CHRISTOPHER HOUGHTON VS. STEVE HOURAN (L-1982-15, BERGEN COUNTY AND STATEWIDE) ( 2018 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2056-16T3
    CHRISTOPHER HOUGHTON,
    Plaintiff-Respondent,
    v.
    STEVE HOURAN, HOURAN FUCETOLA
    CONSTRUCTION, LLC, and HOURAN
    USA CONSTRUCTION, LLC,
    Defendants/Third-Party
    Plaintiffs-Appellants,
    v.
    SHEILA HOUGHTON,
    Third-Party Defendant-
    Respondent,
    and
    S&L ARCHITECTURE STUDIO, LLC,
    Third-Party Defendant.
    _________________________________
    Argued May 23, 2018 – Decided June 21, 2018
    Before Judges Koblitz, Manahan, and Suter.
    On appeal from Superior Court of New Jersey,
    Law Division, Bergen County, Docket No. L-
    1982-15.
    Michael J. Confusione argued the cause for
    appellants   (Hegge   &    Confusione,   LLC,
    attorneys; (Michael J. Confusione, of counsel
    and on the brief).
    Jeffrey S. Wilson argued the cause for
    respondents   (Hedinger   &    Lawless   LLC,
    attorneys; Jeffrey S. Wilson, on the brief).
    PER CURIAM
    Defendants       Steve    Houran   (Houran),      Houran      Fucetola
    Construction, LLC (Houran Fucetola), and Houran USA Construction,
    LLC   (Houran   USA)    (collectively    defendants)    appeal   from     the
    December 20, 2016 judgment entered against them in favor of
    plaintiff Christopher Houghton for defendants' breach of contract
    and violation of home improvement regulations.              We affirm the
    liability and compensatory damages portion of the judgment because
    there was substantial evidence to support them.             We vacate the
    attorney's fee award because of a lack of findings under Rule 1:7-
    4(a) and remand that issue for findings of fact and conclusions
    of law.    We also vacate the judgment based on a lack of findings,
    to the extent that it imposed individual liability upon defendant
    Houran for compensatory damages and for attorney's fees, and remand
    those issues to the trial court for findings consistent with Rule
    1:7-4(a).    We have not retained jurisdiction.
    In   September    2014,   plaintiff   filed   a   complaint    seeking
    compensatory, treble and punitive damages and attorney's fees from
    2                               A-2056-16T3
    defendants     for   breach     of   contract,     misrepresentation,         and
    violation of the Consumer Fraud Act (CFA), N.J.S.A. 56:8-1 to -
    48, arising from a home improvement contract that he signed with
    Houran Fucetola. Defendants' answer1 included a counterclaim for
    breach   of   contract    and   unjust     enrichment   and     a    third-party
    complaint     against    plaintiff's       wife,   Sheila    Houghton,     which
    additionally alleged tortious interference with the contract.2
    Sheila Houghton filed a third-party counterclaim.
    I
    A bench trial was conducted in November 2016, from which we
    glean the facts.        In 2013, Kenneth Schier of S&L Architecture
    Studio was hired to prepare architectural plans for an addition
    to plaintiff's home in Ridgewood, New Jersey.               Plaintiff searched
    for a contractor through Home Advisors.             Defendant Steve Houran
    received the referral, contacted plaintiff and met with him.
    Plaintiff gave Houran a copy of the architectural plans.                  Houran
    prepared the written contract based on these plans.                 It was signed
    on September 16, 2013, by plaintiff and Houran Fucetola.
    1
    Defendants' answer acknowledged that Steve Houran is the owner
    and managing member of Houran Fucetola and Houran USA.
    2
    Defendants filed a third party complaint against S&L Architecture
    Studio, LLC. This claim was dismissed.
    3                                 A-2056-16T3
    The contract did not include the business address of Houran
    Fucetola, the start and completion date for the project or the
    total price to be paid by plaintiff. It did include sub-categories
    of work to be completed and the price for the foundation, framing,
    roofing, siding, flooring, electrical, and plumbing.              The contract
    included    a   schedule    of   payments   that   were    due    upon   certain
    benchmarks.
    Work commenced on the addition in March 2014, after building
    permits    were   obtained.      The   construction   project      immediately
    struck a sour note, with the defendants undertaking demolition
    work while the Houghtons were away, contrary to their instruction.
    The work proceeded until April 23, 2014, when Houran sent a
    termination notice, claiming that delays were attributable to the
    owner's interference with the scope of the work and "trigger[ed]"
    by "the decision to remove portions of the contract."                    By that
    point,    plaintiff   had   paid   $51,861.74,     which    was    80%   of   the
    contract.       The construction was not finished.           Plaintiff hired
    contractors to remediate and complete the work.
    Schier testified as an expert in residential construction
    that there were multiple problems with the construction which was
    "[b]elow acceptable reasonable standards," describing it as "the
    worst construction project [he] had ever seen in [his] career."
    He testified that the foundation was improperly constructed, the
    4                                 A-2056-16T3
    ridge beam was not made of microllam as required by the plans, the
    construction    used    improper   fasteners,    lacked      headers,     used
    improper joist hangers, did not have hurricane straps, was missing
    floor joists, and the second floor stairs now were sagging.              There
    were other workmanship problems as well.
    The   Village     of   Ridgefield    building     inspector,      Carlo
    Madrachimov, testified, "there [were] multiple failures on this
    . . . project," which included the depth of the footing, framing
    deficiencies, and use of a ridge beam made of "regular nominal
    lumber."    He said that the architect's plans were not followed.
    Houran testified that he had many years' experience in the
    construction industry and completed hundreds of home improvement
    renovations. He said they ran into some issues in the construction
    that required four change orders, all of which were agreed to by
    plaintiff through email.       His firm was not able to complete the
    project because plaintiff "excised" parts of the contract.                  He
    blamed Sheila Houghton for interfering with their work.                 Houran
    was   not   permitted   to   testify   about   issues   he   had   with    the
    architectural plans because defendants had not named any expert
    witnesses in their answers to discovery.         David Sanchez, who was
    employed by Houran USA on the project, testified that Sheila would
    not let the project go forward as she "was always there having a
    5                             A-2056-16T3
    little comment or asking something or saying something to do their
    own way."
    The trial court issued a written opinion on November 17,
    2016,3 finding that defendants breached the contract by sending
    the termination notice and that Sheila did not interfere with
    defendants' work.         The court described Houran's testimony as
    "lacking detail, or any support by reference to the applicable
    architectural codes."       The court did not consider his testimony
    credible because photographs in evidence showed "the poor quality
    of his work."     The court found that plaintiff suffered actual
    damages of $41,493.06, consisting of the cost to remediate and to
    complete the work, less the balance remaining on the contract.
    The court held that the contract violated portions of the
    "Home    Improvement      Practices"        regulations,   N.J.A.C.    13:45A-
    16.2(a)(12),    because    it   did    not    include   defendants'   business
    address, the dates or time period the work would begin or be
    completed by, or the total price to be paid by the buyer.                   The
    court denied plaintiff's request for treble damages under the CFA,
    however, because his damages arose from "shoddy work and breach
    of contract," and were not causally related to the CFA violations.
    3
    The record does not include an order from November 17, 2016.
    6                              A-2056-16T3
    Plaintiff was entitled to an award of attorney's fees under the
    CFA, citing Cox v. Sears Roebuck & Co., 
    138 N.J. 2
     (1993).
    The trial court's December 20, 2016 "Order for Judgment"
    provided in the "whereas" clauses that "sufficient evidence had
    been presented that the defendant Steven Houran was individually
    liable under the 'Home Improvement Practices' regulations of the
    CFA"   and   that   plaintiff's    attorney's   fee   certification   was
    "reasonable and proper based on the complexity of this case and
    the amount of time reasonably expected for a case of this nature."
    The court entered a judgment against all defendants, including
    Houran individually, in the amount of $68,193.06, consisting of
    $41,493.06 in compensatory damages and $26,700 in attorney's fees
    and costs.
    On appeal, defendants contend that the trial court erred by
    finding that they breached the contract and by rejecting their
    claim of anticipatory breach by plaintiff.            Houran contends he
    should have been able to testify as an expert about the work
    performed by his company.         Even if there were liability on the
    part of the company because the contract was breached or the home
    improvement regulations were violated, defendants claim the court
    should not have held Houran individually liable for damages or for
    attorney's fees.      Although not raised before the trial court,
    7                           A-2056-16T3
    defendants argue the court erred by not apportioning the award of
    attorney's fees between the breach of contract and CFA claims.
    II
    We afford a deferential standard of review to the factual
    findings of the trial court on appeal from a bench trial.                   Rova
    Farms Resort, Inc. v. Inv'rs Ins. Co., 
    65 N.J. 474
    , 483-84 (1974).
    These findings will not be disturbed unless they are "so manifestly
    unsupported by or inconsistent with the competent, relevant and
    reasonably   credible    evidence    as    to    offend    the   interests    of
    justice."    
    Id. at 484
     (quoting Fagliarone v. Twp. of N. Bergen,
    
    78 N.J. Super. 154
    , 155 (App. Div. 1963)).                However, our review
    of a trial court's legal determinations is plenary.                 D'Agostino
    v. Maldonado, 
    216 N.J. 168
    , 182 (2013) (citing Manalapan Realty,
    L.P. v. Twp. Comm. of Manalapan, 
    140 N.J. 366
    , 378 (1995)).
    There was ample evidence to support the court's finding that
    defendants breached this contract.              To establish his breach of
    contract claim, plaintiff was required to prove that (1) "[t]he
    parties entered into a contract containing certain terms"; (2)
    "plaintiff did what the contract required                 [him] to do"; (3)
    "defendant[s]   did     not   do    what   the     contract      required    the
    defendant[s] to do"; and (4) "defendant[s'] breach, or failure to
    do what the contract required, caused a loss to the plaintiff."
    Model Jury Charge (Civil), 4.10A "The Contract Claim - Generally"
    8                                A-2056-16T3
    (approved May 1998); see Globe Motor Co. v. Igdalev, 
    225 N.J. 469
    ,
    482 (2016).    No one disputed that there was a written contract and
    that plaintiff paid defendants pursuant to the contract.
    The contract provided that the work was to be completed per
    the final architectural plans.          The evidence, which largely was
    unrefuted, showed that defendants' construction work varied widely
    from these plans, consisting of among other things, improper ridge
    beams,   headers,    fasteners,    hangers       and   straps.       Houran's
    testimony, found not to be credible, was inconsistent with the
    photographic evidence.     The work that was performed by defendants
    needed   to   be   repaired,   resulting    in    additional     expenses    to
    plaintiff.
    We agree with the trial court that the evidence did not
    support defendants' anticipatory breach of contract claim.                  "An
    anticipatory breach is a definite and unconditional declaration
    by a party to an executory contract – through word or conduct –
    that he will not or cannot render the agreed upon performance."
    Ross Sys. v. Linden Dari-Delite, Inc., 
    35 N.J. 329
    , 340-41 (1961).
    If the breach goes to the essence of the contract, the non-
    breaching party may treat the contract as terminated and refuse
    to render continued performance.            
    Id. at 341
    .          Anticipatory
    repudiation can be found "where reasonable grounds support the
    obligee's belief that the obligor will breach the contract.'"
    9                                 A-2056-16T3
    Spring Creek Holding Co. v. Shinnihon U.S.A. Co., 
    399 N.J. Super. 158
    , 180 (App. Div. 2008) (quoting Danzig v. AEC Corp., 
    224 F.3d 1333
    , 1337 (2000)).
    Houran's and Sanchez's testimony that Sheila "interfered" and
    asked them to "change" things evidenced nothing specific that
    would have prevented performance under the contract.                    Houran
    testified he could have completed the contract, which undercut his
    claims   about   Sheila.    Houran     also   complained      that   plaintiff
    "excised" certain portions of the contract              but this was not
    material   because   by    that    time,    plaintiff   had    substantially
    performed and defendant never demanded reasonable assurance from
    plaintiff.   See Spring Creek, 339 N.J. Super. at 179-80.
    Defendants contend the court erred by not allowing Houran to
    testify as an expert witness.             "The admission or exclusion of
    expert testimony is committed to the sound discretion of the trial
    court." Townsend v. Pierre, 
    221 N.J. 36
    , 52 (2015). "The decision
    as to exclusion must stand unless so wide of the mark that a
    manifest denial of justice resulted."           Ratner v. General Motors
    Corp., 
    241 N.J. Super. 197
    , 202 (App. Div. 1990).
    Houran testified as a fact witness about construction of the
    addition; he did not have training or experience to testify about
    the architectural plans.          Also, defendants did not provide the
    names of, or reports from, any expert witnesses in their answers
    10                                A-2056-16T3
    to discovery.        We discern no abuse of discretion by precluding
    Houran's testimony as an expert under these circumstances.
    Defendants appeal the judgment to the extent that it imposed
    individual liability on Houran to pay damages and attorney's fees
    because plaintiff's contract was with Houran Fucetola and not
    Houran individually.         The judgment simply provided in a "whereas"
    clause that "sufficient evidence had been presented that the
    defendant Steve Houran was individually liable," citing to the
    home improvement regulations of the CFA.             The trial court made no
    findings of fact to support this portion of the judgment.
    Rule 1:7-4(a) requires that in all actions tried without a
    jury the court "shall by an opinion or memorandum decision, either
    written or oral, find the facts and state its conclusions of law."
    "The purpose of the rule is to make sure that the court makes its
    own determination of the matter."             In re Tr. Created by Agreement
    Dated Dec. 20, 1961, by & between Johnson and Hoffman, Lienhard &
    Perry, 
    399 N.J. Super. 237
    , 254 (App. Div. 2006).                "When a trial
    court issues reasons for its decision, it 'must state clearly
    [its] factual findings and correlate them with relevant legal
    conclusions,    so    that    parties   and    the   appellate   courts   [are]
    informed of the rationale underlying th[ose] conclusion[s].'"
    Avelino-Catabran v. Catabran, 
    445 N.J. Super. 574
    , 594-95 (App.
    11                             A-2056-16T3
    Div. 2016) (alterations in original) (quoting Monte v. Monte, 
    212 N.J. Super. 557
    , 565 (App. Div. 1986)).
    Here, the compensatory damages portion of the judgment was
    based on a breach of contract.     The contract was between Houghton
    and Houran Fucetola.     Houran was not individually liable solely
    as a managing member of the limited liability company.                 See
    N.J.S.A. 42:2C-30 (providing that "[t]he debts, obligations, or
    other liabilities of a limited liability company . . . are solely
    the debts, obligations, or other liabilities of the company[,] and
    [they] do not become the debts, obligations, or other liabilities
    of a member or manager solely by reason of the member acting as a
    member or manager acting as a manager").
    The   power   to   look   beyond   the   corporate   form   is   well
    established. Stochastic Decisions, Inc. v. DiDomenico, 
    236 N.J. Super. 388
    , 393 (App. Div. 1989).       "It is only upon proof of fraud
    or injustice that a court will pierce the corporate veil to impose
    liability on the corporate principals."         Touch of Class Leasing
    v. Mercedes-Benz Credit, 
    248 N.J. Super. 426
    , 441 (App. Div. 1991)
    (citations omitted).
    Here, the court made no findings of fraud or injustice that
    would support its order that Houran was individually responsible
    for the breach of contract by the limited liability companies.
    In the absence of findings, we must vacate the judgment to the
    12                             A-2056-16T3
    extent it imposed individual liability on Houran and remand that
    issue to the trial court for appropriate findings of fact and
    conclusions of law.
    The December 20, 2016 judgment awarded $26,700 in attorney's
    fees and costs to plaintiff against defendants, including Houran
    individually.      Defendants   contend       the   court   erred   in    awarding
    attorney's fees against defendant Houran individually and by not
    allocating fees between the breach of contract and CFA claims.
    An    award    of   attorney's    fees    is    reviewed    for   "abuse     of
    discretion."       Masone v. Levine, 
    382 N.J. Super. 181
    , 193 (2005).
    "[A]buse of discretion is demonstrated if the discretionary act
    was not premised upon consideration of all relevant factors, was
    based upon consideration of irrelevant or inappropriate factors,
    or amounts to a clear error in judgment."                
    Ibid.
     (citing Flagg v.
    Essex Cty. Prosecutor, 
    171 N.J. 561
    , 571 (2002)).
    The CFA allows courts to award "reasonable attorney's fees"
    to a successful plaintiff under certain circumstances.                    N.J.S.A.
    56:8-19.     A plaintiff may recover attorney's fees for violations
    of the CFA even where the plaintiff has failed to establish an
    ascertainable loss.       Cox, 138 N.J. at 24; Branigan v. Level on the
    Level, Inc., 
    326 N.J. Super. 24
    , 31 (App. Div. 1999).                    Here, the
    trial     court    awarded   fees     although      it   found   there    was     no
    13                                  A-2056-16T3
    ascertainable   loss    by    plaintiff     arising   from    the   regulatory
    violations.
    An    employee    or    officer   of   a   corporation    can    be    held
    individually liable under the CFA "when the basis for the CFA
    claim is a regulatory violation rather than an affirmative act or
    knowing misrepresentation."        Allen v. V & A Bros., Inc., 
    208 N.J. 114
    , 133 (2011).       In Allen, the Court recognized this involved
    "fact-sensitive determinations."            "[I]ndividual liability for a
    violation of the CFA will necessarily depend upon an evaluation
    of both the specific source of the claimed violation that forms
    the basis for the plaintiff's complaint as well as the particular
    acts that the individual has undertaken."             
    Id. at 136
    .     The same
    analysis should apply when determining whether attorney's fees
    awarded under the CFA for regulatory violations can be assessed
    individually against an employee or officer of a corporation or
    limited liability company.
    The   trial   court     awarded    attorney's     fees   based    on   the
    uncontested violation of the home improvement regulations.                  The
    contract itself had made no provision for an award of fees in the
    event of a breach.      The judgment provided in a "whereas" clause
    that plaintiff's counsel submitted a certification "in accordance
    with Rule 4:42-9(a) and RPC 1.5(a)" in the amount of $26,700 and
    the court found that amount "to be reasonable and proper based on
    14                              A-2056-16T3
    the complexity of this case and the amount of time reasonably
    expected for a case of this nature."     However, the court made no
    findings about the fees charged, the hours spent on the case,
    whether the hours related to the breach of contract or CFA claim
    or any of the other factors under RPC 1.5.     See R. 1:7-4(a).
    We do not know whether the court determined a lodestar or
    whether it chose to enhance it.    See Rendine v. Pantzer, 
    141 N.J. 292
    , 337 (1995) (providing that after determining the lodestar,
    the trial court should "consider whether to increase that fee to
    reflect the risk of nonpayment in all cases in which the attorney's
    compensation   entirely   or   substantially   is   contingent     on    a
    successful outcome").     The court did not give reasons for why
    Houran should be held individually liable for these fees.
    Defendants complain that the attorney fee award should be
    allocated because there were no ascertainable losses attributable
    to the CFA claim.    However, attorney's fees do not have to be
    proportionate to the damages.     "Although there is no requirement
    that an award of attorneys' fees be proportionate to damages, 'the
    amount of damages a plaintiff recovers is certainly relevant to
    the amount of attorney's fees to be awarded . . . .'"      Chattin v.
    Cape May Greene, Inc., 
    243 N.J. Super. 590
    , 616 (App. Div. 1990)
    (quoting Riverside v. Rivera, 
    477 U.S. 561
    , 574 (1986)).
    15                              A-2056-16T3
    We vacate the award of attorney's fees because of these lack
    of findings.   We remand the issue of attorney's fees to the trial
    court to make findings of fact and conclusions of law.     In that
    regard the court is to determine the amount of attorney's fees
    that are reasonable and then whether the fees should be assessed
    against Houran individually.
    Affirmed in part; vacated and remanded in part.      We do not
    retain jurisdiction.
    16                         A-2056-16T3