IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 40:55D-19 FOR A DETERMINATION THAT THE MONTVILLE-WHIPPANY 230KV TRANSMISSION PROJECT IS REASONABLY NECESSARY FOR THE SERVICE, CONVENIENCE OR WELFARE OF THE PUBLIC (NEW JERSEY BOARD OF PUBLIC UTILITIES) ( 2019 )


Menu:
  •                             NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2183-17T3
    IN THE MATTER OF THE
    PETITION OF JERSEY CENTRAL
    POWER & LIGHT COMPANY
    PURSUANT TO N.J.S.A. 40:55D-19
    FOR A DETERMINATION THAT
    THE MONTVILLE-WHIPPANY 230
    KV TRANSMISSION PROJECT IS
    REASONABLY NECESSARY FOR
    THE SERVICE, CONVENIENCE
    OR WELFARE OF THE PUBLIC.
    ___________________________________
    Submitted October 3, 2019 – Decided November 1, 2019
    Before Judges Nugent and DeAlmeida.
    On appeal from the New Jersey Board of Public
    Utilities, Docket No. EO15030383.
    Weiner Law Group LLP, attorneys for appellant
    Montville Township Board of Education (Stephen J.
    Edelstein, of counsel and on the brief; Aimee S.
    Weiner, on the brief).
    Cozen O'Connor, PC, attorneys for respondent Jersey
    Central Power & Light Company (Gregory Eisenstark,
    on the brief).
    Gurbir S. Grewal, Attorney General, attorney for
    respondent New Jersey Board of Public Utilities (Jason
    W. Rockwell, Assistant Attorney General, of counsel;
    Andrew M. Kuntz, Deputy Attorney General, on the
    brief).
    PER CURIAM
    Appellant Montville Township Board of Education (BOE) challenges the
    November 21, 2017 final order of respondent New Jersey Board of Public
    Utilities (BPU) granting the petition of respondent Jersey Central Power & Light
    Company (JCP&L) to construct a transmission line project not subject to the
    Municipal Land Use Law (MLUL), N.J.S.A. 40:55D-1 to -163, or any other
    governmental ordinances or regulations, permits, or license requirements made
    under the authority of the MLUL. We affirm.
    I.
    The following facts are derived from the record. JCP&L is a public utility
    in the business of purchasing, distributing, transporting, and selling electricity
    to approximately 1.1 million customers in New Jersey. It is subject to BPU's
    regulatory supervision and control. See N.J.S.A. 48:2-13(a).
    JCP&L filed a petition with the BPU pursuant to N.J.S.A. 40:55D-19
    seeking approval to construct a seven-mile long 230 kV transmission line
    between its substations in East Hanover Township and Montville Township (the
    A-2183-17T3
    2
    Project). The transmission line will be constructed in thirteen segments, mostly
    along existing transmission lines in JCP&L's existing right of way (ROW). The
    Project also includes upgrades to the two substations. The petition required BPU
    to determine whether the Project is reasonably necessary for the service,
    convenience, or welfare of the public and is, therefore, not subject to zoning and
    land use ordinances, or other government regulations enacted pursuant to the
    MLUL.
    BPU transferred the petition to the Office of Administrative Law for a
    hearing. BOE thereafter intervened. 1 An Administrative Law Judge (ALJ) held
    a three-day evidentiary hearing at which JCP&L presented live and pre-filed
    testimony describing the need for the new transmission line.
    The ALJ found that PJM Interconnection, LLC (PJM), a regional
    transmission organization, was approved by the Federal Energy Regulatory
    Commission to plan the region's electricity transmission grid. PJM ensures
    transmission owners, including JCP&L, comply with North American Electric
    Reliability Corporation (NERC) reliability standards.
    1
    Montville Township also intervened, but resolved its objections to the Project
    through a stipulation with JCP&L altering the Project's route.
    A-2183-17T3
    3
    PJM's responsibilities include identifying violations of NERC's reliability
    criteria.   There are three categories of conditions used to assess criteria
    violations: (1) Category A examines whether a system functions properly and
    can meet customer demand needs under normal operating conditions; (2)
    Category B examines system function when there is a loss of any single
    generating unit, transmission line, transformer, circuit breaker, capacitor, or
    single pole of a bi-polar transmission line; and (3) Category C examines system
    functionality when there are events resulting in the loss of any Category B
    element followed by the loss of a second element in the transmission system.
    In 2012, PJM identified a Category C reliability violation in JCP&L's bulk
    electric system resulting from the hypothetical outage of the Montville-Roseland
    230 kV line followed by the loss of either the Kittatinny-Newton 230 kV line or
    the Newton-Montville 230 kV line. This scenario would result in an interruption
    in service affecting approximately 86,719 JCP&L customers and violate PJM's
    planning criteria. A failure of this magnitude also could result in significant
    financial penalties for JCP&L. PJM determined the Project, if constructed,
    would address the criteria violation.
    JCP&L presented testimony detailing its consideration of alternative
    routes and methods to address the criteria violation. The utility considered
    A-2183-17T3
    4
    constructing a 115 kV transmission line, but rejected that option because its
    substations were not designed to support an additional 115 kV circuit, and an
    additional 115 kV line would not provide a satisfactory level of resilience.
    JCP&L also considered placing a 230 kV transmission line underground. The
    utility rejected this option because the underground transmission line would: (1)
    create several environmental issues related to wetlands and other sensitive areas;
    (2) multiply the costs of the Project by four to ten times; (3) increase the
    magnetic field exposure at ground level because the transmission line would be
    closer to the surface; and (4) increase repair time of the transmission line.
    JCP&L also performed a routing study that considered three alternative
    routes. One of the alternatives had two alternate segments. The routing study
    concluded the proposed route was superior because it is the shortest, minimizes
    the overall effect of the Project on the natural and human environment, avoids
    unreasonable costs and special design requirements, and best complies with the
    BPU's requirement concerning the use of existing ROWs because eighty-nine
    percent of the route parallels or rebuilds existing transmission lines.
    JCP&L presented two expert witnesses to discuss the effects of electric
    and magnetic fields (EMF), audible noise, and radio noise associated with the
    A-2183-17T3
    5
    Project. The experts concluded the EMF exposure when the Project is operating
    would be well below State and international exposure limits.
    At the hearing, BOE's President testified. She was not qualified as an
    expert witness in any field. She explained BOE takes issue with segment 10 of
    the Project, which calls for the construction of a transmission line adjacent to
    one of BOE's schools, the Robert R. Lazar Middle School.                The new
    transmission line would be carried on new 110-foot-tall monopoles constructed
    next to existing transmission lines in an existing JCP&L ROW abutting the
    property on which the school is located. The new monopoles will be seventy
    feet from the edge of the ROW and approximately 175 feet closer to the school
    than the existing transmission lines. Some of the trees that presently serve as a
    buffer between the school and the existing transmission line would be removed.
    The BOE President expressed concern regarding the height of the new
    monopoles and their proximity to the school. She stated that the BOE was
    concerned about the potential health effects on students and faculty arising fro m
    exposure to EMF and noise from the Project. BOE offered no expert testimony
    to substantiate its concern or any evidence with respect to the EMF and noise it
    contends would be generated by the Project. The BOE President also testified
    BOE has aesthetic concerns related to vegetation clearance near the school and
    A-2183-17T3
    6
    the visual prominence of the new monopoles from school property. Finally, the
    BOE President testified BOE was concerned the Project would limit potential
    expansion of the school building due to the proximity of the new monopoles.
    BOE did not identify any present plans for expansion of the school and offered
    no expert testimony opining on potential building expansion limitations.
    In rebuttal, JCP&L offered testimony from three witnesses with expertise
    in electric transmission facilities confirming the Project will meet all safety and
    design criteria, including with respect to EMF exposure and noise. In addition,
    the witnesses testified the proposed new monopoles will be shorter than existing
    structures. The witnesses also testified no building expansion would be allowed
    in JCP&L's existing ROW, whether or not the Project is constructed, and the
    Project would not affect construction outside the ROW.
    The ALJ issued an initial decision concluding the Project is reasonably
    necessary for the service, convenience, or welfare of the public to enable JCP&L
    to provide safe, adequate, and reliable service. BOE filed exceptions.
    On November 21, 2017, BPU issued a final order adopting the ALJ's
    initial decision in part 2, finding:
    (1) That, in light of the NERC criteria violation and
    reliability concerns identified in this proceeding, there
    2
    BPU modified the decision to account for the Montville/JCP&L stipulation.
    A-2183-17T3
    7
    is no reasonable, practical, and permanent alternative to
    the construction and operation of the Project that would
    have any less adverse impact upon the environment,
    surrounding community, or local land use ordinances;
    (2) That JCP&L conducted a good faith, reasonable,
    and extensive analysis of alternative methods for the
    Project, and the Project represents the most effective
    and efficient solution to the expected reliability criteria
    violations;
    (3) That the findings contained within this Order are
    the result of a thorough and complete review of the
    record in the proceeding. The Board's findings are
    limited to the facts and circumstances of this particular
    Project along this particular route and shall not be
    construed as a determination by this Board on any other
    application[; and]
    (4) That the Project as proposed is to be designed and
    constructed in accordance with all applicable industry
    standards in a manner that will minimize impacts upon
    the environment, to the extent known or predictable[.]
    In light of these findings, BPU determined JCP&L met its burden of proof under
    N.J.S.A. 40:55D-19 and ordered "that neither N.J.S.A. 40:55D-1, et seq., nor
    any other governmental ordinances or regulations, permits or license
    requirements made under the authority of N.J.S.A. 40:55D-1, et seq. shall apply
    to the siting, installation, construction, or operation of the Project . . . ."
    This appeal followed.       BOE makes the following arguments for our
    consideration:
    A-2183-17T3
    8
    POINT I
    UNDER THE APPLICABLE STANDARD       OF
    REVIEW, THE BPU'S DECISION MUST     BE
    REVERSED.
    POINT II
    THE BPU ERRED WHEN IT DETERMINED THAT
    JCP&L DEMONSTRATED THAT THE PROJECT IS
    REASONABLY NECESSARY FOR THE SERVICE,
    CONVENIENCE, OR WELFARE OF THE PUBLIC.
    POINT III
    THE BPU'S DECISION IS INCONSISTENT WITH
    ITS PRIOR DIRECTIVE THAT REASONABLE
    EFFORTS SHOULD BE MADE TO INCREASE THE
    DISTANCE BETWEEN TRANSMISSION LINES
    AND THE LAZAR MIDDLE SCHOOL.
    POINT IV
    THE BPU ERRONEOUSLY CONCLUDED THAT
    JCP&L CONSIDERED ALTERNATIVE ROUTES
    AND METHODS, INCLUDING THOSE RAISED BY
    THE BOARD.
    i.   THE BOARD PROPOSED, AND JCP&L
    FAILED TO ADEQUATELY CONSIDER, A 115 KV
    LINE ALTERNATIVE AND ITS ADVANTAGES AS
    COMPARED TO THE PROPOSED PROJECT.
    ii. JCP&L  FAILED    TO   ADEQUATELY
    CONSIDER A PARTIALLY UNDERGROUND
    ALTERNATIVE AND ITS ADVANTAGES AS
    COMPARED TO THE PROPOSED PROJECT.
    A-2183-17T3
    9
    iii. JCP&L   FAILED  TO    ADEQUATELY
    CONSIDER AN UNDER-BUILD ALTERNATIVE AT
    THE LAZAR MIDDLE SCHOOL PROPERTY AND
    ITS ADVANTAGES AS COMPARED TO THE
    PROPOSED PROJECT.
    II.
    The scope of our review of a final decision of an administrative agency is
    limited and we will not reverse such a decision unless it is "arbitrary, capricious,
    or unreasonable, or . . . not supported by substantial credible evidence in the
    record as a whole." In re Stallworth, 
    208 N.J. 182
    , 194 (2011) (citing Henry v.
    Rahway State Prison, 
    81 N.J. 571
    , 579-80 (1980)).             When making that
    determination, we consider:
    (1) whether the agency's action violates express or
    implied legislative policies, that is, did the agency
    follow the law; (2) whether the record contains
    substantial evidence to support the findings on which
    the agency based its action; and (3) whether in applying
    the legislative policies to the facts, the agency clearly
    erred in reaching a conclusion that could not reasonably
    have been made on a showing of the relevant factors.
    [Ibid. (citing In re Carter, 
    191 N.J. 474
    , 482-83
    (2007)).]
    We are, however, "in no way bound by the agency's interpretation of a statute
    or its determination of a strictly legal issue." Carter, 
    191 N.J. at 483
     (quoting
    Mayflower Sec. Co. v. Bureau of Sec., 
    64 N.J. 85
    , 93 (1973)).
    A-2183-17T3
    10
    When reviewing BOE's arguments we remain mindful that "[t]he
    Legislature has endowed the BPU with broad power to regulate public utilities
    [and] considerable discretion in exercising those powers." In re Pub. Serv. Elec.
    & Gas Co.'s Rate Unbundling, 
    167 N.J. 377
    , 384-85 (2001) (quoting In re
    Elizabethtown Water Co., 
    107 N.J. 440
    , 449-50 (1987)). The Board's decisions
    are presumed to be valid "and will not be disturbed unless [the court] find[s] a
    lack of 'reasonable support in the evidence.'" Id. at 385 (quoting In re Jersey
    Cent. Power & Light Co. 
    85 N.J. 520
    , 527 (1981)).
    BPU is authorized by statute to approve a public utility's proposed use of
    its property without the need to comply with ordinances or regulations enacted
    pursuant to the MLUL.       According to N.J.S.A. 40:55D-19, where, after a
    hearing, BPU finds a public utility's proposed use of land
    is necessary for the service, convenience or welfare of
    the public . . . and that no alternative site or sites are
    reasonably available to achieve an equivalent public
    benefit, the public utility . . . may proceed in accordance
    with such decision of the [BPU], any ordinance or
    regulation made under the authority of [the MLUL]
    notwithstanding.
    When making a determination under the statute, BPU must weigh the interests
    of all parties. Where the interests are equal, "the utility is entitled to the
    preference, because the legislative intent is clear that the broad public interest
    A-2183-17T3
    11
    to be served is greater than local considerations." In re Public Serv. Elec. & Gas
    Co., 
    35 N.J. 358
    , 377 (1961). A utility need not prove that a proposed project
    is "absolutely or indispensably[] necessary" but only that it is "reasonably
    necessary" for the service, convenience, or welfare of the public. 
    Ibid.
    After a careful review of the record in light of these precedents, we
    conclude there is substantial credible evidence supporting BPU's final order.
    BPU found credible the testimony of numerous witnesses, including experts,
    detailing the reliability criteria violation in JCP&L's present transmission
    system and how the Project will address that violation and enhance the utility's
    resilience. BOE raises no convincing argument that BPU's decision is lacking
    in evidentiary support or that the agency acted outside its statutory authority .
    In addition, BPU considered detailed testimony explaining the alternate
    transmission routes and configurations considered by JCP&L before it
    determined the route and configurations for which JCP&L sought approval were
    the most ideally suited to solve the reliability criteria violation. The proposed
    route was the shortest of the alternatives, had the least environmental impact,
    and did not present the complications, environmental threats, and costs
    associated with putting a new transmission line underground, as proposed by
    A-2183-17T3
    12
    BOE. The argument JCP&L did not consider alternatives to the Project is
    unsupported by the record.3
    BPU also accepted expert testimony the Project, when operational, will
    emit EMF well below acceptable levels. BOE presented only one witness, its
    President, who does not have expertise in electricity transmission lines or EMF.
    She expressed BOE's concerns regarding the safety of the Project, but offered
    no expert testimony or other evidence supporting BOE's contention the Project
    will emit EMF dangerous to students and faculty or pose other harms.
    BOE's President also expressed concerns about the visual environment at
    the Lazar school. It was well within the BPU's authority to determine the BOE's
    aesthetic concerns were outweighed by the public need for the Project. Finally,
    BOE's President speculated the Project may limit school expansion plans that
    might one day materialize. BPU acted within its authority when it determined
    that concerns regarding potential expansion of the school were baseless because
    construction in the utility's ROW would be precluded whether or not the Project
    was constructed, and the record contains no evidence that expansion outside the
    ROW would be curtailed unreasonably.
    3
    Although BOE argues constructing an underground transmission line in the
    area of the middle school is a preferable alternative, it offered no testimony with
    respect to the feasibility, cost, or efficacy of such an alternative.
    A-2183-17T3
    13
    We do not agree with BOE's argument BPU's final order must be vacated
    under res judicata or collateral estoppel. "The term 'res judicata' refers broadly
    to the common-law doctrine barring relitigation of claims or issues that have
    already been adjudicated."     Velasquez v. Franz, 
    123 N.J. 498
    , 505 (1991)
    (emphasis in original).    "The application of res judicata doctrine requires
    substantially similar or identical causes of action and issues, parties, and relief
    sought." Culver v. Ins. Co. of North Am., 
    115 N.J. 451
    , 460 (1989) (emphasis
    in original). "In addition, there must be a 'final judgment by a court or tribunal
    of competent jurisdiction.'" 
    Ibid.
     (quoting Charlie Brown of Chatham v. Bd. of
    Adjustment, 
    202 N.J. Super. 312
    , 327 (App. Div. 1985)).
    "Collateral estoppel, in particular, represents the 'branch of the broader
    law of res judicata which bars relitigation of any issue which was actually
    determined in a prior action, generally between the same parties, involving a
    different claim or cause of action.'" Tarus v. Borough of Pine Hill, 
    189 N.J. 497
    , 520 (2007) (quoting Sacharow v. Sacharow, 
    177 N.J. 62
    , 76 (2003)). "A
    court has broad discretion to determine whether application of collateral
    estoppel is appropriate." Adelman v. BSI Fin. Servs., Inc., 
    453 N.J. Super. 31
    ,
    39 (App. Div. 2018). In order
    [f]or the doctrine of collateral estoppel to apply to
    foreclose the relitigation of an issue, the party asserting
    A-2183-17T3
    14
    the bar must show that: (1) the issue to be precluded is
    identical to the issue decided in the prior proceeding;
    (2) the issue was actually litigated in the prior
    proceeding; (3) the court in the prior proceeding issued
    a final judgment on the merits; (4) the determination of
    the issue was essential to the prior judgment; and (5)
    the party against whom the doctrine is asserted was a
    party to or in privity with a party to the earlier
    proceeding.
    [Olivieri v. Y.M.F. Carpet, Inc., 
    186 N.J. 511
    , 521
    (2006) (quoting In re Estate of Dawson, 
    136 N.J. 1
    , 20-
    21 (1994)).]
    "A fundamental tenet of collateral estoppel is that the doctrine cannot be
    used against a party unless that party either participated in or was 'in privity with
    a party to the earlier proceeding.'" State v. K.P.S., 
    221 N.J. 266
    , 277 (2015)
    (quoting In re Estate of Dawson, 
    136 N.J. 1
    , 20 (1994)). "That tenet prohibits
    application of collateral estoppel if a party has not had a 'full and fair opportunity
    to litigate an issue.'" State v. McKinney, 
    223 N.J. 475
    , 493 (2015) (quoting
    K.P.S., 221 N.J. at 278)). "A relationship is usually considered 'close enough'
    only when the party is a virtual representative of the non-party, or when the non-
    party actually controls the litigation." O'Brien v. Telcordia Techs., Inc., 
    420 N.J. Super. 256
    , 269 (App. Div. 2011) (quoting Zirger v. Gen. Accident Ins. Co.,
    
    144 N.J. 327
    , 338 (1996)).
    A-2183-17T3
    15
    BOE argues BPU's decision must be reversed because it is inconsistent
    with a 2010 BPU decision regarding a 145-mile-long 550 kV Public Service
    Electric & Gas (PSE&G) project which passed through Montville. A portion of
    the transmission line for that project ran adjacent to the Lazar school. BOE
    intervened in that matter, identifying three transmission towers it argued were
    too close to the school. BOE identified locations where those towers could be
    moved. BPU found that moving the towers would be "prudent and reasonable"
    and directed PSE&G to provide a report identifying a relocation or realignment
    of the towers unless it would be "highly impractical or not possible" to do so.
    JCP&L was not a party to the PSE&G application. It did not participate
    in the 2010 proceeding. We reject BOE's argument that JCP&L is in privity
    with PSE&G because both are public utilities with parallel ROWs adjacent to
    the school. In addition, the utilities' two applications do not concern the same
    subject matter.   The PSE&G project and the Project are distinct and were
    evaluated by BPU on the basis of their individual characteristics and locations.
    To the extent we have not specifically addressed any of BOE's remaining
    arguments, we conclude they lack sufficient merit to warrant discussion in a
    written opinion. R. 2:11-3(e)(1)(E).
    Affirmed.
    A-2183-17T3
    16