PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE) ( 2020 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2978-18T1
    PATERSON MEDICAL PLAZA,
    LLC,
    Plaintiff-Respondent,
    v.
    LITANA DEVELOPMENT, INC.,
    Defendant-Appellant.
    _____________________________
    Argued telephonically March 25, 20201 –
    Decided April 13, 2020
    Before Judges Fuentes, Mayer and Enright.
    On appeal from the Superior Court of New Jersey, Law
    Division, Passaic County, Docket No. L-4395-16.
    Robert Ethan Bennet argued the cause for appellant
    (Tesser & Cohen, attorneys; Danielle E. Cohen and
    Robert Ethan Bennett, on the briefs).
    1
    This matter was argued telephonically in accordance with the Chief Justice
    Rabner's March 15, 2020 Notice to the Bar.
    Mandelbaum Salsburg PC, attorney for respondent
    (Ryan M. Buehler, on the brief). 2
    PER CURIAM
    Defendant Litana Development, Inc. (Litana) appeals from a February 22,
    2019 order denying its motion to confirm an arbitration award and March 1 and
    March 8, 2019 orders compelling re-arbitration.         We reverse the orders
    compelling re-arbitration and remand the matter to the trial court to confirm the
    arbitration award and to consider the additional relief requested in Litana's
    motion to confirm the award.
    Plaintiff Paterson Medical Plaza, LLC (PMP) contracted with Litana for
    construction of a medical facility. Upon completion of the work, Litana claimed
    PMP failed to pay for all work and services performed pursuant to the parties'
    written contract and signed change orders.
    2
    On January 28, 2020, the day before the originally scheduled argument date,
    counsel for Paterson Medical Plaza, LLC advised that he could not appear
    because his legal services had been terminated by the client. Counsel requested
    an adjournment of the January 29, 2020 argument to allow the client to retain
    new counsel and we adjourned the matter to March 25, 2020. Because Paterson
    Medical Plaza, LLC is a corporation, Rule 1:21-1(c) requires any appearance in
    court be "through an attorney authorized to practice law in this State." Despite
    several inquiries by staff at the Appellate Division Clerk's Office, Paterson
    Medical Plaza, LLC failed to retain new counsel and therefore we consider the
    written arguments in the merits brief filed on behalf of Paterson Medical Plaza,
    LLC.
    A-2978-18T1
    2
    Litana claimed its last day of work on the project was August 9, 2016. A
    few days later, PMP terminated the contract with Litana. On October 24, 2016,
    Litana filed a construction lien claim against PMP's property in the amount of
    $272,050.
    PMP immediately filed an order to show cause and verified complaint
    seeking to discharge Litana's construction lien. In the verified complaint, PMP
    claimed Litana's lien amount was "willfully exaggerated." In addition to the lien
    discharge, PMP sought damages for breach of contract, breach of the implied
    covenant of good faith and fair dealing, lost profits, and unjust enrichment.
    Litana filed an answer and counterclaim. In its counterclaim, Litana requested
    damages based on breach of contract.
    The trial court denied PMP's application to discharge the lien. Thereafter,
    PMP filed a motion to compel arbitration. In a March 13, 2017 order, the judge
    compelled the parties to arbitrate their disputes and retained jurisdiction to
    enforce the arbitrator's award. 3
    Arbitration hearings were held over a five-day period in 2018. PMP's
    claim before the arbitrator focused solely on discharging the construction lien.
    PMP argued the lien amount alleged by Litana was grossly overstated. In
    3
    The trial court stayed the litigation pending the arbitration.
    A-2978-18T1
    3
    arbitration, Litana sought in excess of $1 million in damages, plus interest and
    attorney's fees. Litana arrived at that amount based on the parties' written
    contract, signed change orders, and its alleged additional costs associated with
    the project.
    The arbitrator heard testimony from the parties' witnesses and reviewed
    documents provided in support of their claims. Based on the testimony and
    documents, the arbitrator found Litana's lien claim was not overstated and
    ordered PMP to pay Litana the sum of $552,202.22.
    In his April 17, 2018 single-spaced, seven-page written award, the
    arbitrator determined Litana's work and services under the base contract and
    signed change orders totaled $4,682,314.81. 4 The arbitrator rejected some of
    Litana's claimed $808,202.22 in additional documented expenses and its claimed
    additional work in the amount of $47,620. He concluded there was no writing
    memorializing the $47,620 sum and therefore denied Litana's request for
    payment of that amount. The arbitrator also rejected Litana's claim that it
    allegedly advanced $420,000 to PMP, finding "little persuasive explanation . . .
    4
    This amount represents the original contract amount of $4,051,000, plus a
    December 31, 2013 written change order for $414,314.81, plus an October 6,
    2014 written change order for $175,000, plus a September 18, 2015 written
    change order for $42,000.
    A-2978-18T1
    4
    as to why payments totaling $420,000 were made by Litana to PMP." The
    arbitrator concluded the $420,000 sum represented "the return to PMP of unused
    proceeds of the construction loan." The arbitrator "accept[ed] the testimony and
    proofs presented by Litana with regard to the balance of the additional
    documented expenses it claim[ed]," determining the sum of $388,202.22 was
    sufficiently documented. The arbitrator calculated the total work and services
    provided by Litana to PMP was valued at $5,070,517.03. 5
    The arbitrator denied Litana's request for interest, attorney's fees, and
    costs, finding the parties had a "good faith dispute[]" and Litana lacked
    documentation related to some of the work because the parties had a
    "cooperative and informal relationship."
    At the arbitration, PMP did not claim it was owed any money but argued
    it was entitled to set-off amounts against Litana's claims. The arbitrator rejected
    certain of PMP's set-off claims based on alleged deficiencies and incomplete
    work performed by Litana and explained why he rejected those set-off amounts.
    The arbitrator also denied PMP's claim for lost profits as speculative.
    5
    The arbitrator arrived at this amount by adding the base contract and change
    order work, totaling $4,682,314.81, plus the additional work performed by
    Litana in the amount of $388,202.22.
    A-2978-18T1
    5
    However, the arbitrator awarded PMP the following credits: $80,000 for
    stucco work not completed by Litana; $34,000 for elevator repair work; $4750
    for the elevator room HVAC; and $4300 for installation of the elevator room
    floor. The total amount credited to PMP by the arbitrator was $123,050. The
    arbitrator's credit calculation in favor of PMP far exceeded Litana's suggested
    credit of $15,000 for the work it did not perform.6 The arbitrator determined
    PMP paid Litana a total of $4,395,264.81.
    Deducting the amount paid by PMP, and crediting PMP for defective work
    and work not performed by Litana, the arbitrator concluded Litana was owed
    $552,202.22.7
    Dissatisfied with the award, PMP sought a modification from the
    arbitrator. Based on his review of the post-arbitration submissions, the arbitrator
    denied PMP's request to modify the award because "[t]here [were] no 'clerical,
    typographical, technical, or computational errors in the [a]ward.' I see no reason
    6
    PMP claims the arbitrator's award failed to consider a $15,000 credit.
    However, the arbitrator credited PMP in an amount nearly ten times the credit
    amount Litana argued should be applied for incomplete work.
    7
    The arbitrator's ultimate award reflects his determination that $5,070,517.03
    represented the work and services provided by Litana, minus PMP's payment to
    Litana in the amount of $4,395,264.81, minus the total credit due to PMP in the
    amount of $123,050.
    A-2978-18T1
    6
    to re-determine the merits of this matter even if I had the power to do so." In a
    May 15, 2018 decision, the arbitrator affirmed his prior award.
    On June 26, 2018, Litana filed a motion to confirm the arbitration award
    and for other relief. PMP filed a cross-motion for modification, correction, or
    vacation of the award.
    The motion judge heard argument on the parties' motions in October 2018.
    At the conclusion of the argument, the judge requested the parties provide
    additional information.
    After receiving the parties' supplemental submissions, the judge asked
    counsel to reargue the motions on February 22, 2019. In a decision placed on
    the record on that date, the judge denied Litana's motion to confirm the
    arbitration award. In orders dated March 1 and March 8, 2019, the judge vacated
    the arbitration award and ordered re-arbitration before the same arbitrator.
    The judge explained he read the arbitrator's decision "probably five or six
    times" and stated, "quite frankly, I can't follow it." He found the arbitrator "was
    required to provide a reasoned decision" and did not "give a well-reasoned
    second opinion." The judge indicated the arbitrator needed "to opine with more
    specificity . . . . And while [the arbitrator] put a lot of information in, I don't
    find that it particularly was well reasoned or reasoned at all . . . . "
    A-2978-18T1
    7
    On appeal, Litana argues the judge erred by declining to confirm the
    arbitrator's award, vacating the arbitration award, and ordering re-arbitration.
    "[T]he scope of review of an arbitration award is narrow." Fawzy v.
    Fawzy, 
    199 N.J. 456
    , 470 (2009).               Our Supreme Court has held that
    "[a]rbitration can attain its goal of providing final, speedy and inexpensive
    settlement of disputes only if judicial interference with the process is minimized;
    it is, after all, 'meant to be a substitute for and not a springboard for litigation. '"
    Barcon Assocs., Inc. v. Tri-County Asphalt Corp., 
    86 N.J. 179
    , 187 (1981)
    (quoting Korshalla v. Liberty Mut. Ins. Co., 
    154 N.J. Super. 235
    , 240 (Law Div.
    1977)).    With this goal in mind, "[a]rbitration should spell litigation's
    conclusion, rather than its beginning . . . . " Borough of E. Rutherford v. E.
    Rutherford PBA Local 275, 213 N.J 190, 201 (2013) (quoting N.J. Tpk. Auth.
    v. Local 196, I.F.P.T.E., 
    190 N.J. 283
    , 292 (2007)).
    "The public policy of this State favors arbitration as a means of settling
    disputes that otherwise would be litigated in a court." Badiali v. N.J. Mfrs. Ins.
    Grp., 
    220 N.J. 544
    , 556 (2015). As a result, "courts grant arbitration awards
    considerable deference."      E. Rutherford PBA Local 275, 213 N.J. at 201.
    Because a trial court's decision to affirm or vacate an arbitration award is a
    decision of law, our review is de novo. Minkowitz v. Israeli, 433 N.J. Super.
    A-2978-18T1
    8
    111, 136 (App. Div. 2013) (citing Manger v. Manger, 
    417 N.J. Super. 370
    , 376
    (App. Div. 2010)).
    N.J.S.A. 2A:23B-22 sets forth the standard for confirming an arbitration
    award. The statute provides:
    After a party to an arbitration proceeding receives
    notice of an award, the party may file a summary action
    with the court for an order confirming the award, at
    which time the court shall issue a confirming order
    unless the award is modified or corrected pursuant to
    section 20 or 24 of this act or is vacated pursuant to
    section 23 of this act.
    [N.J.S.A. 2A:23B-22 (emphasis added).]
    Arbitration awards may be vacated, modified, or corrected by a court if
    (1) "procured by corruption, fraud, or other undue means"; (2) the arbitrator was
    partial or corrupt, or committed misconduct thereby prejudicing the parties'
    rights; (3) the arbitrator refused to postpone the hearing when there was
    sufficient cause to do so, failed to consider material evidence, or otherwise
    inappropriately conducted the hearing so as to prejudice the rights of the parties;
    (4) the arbitrator exceeded his or her powers; (5) there was no agreement to
    arbitrate; or (6) the arbitration was conducted without sufficient notice,
    substantially prejudicing the rights of the parties. See N.J.S.A. 2A:23B-23(a).
    A-2978-18T1
    9
    A court may also modify or correct an award if (1) there was an evident
    mathematical mistake; (2) the arbitrator made an award on a claim not submitted
    to arbitration; or (3) "the award is imperfect in a matter of form not affecting the
    merits of the decision . . . ." N.J.S.A. 2A:23B-24(a).
    A court may only confirm, vacate, modify, or correct arbitration awards
    on the grounds provided in the statute. See N.J.S.A. 2A:23B-20 to -24. The
    statute "directs a court to correct errors; it does not provide for remand to the
    arbitrator." Tretina Printing, Inc. v. Fitzpatrick & Assocs., Inc., 
    135 N.J. 349
    ,
    360 (1994). As our Supreme Court stated in Tretina:
    the Legislature intended that courts correct mistakes
    that are obvious and simple – errors that can be fixed
    without a remand and without the services of an
    experienced arbitrator . . . . [I]n the absence of a
    statutory provision or an authorization in the arbitration
    agreement, a court that is asked to vacate, modify, or
    confirm an award usually has no power, except by the
    consent of the parties, to recommit the matter to the
    arbitrator.
    [Id. at 360-61.]
    Here, PMP's request to discharge the construction lien and Litana's claim
    for monies owed by PMP were decided by the arbitrator. The judge's inability
    to follow the arbitrator's decision is not one of the enumerated statutory grounds
    to vacate, modify, or correct an arbitration award.
    A-2978-18T1
    10
    The judge cited no statutory basis for vacating the arbitration award. The
    judge's failure to understand how the arbitrator arrived at the award is not
    sufficient ground to vacate the award. The arbitrator considered the evidence
    and testimony presented, and then articulated his findings in support of the
    award. Having reviewed the record, we discern no basis to vacate the arbitration
    award or compel re-arbitration.
    Therefore, we reverse the judge's orders denying Litana's motion to
    confirm the arbitration award and compelling re-arbitration. We remand the
    matter to the trial court to enter an order reinstating and confirming the
    arbitration award.     Because the motion judge did not consider Litana's
    application to enforce the construction lien or award attorney's fees, interest, and
    costs, the judge shall consider these issues on remand. We take no position on
    the disposition of these issues.
    Reversed and remanded. We do not retain jurisdiction.
    A-2978-18T1
    11