has identified Palmieri
    as the subcontractor it will subcontract with
    to perform the electrical work. While there
    may be an inherent assumption that Palmieri
    will also purchase the associated materials,
    the statutory provision at issue here does not
    mandate that that be the case.
    5                               A-3818-16T3
    Next, the SDA rejected Epic's argument that if Hall purchased
    the electrical supplies, it was required by both the statute and
    Section 1.3 of the bid specifications to disclose itself as "self-
    performing" the specified electrical work, and that Hall's failure
    to do so was a material defect in its bid.      The SDA found it
    "plainly evident" that
    the terms of the [request for proposals] only
    impose the self-performing identification and
    DPMC      classification       and      [SDA]
    prequalification for the performance of any
    "work" in the applicable branches. There is
    absolutely no reference to the provision of
    materials in the context of the above
    requirements.     As such, there was no
    requirement for Hall to identify itself as
    "self[-]performing"   in   the   context   of
    purchasing or obtaining materials for work
    relating to the four branches.
    . . . .
    This analysis is entirely consistent with
    common sense.     As noted by Hall in its
    submissions, anyone can purchase electrical
    equipment from a supplier. Put another way,
    one need not be licensed as an electrical
    contractor to obtain such equipment.
    Furthermore,    simply     because    the
    electrical   subcontractor    might   not   be
    purchasing the equipment does not mean that
    the electrical subcontractor can disclaim
    responsibility for the electrical work.
    N.J.S.A.   45:5A-9(a)    provides    that   an
    electrical contractor "shall assume full
    responsibility for inspection and supervision
    of all electrical work to be performed by the
    permittee in compliance with recognized safety
    standards." As such, even if the electrical
    6                          A-3818-16T3
    equipment is purchased by another entity, the
    electrical contractor retains the statutory
    duty to ensure that the electrical work is
    performed in compliance with recognized safety
    standards.
    We   would  also   note  that   N.J.S.A.
    2A:52:18A-243(a) makes explicit reference to
    "materials" when discussing plumbing and gas
    fitting, steam and hot water heating and
    ventilating apparatus, steam power plants,
    structural steel and miscellaneous ironwork.
    Significant by its omission is the absence of
    a similar reference to materials in the
    context of electrical work.     As such, the
    terms of the statute itself suggest an
    intentional exclusion of the provision of
    electrical materials from the scope of
    electrical work.
    II.
    On appeal, Epic argues that Hall's bid should have been
    disqualified because (1) it did not disclose its intention to
    self-perform work and the SDA's definition of "work" includes the
    providing of materials to a project; and (2) Hall's arrangement
    with Palmieri is an "improper sidestep" to the DPMC aggregate
    rating system.   We disagree.
    The general purpose of all public bidding laws is to "secure
    for the taxpayers the benefits of competition and to promote the
    honesty and integrity of the bidders and the system."       In re
    Protest of the Award of On-Line Games Prod. & Operation Servs.
    Contract, Bid No. 95-X-20175, 
    279 N.J. Super. 566
    , 589 (App. Div.
    1995).   The laws are to be "construed as nearly as possible with
    7                         A-3818-16T3
    sole reference to the public good.           Their objects are to guard
    against favoritism, improvidence, extravagance and corruption;
    their aim is to secure for the public the benefits of unfettered
    competition."      
    Ibid.
     (quoting Keyes Martin & Co. v. Dir., Div. of
    Purchase & Prop., 
    99 N.J. 244
    , 256 (1985)).              The conditions and
    specifications of a bid "must apply equally to all prospective
    bidders; the individual bidder cannot decide to follow or ignore
    these conditions . . . ."          Hall Constr. Co. v. N.J. Sports &
    Exposition Auth., 
    295 N.J. Super. 629
    , 635 (App. Div. 1996).
    Moreover,    any   material    departure   from    the   bid   specifications
    renders a bid non-conforming and invalid.            
    Ibid.
         Although minor
    or inconsequential discrepancies and technical omissions can be
    waived, material conditions cannot be waived by the contracting
    authority.    Meadowbrook Carting Co. v. Borough of Island Heights,
    
    138 N.J. 307
    , 314 (1994).
    Hence, in cases involving public bidding, the trial court
    must review a public body's determination as to whether a bid was
    conforming    to   determine    whether    its    decision     was   arbitrary,
    unreasonable, or capricious.        On-Line Games, 
    279 N.J. Super. at 590
    .   One legitimate inquiry in reviewing a public body's decision
    on whether a bid was conforming is whether there is substantial
    evidence in the record to support the conclusion.              Waste Mgmt. of
    8                                  A-3818-16T3
    N.J., Inc. v. Union Cty. Utils. Auth., 
    399 N.J. Super. 508
    , 525-
    26 (App. Div. 2008).
    When either a contractor or a subcontractor submits a bid for
    a project, it must also submit a certification that the award of
    "the subject contract would not cause the firm to exceed its
    aggregate rating . . . ."            N.J.A.C. 17:19-2.13(a).        Along with
    this certification, the firm must submit a statement of its current
    "backlog of uncompleted construction work, including public and
    private contracts."       N.J.A.C. 17:19-2.13(a).         "A firm shall not
    be   awarded   a   contract    which,    when   added    to   the   backlog    of
    uncompleted construction work [as shown on Form DPMC 701] would
    exceed the firm's aggregate rating." N.J.A.C. 17:19-2.13(c). This
    regulation     applies   to   both   contractors   and    subcontractors       in
    school building bidding situations under N.J.S.A. 18A:18A-18.
    Advance Elec. Co., Inc. v. Montgomery Twp. Bd. of Educ., 
    351 N.J. Super. 160
    , 176 (App. Div. 2002).
    The aggregate rating limit laws ensure that a bidder is
    financially qualified to perform the work in addition to its other
    contracts.     See Brockwell & Carrington Contractors, Inc. v. Kearny
    Bd. of Educ., 
    420 N.J. Super. 273
    , 280 (App. Div. 2011); Seacoast
    Builders Corp. v. Jackson Twp. Bd. of Educ., 
    363 N.J. Super. 373
    ,
    378 (App. Div. 2003) ("[T]he plain intent of the regulation was
    to insure the bidder's financial responsibility to undertake the
    9                               A-3818-16T3
    work by requiring aggregate-rating compliance both when the bid
    is submitted and when the contract is awarded.").        Significantly,
    it is a material, non-waivable defect of a bid for a contractor
    to name a subcontractor who is not qualified by reason of failure
    to comply with its aggregate rating limit. Brockwell & Carrington,
    
    420 N.J. Super. at 282
    .
    That   said,   N.J.S.A.   18A:18A-18(b)    does   not   require   the
    submission of a pre-bid quote from a subcontractor before awarding
    a contract to a contractor. While there is no obligation to submit
    such a quote, a contractor may not execute a contract with a public
    entity that will place it over that limit, and a public entity is
    not authorized to execute that contract.       Brockwell & Carrington,
    
    420 N.J. Super. at 282
    .   Thus, if Palmieri's quote put it over its
    $15 million limit, it would be a material breach of the bid
    specifications.
    Applying these well-established principles to this case, we
    affirm substantially for the reasons expressed by the SDA in its
    April 27, 2017 administrative determination, which is supported
    by sufficient credible evidence.       R. 2:11-3(e)(1)(D).    We conclude
    that, for purposes of calculating its aggregate rating limit,
    Palmieri was not required to include on its DPMC disclosure form
    the value of the electrical equipment supplied by Hall, which was
    not within the scope of Palmieri's subcontract.              Accordingly,
    10                              A-3818-16T3
    Palmieri's quote, when coupled with the value of its uncompleted
    work, did not exceed its $15 million aggregate rating limit.
    Further, N.J.S.A. 52:18A-243 did not prohibit Hall from purchasing
    the electrical supplies for the project, nor did its purchase of
    such supplies in its capacity as general contractor constitute
    self-performance of the Project's electrical work.
    Affirmed.
    11                          A-3818-16T3