TARTA LUNA PROPERTIES, LLC VS. HARVEST RESTAURANTS GROUP, LLC (C-000101-16, UNION COUNTY AND STATEWIDE) ( 2021 )


Menu:
  •                NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-4994-18T3
    TARTA LUNA PROPERTIES,
    LLC, a New Jersey Limited
    Liability Company, and
    125 ELM STREET, LLC,
    a New Jersey Limited                  APPROVED FOR PUBLICATION
    Liability Company,                          January 28, 2021
    APPELLATE DIVISION
    Plaintiffs-Respondents/
    Cross-Appellants,
    v.
    HARVEST RESTAURANTS
    GROUP LLC, a New Jersey
    Limited Liability Company,
    CHESTER GRABOWSKI,
    and ROBERT J. MOORE,
    Defendants-Appellants/
    Cross-Respondents.
    ___________________________
    Argued November 9, 2020 – Decided January 28, 2021
    Before Judges       Currier,   Gooden    Brown      and
    DeAlmeida.
    On appeal from the Superior Court of New Jersey,
    Chancery Division, Union County, Docket No. C-
    000101-16.
    Joseph P. LaSala argued the cause for
    appellants/cross-respondents (McElroy, Deutsch,
    Mulvaney & Carpenter, LLP, attorneys; Joseph P.
    LaSala, of counsel and on the briefs; George C. Jones,
    on the briefs).
    Sheppard A. Guryan argued the cause for
    respondents/cross-appellants (Lasser Hochman, LLC,
    attorneys; Sheppard A. Guryan and Bruce H. Snyder,
    of counsel and on the briefs).
    The opinion of the court was delivered by
    CURRIER, J.A.D.
    This litigation arises out of the lease of a building in Westfield in which
    defendants intended to open a restaurant. The lease agreement contemplated
    an extensive rebuilding and repair of the premises. During the renovations,
    plaintiffs raised numerous issues regarding the quality of the construction.
    They eventually instituted suit seeking the termination of the lease and
    imposition of a forfeiture as well as an increase in rent. After a bench trial, the
    Chancery court entered judgment in favor of defendants, finding plaintiffs'
    claims meritless. However, in determining an award of fees was warranted by
    principles of equity, the court awarded plaintiffs nearly $1,000,000 in counsel
    and expert fees.
    Defendants appeal from the order granting fees. Plaintiffs appeal from
    the order denying their request to impose forfeiture and from the calculation of
    the fee award.     Because the fee award was not supported by a contract
    provision, statutory authority or court rule nor the equities of the
    A-4994-18T3
    2
    circumstances, we conclude the court mistakenly exercised its discretion in its
    award of fees to plaintiffs – the non-prevailing party. We affirm the denial of
    forfeiture.
    I.
    A.
    Plaintiff Tarta Luna is the owner of premises located at 115 Elm Street,
    Westfield. Plaintiff 125 Elm is the owner of premises located at 125 Elm
    Street, which adjoins 115 Elm. The two premises share a common wall. The
    managing partners of the two entities, Norman and Carol Greco respectively,
    are married to one another.
    Defendant Harvest Restaurants Group LLC (Harvest) owns and operates
    several restaurants. 1 On October 15, 2013, Harvest entered into an agreement
    with Tarta Luna to lease the premises at 115 Elm Street for a twenty-year term.
    Harvest intended to make extensive renovations to the premises, including the
    reconstruction of the rear annex with a new basement, alteration of the ground
    floor layout, and the addition of a new second floor with a gable roof f or
    dining space and an outdoor herb garden.
    1
    Defendant Chester Grabowski is the managing member of the LLC. He and
    defendant Robert J. Moore personally guaranteed Harvest's obligations under
    the lease agreement.
    A-4994-18T3
    3
    After executing the lease agreement, Harvest retained the services of a
    licensed architect and licensed structural engineer to develop the renovation
    plans. Norman Greco, on behalf of Tarta Luna, authorized Harvest to present
    the plans to the Westfield Planning Board. The preliminary and final major
    site plans were approved by the Planning Board in October 2014.
    Construction began in February 2015.
    Grabowski testified that after the Planning Board approved the plans, he
    met with the Grecos and Moore to discuss Harvest's interest in extending the
    lease an additional five years. Carol suggested the rent increase as of the
    twenty-first year should be based on the market value of the premises at that
    time, accounting for the renovations and increased square footage. Grabowski
    agreed and asked his attorney to prepare a lease extension reflecting the new
    terms. Although plaintiffs' attorney forwarded the new document, there was
    no response from the Grecos and the agreement was never signed. Grabowski
    stated he wished to extend the lease so Harvest would not lose the building
    after investing so deeply in the extensive renovations.
    Pursuant to the lease agreement, the monthly rent was scheduled to
    increase every five years. However, Grabowski testified that in the summer of
    2015, Norman Greco wanted to immediately increase the monthly rent – from
    $10,600 to $28,625 – to reflect the increased square footage due to the
    A-4994-18T3
    4
    renovations. When Grabowski refused to agree to the proposed increase, he
    stated that Norman threatened to "make his life miserable."
    In September 2015, Carol Greco raised concerns about the construction
    of the new second story wall, specifically that it was being bolted to the
    existing common wall between 115 and 125 Elm Street. She discussed the
    issue with Grabowski and the Westfield construction official.
    In May 2016, Carol retained a local architect – George Sincox. After
    reviewing the filed permit plans, Sincox sent several emails to the New Jersey
    Department of Community Affairs (DCA), informing it of his concerns with
    the construction of the common wall.        Sincox advised the DCA that the
    common wall was not comprised of concrete masonry units as shown on the
    plans, but the builder was using hollow core terracotta instead, creating a less
    stable structure. He also queried the fire rating of the common wall and said
    that defendants were not complying with the applicable building codes. The
    DCA forwarded the emails to the Town construction official, asking him to
    address Sincox's concerns with defendants' architect.
    Grabowski testified that he informed Harvest's architect, engineer, and
    attorneys of the Grecos' complaints.        He stated that he relied on his
    "professionals," as well as the Westfield construction official, to perform the
    renovations in a satisfactory manner.
    A-4994-18T3
    5
    In June 2016, defendants' architect addressed Sincox's concerns with the
    construction official. In his letter, the architect stated that prior to demolition
    the "exact composition of the common wall was not visible . . . hence an
    assumption was made as to its construction type based on other parts of the
    building . . . ." The architect further explained:
    This assumption was that the wall has been
    constructed of concrete masonry units, to be verified
    in field and that the wall will provide for a three-hour
    fire resistance. In fact, based on field dimensions and
    the surveys of the property we had reason to believe
    that there were two walls adjacent to each other. It
    was not [until we were] well into the interior
    demolition when we discovered the wall is in fact a
    common wall.
    During construction I was not notified that field
    conditions varied from assumed and that this wall was
    in fact not constructed from concrete masonry units.
    It was not until recently that it became clear that the
    wall is made of terracotta blocks.
    Defendants' architect then discussed several fire rating manuals and
    determined that the wall had a three-hour rating as recommended by the
    National Institute of Building Sciences.
    Although the Town construction official initially issued a stop
    construction order in May 2016 in response to the Grecos' concerns, he
    rescinded the order shortly thereafter. The June 1, 2016 Notice of Abatement
    stated "5/31/16 – Upon State inspection, no sign of structural damage to
    A-4994-18T3
    6
    adjoining building.   Wall construction is complete in accordance with the
    approved plans (protection of adjoining building is applicable during
    construction)." The official added a handwritten note, stating he had advised
    the DCA that "the party wall in question has already been built. No problem
    with the wall or the next[-]door property."
    Plaintiffs were not satisfied with defendants' response to the issues they
    had raised with the renovations.      Therefore, in addition to Sincox, they
    retained Anthony J. Pagnotta as an engineering expert, and legal counsel. On
    June 17, 2016, Pagnotta conducted a structural review of the premises and,
    among other things, highlighted the issue with the composition of the walls.
    Plaintiffs' counsel sent a letter to Harvest on June 23 detailing Pagnotta's
    findings.   A similar letter was sent in late July to the Town construction
    official.
    Defendants' engineer responded to counsel's letter in July, advising he
    would construct a structurally independent load-bearing wall, rather than
    anchoring to the existing terracotta wall. New construction drawings were
    submitted. In a certification dated October 25, 2016, the Town construction
    official stated he "personally inspected the structurally independent bearing
    wall to confirm that it was constructed in accordance with the drawings." The
    official concluded that the construction "was performed in accordance with all
    A-4994-18T3
    7
    plans and drawings submitted, conformed with all permits issued, and was in
    compliance with all applicable Codes." 2
    B.
    On August 17, 2016, plaintiffs applied for an order to show cause,
    supported by their Verified Complaint and certifications from Pagnotta and
    Sincox. Plaintiffs sought: (1) a preliminary and permanent injunction barring
    Harvest from continuing renovation activities or opening the premises as a
    restaurant to the public until all of the issues identified by plaintiffs were fully
    addressed and resolved; (2) relief for defendants' breach of the lease
    agreement; and (3) a recalculation of defendants' monthly rent obligation based
    on the new square footage of the premises.
    On August 30, 2016, the Chancery court ordered defendants to respond
    to the questions raised by plaintiffs' professionals, provide relevant
    documentation related to the premises, and allow plaintiffs access to the
    premises. The order also prevented defendants from opening the premises to
    the public.
    2
    The Westfield official later indicated, during his February 7, 2017
    deposition, that he inspected the structurally independent load-bearing wall
    during a February 2016 framing inspection, before it was designated as a load -
    bearing wall.
    A-4994-18T3
    8
    Defendants subsequently applied to the court for an order permitting
    them to open the restaurant for business. After hearing argument on the order
    to show cause and defendants' motion, and relying on the construction
    official's certifications, 3 the court denied plaintiffs' application and granted
    defendants permission to open the premises upon the issuance of a Certificate
    of Occupancy (CO) from the town. On November 11, 2016, Westfield issued
    the CO and defendants opened the restaurant.
    Several days later, plaintiffs challenged the issuance of the CO. The
    Union County Construction Board of Appeals failed to act within the time
    limit prescribed by N.J.S.A. 52:27D-127(b), resulting in an automatic denial of
    plaintiffs' claim.
    On December 8, 2016, defendants filed their answer and counterclaims
    in the Chancery Division action. Defendants alleged, among other things, that
    plaintiffs' true motivation for initiating proceedings was to "extort additional
    rent[.]"
    Several days later, plaintiffs' counsel served Harvest with a notice of
    termination that sought to terminate the lease agreement based on Harvest's
    failure to remedy the violations raised in plaintiffs' June 23, 2016 letter.
    3
    The official submitted the October 25, 2016 certification referred to above in
    which he stated that the construction had passed all final inspections and the
    property was safe for its intended use and occupancy.
    A-4994-18T3
    9
    Plaintiffs also filed a Complaint in Lieu of Prerogative Writs in the Superior
    Court, Law Division, Union County, against the Town of Westfield, its
    building inspector, and Harvest, seeking to rescind and vacate the CO. The
    action was transferred to the Chancery Division for management with the
    pending action. 4
    In February 2017, plaintiffs moved to dismiss defendants' counterclaims
    and for leave to file and serve a supplemental complaint alleging the lease
    agreement had been terminated and seeking possession, damages, and holdover
    rent.    The court granted plaintiffs' motion, permitting them to file a
    supplemental complaint and dismissed some of defendants' counterclaims
    based on the litigation privilege. 5
    C.
    On March 16, 2017, plaintiffs moved for an order requiring the closing
    of the restaurant or, in the alternative, for an immediate evidentiary hearing.
    Plaintiffs challenged defendants' compliance with the applicable building
    codes. Each side presented certifications from their respective experts. After
    argument, the court denied the motion, finding plaintiffs had not met their
    4
    The complaint was dismissed as moot after the Chancery court issued its
    December 12, 2017 order.
    5
    The remaining counterclaims were dismissed under a May 15, 2017 order.
    A-4994-18T3
    10
    burden to obtain injunctive relief. The court noted the parties had agreed to
    the appointment of an independent engineering expert to review the
    construction work and address the issue of the safety of the structure.
    When the parties failed to reach a consensus, the court appointed Glenn
    Kustera, P.E., to serve as the third-party expert.           While Kustera was
    conducting his investigation, plaintiffs' engineer produced sketches showing
    the second story wall was anchored to the terracotta wall with a type of screw
    only meant for use with concrete block. As a result, plaintiffs requested a
    court order to cease all construction. On August 16, 2017, the court granted
    plaintiffs' request to open and inspect a portion of the area between the rear
    wall of the restaurant and the terracotta common wall. The parties and their
    experts, including Kustera, were permitted to attend the inspection.
    On August 22, 2017, Kustera issued his report, addressing whether the
    structural design of the building complied with the applicable building codes.
    The expert concluded that "the building addition is not code compliant and has
    potentially serious structural deficiencies particularly with regard to the lateral
    stability of the building." He recommended a "comprehensive architectural
    and structural review" "to determine the extent of the improvements required
    to attain code compliance."
    A-4994-18T3
    11
    Two days later, defendants informed plaintiffs and the court that they
    had asked "two new, independent structural engineering firms to consider the
    [Kustera] report and provide recommendations." On August 30, defendants
    told the court that "[i]n light of the [Kustera] report, the goal of all concerned
    should be the immediate remediation of [the restaurant].         Defendants are
    dedicated to that result."   Thereafter, defendants retained a new structural
    engineering firm, 6 architects, New Jersey building code specialists, and a fire
    engineering consultant to design and implement code-compliant plans for the
    reconstruction of the restaurant.
    In late October 2017, the court held a status conference to ascertain the
    parties' progress. After hearing from counsel and Kustera, the court ordered
    the parties' experts to meet the following week to discuss a plan for getting the
    premises code-compliant and scheduled a follow-up conference for November
    8, 2017.
    During the November 8 conference, the court questioned Kustera
    whether the restaurant needed to be closed immediately due to safety concerns.
    Kustera responded that there was "a real safety risk[]" as "[n]obody knows
    when there's going to be a significant loading event, an earthquake, a high
    6
    Defendants had to retain a third structural engineer when the second firm
    advised they did not have enough time to devote to the project.
    A-4994-18T3
    12
    wind event, act of . . . nature and for that reason, . . . it's not safe." As a result,
    the court determined it needed to address plaintiffs' application to close the
    restaurant for the duration of the remedial reconstruction.
    D.
    The Chancery court heard testimony over three days in November 2017
    from Kustera, as well as experts from both sides.              In a comprehensive
    December 12, 2017 written opinion, the court noted that all of the experts
    agreed that the building was not compliant with the applicable building code.
    The court found that defendants' original structural engineer applied the wrong
    code when he designed the building and that the "error was compounded when
    the Township of Westfield's Building inspector also applied the wrong code
    and granted a [CO] for the building."
    The court further found it was necessary to grant a preliminary
    injunction.   Because the construction proceeded under the wrong building
    code, the court found there was damage to the joint wall of 115 and 125 Elm
    Street. As a result, the court was "convinced there [was] an immediate risk to
    the general public and the employees of 115 Elm Street." Therefore, there was
    irreparable harm if the building was not closed.
    The court also weighed the hardship which would be incurred by the
    parties. The judge stated that:
    A-4994-18T3
    13
    [t]he hardships the defendant will face will be harm to
    the Harvest Group and [the restaurant's] good name,
    loss of revenue from being shut down and fifty-five
    employees being unemployed during the holiday
    season and into the New Year. Harvest has been on
    notice of the structural issues at least since [p]laintiffs
    began the suit on August 17, 2016. A plan to repair
    the deficiencies has yet to be developed. The hardship
    that [p]laintiff[s] will face include danger to their
    building and the danger to the public at large. Public
    safety is of utmost importance and causes the balance
    of hardships to weigh in favor of [p]laintiff[s].
    Therefore, the court granted plaintiffs' application for a preliminary
    injunction and enjoined defendants from "engaging in any activities,
    occupying, operating any business, or opening to the public in any manner any
    portion of the [p]remises." The order was effective December 15, 2017 and
    prohibited the restaurant from opening without further order from the court.
    In the following weeks, defendants' design professionals met with
    plaintiffs' professionals to review defendants' plans to bring the premises into
    code compliance. The plans, which included the installation of steel columns,
    beams, and supports inside the premises and the construction of a new concrete
    wall adjacent to the shared wall, were approved by plaintiffs' professionals in
    early April 2018. The parties also agreed that the remedial construction would
    be overseen by the Mountainside Construction Department.
    On April 13, 2018, defendants submitted the plans to Mountainside
    officials for review and approval. The plans were approved on April 26 and
    A-4994-18T3
    14
    Mountainside indicated it was prepared to issue construction permits.
    Plaintiffs, however, refused to consent to the issuance of the permits because
    of issues related to handicap access and drainage. Defendants then moved for
    the court's authorization to begin the construction. The motion was granted on
    June 11, 2018.
    On December 3, 2018, the court permitted the restaurant to reopen upon
    the completion of all necessary inspections and the issuance of a CO. More
    than five years had passed since the execution of the lease for the premises.
    During that time, despite long periods of closure, defendants complied with its
    obligation to pay rent, real estate taxes, insurance, and other costs associated
    with the tenancy in addition to spending nearly $3,000,000 in renovation and
    remedial construction costs.
    E.
    The court conducted a second bench trial, in August 2018, to resolve
    plaintiffs' claims of forfeiture of the property, request for increased rent, and
    for attorneys' fees. On October 12, 2018, the court issued a written opinion
    and order.
    In denying plaintiff's application for forfeiture, the court stated "[t]here
    [was] no doubt that the addition, as originally constructed, was not in keeping
    with applicable building codes." However, the court noted that defendants
    A-4994-18T3
    15
    relied upon engineering and architectural professionals for the design and
    construction of the building as well as the Westfield construction official who
    issued a CO. The court refused to "find fault with defendant[s] for fo llowing
    their professionals' advice." The judge noted that defendants "were relying on
    properly credentialed experts[,]" and "had no legal requirement to ignore their
    experts' advice . . . until . . . the court heard evidence from the various experts,
    held a hearing, and determined that the building did not comply with code."
    She found defendants "[could not] be faulted for believing their plans were
    proper since they had been approved by the Building Inspector."
    In denying plaintiffs' claim for forfeiture, the judge reasoned:
    Defendants leased an older building in need of
    substantial improvements.          Defendants invested
    7
    $2,000,000 in improving the building to a point
    where it is one of, if not the nicest, restaurant in
    Westfield, NJ. Defendants added a second floor and
    forty new seats. If [p]laintiffs were to be successful in
    this request for forfeiture it would greatly and unjustly
    enrich [Tarta Luna]. [Tarta Luna] has received
    monthly rent and has not suffered any harm, save
    attorney fees and expert fees.          [Plaintiffs] have
    received the monthly rent. [They] [are] in the same
    position [they] would have been if the forfeiture had
    not occurred. Fed[.] Deposit Ins[.] Corp. v. Rosen[,]
    188 N.J. S[uper]. 230 ([App. Div.]1983).              The
    application for forfeiture is denied.
    7
    An additional $800,000 was spent on repairs but there is no way for the court
    to ascertain the cost had the building been constructed correctly the first time.
    (footnote in original).
    A-4994-18T3
    16
    The court then turned to plaintiffs' request for increased rent. Plaintiffs
    contended they were entitled to additional rent because of the addition of a
    second floor, which increased the original square footage figure used to
    calculate the rent obligation in the lease. The judge rejected plaintiffs' request,
    noting that the lease did not provide for an increase in rent if the square
    footage were to be enlarged, and she would not make a better contract for the
    parties than they had made for themselves. She further reasoned that it was
    not the intent of the parties to increase the rent, stating plaintiffs' requested
    increase would "be patently unfair . . . when defendants have expended
    considerable funds to build the second floor."
    Lastly, the court addressed the issue of attorneys' fees.          Plaintiffs
    contended that the court could award fees under several provisions of the lease
    agreement. The court disagreed, finding there was no contractual basis for the
    award of fees. The judge stated: "The court cannot find any statute, court rule,
    or contract provision that supports the granting of legal and expert fees to
    [plaintiffs]."
    However, given her findings that "the renovations, as originally
    constituted were dangerous to people[,]" "severe damage could have been done
    to the building[,]" and "[t]o bring this action before the court it was necessary
    [for plaintiffs] to incur approximately $1,000,000 in attorneys' fees[,]" the
    A-4994-18T3
    17
    judge concluded that an equitable remedy was warranted.             She ordered
    plaintiffs to submit a certification of services, permitted defendants to respond,
    and scheduled oral argument.
    Plaintiffs submitted certifications from counsel, Pagnotta, Sincox, and
    Carol Greco. They sought attorneys' fees in the amount of $1,052,341.50, and
    disbursements and costs, including expert fees, in the amount of $170,968.17,
    for a total of $1,223,309.67. Defendants, in response, submitted a certification
    from counsel along with an expert certification from Dennis J. Drasco, Esq.
    Drasco represented he was a New Jersey attorney who "specializ[ed] in the
    litigation and trial of complex, commercial, construction . . . cases[.]" He
    submitted a certification in which he opined as to the reasonableness of the
    attorneys' fees request based on his review of plaintiffs' certifications and the
    court's orders.
    After oral argument on the fee application, the judge issued an opinion
    on June 20, 2019, awarding plaintiffs attorneys' fees and costs in the amount of
    $930,710.33. The judge reasoned that the award of attorneys' fees was "based
    on equitable principles as a result of this court's determination that the safety
    of the public had been compromised by the decision to open [the restaurant]."
    She then clarified that the award was limited in scope and did not include fees
    for items unrelated to the renovations.
    A-4994-18T3
    18
    The judge did not consider Drasco's expert certification. Although she
    recognized him as "a well-qualified professional," the judge disregarded his
    certification because its content did not concern "a subject beyond the ken of
    the factfinder[.]"
    The judge then turned to a consideration of the reasonableness of the
    amount of the counsel fee request. She concluded plaintiffs' counsel's hourly
    rates were reasonable, a concession also made by defendants. The court went
    through the billing entries carefully, making deductions where she found the
    time billed was excessive or unnecessary or where there was no explanation of
    the task.
    In further explaining her award and its calculations, the judge described
    her "feel for the case" she had developed during the proceedings. She stated
    that defendants were convinced plaintiffs' claims were simply an attempt to
    extort higher rent and thus did not appropriately weigh their concerns. On the
    other hand, the judge said plaintiffs were "not any better[,]" as they leased
    defendants an old building, knowing "extensive renovations" were required
    and were somewhat obstinate in permitting defendants to perform such work.
    "Against this background," the judge concluded that,
    [p]laintiffs' litigious approach to the case increased
    attorneys' fees in a manner which is not easily shown
    on the timesheets. From the beginning, [p]laintiffs
    argued everything was a great injustice and danger. A
    A-4994-18T3
    19
    good example of this would be their insistence on
    drainage studies where the town did not require them
    and the court ruled were unnecessary.
    The court continued,
    Perhaps the best example is the incident with the "hot
    wall." An employee of [the restaurant] discovered a
    wall was "hot." The Fire Department was called and
    all customers were asked to leave the building. The
    Department of Health and Fire Department allowed
    the restaurant to reopen shortly thereafter. Despite
    Harvest taking all the proper steps, [p]laintiffs
    overreacted by filing an Order to Show Cause. The
    court has not allowed these fees but cites to the event
    as an example of the dynamics of the case.
    The court certainly does not find [d]efendant[s]
    blameless.        They continued to build without
    authorization, thus requiring monitoring by the
    plaintiff.      But in balance, the court believes
    [p]laintiff[s'] actions inflated the legal work required.
    Accordingly, the judge reduced the overall award to plaintiffs by five percent.
    The result was an award to plaintiffs of $930,710.33 in attorneys' and expert
    fees.
    II.
    Defendants appeal from the award of attorneys' fees, calculation of the
    award, and the exclusion of the Drasco expert certification. In a cross-appeal,
    plaintiffs contend the trial court erred in denying their claim for forfeiture and
    in its calculation of the attorneys' fees award.
    A-4994-18T3
    20
    A Chancery judge has broad discretion "to adapt equitable remedies to
    the particular circumstances of a given case."    Marioni v. Roxy Garments
    Delivery Co. Inc., 
    417 N.J. Super. 269
    , 275 (App. Div. 2010) (citations
    omitted); see also Salorio v. Glaser, 
    93 N.J. 447
    , 469 (1983) (noting equitable
    remedies "are distinguished by their flexibility, their unlimited variety," and
    "their adaptability to circumstances"). In reviewing an equitable remedy, we
    consider three specific components. Marioni, 
    417 N.J. Super. at 275
    .
    First, the facts the judge adopts in an equity case are entitled to
    deference "when supported by adequate, substantial[,] and credible evidence."
    Rova Farms Resort, Inc. v. Investors Ins. Co. of Am., 
    65 N.J. 474
    , 484 (1974).
    Second, in drawing conclusions from those facts, the Chancery judge i s
    required to apply accepted legal and equitable principles; no deference is
    afforded in this regard. Manalapan Realty, L.P. v. Twp. Comm. of Twp. of
    Manalapan, 
    140 N.J. 366
    , 378 (1995). And third, we will decline to intervene
    absent an abuse of discretion, or where the judge's conclusions prove
    inconsistent with her own findings of fact. Marioni, 
    417 N.J. Super. at 275-76
    .
    A court abuses its discretion "when a decision is made without a rational
    explanation, inexplicably departed from established policies, or rested on an
    impermissible basis." Pitney Bowes Bank, Inc. v. ABC Caging Fulfillment,
    A-4994-18T3
    21
    
    440 N.J. Super. 378
    , 382 (App. Div. 2015) (citing Flagg v. Essex Cnty.
    Prosecutor, 
    171 N.J. 561
    , 571 (2002)).
    A.
    Here, despite concluding that plaintiffs did not prevail on any of their
    claims, the court awarded them counsel fees and expert expenses. Defendants
    assert the court abused its discretion because there was no basis in law or
    equity to support the award.
    Generally, we will only disturb an award of attorneys' fees upon a clear
    abuse of discretion.    J.E.V. v. K.V., 
    426 N.J. Super. 475
    , 492 (App. Div.
    2012).     Despite the significant discretion a trial court has in awarding
    attorneys' fees, "such determinations are not entitled to any special deference i f
    the judge misconceives the applicable law, or misapplies it to the factual
    complex." Porreca v. City of Millville, 
    419 N.J. Super. 212
    , 224 (App. Div.
    2011) (citations omitted).
    New Jersey is an "American Rule" jurisdiction, reflecting a "strong
    public policy against shifting counsel fees from one party to another." In re
    Estate of Stockdale, 
    196 N.J. 275
    , 307 (2008). The American Rule prohibits
    recovery of attorneys' fees "by the prevailing party against the losing party."
    
    Ibid.
     A few exceptions, not applicable here, are authorized under Rule 4:42-
    9(a).
    A-4994-18T3
    22
    Our Supreme Court has also recognized several "exceptions to the
    American Rule that are not otherwise reflected in the text of Rule 4:42-9" and
    are not allowed pursuant to a statute, court rule, or contract. In re Estate of
    Vayda, 
    184 N.J. 115
    , 120-21 (2005).         This category of common law fee-
    shifting arises out of fiduciary breaches in certain settings, for example the
    attorney-client relationship or attorneys acting as escrow agents. See In re
    Estate of Folcher, 
    224 N.J. 496
    , 507 (2016).
    Here, the Chancery court correctly concluded that no provision in the
    lease agreement authorized attorneys' fees either expressly or impliedly. The
    court properly rejected plaintiffs' reliance on four specific paragraphs of the
    lease for an award. Paragraphs five, six (b), and twenty-two were silent as to
    attorney's fees and it would be error for the court to construe the provisions
    any differently than how they were written. See N. Bergen Rex Transp., Inc.
    v. Trailer Leasing Co., a Div. of Keller Sys. Inc., 
    158 N.J. 561
    , 570 (1999)
    (noting courts will strictly construe a contract provision in light of the general
    policy disfavoring the award of attorneys' fees).      Paragraph fourteen does
    permit the recovery of attorneys' fees, but only in the context of
    indemnification for damages to property or persons caused by defendants or
    their agents. This clause did not apply under the circumstances present here.
    A-4994-18T3
    23
    Therefore, there was no statutory or contractual basis for an award of
    fees. Nor was there a breach of a fiduciary relationship as occurred in Folcher.
    Although the Chancery judge also concluded there was no established
    basis to support a fee award, she nevertheless found that equitable principles
    demanded the remedy, because "the safety of the public had been
    compromised by the decision to open [the restaurant]." The general concept of
    public safety has not previously been recognized as an exception to the policy
    preventing fee-shifting, and although it might support an award under certain
    egregious circumstances, those circumstances were not present here.
    Plaintiffs contend there is precedent for the court's award under Red
    Devil Tools v. Tip Top Brush Co., 
    50 N.J. 563
    , 575 (1967). We disagree. In
    Red Devil, the Chancery court found the defendants had wrongfully
    appropriated the plaintiff's trademark and had infringed upon it, and their
    appropriation and infringement had been "conscious and deliberate, having
    been carried out to take advantage of plaintiff's mark and established
    reputation for the purpose of selling more brushes with greater benefits to
    defendants than would have been possible without the use of plaintiff's mark."
    
    Id. at 566
    .
    The Supreme Court agreed that the plaintiff was entitled to injunctive
    relief.     
    Id. at 572
    .   In addition, the plaintiff sought an accounting of the
    A-4994-18T3
    24
    defendants' profits.   However, because the plaintiff had not demonstrated
    damage to its business or goodwill through the sale of the brushes, the Court
    did not grant the accounting.
    The Court stated that the grant of additional relief beyond an injunction
    was not "automatic for the true judicial goal is a just decree which satisfies 'the
    equities of the case.'" 
    Id. at 573
    . Any additional relief was dependent "on the
    particular circumstances as they appear from the totality of the evidence
    presented." 
    Ibid.
     Because the defendants had engaged in "shenanigans," and
    their conduct was "wrongful," "conscious and deliberate," the Court
    determined a deterrent was warranted. As a result, the plaintiff was awarded
    litigation fees, including a reasonable counsel fee. 
    Id. at 575
    .
    In explaining the grant of relief, the Court stated that it protected "the
    plaintiff for the future[,] [took] care of its actual damage to date, . . . cut into
    any unjust enrichment of the defendants" and served a deterrent purpose. 
    Ibid.
    The Court concluded:
    Here the plaintiff's claim was for equitable relief by
    way of injunction and accounting. Although the trial
    court granted such relief in full, it appears to us that
    the equities would be better fulfilled and the
    administration of justice better served by substituting
    an award of litigation costs for an ill-suited and more
    burdensome accounting. This course furnishes a fair
    measure of compensation in lieu of rather than in
    addition to the plaintiff's claimed right of recovery on
    A-4994-18T3
    25
    its substantive cause of action, and, viewed
    realistically, does not transgress on the safeguards
    contemplated by the court rules.
    [Id. at 576.]
    Therefore, the counsel fee award was substituted as a more applicable measure
    of damages than the accounting originally sought.
    We see no similarity between the circumstances in Red Devil and those
    presented here.    Conspicuously lacking in this matter is evidence of any
    "willful and calculated" misconduct that the Court found existed in Red Devil
    and warranted the deterrence of a fee award. 
    Id. at 574
    . To the contrary, the
    Chancery court here specifically concluded that defendants had not engaged in
    any intentional misconduct. Instead, they had relied on the advice of their
    professional architectural and engineering experts as well as the approval and
    issuance of the requisite permits from the municipality and its construction
    officials.   Defendants had no cause or obligation to ignore their own
    professionals and municipal officials until an independent expert uncovered
    deficiencies in the renovation construction.
    Defendants agreed to the appointment of an independent expert. Within
    two days of receipt of the expert's report, defendants informed plaintiffs and
    the court of its retention of a new structural engineering firm. Defendants also
    replaced its architectural firm and added additional experts to its team,
    A-4994-18T3
    26
    including firewall and building code specialists. Finally, defendants agreed
    that a different town should be responsible for overseeing and approving the
    construction and the issuance of required permits and eventually a CO.
    Moreover, defendants here were not unjustly enriched. To the contrary,
    despite the prolonged closure of the business, defendants complied with their
    contractual obligations and paid plaintiffs the required rent during the five
    years of renovations and construction remediation despite only being open for
    business for one year during that time. Plaintiffs also cannot identify any
    deterrent value an award of fees might have under these circumstances.
    Defendants leased the building from plaintiffs with expectations of opening a
    restaurant. Both parties understood the extensive renovations needed in light
    of the age of the building. Under the triple net lease, defendants agreed to
    shoulder all of the expenses even though at the termination of the lease,
    plaintiffs would remain the owners of the much-improved space.
    Moreover, the facts here did not warrant an alternate remedy as the
    Court found necessary in Red Devil. Plaintiffs were not successful on their
    primary causes of action for termination of the lease and additional rent. The
    Chancery court responded to plaintiffs' claims of construction deficiency by
    closing the restaurant until the construction issues were resolved and the
    building was compliant with the building codes. In addition, if the building
    A-4994-18T3
    27
    inspector had properly inspected the premises (as he certified was done)
    defendants would have been put on notice of defects with their renovations and
    litigation might have been avoided altogether. Finally, as the court noted,
    plaintiffs have greatly benefitted from the renovations resulting in a much -
    improved building.
    Therefore, for the reasons stated, the Chancery court's award of
    attorneys' and expert fees was a mistaken exercise of discretion as it d eparted
    from well-established precedent and was not founded on any statute, court
    rule, or contract provision.    Nor was the award supported by equitable
    principles in the absence of any willful misconduct. We reverse the court's
    order granting counsel and expert fees.
    B.
    In its cross-appeal, plaintiffs contend the Chancery court abused its
    discretion in denying the motion to terminate the lease and to impose a
    forfeiture on defendants. Plaintiffs rely on Dunkin' Donuts of Am., Inc. v.
    Middletown Donut Corp., 
    100 N.J. 166
     (1985), and assert they were deprived
    of a bargained-for remedy under the lease agreement. Because we find the
    court's decision denying forfeiture was supported by the credible evidence in
    the record and did not constitute a misapplication of the relevant law, we
    affirm.
    A-4994-18T3
    28
    As the Supreme Court stated in Dunkin' Donuts, "the settled precedent is
    that in the absence of fraud, accident, or mistake, a court of equity cannot
    change or abrogate the terms of a contract." 
    Id. at 183
    . Moreover, the Court
    "recognize[d] that although ordinarily equity will not divest legal rights, this
    maxim must yield if 'extraordinary circumstances' or 'countervailing equities'
    call for such relief." 
    Id. at 184
    . (quoting Monmouth Lumber Co. v. Indem. Ins.
    Co. of Am., 
    21 N.J. 439
    , 451 (1956)); see also Mandia v. Applegate, 
    310 N.J. Super. 435
    , 449 (App. Div. 1998) (citing 49 Am. Jur. 2d Landlord and Tenant
    § 339 (1995)) (holding court may deny forfeiture to prevent unduly oppressive
    result, unconscionable advantage to landlord, or unconscionable disadvantage
    to tenant).
    As the Chancery court concluded, plaintiffs properly served the notice to
    cure required under paragraph twenty-nine of the lease agreement. And, as
    described above, defendants' renovations did not comply with the applicable
    building codes, causing the independent expert Kustera to opine that the
    premises posed a safety risk. However, the Chancery court also found that
    defendants could not be faulted for relying on their own professionals,
    particularly because the municipality, through its construction official,
    approved defendants' plans and issued the required permits and a CO.
    A-4994-18T3
    29
    The matter before us is readily distinguishable from Dunkin' Donuts. In
    that case, the Court imposed a forfeiture and terminated the defendant's lease
    of two Dunkin' Donuts franchise locations. 
    100 N.J. at 185-86
    . The Court
    noted forfeiture was an extreme remedy but imposed it because there were
    "insufficient countervailing equities" where the defendant "was guilty of
    unconscionable cheating[]" in the form of a "substantial, intentional, and long -
    continued underreporting of gross sales[]" to underpay franchise fees. 
    Id. at 172, 182-86
    . Here, defendants did not intentionally violate the building codes,
    but rather relied upon their professionals and approval from the governing
    authorities.
    Moreover, as the Chancery court noted, imposing a forfeiture on
    defendants would "greatly and unjustly enrich" plaintiffs. Defendants spent
    nearly $3,000,000 to transform the premises into an upscale attractive
    restaurant.    Defendants paid rent, property taxes and all of the expenses
    associated with the lease. A termination of the lease following defendants'
    substantial investment in the premises would result in a windfall for plaintiffs.
    Therefore, the court did not abuse its discretion in its determination not to
    impose a forfeiture.
    A-4994-18T3
    30
    In light of our determination regarding the counsel fee award, we need
    not address the arguments regarding the award calculation or the admiss ibility
    of defendants' expert report.
    We reverse the order granting counsel and expert fees. The cross-appeal
    is affirmed.
    A-4994-18T3
    31