JAMES FITZGIBBON, III VS. STAFFORD TOWNSHIP BOARD OF EDUCATION (L-1107-18, OCEAN COUNTY AND STATEWIDE) ( 2019 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-4411-17T2
    JAMES FITZGIBBON, III,
    Plaintiff-Appellant,
    v.
    STAFFORD TOWNSHIP
    BOARD OF EDUCATION and
    FALASCA MECHANICAL, INC.,
    Defendants-Respondents.
    ________________________________
    Argued March 4, 2019 – Decided May 13, 2019
    Before Judges Messano and Rose.
    On appeal from Superior Court of New Jersey, Law
    Division, Ocean County, Docket No. L-1107-18.
    Evan M. Labov argued the cause for appellant (Hankin
    Sandman Palladino & Weintrob, attorneys; John F.
    Palladino, Evan M. Labov, and Sean P. Higgins, on the
    briefs).
    Brent R. Pohlman argued the cause for respondent
    Stafford Township Board of Education (Methfessel &
    Werbel, attorneys; Brent R. Pohlman and Jason D.
    Dominguez, on the brief).
    Steven A. Berkowitz argued the cause for respondent
    Falasca Mechanical, Inc. (Berkowitz & Associates, PC,
    attorneys; Steven A. Berkowitz, on the brief).
    PER CURIAM
    On February 22, 2018, defendant Stafford Township Board of Education
    (the Board) requested bids for mechanical/plumbing improvements to the
    Stafford Schools. The public bid package required that
    [a]ll bidders must be pre-qualified by the New
    Jersey Schools Development Authority and the State of
    New Jersey, Department of the Treasury. All bidders
    must submit with their bid a current copy of their
    "Notice of Classification" and the "Total Amount of
    Uncompleted Contracts" . . . including the same
    documentation for all subcontractors.
    [(emphasis added).]
    The Board received two bids on March 16, 2018, the lowest from Surety
    Mechanical Services, LLC (Surety), and the second from defendant Falasca
    Mechanical, Inc. (Falasca). The Board rejected Surety's bid as non-conforming,
    because it failed to name its subcontractor(s), as required by the specifications
    and the Public School Contracts Law (the Act), N.J.S.A. 18A:18A–1 to –60.
    The Board awarded the $3.793 million contract to Falasca.
    Falasca's bid package included certifications from its two subcontractors
    stating their "Total Amount of Uncompleted Contracts" (form DPMC 701), as
    A-4411-17T2
    2
    required by N.J.A.C. 17:19-2.13. That Treasury Department regulation provides
    in pertinent part:
    (a) A firm shall include with each bid a certification
    that the firm’s bid for the subject contract would not
    cause the firm to exceed its aggregate rating limits,
    including consideration of its backlog of uncompleted
    construction work, including public and private
    contracts.
    (b) If at the time of a bid opening a question arises as
    to whether a bid for a project is within a firm's existing
    classification or aggregate rating, the bid shall be
    opened, and if the bid is at variance with the firm's trade
    classification or aggregate rating, the bid shall be
    rejected.
    (c) A firm shall not be awarded a contract which, when
    added to the backlog of uncompleted construction work
    would exceed the firm's aggregate rating. The backlog
    of uncompleted construction work shall be the total
    contract value of unbilled work, as evidenced by the
    most recent approved invoice (or other similar
    documentation) received by the bidder before or on the
    date of the bid.
    [Ibid. (emphasis added).] 1
    1
    The aggregate rating is "permissible aggregate work volume based upon the
    given contractor's submissions detailing financial ability." Brockwell &
    Carrington Contractors, Inc. v. Kearny Bd. of Educ., 
    420 N.J. Super. 273
    , 276
    (App. Div. 2011). Under N.J.A.C. 17:19-2.13, the bidder must demonstrate
    "that the bid does not exceed its aggregate rating less uncompleted work . . . ."
    Seacoast Builders Corp. v. Jackson Twp. Bd. of Educ., 
    363 N.J. Super. 373
    , 378
    (App. Div. 2003).
    A-4411-17T2
    3
    Both subcontractors stated their respective "amount of uncompleted work . . .
    from all sources (public and private)[,]" and each certified, "that the amount of
    this bid proposal, including all outstanding incomplete contracts does not exceed
    my prequalification dollar limit." However, both certifications predated the
    receipt of bids by several weeks; in fact, both predated the Board's advertisement
    for bids.
    Plaintiff James FitzGibbon, III, a resident and taxpayer of Stafford
    Township, filed a verified complaint seeking an order to show cause that
    Falasca's bid was materially defective, because the subcontractors' certifications
    were not current at the time of the bid. The Law Division judge denied plaintiff's
    request for temporary restraints, but she set the matter down for a hearing in
    short order.
    After considering oral argument on the return date, the judge concluded
    plaintiff failed to meet the requisite standard for injunctive relief. In particular,
    the judge concluded plaintiff did not establish "an ultimate, reasonable chance
    of success on the merits . . . ." See, e.g., Garden State Equal. v. Dow, 
    216 N.J. 314
    , 320 (2013) (holding successful request for injunctive relief must
    demonstrate "the applicant's claim rests on settled law and has a reasonable
    probability of succeeding on the merits . . . ."). The judge reasoned:
    A-4411-17T2
    4
    I'll assume for purposes of this application that the
    subcontractors were not made aware previously that
    [their DPMC 701s were] being submitted and . . . have
    not actually submitted a pre-bid for the project directly
    to Falasca. That it's clear that Falasca had a business
    relationship with these [sub]contractors.                That
    ultimately the risk of the project falls to the successful
    bidder. I agree that there was no risk to the Board by
    this . . . defect, if, in fact, it's considered a defect, and
    without any risk to the Board it does not constitute a
    material defect . . . .
    The judge dismissed the complaint and denied plaintiff's request for a stay.
    Plaintiff sought to file an emergent motion for a stay pending appeal to
    this court. A panel of our colleagues entertained the application but denied
    plaintiff's motion. Plaintiff then filed an emergent application for a stay with
    the Supreme Court, which entered a one-justice order denying the application
    "for failure to satisfy the standards for emergent relief stated in Crowe v.
    DeGioia, 
    90 N.J. 126
     (1982)."
    Before us, plaintiff argues "Falasca's failure to provide a current
    statement" of their subcontractor's uncompleted work made the bid materially
    defective. Our courts have adopted a two-prong test first articulated by Judge
    Pressler in Township of River Vale v. R.J. Longo Construction Co., 
    127 N.J. Super. 207
    , 216 (Law Div. 1974), for determining whether a deviation is
    material.
    A-4411-17T2
    5
    A deviation is material if: (1) waiver of such defect
    deprives the purchaser of its assurance that the contract
    will be entered into, performed, and guaranteed
    according to the specified requirements, and (2) it
    adversely affects the competitive bidding process by
    placing a bidder in a position of advantage over other
    bidders, or by otherwise undermining the necessary
    common standard of competition.
    [Hall Constr. Co. v. N.J. Sports & Exposition Auth.,
    
    295 N.J. Super. 629
    , 637 (App. Div. 1996) (citing
    Meadowbrook Carting Co. v. Borough of Island
    Heights, 
    138 N.J. 307
    , 315 (1994)).]
    Plaintiff argues the Board lacked discretion to waive a material defect and award
    Falasca the contract. See Meadowbrook Carting, 
    138 N.J. at 314-15
    .
    Defendants counter these arguments, contending Falasca's bid was not
    materially defective. Defendants also contend the appeal is moot, because the
    work has essentially been completed. 2 Plaintiff does not dispute this, but argues
    the appeal presents an issue of great public importance that will continue to
    2
    Falasca also argues that plaintiff failed to prove that the awarded contract
    actually caused the subcontractors to exceed their aggregate limits, which, it
    contends, was evidence critical to plaintiff's success. We reject this argument
    out of hand. Plaintiff never had the opportunity to engage in even limited
    discovery, nor does the appellate record include anything indicating that Falasca
    provided information to the judge at the time of the hearing regarding the
    subcontractors' current aggregate limits at the time of the bid. We also reject
    the idea that plaintiff was required to furnish that proof in order to succeed.
    A-4411-17T2
    6
    evade review. Without accepting defendants' arguments on the merits, we
    dismiss the appeal as moot.
    "Mootness is a threshold justiciability determination rooted in the notion
    that judicial power is to be exercised only when a party is immediately
    threatened with harm." Betancourt v. Trinitas Hosp., 
    415 N.J. Super. 301
    , 311
    (App. Div. 2010) (citing Jackson v. Dep't of Corr., 
    335 N.J. Super. 227
    , 231
    (App. Div. 2000)). "An issue is 'moot when our decision sought in a matter,
    when rendered, can have no practical effect on the existing controversy.'" Redd
    v. Bowman, 
    223 N.J. 87
    , 104 (2015) (quoting Deutsche Bank Nat'l Tr. Co. v.
    Mitchell, 422 N.J Super. 214, 221-22 (App. Div. 2011)). However, courts may
    decide such cases where the issues "are of substantial importance and are
    capable of repetition while evading review" unless determined by courts.
    Advance Elec. Co. v. Montgomery Twp. Bd. of Educ., 
    351 N.J. Super. 160
    , 166
    (App. Div. 2002) (citing Mistrick v. Div. of Med. Assistance & Health Servs.,
    
    154 N.J. 158
    , 165 (1998)).
    We acknowledge the public bidding process raises issues of substantial
    public importance. 
    Id. at 166-67
    . In Advance Electric, we considered the merits
    of an otherwise moot appeal because the plaintiff/unsuccessful bidder presented
    a facial challenge to the Act, arguing, in part, the failure to adopt regulations
    A-4411-17T2
    7
    governing the qualifications of subcontractors forced school boards to solicit
    separate bids for each portion of the work. 
    Id. at 164, 167-68
    . We concluded
    that the "issue plainly is capable of frequent recurrence until such time as either
    subcontractor qualification regulations are specifically adopted under the Act,
    or until the issues that [the plaintiff] now raises are judicially resolved." 
    Id. at 167
    .
    On the other hand, in Betancourt, we recognized the "public interest in
    decisions regarding the termination of life-sustaining medical treatments[,]" 
    415 N.J. Super. at 313
    , and that the case "involve[d] a situation that could evade
    judicial review." 
    Id. at 314
    . Nevertheless, we dismissed the appeal as moot
    based on the "unusual circumstances of [the] case [that] ma[d]e a recurrence of
    this specific set of facts unlikely." 
    Id. at 315, 319
    .
    We do not minimize the bona fides of plaintiff's claim.         In Seacoast
    Builders, although on different facts, and interpreting a prior version of N.J.A.C.
    17:19-2.13, we held "it [was] plain that the bidder must include with its bid the
    required certification that the bid does not exceed its aggregate rating less
    uncompleted work and that that condition must also be met at the time of the bid
    award." 363 N.J. Super. at 378 (emphasis added). Nor do we necessarily agree
    with the judge's assessment of the potential materiality of the defect.          See
    A-4411-17T2
    8
    Brockwell, 
    420 N.J. Super. at 276, 278-79
     (finding a bid was materially
    defective when the subcontractor's bid exceeded its aggregate limits less its
    backlog of uncompleted contracts).
    However, the record fails to reveal that contractors and subcontractors
    routinely supply stale DPMC 701 forms, or that public entities frequently excuse
    that conduct, such that the particular facts presented pose a prevalent problem
    in the realm of the public bidding statutes. 3 More importantly, we doubt that if
    such a problem were recurrent, it would escape our review. See Barrick v. State,
    Dep't of Treasury, 
    218 N.J. 247
    , 264 (2014) (noting "[a]ppellate review" of
    public bidding disputes "should be pursued with . . . alacrity"). Unfortunately,
    although plaintiff exercised diligence in pursuing his right to timely review in
    this case, it proved elusive. We trust it will not happen again.
    Dismissed.
    3
    Plaintiff supplied an unpublished opinion of another panel, in which our
    colleagues held that the failure to put any dollar amount of uncompleted work
    on the DPMC 701 was a material defect that could not be waived. The appeal
    in that case was not moot and presented different facts from those presented
    here.
    A-4411-17T2
    9