I/M/O Authorization for Freshwater Wetlands Statewide General Permit 6, Etc. I/M/O Care One, Inc. ( 2013 )


Menu:
  •                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2231-08T2
    A-3837-09T2
    A-3400-10T2
    IN THE MATTER OF AUTHORIZATION FOR
    FRESHWATER WETLANDS STATEWIDE GENERAL         APPROVED FOR PUBLICATION
    PERMIT 6, SPECIAL ACTIVITY TRANSITION
    AREA WAIVER FOR STORMWATER MANAGEMENT,             December 11, 2013
    WATER QUALITY CERTIFICATION, AND
    ACCESS WAIVER FOR GENERAL PERMITS.              APPELLATE DIVISION
    ____________________________________
    IN THE MATTER OF CARE ONE, INC.
    ____________________________________
    IN THE MATTER OF AUTHORIZATION FOR
    FRESHWATER WETLANDS STATEWIDE
    GENERAL PERMIT 6. (Revised or
    Modified Permit).
    ____________________________________
    Argued March 12, 2013 – Decided September 9, 2013
    Before Judges Fisher, Waugh, and Leone.
    On appeal from the New Jersey Department of
    Environmental Protection, 1103-07-0007.1.
    R. William Potter argued the cause           for
    appellants Residents for Enforcement          of
    Existing Land Use Code, Susan Tierney,       and
    Pond Run Watershed Association (Potter       and
    Dickson, attorneys; Mr. Potter, on           the
    briefs).
    Jill Denyes, Deputy Attorney General, argued
    the   cause    for   respondent   New   Jersey
    Department    of    Environmental   Protection
    (Jeffrey   S.    Chiesa,   Attorney   General,
    attorney; Lewis A. Scheindlin, Assistant
    Attorney General, of counsel; Ms. Denyes, on
    the brief).
    Richard M. Hluchan argued the cause for
    respondent Care One, Inc. (Hyland Levin LLP,
    attorneys; Mr. Hluchan, of counsel; Robert
    S. Baranowski, Jr., on the brief).
    Nicholas B. Patton argued the cause for
    amici   curiae,  Delaware   Riverkeeper  and
    Delaware Riverkeeper Network (Mr. Patton and
    Jane P. Davenport McClintock, on separate
    briefs.)
    The opinion of the court was delivered by
    WAUGH, J.A.D.
    In   these   consolidated   actions,   appellants       Residents   for
    Enforcement of Existing Land Use Code, Susan Tierney, and the
    Pond   Run   Watershed   Association     appeal   several   administrative
    decisions by respondent New Jersey Department of Environmental
    Protection     (Department)   in   connection     with   its    grant   of    a
    general freshwater wetlands permit and transition area waivers
    to respondent Care One, Inc. (CareOne), which seeks to expand
    its assisted living facility in Hamilton Township.                We dismiss
    the appeal in Docket No. A-3400-10 as interlocutory.               We affirm
    the administrative agency action in Docket No. A-3837-09, and
    reverse the administrative agency actions in Docket No. A-2231-
    08.    Finally, we remand for further proceedings consistent with
    this opinion.
    2                               A-2231-08T2
    I.
    We discern the following facts and procedural history from
    the record on appeal.
    In     1999,    the    Department        granted    CareOne      a    freshwater
    wetlands permit to fill 0.97 acres of isolated wetlands and to
    create a stormwater management basin, also known as a detention
    basin,1    for   construction      of   an     assisted      living       facility    on
    approximately seven acres in Hamilton Township, Mercer County.
    The facility, known as CareOne at Hamilton, is located on the
    northern     corner    of    the   intersection         of    Cypress       Lane     and
    Whitehorse-Hamilton Square Road.                A 0.47 acre portion of the
    permitted area was left undisturbed.
    In 2007, CareOne wanted to construct a two-story, 62,259
    square foot addition, as well as a paved parking lot.                                The
    proposed construction would require the filling of the existing
    detention    basin    and    other      wetlands    on       the   site,     and     the
    construction of a new, L-shaped detention basin along Cypress
    Lane.
    1
    "'Detention basin' . . . means a human-made impoundment area
    made by constructing an embankment, or excavating a pit, or
    both, for the purpose of temporarily storing stormwater."
    N.J.A.C. 7:7A-1.4.
    3                                    A-2231-08T2
    In April, CareOne submitted a combined application for a
    "Letter    of    Interpretation"      (LOI)     to    delineate    the      site's
    freshwater wetlands and a "Freshwater Wetlands Statewide General
    Permit    No.   6"    (GP6),   see    N.J.A.C.       7:7A-5.6,    to   fill      the
    undisturbed segment of the land covered by the 1999 permit, or
    21,800 square feet (0.5 of an acre) of freshwater wetlands, and
    to disturb an additional 35,906 square feet (0.82 of an acre) of
    the adjoining transition area.2
    According to CareOne, the nearest waterway to the site is
    Pond Run.       The affected onsite wetlands were isolated and of
    intermediate resource value, requiring an adjacent transition
    area of fifty feet.       No bog turtle populations would be impacted
    and "no flood hazard permit was required," because no activities
    were proposed within the flood hazard area or riparian zones.
    CareOne's        application     package    contained,       among       other
    documents:      (1) a March 2007 "Statement of Compliance" by its
    licensed professional engineers, Taylor Wiseman & Taylor (TWT),
    which included a "Freshwater Wetlands Delineation Report"; (2)
    grading and groundwater recharge plans, maps, soil boring logs,
    vegetative      and    hydrological     analyses,       photographs,       and     a
    2
    N.J.S.A. 13:9B-3 defines "transition area" as "an area of land
    adjacent to a freshwater wetland which minimizes adverse impacts
    on the wetland or serves as an integral component of the
    wetlands ecosystem."
    4                                  A-2231-08T2
    description of the onsite vegetative species; (3) two stormwater
    management        reports    by    TWT     dated       March      2007,      "Drainage      and
    Detention Calculations," and "Detention Facilities Operation and
    Maintenance Manual"; and (4) a March 2007 preliminary and final
    site plan.         CareOne also provided the required notice of its
    project to Hamilton Township and landowners within 200 feet of
    the site.         The Department published notice of the applications
    in the DEP Bulletin on May 2, 2007.
    In   March     2008,       CareOne       responded         to   the    Department's
    request     for    additional       information             by   submitting     (1)     hydro-
    graphs, including inflow and outflow hydrographs of the existing
    and    proposed     basins    for        the     two-,       ten-,     twenty-five-,        and
    hundred-year        storms;       (2)    calculations            and   diagrams    for      two
    recharge areas, one each in the front and rear of the building,
    showing     that    they    both        would       drain    within     the   Department's
    required seventy-two-hour limit; (3) existing and proposed flow
    charts, and drainage area and grading maps; (4) a February 2008
    revision of TWT's "Drainage and Detention Calculations"; and (5)
    a     February     2008     revision        of       TWT's       "Detention      Facilities
    Operation and Maintenance Manual."
    CareOne's      proposed          stormwater          management    plan     included
    (1) the new detention basin designed to meet the two-year, ten-
    year, and hundred-year storm flow estimates and to "dry out"
    5                                     A-2231-08T2
    within    the     seventy-two-hour              time    limit     required      by     the
    Department; (2) two recharge areas with VortSentry® treatment
    devices   to    manage       stormwater      quality       by    removing    the     total
    suspended solids (TSS) in any runoff within 17.3 hours; (3) two
    "StormChambers"        to    meet    infiltration        or     groundwater     recharge
    estimates; and (4) an "Emergency Spillway" that would convey any
    flows from a hundred-year storm.
    While       the     Department's        staff       was     reviewing      CareOne's
    application     and     submissions,        CareOne      applied    to   the    Hamilton
    Township Zoning Board of Adjustment (Zoning Board) for use and
    site plan approvals and bulk variances for its project.                         On June
    9, 2009, the Zoning Board voted to deny CareOne's request for
    site plan approval with bulk variances.                       The decision is not in
    the record.      CareOne did not appeal the Zoning Board's denial.
    In    a     May    8,    2008    internal         "Engineer's    Report     for    SWM
    [stormwater       management]            review,"       the     Department's         staff
    recommended "approval," concluding that "[t]his project is in
    conformance      with        all    of    the     engineering       aspects     of     the
    Stormwater rules."             The staff also            (1) determined that the
    "[o]verall proposed land disturbance is more than 1 acre and new
    impervious      area    is    more   than       1/4    acre,    therefore     review   of
    stormwater management was required for this project"; (2) found
    that CareOne's submitted Nonstructural Strategies Points System
    6                                   A-2231-08T2
    (NSPS)        spreadsheet         had     been     "completed     correctly";        (3)
    "accepted" CareOne's calculations that its proposed TSS removal
    plans    of    an    extended      detention       basin   and   two   water   quality
    treatment devices to treat any runoff from the new parking lot
    and sidewalks, and from the pre-existing impervious area, would
    remove approximately seventy-four percent of TSS; (4) noted that
    CareOne   had       proposed      two    recharge    chambers,    or   bio-retention
    swales, to provide the required recharge volume within seventy-
    two hours; and (5) found that stormwater flows would be "further
    reduced due to Bio[s]wales."3                    Finally, the staff approved the
    drawings that CareOne had submitted, including CareOne's overall
    site plan, grading plan, utility plan, and construction details.
    On June 19, CareOne submitted a separate application to the
    Department          for    a     "Special     Activity      Transition     Area      for
    Stormwater Management."                 The application, which included a June
    2008    version       of   TWT's        "Statement    of   Compliance,"    concerned
    proposed construction on a section of CareOne's property that
    was    part    of    the       transition    area    associated    with   freshwater
    wetlands on the other side of Whitehorse-Hamilton Square Road.
    Because the offsite wetlands were of exceptional resource value,
    they required a 150-foot transition area, which extended across
    3
    Bioswales are stormwater runoff conveyance systems that provide
    an alternative to storm sewers.
    7                                A-2231-08T2
    the road onto CareOne's property.4                  CareOne provided the required
    notice to Hamilton Township and adjacent landowners.
    Objectors, including appellants and other property owners
    living in the adjacent Society Hill community, opposed CareOne's
    proposal.            Their     major        concerns          centered       on     stormwater
    management and local flooding risks.                           The Department assured
    them    that    their        concerns       would        be    considered          before    any
    approvals were given.
    On June 24, appellants' engineer, John A. Miller, P.E., of
    Princeton      Hydro,       LLC    (Princeton       Hydro),         sent     the    Department
    fourteen     detailed        objections       to    CareOne's            stormwater    control
    plan.     He opined that the plan would not prevent runoff or the
    resulting      periodic       inundation       of    neighboring            properties       and
    downstream      pollution.             He     pointed          to    CareOne's        lack    of
    conformity with non-structural strategies, peak flow reductions,
    water     quality      runoff       treatment,       maintenance            of     groundwater
    recharge,      and    safety       standards.        He       asserted       that    CareOne's
    design:      (1) failed to address as a primary consideration the
    use     of     natural            (non-structural)             stormwater           management
    techniques,          such     as     "minimizing              disturbance,          minimizing
    impervious     surfaces,          minimizing       the    use       of    stormwater    pipes,
    4
    See N.J.A.C. 7:7A-2.7 (governing transition                                 areas    due    to
    freshwater wetlands on adjacent property).
    8                                        A-2231-08T2
    [and]    preserving    natural     drainage      features,"          as    required     by
    Departmental       regulations;     (2)       improperly        exempted         existing
    impervious     groundwater      recharge;       (3)     improperly         allowed     the
    post-development rate of runoff to exceed the pre-development
    runoff rate in at least two locations; (4) failed to consider
    the     recharge    capabilities    of        certain       soils,    which      led    to
    erroneous     stormwater       calculations;          (5)      planned      to    employ
    manufactured       treatment    devices       that      were    not       effective     at
    reducing nonpoint water pollution; (6) violated safety standards
    by installing retaining walls around the detention basin; (7)
    proposed a wetland basin that conflicted with TWT's statements
    at the zoning board hearing proposing a dry basin; (8) failed to
    account for runoff from existing wetland after it is filled; (9)
    relied on onsite soil testing logs that erred in regard to the
    depth    to   seasonal   high     groundwater,          understated         groundwater
    levels and overstated recharge, and ultimately understated the
    amount of stormwater runoff; (10) relied on "test pits" that
    were not dug to sufficient depths or in the deepest location of
    the proposed detention basin to verify groundwater depth; (11)
    relied on a soil survey that contradicted the submitted soil
    boring logs; (12) relied on a flawed annual groundwater recharge
    analysis, resulting in the under-assessment of stormwater flows;
    (13) violated best management practices by failing to test near
    9                                      A-2231-08T2
    the proposed recharge facility; and (14) failed to describe the
    construction schedule to ensure the maintenance of stormwater
    controls as the existing basin is being filled.
    In addition, appellant Tierney, an adjacent property owner,
    sent   an   email   to   the   Department    complaining      about    CareOne's
    stormwater management plan and the loss of the site's natural
    resources.    She was concerned that CareOne's site plan contained
    only one stormwater basin:
    My concern with the stormwater basin is
    based on the fact that [the] property was
    also once wetlands and we have very wet
    ground surface for days following rain.    In
    the month of December when a stormwater
    outlet to our basin was obstructed we had a
    couple feet of standing water for over 20
    days.    This standing water shows soils
    adjacent to CareOne do not provide recharge
    in a 72 hour period.     CareOne's stormwater
    basin is connected to the area of existing
    wetlands. . . .         I am concerned the
    increased permeable surface, loss of natural
    vegetation   and   surface   area   and   the
    questionable recharge properties may lead to
    flooding of adjacent areas and support a
    mosquito breeding area.
    Following    receipt     of    appellants'     comments,      the     Department
    requested    additional    information      from   CareOne,    which    filed    a
    September 2008 revision of its "Detention Facilities Operation
    and Maintenance Manual."
    On October 7, the Department's staff contacted Princeton
    Hydro by telephone to discuss CareOne's stormwater design, and
    10                                 A-2231-08T2
    then    responded         to    follow-up          emails       from    Princeton            Hydro   on
    November       7    and    13.         The     staff       told    Princeton            Hydro     that
    CareOne's      new     basin     was     not       required       to    be     "a      1:1   wetlands
    replacement"         for       the     existing          "wet     basin,"           which     CareOne
    proposed to fill and replace, because the basin had been created
    under the 1999 permit.
    The     staff      also       told    Princeton          Hydro        that      filling       the
    existing basin did not need to be part of CareOne's current
    application, because the Department had "decided that requiring
    . . . a permit for creating these wetlands and then another
    permit    to       fill    these      same     wetlands         would     be      regulating         the
    disturbance twice."                That advice, however, was not consistent
    with the Department's earlier instruction to CareOne, in March
    2008, that filling the existing basin and then creating a new
    basin    involving         the       special       transition          area       of   the    offsite
    wetlands required a separate General Permit No. 1 (GP1) wetlands
    permit "for replacement of this wetland basin."
    On November 20, the Department issued CareOne an LOI/Line
    Verification, specifying the boundary of the freshwater wetlands
    and waters on the property, including the transition area for
    the offsite wetlands.                 Based upon its own site inspection and
    the     information        submitted          by        CareOne,       the     Department          also
    determined         that    the       onsite     wetlands         were        of     "intermediate"
    11                                         A-2231-08T2
    resource    value,   "isolated         and        not   part    of    a    surface     water
    tributary system."
    On    the   same    day,     the       Department         issued       CareOne     the
    following    approvals:          (1)     a        GP6    permit,      which    authorized
    activity involving the filling of 21,800 square feet (0.5 of an
    acre) and the filling of the existing detention basin, including
    a   transition    area    waiver       for        access;      (2)    a    Water   Quality
    Certification; and (3) a Special Activity Transition Area Waiver
    for   Stormwater     Management,         which          authorized        disturbing     the
    transition area of the offsite wetlands.                             As the Department
    acknowledges,     there    was    no    reference         to    CareOne's      stormwater
    management plan or the agency's review of that plan on the face
    of those approvals.
    The Department published notice of its permit approval in
    the DEP Bulletin on December 3, and its approval of the special
    transition area waiver on January 14, 2009.                          The Department did
    not mention either a public comment period or the right to seek
    a hearing for those approvals.                     However, the permit document
    itself provided that, "[i]n accordance with N.J.A.C. 7:7A-1.7,
    any person who is aggrieved by th[e] decision may request a
    hearing within 30 days after notice of the decision is published
    in the DEP Bulletin."            On January 2, 2009, appellants filed a
    timely     "Adjudicatory    Hearing          Request"          with    the    Department,
    12                                    A-2231-08T2
    asserting     that    alleged     defects      in    CareOne's         stormwater    plan
    would cause the discharge of large volumes of stormwater onto
    their properties.
    On January 5, appellants appealed the Department's November
    2008   decision      granting     CareOne      the   GP6,     the      transition    area
    waivers, and the water quality certificate.                            That appeal was
    assigned Docket No. A-2231-08.
    On May 7, the Department moved for an order remanding the
    matter to the Department for additional fact finding.                            It also
    sought dismissal of the appeal without prejudice.                             The purpose
    of    the   remand    was   to    address      the    issue       of    the    stormwater
    management plan, which, as noted, had not been mentioned on the
    face of the Department's approvals.                    The Department's section
    chief asserted in her supporting certification that she would
    meet with appellants and their consultant, Princeton Hydro, "to
    discuss     concerns    expressed    in     their     submitted         comments,"     and
    "[i]f the Department conclude[d] that the project . . . meets
    the    Stormwater      Management    Regulations,           the     Department      shall
    issue an amended decision setting forth the factual basis for
    that determination."
    On June 22, we granted the Department's motion for remand
    in Docket No. A-2231-08, but denied its motion to dismiss the
    appeal.        Instead,      we     retained         jurisdiction         and     ordered
    13                                     A-2231-08T2
    completion of the remand by September 25.                          We noted that we
    would allow for "an appropriate extension" of the deadline if
    the Department needed a "hearing . . . to properly complete
    th[e] remand."         Although we granted extensions at the request of
    both sides, the Department did not hold a hearing.
    In      August,        Department      staff   met     with      appellants      and
    representatives of Princeton Hydro, the Delaware Riverkeeper,
    and the Delaware Riverkeeper Network.5                  Appellants' counsel also
    submitted       written     comments    and     legal    arguments.          Department
    staff subsequently met with CareOne to discuss the objections
    raised     by    the    project's       opponents.           In    October,     CareOne
    submitted new revisions of its preliminary and final site plan,
    its drawings, and TWT's "Drainage and Detention Calculations"
    and "Detention Facilities Operation and Maintenance Manual."
    On      December        1,   Princeton       Hydro    sent      the      Department
    objections      to   the    newly   revised      plans.       It    argued    that   the
    Department should require CareOne to apply for an individual
    permit   instead       of    a   general    permit,      because:     (1)     CareOne's
    filling, relocating, and enlarging the existing detention basin
    together    with       filling    the   wetlands      that    had    formed     in   the
    uplands surrounding that basin since its 1999 construction did
    5
    We subsequently granted amicus status to                            the     Delaware
    Riverkeeper and the Delaware Riverkeeper Network.
    14                                  A-2231-08T2
    not fall within the scope of the 1999 permit or qualify for a
    GP1 under the N.J.A.C. 7:7A-5.1, which states that "[a]ctivities
    under [GP1] shall not expand, widen or deepen the previously
    authorized feature"; (2) the wetlands inside the existing basin
    and   the   new     wetlands   created      in   the     uplands   could    not     be
    considered isolated for GP6 purposes because of the existing
    discharge     pipe    connecting     them    and    making    them   part      of   a
    tributary system, and N.J.A.C. 7:7A-5.6 authorizes activities
    "if the freshwater wetlands . . . are not part of a surface
    water tributary system"; and (3) CareOne's proposed activities
    combined     with     its    activities     in     the    existing    basin       and
    associated wetlands exceeded the one-acre limit for a GP6 and
    did not qualify for an exception under N.J.A.C. 7:7A-4.4(a).
    On    January    26,   2010,   the    Department       submitted     a   fact-
    finding remand report, entitled "Engineering and Environmental
    Report," to the Clerk of the Appellate Division.                   In the remand
    report, the Department explained that "a number of revisions
    were made to the proposed design of the site and the stormwater
    management calculations by design engineer Gary Vecchio, P.E.,
    as requested by the Department."
    The Nonstructural Strategies Point System
    (NSPS) spreadsheet has been revised to
    demonstrate that the project complies with
    the   requirements  of   N.J.A.C.  7:8-5.3.
    Various adjustments were made to the runoff
    and recharge calculations, based on revised
    15                                  A-2231-08T2
    assumptions of soil types and drainage
    areas.    Additionally, the proposed water
    quality treatment devices were modified as
    requested, so that only the water quality
    design storm, which is 1.25 inches of rain
    in a two-hour period, as defined at N.J.A.C.
    7:8-5.5(a) will be treated.    Modifications
    were also made to the stormwater management
    operation    and   maintenance   manual,   a
    construction sequence was provided, and
    runoff   to   depressed  areas  onsite   was
    reevaluated.
    However, the Department informed us that CareOne still needed to
    make additional design alterations to address Princeton Hydro's
    December      2009    concerns     "with       which   the      Department      is    in
    agreement."
    More specifically, the Department agreed that (1) CareOne's
    new   inlet    proposed     for   Whitehorse-Hamilton           Square    Road       also
    conveyed water into the proposed new detention basin, and that
    CareOne    had    not     included     those     runoff      projections       in    its
    calculations     for      the   basin's    capacity;      (2)    CareOne's       design
    assumed the wrong soil type in its stormwater calculations in
    contradiction        to   the   soil    borings,       and    underestimated         and
    underreported the difference in runoff quantities, "resulting in
    additional     runoff     downstream      that    is   unaccounted       for   in    the
    submitted calculations"; (3) CareOne did not provide proof that
    its proposed storm sewer system could carry stormwater into the
    proposed new detention basin during a hundred-year storm, or
    that the basin would function properly and not back up during
    16                                   A-2231-08T2
    this storm; (4) CareOne's operation and maintenance manual did
    not address goose and invasive species control; (5) there was a
    contradiction between CareOne's submitted materials and a detail
    sheet       regarding        maintenance             methods        for         the      proposed
    StormChambers infiltration units; (6) CareOne needed to conduct
    "[a]dditional field work . . . to verify the functionality of
    the proposed hybrid basin, given that the seed mixture proposed
    on    the   plans    for     the   'wet'       bottom        of    the     basin       is    highly
    dependent      on     the       soils        being     saturated";             (7)      CareOne's
    stormwater        calculations          failed        to     compute           drainage        times
    "necessary to verify that storage exists for the next storm
    event";     (8)    that,     based      on    submitted        soil       boring       logs,      the
    system near one of the test pits "could be influenced by a
    perched      water    table,       which       would       surcharge            the    area       and
    overwhelm     the    proposed       facility";         and        (9)    CareOne       needed      to
    address     Princeton        Hydro's         conclusion        that       the     "Groundwater
    Recharge     Trench"       to   the     StormChambers             "does    not    satisfy         the
    Stormwater Rule design standards."
    The Department further advised us that, after addressing
    those issues, CareOne would need to "apply for a modification of
    the    freshwater      wetlands         permits       in     order        to    formalize         the
    Department's        review      and     approval        of     these       changes."              The
    Department     also     asked      Princeton         Hydro     to       provide       engineering
    17                                           A-2231-08T2
    calculations for "further illumination . . . regarding runoff
    from    adjacent          properties,"              adding    that,          based      on       the
    information,         it     might       require        CareOne          to    make      "further
    amendments      to        the    stormwater           management         design       of      th[e]
    project."
    On March 10, the Department's Acting Commissioner denied
    appellants' request for an adjudicatory hearing, finding that
    they had "demonstrated neither a risk of erroneous deprivation
    of a particularized property right nor any statutory right to an
    administrative hearing."                On April 26, appellants filed a notice
    of appeal with respect to the denial of their hearing request.
    That matter was assigned Docket No. A-3837-09.6
    On   August        30,    in     response       to    the    Department's            remand
    report,     CareOne       submitted          revised    plans      and       drawings      to    the
    Department.      These included (1) revised preliminary and final
    site   plans;    (2)       revised          drawings    for     existing        and     proposed
    drainage      areas;            (3)         revised     "Drainage             and     Detention
    Calculations";        and       (4)     a     new     version      of    TWT's       "Detention
    Facilities      Operation             and     Maintenance       Manual."              In      those
    documents, CareOne proposed two new groundwater recharge areas
    that, based on its new soil borings and permeability tests, will
    6
    On the same day, appellants filed a motion for summary
    disposition in Docket No. A-2231-08. That motion was denied on
    June 8.
    18                                         A-2231-08T2
    "completely drain" in 3.3 hours and 7.3 hours, respectively,
    which was less than the recharge volume required within seventy-
    two hours.     CareOne also reported that it had performed another
    soil boring "to make sure the invert of basin . . . has at
    minimum a 1" separation from the seasonal high water table."
    Based on those results and its revised conditions, drainage, and
    detention calculations, CareOne concluded that "the total annual
    recharge volume will be greater than the post-development annual
    recharge deficit, and it added that a proposed new "Emergency
    Spillway"    will    "convey   flow[s]   of   the    100-year    inflow   peak
    [plus] 50%."
    In a February 1, 2011 letter to CareOne concerning the
    2008-approved GP6 and transition area waivers, the Department
    stated in part:
    As a result of the pending appeal of the
    above permits, the State requested that the
    Appellate Division remand these permits back
    to   the  Department    for   reconsideration.
    Since that time, the Department reviewed
    concerns   raised   by   objectors,   reviewed
    additional information submitted by the
    permittee's   consultant    [TWT],  as   noted
    below, and has determined that it is
    necessary   and   appropriate    to  issue   a
    modified permit.
    [(Emphasis added).]
    The Department's letter listed information and documents it had
    reviewed,    which    included    (1)    Princeton     Hydro's    June    2008
    19                               A-2231-08T2
    comments;    (2)   CareOne's    revised       drawings,   calculations,     and
    manuals prepared by TWT in October 2009; (3) Princeton Hydro's
    December 2009 comments to the new revisions; and (4) CareOne's
    subsequently revised drawings, calculations and manuals prepared
    by TWT in July 2010, and submitted to the Department in August
    2010.
    The Department's letter continued:
    This modification letter approves:
    1. At the Department's request, a
    safety fence is now to be installed around
    the perimeter of the entire detention basin.
    This is necessary since the detention basin
    design includes small retaining walls in
    place of earthen slopes along the outer
    edges of the detention basin.
    2. The relocation of manufactured water
    quality treatment devices which are to be
    located connected and adjoining to the storm
    water pipes.     Constructing these devices
    adjacent to stormwater pipes allows larger
    storm flows to by-pass the water quality
    devices which makes them more efficient in
    treating water quality.
    3. Groundwater recharge chambers are to
    be relocated.   This is necessary since the
    chambers were previously proposed in an area
    where soils are not permeable enough to
    provide adequate groundwater recharge.
    [(Emphasis added).]
    The     modification   letter   also        approved   various   drawings    as
    revised by TWT, including a new site plan, grading plan, utility
    20                            A-2231-08T2
    plan,   profiles,   construction   details,   and   basin   construction
    sequence plan.
    However, the Department noted that
    [t]his approval is subject to the following
    conditions:
    1. The applicant [CareOne] is required
    to provide a revised Groundwater Recharge
    Spread Sheet (NJGRS) and confirm that the
    soil types determined by field infiltration
    tests were used in the recharge spread
    sheets, where appropriate.    If the project
    does not provide adequate recharge in the
    proposed   condition,   additional  recharge
    structures must be provided.
    2. The applicant [CareOne] is required
    to seed the basin with a grass seed mixture
    of wet tolerant and dry tolerant varieties.
    Therefore, a revised Landscape Map must be
    submitted reflecting this change.
    All   required   information   must   be
    submitted to this office within 60 days of
    receipt of this letter.      Furthermore, no
    disturbance    or   construction    may    be
    undertaken in regulated areas until the
    permittee   has   submitted    the   required
    information and received a written approval
    of the same from the Department. All other
    conditions of the original permit remain in
    force, and this revision does not extend the
    original permit expiration date.
    [(Emphasis added).]
    At the same time, the Department's staff issued two new
    reports, both dated February 1:         (1) a new "Engineer's Report
    for SWM review" with supporting calculations; and (2) a               new
    "Engineering and Environmental Report."
    21                           A-2231-08T2
    In its new SWM review report, the Department staff found
    that, because CareOne's "[o]verall proposed land disturbance is
    more than 1 acre and new impervious area is more than 1/4 acre,"
    "review of stormwater management was required for this project."
    Having      reviewed      CareOne's       most        recent      submissions           and
    calculations,     it     recommended       "approval."            The        staff     also
    accepted    CareOne's     proposed      TSS    removal    rate       and     found     that
    CareOne's     operation    and    maintenance        manual    was      in    accordance
    with N.J.A.C. 7:8-5.8.           Finally, the report noted the receipt of
    objection letters from Princeton Hydro for CareOne's "original
    stormwater     design,"     after       which    "[t]he        revised        stormwater
    management     report     and     plans       were     reviewed       twice     by      the
    objector's     engineer    and     no   comments       were    received        for     this
    revision."
    The   Department's        revised    "Engineering         and     Environmental
    Report,"     contained     the    following      findings:        (1)      CareOne      had
    included a proposed inlet on Whitehorse-Hamilton Square Road in
    its   basin    inflow/outflow        calculations,        which       satisfied         the
    Department's concern that "the basin calculations count all of
    the runoff from the impervious areas"; (2) CareOne had relocated
    its   proposed   groundwater       recharge,         giving    the    project        "9,000
    cubic feet of groundwater recharge beyond what was provided in
    the originally approved design," but the Department still needed
    22                                    A-2231-08T2
    CareOne    to    verify     that    it    had   "not    underestimated       existing
    groundwater       recharge    on    the    site";      (3)    CareOne   "ha[d]     now
    analyzed the proposed storm sewer system based on a                           25-year
    storm event and a 100-year storm event, and ha[d] demonstrated
    that the proposed system has adequate capacity," and that if the
    storm pipes got backed up, "the majority of any overflow from
    catch basins [would] still enter the detention basin by overland
    flow";     (4)    CareOne     had    revised      its    "Detention     Facilities
    Operation and Maintenance Manual" to provide for invasive plant
    species and goose control, along with "an acceptable maintenance
    protocol for the proposed StormChamber infiltration units"; (5)
    CareOne would "be required to seed the basin with a grass seed
    mixture consisting of wet tolerant and dry tolerant varieties,"
    ensuring the grass would survive; (6) CareOne had revised its
    plans     to     include     new    drainage     time        calculations,     "which
    demonstrate[d] that the proposed drainage-times are less than 72
    hours," and had provided a new test pit "at the exact location
    of the recharge system," which showed "that location is not
    influenced by a perched water table" and that groundwater "was
    not encountered [anywhere] down to a depth . . . more than 2
    feet below the bottom of recharge facility"; and (7) CareOne had
    relocated its recharge areas to different locations above the
    seasonal        high   groundwater          table,      which      satisfied       the
    23                                A-2231-08T2
    Department's concern that CareOne's proposed trench did not meet
    SWM design standards.
    The Department concluded:
    As a result of the objector's claim[s],
    the applicant's consultant [TWT] has now
    revised plans and stormwater management
    report as submitted to the [Department] on
    August 30, 2010 to address the groundwater
    recharge, details of the recharge chambers
    and water quality bypass.     The applicant's
    consultant also verified the depth of the
    groundwater where claims were made regarding
    inadequate   documentation.       The   revised
    project   meets   all   of    the    stormwater
    management   regulations    subject    to   the
    conditions listed in the revised approval
    letter.
    Finally, the Department reiterated that "no additional comments
    were received from the Objector's consultant."
    On February 15, Princeton Hydro submitted updated comments
    and objections concerning CareOne's August 2010 plans, reports,
    and drawings to the Department.            According to Princeton Hydro,
    it   "had   not   known   about"   TWT's    August   submissions    to   the
    Department until the Department's staff had contacted Miller on
    November 29.
    On February 16, the Department moved to dismiss Docket No.
    A-2231-08 as moot, and CareOne joined in the motion.               On March
    17, we reserved decision on the Department's motion to dismiss,
    pending determination on the merits of the appeal.
    24                             A-2231-08T2
    In the March 9 DEP Bulletin, the Department published a
    "NOTICE   OF   INTENT   TO   SETTLE"   based   on   its   most     recent
    correspondence to CareOne.    The notice provided as follows:
    On February 1, 2011[,] a revision
    letter was issued to the applicant Care One
    for   the  previously   approved   Freshwater
    Wetlands   Transition    Area    Waiver   for
    Stormwater Management and General Permit No.
    6. . . .
    The revision letter approves:
    (1) A safety fence to be constructed
    around the perimeter of the entire
    detention basin.
    (2) The relocation of manufactured
    water quality treatment devices which
    are   to   be  located   connected and
    adjoining to storm water pipes.
    (3) Groundwater recharge       chambers   are
    to be relocated.
    The applicant is still required             to
    submit the following information:
    (1) A revised Groundwater Recharge
    Spread Sheet (NJGRS) must be submitted
    and   if   not   acceptable   additional
    recharge structures must be provided.
    (2) A revised Landscape Map must be
    submitted showing the basin is seeded
    with a grass seed mixture of wet
    tolerant and dry tolerant varieties.
    Seven (7) drawings prepared by Taylor,
    Wiseman and Taylor, dated March 30, 2007 and
    last revised July 30, 2010 were approved
    with this revision.
    25                             A-2231-08T2
    The    notice   further   provided    that    "[a]ny   comments,      concerning
    this    revision,    must   be    submitted     within    15   days    to     [the
    Department]."
    On March 18, appellants filed a notice of appeal from the
    Department's February 1, 2011 decision, which they characterized
    as "a revised permit."            That matter was assigned Docket No.
    A-3400-10.7
    In   March,   CareOne   submitted     additional   revisions      to    the
    Department in response to the two conditions in its February 1
    letter.      In a letter dated April 20, the Department confirmed
    that CareOne had satisfied those conditions.                   The Department
    found    that   "[t]he    project    now    complies   with    the    Stormwater
    Management Regulations, N.J.A.C. 7:8."            The Department published
    notice of its April 20 letter in the May 11 DEP Bulletin under
    the heading "NOTICE OF INTENT TO SETTLE AND ISSUE PERMIT."                     The
    notice referred to the fifteen-day public comment period.
    In June, the Department filed its fourth statement of items
    comprising the record.           In July, appellants filed a motion to
    correct the administrative record by adding an April 8 letter
    they contend Princeton Hydro sent to the Department concerning
    7
    In April, CareOne moved to consolidate the three appeals and
    appellants moved to stay any construction pending appeal.    We
    granted the consolidation motion in May, but denied the request
    for a stay.
    26                               A-2231-08T2
    objections     to    the    Department's          revision     letter.       While   the
    motion was pending, the Department filed its fifth statement,
    which   included      other      items   received        by   the     Department    after
    February      1,    but    did   not     include     the      April    8   letter    from
    Princeton Hydro.
    We initially denied appellants' motion to supplement, but
    on reconsideration reserved the issue pending a decision on the
    merits.    We observed that
    [i]t is not clear from the motion that the
    document at issue was filed with [the
    Department] when it made the decision as to
    which there is an appeal pending or whether
    [the   Department]   has   included   in  its
    statement of the record of appeal other
    documents that were received by it following
    such decision.    Consequently, we defer the
    issue to the merits panel.         Movant may
    include the document in its appendix and
    comment on it in argument, subject to the
    decision of the merits panel whether to
    consider the document.
    Because the Department published its April 20 letter as a notice
    of   intent    to    settle      in    the   May    11   DEP    Bulletin,     we    grant
    appellants' motion to include Princeton Hydro's April 8 letter
    in the record on appeal.
    In that letter, Princeton Hydro wrote:
    There are a number of disconcerting
    items that [the Department] has failed to
    recognize through this lengthy and abnormal
    process.     The point system that [the
    Department] is relying on to confirm the
    applicant has satisfied the Rule's non-
    27                                A-2231-08T2
    structural strategies is not part of the
    Stormwater Rule or BMP manual and did not go
    through a formal adoption process. The
    [Department] accepted a fence in lieu of
    meeting the Safety Standards for Stormwater
    Management Basins (N.J.A.C. 7:8-6.2(c)3) and
    the Municipal Land Use Law, [N.J.S.A.]
    40:55D-95.1,     endangering    the     public.
    Further,   [the   Department]   relied   on   a
    Certification Letter from the applicant's
    engineer for soils data and groundwater
    recharge design rather than evaluating the
    conclusions    and   integrity    of    design.
    Equally important to the defects in the
    application with regard to the Stormwater
    Rule,   the   [Department]    has    completely
    ignored   the    wetland   permitting    issues
    discussed in the September 10, 2009 meeting
    with   [the   Department]    followed    by   a
    Princeton Hydro letter on December 1, 2009
    to [the Department].
    Continued    nonconformance    is   fully
    described in a Princeton Hydro review letter
    dated February 15, 2011 submitted to your
    office.   This letter details the persistent
    lack   of   conformity   with   non-structural
    strategies, peak flow reductions, water
    quality runoff treatment, maintenance of
    groundwater recharge and satisfying safety
    standards.   The February 1, 2011 letter to
    modify the permit is seemingly based on the
    content of a [Department] Engineering and
    Environmental Report dated February 1, 2011.
    After much time and commenting to the
    [Department], the conditions assigned to the
    modified    permit,    requiring    additional
    information to be submitted, acknowledges
    the further failure of the applicant to
    comply with the Rules.    The original permit
    had no such required conditions to supply
    additional information. In fact, with these
    conditions of approval, the modified permit
    is additionally flawed since it will require
    the submission of additional information,
    and this being critical information to
    28                          A-2231-08T2
    verify compliance with the Stormwater Rule.
    If   additional   recharge  facilities   are
    required, additional soil testing will also
    be necessary.    Even if the conditions are
    met, there are a number of outstanding
    comments, detailed in Princeton Hydro's
    February 15, 2011 letter.     The continual
    unconventional [Department] review process
    will further the cycle of revisions, reviews
    and more comments into the foreseeable
    future and beyond.
    With the Princeton Hydro June 24, 2008
    letter, [the Department] should not have
    issued a permit and, on a technical level,
    [should] have realized this in its first
    Engineering and Environmental Report dated
    January 26, 2010. After a permit was issued
    and following a September 10, 2009 meeting
    with [the Department] and Princeton Hydro
    letter dated December 1, 2009 to [the
    Department], [the Department] should have
    rescinded the permit.   As the February 15,
    2011 Princeton Hydro letter demonstrates,
    the modified permit, like the original, is
    flawed and should have been held, or as now
    issued, rescinded.
    II.
    Before turning to the substantive issues raised on this
    appeal, we first address the motion to dismiss that was reserved
    pending our consideration of the merits.
    The Department and CareOne seek dismissal of Docket No. A-
    2231-08, the appeal concerning the Department's 2008 permit and
    related approvals, arguing that the issue is moot because the
    2008 permit was superseded by the subsequent modifications that
    are   the   subject   of   the   appeal    in   Docket   No.   3400-10.     Our
    29                               A-2231-08T2
    problem with respondents' argument is that the Department never
    took     final     administrative        action     with     respect       to      those
    modifications.       See N.J.A.C. 7:7a-14.1(a) and -14.3 (modifying
    an issued permit).
    In   both   instances,      the   Department       published       notices      of
    intent      to   settle,   which    triggered       public     comment      periods.
    However,     the   Department   took      no    formal     action   to     adopt      the
    modifications after the close of the comment period.                      See, e.g.,
    Dragon v. N.J. Dep't of Envtl. Prot., 
    405 N.J. Super. 478
    , 492
    (App. Div.) (discouraging use of agency's settlement power to
    avoid    regulatory    compliance),        certif.       denied,    
    199 N.J. 517
    (2009).8     Because there was no final administrative action, the
    appeal in Docket No. 3400-10 is interlocutory.
    As a result, we deny the motion to dismiss Docket No. A-
    2231-08 and instead dismiss Docket No. 3400-10 as interlocutory.
    Inasmuch as the issues have been fully briefed and argued, we
    reluctantly consider the subsequent actions taken to have been a
    consequence of our 2009 remand and, therefore, included in the
    earlier appeal in Docket No. A-2231-08.
    Nevertheless,       we   note          the   Department's          continuing
    modification of the permit and other approvals long after the
    8
    We again caution against the use of a notice of settlement to
    avoid regulatory compliance.
    30                                     A-2231-08T2
    expiration of the remand period was inappropriate.                            Once it had
    determined that the information on which the 2008 approvals were
    issued was inaccurate or insufficient, the better practice would
    have been to withdraw the permit pending further review of the
    applications.         Once it had finalized the approvals, it should
    have     reissued     them,     as      revised,       with     appropriate         notice,
    publication, and compliance with administrative procedures.
    III.
    We now turn to the merits of the appeal, starting with the
    issue    raised      in   Docket     No.      A-3837-09     concerning        the    Acting
    Commissioner's        denial       of       the     appellants'       request       for    an
    adjudicatory hearing.
    A third-party objector's right to a formal administrative
    hearing is delineated and circumscribed by the Administrative
    Procedure Act (APA), N.J.S.A. 52:14B-1 to -25.                           Although "the
    APA does not foreclose such third parties from seeking judicial
    review    of   the    merits    of      a    permit    once    it   is   issued       by   an
    agency," In re Riverview Dev., LLC, 
    411 N.J. Super. 409
    , 425
    (App. Div.), certif. denied, 
    202 N.J. 347
     (2010), it gives the
    non-applicant        objector        no      automatic        right      to     a    formal
    administrative        hearing      to     contest     the     issuance    of    a    permit
    unless he or she can establish a statutory or constitutional
    right to that hearing.             In re NJPDES Permit No. NJ0025241, 185
    31                                    A-2231-08T2
    N.J. 474, 481 (2006); In re Freshwater Wetlands Statewide Gen.
    Permits, 
    185 N.J. 452
    , 463 (2006); Spalt v. N.J. Dep't of Envtl.
    Prot.,     
    237 N.J. Super. 206
    ,   212     (App.     Div.    1989),     certif.
    denied,     
    122 N.J. 140
       (1990).           In   fact,    the    APA    expressly
    prohibits a state agency from promulgating rules or regulations
    entitling        a    third    party      to    an     administrative          appeal    as    a
    contested case under the APA unless "specifically authorized to
    do so by federal law or State statute," or unless a person "has
    [a] particularized interest sufficient to require a hearing on
    constitutional or statutory grounds."                        N.J.S.A. 52:14B-3.1(d),
    -3.2(c), -3.3.
    The    Freshwater         Wetlands        Protection       Act    (FWPA),    N.J.S.A.
    13:9B-1 to -30, does not provide third-party objectors with the
    right to a plenary administrative hearing to challenge DEP's
    issuance of a permit.               Under N.J.S.A. 13:9B-20, only applicants
    may   request          an      adjudicatory           hearing      to     challenge        the
    Department's decision concerning a FWPA permit.                                Consequently,
    appellants'          challenge      to    the        Department's       action    does     not
    qualify for an adjudicatory hearing unless they establish that
    one or more of their constitutional rights are at stake.
    In    rejecting         appellants'       request,        which    was    premised      on
    CareOne's        project      posing      a     threat     of    increased       stormwater
    discharge to their properties, the Acting Commissioner relied on
    32                                  A-2231-08T2
    In re Freshwater Wetlands, 
    supra,
     
    185 N.J. at 470
    .                   In that
    case, the Supreme Court, referring to our decision in Spalt,
    supra, 
    237 N.J. Super. at 212
    , observed that
    Judge (later Justice) Coleman held that
    "simply because some of the plaintiffs
    reside close to the proposed [marina] site
    and are fearful of resultant injury to their
    property, does not mean they are entitled to
    an adjudicatory hearing." Further elaborat-
    ing on that theme, Judge Coleman noted that
    "[f]ear of damage to one's recreational
    interest or generalized property rights
    shared   with   other  property   owners   is
    insufficient to demonstrate a particularized
    property right or other special interest."
    [In re Freshwater Wetlands, 
    supra,
     
    185 N.J. at 470
     (citations omitted).]
    Appellants     presented     only    their   fears   of    flooding     and
    Princeton    Hydro's   calculations     evidencing   the      possibility   of
    flooding on neighboring properties from CareOne's project.                  We
    find no error in the Acting Commissioner's determination that
    appellants    "have    not   demonstrated   a    particularized     property
    right which gives rise to a constitutional basis for granting a
    hearing."
    Consequently, we affirm the denial of appellants' request
    for an adjudicatory hearing.
    IV.
    We next address appellants' argument that the Department's
    reliance on the Nonstructural Strategies Points System to assess
    33                               A-2231-08T2
    CareOne's     stormwater      management       plan       was    improper     because
    implementation of the NSPS constituted improper administrative
    rulemaking.9       Before addressing their argument, however, we must
    supply     some     background,    including        the    Department's       general
    stormwater management requirements and its incorporation of the
    NSPS into its permitting process under the FWPA.
    Pursuant to N.J.A.C. 7:7A-2.11, all projects requiring an
    FWPA individual permit and all regulated activities requiring an
    FWPA general permit that propose to disturb one or more acres
    are considered "major development[s]" under N.J.A.C. 7:8-1.2,
    and   trigger        compliance     with      the     Department's         stormwater
    management rules, found at N.J.A.C. 7:8-1.1 to -6.3.                        The same
    requirement applies to a project that would increase impervious
    surfaces    by     one-quarter    acre     (10,890     square      feet)    or   more.
    N.J.A.C. 7:7A-2.11, 7:8-1.2.
    Subchapter 5 of those rules, N.J.A.C. 7:8-5.1 to -5.9, sets
    standards     for     limiting     the     "adverse       impact    of     stormwater
    runoff."          N.J.A.C.   7:8-5.1(a).            Standards      for   controlling
    erosion,      encouraging         and      controlling          infiltration       and
    9
    Although it is not clear that the issue was directly argued
    before the Department, no party has raised that issue, and they
    have addressed the merits of the argument.     Consequently, we
    need not reach that question.
    34                                  A-2231-08T2
    groundwater     recharge,        and     controlling      runoff        quantities      are
    found in N.J.A.C. 7:8-5.4.                 Standards for runoff quality are
    found in N.J.A.C. 7:8-5.5.                 The regulations provide that the
    standards     in     those        two     regulations          "shall     be      met    by
    incorporating nonstructural stormwater management strategies at
    N.J.A.C.     7:8-5.3      into    the    design"       "[t]o     the    maximum    extent
    practicable."       N.J.A.C.      7:8-5.2(a),          -5.3(a)    (emphasis       added).
    The   nine    specific      nonstructural         strategies       that     "shall"      be
    incorporated       into   every     site       design    to     "the    maximum    extent
    practicable" are listed in N.J.A.C. 7:8-5.3(b).
    In   addition,      all     permit       applicants       "shall    identify      the
    nonstructural      strategies       incorporated         into    the     design    of   the
    project."       N.J.A.C.         7:8-5.3(a)      (emphasis       added).          "If   the
    applicant    contends      that     it    is    not    feasible    for     engineering,
    environmental or safety reasons to incorporate any nonstructural
    stormwater management strategies identified in [N.J.A.C. 7:8-
    5.3(b)] . . . into the design of a particular project, the
    applicant shall identify the strategy and provide a basis for
    the contention."          
    Ibid.
     (emphasis added).               It is only when the
    standards     in    N.J.A.C.       7:8-5.4       and    -5.5     cannot     be    met     by
    nonstructural       measures        alone       that      "structural          stormwater
    management measures . . . necessary to meet these standards
    shall be incorporated into the design."                   N.J.A.C. 7:8-5.2(a).
    35                                     A-2231-08T2
    Consequently,             the        Department's             regulations           require
    applicants     for       major        developments,           such        as     CareOne,        to
    demonstrate that, to the "maximum extent practicable," they gave
    nonstructural        stormwater            strategies,         such        as      swales       or
    bioretention        basins,          priority         over     structural          stormwater
    strategies,       such    as     storm       sewers,         pipes,       and     manufactured
    treatment devices.            If they cannot do so, they must prove why
    such priority was not feasible for engineering, environmental or
    safety reasons.10
    When     the     Department            proposed         its        current    stormwater
    management    rules      in    2003,        35    N.J.R.     119(a)       (Jan.     6,     2003),
    commenters     requested             "a     definition"            of     "maximum        extent
    practicable," 36 N.J.R. 670(a), 691 (comments 185-86) (Feb. 2,
    2004).      The     Department            responded     that       the     term     is    "fact-
    sensitive and cannot be reduced to a standard formula.                                         The
    reviewing     agency's         administrative           discretion          in     determining
    compliance with these rules will be guided by the goals of this
    chapter and its statutory mandates."                           
    Ibid.
               The Department
    explained that the term was "used to describe the expenditure of
    effort required to achieve full compliance with the applicable
    10
    The  Department  provides  extensive  guidance   concerning
    nonstructural stormwater management strategies.   See N.J.A.C.
    7:8-5.3(d), -5.9.
    36                                      A-2231-08T2
    standard, taking into account the specific circumstances of the
    development in question."   
    Ibid.
    Commenters further noted that neither the proposed rules
    nor the New Jersey Stormwater Best Management Practices (BMP)
    Manual "include[d] any specifics as to how can one calculate the
    effectiveness of the nonstructural measures incorporated into
    the site design as required under N.J.A.C. 7:8-5.3."       Id. at
    719-20 (comments 473-75).   The Department responded:
    Calculations are performed based upon
    computational methods referenced in N.J.A.C.
    7:8-5.4(a)2i and 5.6.   The factors that are
    utilized in the calculations depend upon the
    nonstructural stormwater strategy and the
    site-specific conditions. . . .      The BMP
    Manual provides guidance on how to adjust
    computations based on the nonstructural
    stormwater BMPs implemented.     Because the
    calculations depend on varying site-specific
    conditions, the Department does not believe
    that   the   formation   of   a    table  is
    appropriate.
    The     applicant's     engineer     must
    demonstrate    and   discuss   the    use   of
    nonstructural      stormwater       management
    techniques throughout a proposed development
    site to demonstrate where each technique is
    utilized.       In   cases   where    specific
    techniques are not used, the applicant's
    engineer must provide the justification.     A
    checklist is included in the BMP Manual to
    assist    designers     to    address     this
    requirement.
    [Id. at 720.]
    37                        A-2231-08T2
    In     2006,    however,      the     Department        created      the        NSPS,
    described    in     the   NSPS    User's      Guide    as    "a    tool   to      assist
    planners,    designers,     and    regulators         in    determining      that      the
    strategies have been used to the 'maximum extent practicable' at
    a major development as required by the Rules" (emphasis added).
    It posted the NSPS User's Guide and the NSPS Excel Spreadsheet
    on   its    website,      along   with     other       guidance      documents         and
    responses    to     "Frequently     Asked      Questions"         relating      to     its
    stormwater management rules.11
    According to the NSPS User's Guide (emphasis added):
    The New Jersey NSPS is a Microsoft Excel-
    based computer spreadsheet program that can
    be used to demonstrate that sufficient
    nonstructural stormwater management measures
    have been incorporated into the design of a
    major land development project to . . . meet
    the maximum extent practicable requirement
    for   nonstructural    strategies    in    the
    Stormwater Management Rules.       The NSPS
    assigns points based upon the existing and
    proposed conditions at the development site.
    A specific percentage of existing or pre-
    developed points must be achieved under
    proposed or post-developed conditions in
    order to demonstrate compliance through the
    NSPS.    As described in detail below, the
    required   percentage  of   existing    points
    varies according to the size of project site
    and the State Planning Area in which it is
    located.
    11
    See N.J. Dep't of Envtl. Prot., Stormwater Magagement:
    Additional   Guidance   Documents,   http://www.njstormwater.org/
    guidance.htm (last visited Aug. 5, 2013).
    38                                     A-2231-08T2
    Appellants       argue    that   the       NSPS    has        the    effect     of   an
    administrative rule and should have been adopted through the
    formal    rulemaking      process.         Both    the        Department      and     CareOne
    argue that formal APA rulemaking is not required because the
    Department is entitled to take informal action to advise and
    supervise the regulated community, such as creating the NSPS and
    using it to review permit and waiver applications.                             They assert
    that     the     NSPS     provides         no     new     substantive           legal       or
    administrative standard or policy that cannot be inferred from
    the existing stormwater management rules.                         Respondents further
    maintain       that     use     of   the        NSPS     is     not        "mandatory"      or
    "dispositive."          Instead,     they       contend       that    the    NSPS     "merely
    serves as a screening device to streamline review."                                 They aver
    that it is only "one way" for the agency to review a project's
    nonstructural features, providing only a preliminary screen for
    minimal    compliance         with   N.J.A.C.          7:8-5.3       standards        without
    "eliminate[ing]          case-specific           departmental              review      of     a
    stormwater plan."
    Respondents'        argument        is      fatally           undercut        by     the
    Department's own "Important Note" in the NSPS User's Guide.
    Important Note:    If the NSPS demonstrates
    that   sufficient  nonstructural   stormwater
    management measures have been utilized at a
    major development, no further proof of
    compliance    with   the    maximum    extent
    practicable requirement shall be required.
    39                                       A-2231-08T2
    However, if the NSPS fails to demonstrate
    such compliance, such results shall not be
    used to disapprove any permit application
    sought by a proposed major development.
    Instead, the applicant for such permit will
    be   required   to   demonstrate  compliance
    through other and/or additional means. This
    includes the Low Impact Development (LID)
    Checklist contained in Appendix A of the New
    Jersey Stormwater Best Management Practices
    Manual,    which    includes    a   rigorous
    alternatives analysis for each measure.
    Finally, it should be noted that the NSPS is
    not presently intended for use on roadway
    construction, improvement, and other linear
    development projects.    As a result, other
    means, including the LID Checklist, should
    be used for such projects.
    [(Emphasis added).]
    It is clear from the language used by the Department itself
    that its review of the use of nonstructural measures does not go
    beyond    the    NSPS     if    the   minimum   number     of    points     have   been
    awarded     to        satisfy      the   "sufficient"           standard,     without
    determining whether the use of additional nonstructural measures
    would have been practicable.               In contrast, failure to use the
    NSPS or to reach the required "sufficient" score will result in
    "a rigorous alternatives analysis for each measure."                          Such an
    application      of    the     NSPS   conflicts     with   the    Department's      own
    assertion,       during      promulgation      of   its    stormwater     management
    regulations, that the term "maximum extent practicable" found in
    N.J.A.C. 7:8-5.3 is "fact-sensitive and cannot be reduced to a
    standard formula."             36 N.J.R. at 691 (response to comments 185-
    40                                  A-2231-08T2
    86).      Indeed,     the     Department           asserted    that     "[b]ecause      the
    calculations       depend     on    varying        site-specific      conditions,       the
    Department does not believe that the formation of a table is
    appropriate."       Id. at 720 (response to comments 473-76).
    Appellants argue that the use of the NSPS, as described by
    the    Department,      improperly        shortcuts         the    application       review
    process because it has not been subjected to the rulemaking
    process and its opportunity for public comment.                       We agree.
    Administrative agencies possess wide latitude in selecting
    the appropriate procedures to effectuate their regulatory duties
    and    statutory    goals.          In   re     Request     for    Solid     Waste   Util.
    Customer Lists, 
    106 N.J. 508
    , 519 (1987); Metromedia, Inc. v.
    Dir., Div. of Taxation, 
    97 N.J. 313
    , 333 (1984); Texter v. Dep't
    of    Human   Servs.,    
    88 N.J. 376
    ,      383-84     (1982).        However,    an
    agency's      "discretion      to    act      formally        or   informally     is    not
    absolute."       In re N.J.A.C. 7:1B-1.1 et seq., 
    431 N.J. Super. 100
    , 133 (App. Div. 2013) (petition for certification pending).
    "The    inquiry      whether        an      agency's        actions    constitute
    improper      rulemaking      is    informed        by   well-settled        principles."
    
    Ibid.
        Guidance documents, standardized forms, and responses to
    "frequently asked questions" can constitute improper rulemaking.
    Id. at 112-14, 138-40.
    41                                 A-2231-08T2
    The    APA     defines       an   administrative       rule       as   an   agency's
    "statement of general applicability and continuing effect that
    implements     or    interprets        law    or    policy,       or    describes         the
    organization, procedure or practice requirements" of the agency.
    N.J.S.A. 52:14B-2(e).              "If an agency determination or action
    constitutes an 'administrative rule,' then its validity requires
    compliance with the specific procedures of the APA that control
    the promulgation of rules."               Airwork Serv. Div. v. Dir., Div. of
    Taxation, 
    97 N.J. 290
    , 300 (1984), cert. denied, 
    471 U.S. 1127
    ,
    
    105 S. Ct. 2662
    , 
    86 L. Ed. 2d 278
     (1985).
    Formal rulemaking "allows the agency to further the policy
    goals of legislation by developing coherent and rational codes
    of conduct 'so those concerned may know in advance all the rules
    of   the    game,     so    to     speak,     and   may     act    with       reasonable
    assurance.'"        Gen. Assembly of N.J. v. Byrne, 
    90 N.J. 376
    , 385-
    86 (1982) (quoting Boller Beverages, Inc. v. Davis, 
    38 N.J. 138
    ,
    152 (1962)).        "The purpose of the APA rulemaking procedures is
    'to give those affected by the proposed rule an opportunity to
    participate in the process, both to ensure fairness and also to
    inform     regulators       of    consequences      which     they      may      not    have
    anticipated.'"         In re Provision of Basic Generation Serv. for
    Period     Beginning       June    1[,]    2008,    
    205 N.J. 339
    ,       349    (2011)
    (quoting In re Adoption of 2003 Low Income Hous. Tax Credit
    42                                     A-2231-08T2
    Qualified Allocation Plan, 
    369 N.J. Super. 2
    , 43 (App. Div.),
    certif. denied, 
    182 N.J. 141
     (2004)).
    The Supreme Court has identified six factors to consider
    when evaluating whether an agency's action, "to be valid, had to
    comply   with   the   requirements    governing      the   promulgation   of
    administrative   rules   as   provided    by   the    APA."    Metromedia,
    
    supra,
     97 N.J. at 328.
    [A]n agency determination must be considered
    an administrative rule when all or most of
    the relevant features of administrative
    rules are present and preponderate in favor
    of   the   rule-making   process.       Such   a
    conclusion would be warranted if it appears
    that the agency determination, in many or
    most of the following circumstances, (1) is
    intended to have wide coverage encompassing
    a large segment of the regulated or general
    public, rather than an individual or a
    narrow select group; (2) is intended to be
    applied generally and uniformly to all
    similarly situated persons; (3) is designed
    to operate only in future cases, that is,
    prospectively;    (4)   prescribes    a    legal
    standard or directive that is not otherwise
    expressly   provided    by   or   clearly    and
    obviously    inferable   from   the    enabling
    statutory authorization; (5) reflects an
    administrative policy that (i) was not
    previously expressed in any official and
    explicit agency determination, adjudication
    or rule, or (ii) constitutes a material and
    significant change from a clear, past agency
    position on the identical subject matter;
    and    (6)     reflects    a    decision      on
    administrative regulatory policy in the
    nature of the interpretation of law or
    general policy. These relevant factors can,
    either singly or in combination, determine
    in a given case whether the essential agency
    43                            A-2231-08T2
    action must be rendered through rule-making
    or adjudication.
    [Id. at 331-32.]
    Although the Court formulated those factors in the context
    of   distinguishing       rulemaking      from    adjudication,           they    also
    provide a test for determining when rulemaking procedures are
    necessary      to     validate   agency       actions    or        determinations.
    Woodland Private Study Grp. v. N.J. Dep't of Envtl. Prot., 
    109 N.J. 62
    , 68 (1987).          "[T]he factors are relevant whenever the
    authority of an agency to act without conforming to the formal
    rulemaking requirements is questioned."              Doe v. Poritz, 
    142 N.J. 1
    , 97 (1995).        They "need not be given the same weight, and some
    factors will clearly be more relevant in a given situation than
    others."       
    Ibid.
          "The   pertinent       evaluation    focuses       on    the
    importance and weight of each factor, and is not based on a
    quantitative compilation of the number of factors which weigh
    for or against labeling the agency determination as a rule."                        In
    re Provision of Basic Generation Serv., 
    supra,
     205 N.J. at 350.
    We are satisfied that the NSPS and its User's Guide meet
    all of the Metromedia factors.            The use or non-use of the NSPS,
    as well as the achievement of or failure to obtain the required
    minimum points on the NSPS, directly affects the Department's
    review   of    all     applications    covered     by   the    "maximum          extent
    possible"     requirement.       In   fact,    avoidance      of    the    "rigorous
    44                                   A-2231-08T2
    review" resulting from failure to use the NSPS provides a clear
    incentive for its use.             The NSPS is intended for ongoing use,
    and     is    not   an   adjudicative     decision    or    application   of    a
    procedure       under    limited    circumstances.          It   establishes    a
    standard for application submissions and agency evaluations that
    is not otherwise expressly provided by or obviously inferable
    from the Department's stormwater management rules or from any
    statute or other regulation.                  It constitutes a material and
    significant change from what applicants are required to submit
    as    to     nonstructural    stormwater       management    strategies   under
    N.J.A.C. 7:8-5.3(a).          As already noted, it also represents a
    significant change from the Department's own position at the
    time it adopted the regulation, when it specifically rejected
    suggestions that it create a formula because compliance with
    those        requirements    is      a   "fact-sensitive"        determination.
    Finally, creating a fixed formula for assigning NSPS points and
    percentages reflects a decision on regulatory policy not found
    in regulations adopted through the APA.
    We conclude that the Department's use of and reliance on
    NSPS in connection with its evaluation of CareOne's applications
    was impermissible because the NSPS procedure was not the subject
    45                            A-2231-08T2
    of formal rulemaking.12       Consequently, in Docket No. A-2231-08,
    we reverse the Department's approval of the applications, as
    well as its issuance and modification of permits and related
    approvals.
    We affirm in Docket No. A-3837-09, and dismiss Docket No.
    A-3400-10    as   interlocutory.          We   remand   the     matter   to    the
    Department for further proceedings consistent with this opinion.
    For   that   reason,   we   need   not    consider   any   of    the   remaining
    points raised on appeal.
    Affirmed in part, reversed in part, dismissed in part, and
    remanded.    We do not retain jurisdiction.
    12
    We express no opinion, one way or another, concerning the
    propriety of the use of the NSPS should the Department adopt it
    through formal rulemaking. We note that, in the context of the
    Delaware and Raritan Canal State Park Law of 1974 (N.J.S.A.
    13:13A-1 to -15), the Department employed the APA's rulemaking
    procedure to provide for use of the NSPS as an evaluative tool.
    See N.J.A.C. 7:45-8.2(a)(16) and -8.4(a), (c).
    46                              A-2231-08T2