EXCEL ENVIRONMENTAL RESOURCES, INC. VS. PIOLI PROPERTIES, LLC (L-0445-17, MIDDLESEX COUNTY AND STATEWIDE) ( 2020 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2314-18T1
    EXCEL ENVIRONMENTAL
    RESOURCES, INC.,
    Plaintiff-Respondent,
    v.
    PIOLI PROPERTIES, LLC,
    Defendant-Appellant.
    ____________________________
    Argued January 22, 2020 – Decided February 21, 2020
    Before Judges Yannotti, Hoffman and Firko.
    On appeal from the Superior Court of New Jersey, Law
    Division, Middlesex County, Docket No. L-0445-17.
    Matthew Joonho Jeon argued the cause for appellant
    (Matthew Jeon, PC, attorneys; Matthew Joonho Jeon,
    on the briefs).
    Ronald E. Steinvurzel argued the cause for respondent
    (Steinvurzel & Levy Law Group, attorneys; Ronald E.
    Steinvurzel, on the brief).
    PER CURIAM
    Following a bench trial, defendant Pioli Properties (Pioli) appeals from the
    Law Division judgment entered in favor of plaintiff Excel Environmental Resources
    for services performed under two vapor mitigation contracts. We affirm.
    I.
    We derive the following facts from the trial record. Bristol Meyers Squib
    (BMS) allegedly caused a release of chlorinated solvents, which dissolved into
    ground water underneath Pioli's property located on Georges Road in New
    Brunswick (the property). According to an investigation report completed for BMS,
    the property required vapor mitigation.
    As a result, on August 1, 2014, plaintiff and Pioli entered into a written
    contract (Contract # 1), whereby plaintiff agreed to design and install a vapor
    mitigation system for the property at a cost of $78,500.00. Plaintiff invoiced Pioli
    regularly from December 31, 2014 until June 30, 2016, billing Pioli a total of
    $79,940.47. Pioli did not pay the amount billed, claiming plaintiff had agreed to
    seek payment from BMS.
    Under the terms and conditions of Contract # 1, plaintiff could "bill for the
    actual hours expended and costs incurred. . . ." and agreed to "not exceed this cost
    estimate without advance Authorization/Extension of Services or other acceptable
    documentation." The contract also stated, "The work outlined in this proposal will
    A-2314-18T1
    2
    be conducted in accordance with [plaintiff's] Standard Terms and Conditions and
    labor rates provided as Attachment A." Attachment A stated, in pertinent part:
    This agreement between [plaintiff] and the client
    identified herein, consisting of a proposal and Standard
    Terms and Conditions, constitutes the entire
    understanding between the parties . . . [Plaintiff] hereby
    objects to any terms contained in any prior or subsequent
    purchase orders, work orders, invoices, acknowledgment
    forms, requests for proposals or other documents received
    from the [c]lient that would otherwise have the effect of
    modifying or abrogating these Standard Terms and
    Conditions in whole or in part.
    In addition, Attachment A included a provision regarding changes to the
    contract:
    [Plaintiff] shall be entitled to additional compensation for
    work in the event that [plaintiff] experiences any increases
    in costs due to changes in the scope of work defined in
    [plaintiff's] original proposal, or for additional work
    requested by client, or changes in the manner or method of
    performance of work, or due to changes in schedule or
    circumstances not solely caused by [plaintiff]. [Plaintiff]
    shall be compensated for all such additional work either
    (1) as previously agreed in writing by the parties; or (2) on
    a time and materials basis in accordance with [plaintiff's]
    then current standard commercial rates.
    Attachment A also contained an estimated costs and schedule
    clause:
    Costs and schedule estimates are based on [plaintiff's] best
    judgment of the requirements known at the time of the
    proposal and can be influenced favorably or adversely by
    A-2314-18T1
    3
    [c]lient's needs and other circumstances. [Plaintiff] will
    endeavor to perform the [s]ervices and accomplish the
    objectives within the estimated costs and schedule, but in
    no event shall [plaintiff's] estimate be interpreted as a not-
    to-exceed or fixed price. . . . [Plaintiff] shall be entitled to
    a change order for additional compensation or additional
    time to perform its work, in the event that work outside the
    [s]ervices is requested or required to be performed by
    [plaintiff], or in the event that the assumptions underlying
    [plaintiff's] proposal prove to be different from the facts
    actually encountered by [plaintiff] during the performance
    of the [s]ervices.
    On June 5, 2015, the parties entered into a second contract (Contract # 2),
    whereby plaintiff agreed to provide certain remedial investigation services on the
    property at a cost of $20,955. Contract # 2 stated "it is . . . an extension to [Contract
    # 1]." On January 19, 2016 and February 26, 2016, Pioli made two payments totaling
    $15,784.04 for work performed pursuant to Contract # 2.
    On March 1, 2016, plaintiff agreed to perform additional services related to
    the remedial investigation work under Contract # 2, at an estimated cost of
    $27,383.00. On March 11, 2016, plaintiff agreed to perform certain supplemental
    services related to the remedial investigation work in Contract # 2, at an estimated
    cost of $5,206.25. Plaintiff performed all required services and billed Pioli
    $60,230.70.
    On November 30, 2016, plaintiff placed a $124,387.13 construction lien
    on defendant's property, after Pioli failed to make any payments regarding
    A-2314-18T1
    4
    Contract # 1 or the remaining payments owed under Contract # 2. On January 20,
    2017, plaintiff filed a complaint seeking a determination that it acquired a "good
    and valid" construction lien on defendant's property, the amount of its lien, and
    the entry of a judgment against Pioli for all amounts due and owing, plus
    interest, costs, and attorney's fees.       Additionally, plaintiff's complaint also
    asserted a claim of unjust enrichment.
    Pioli filed an answer and counterclaim, alleging plaintiff breached its
    contracts and "started charging inflated invoices and changed its initial
    representation stating that it requires additional work and expenses [and] . . . further
    proceeded with the work that exceeds the initial cost estimate without acquiring [its]
    authorization in advance." Pioli further asserted plaintiff failed to request advance
    authorization before completing additional work under Contract # 1, in accordance
    with the contract.
    Regarding Contract # 2, Pioli asserted plaintiff did not produce any report,
    which led Pioli to hire JCS Environmental Consulting Inc. (JSC) to finish plaintiff's
    work. Pioli sought $27,750 as reimbursement for payments it made to complete
    plaintiff's work. Pioli's counterclaim further alleged plaintiff breached the "implied
    covenant of good faith and fair dealing."
    A-2314-18T1
    5
    On August 7, 2018, the matter proceeded to a bench trial. Eric Mertz,
    plaintiff's vice president and director of remediation services, testified first,
    recounting that he met with multiple Pioli principals prior to entering into Contract
    # 1. Mertz stated he did not advise any Pioli principal that BMS would pay
    plaintiff for the work on the property. He confirmed that, prior to the lawsuit,
    Pioli never claimed plaintiff did not finish a task or performed its work
    negligently or deficiently.
    According to Mertz, he believed the contracts required him to obtain
    approval from Pioli to exceed the total budget but not to exceed individual task
    estimates, explaining it was general practice in the industry to shift the invoice
    costs for one task to another in order to keep the overall cost within budget. He
    stated, "The individual tasks are provided for accounting and budgetary
    purposes. Based on our knowledge at the beginning of the project, as the client
    requests more work in one area and requests less work in another area this results
    in exceeding budgets within tasks. . . ."
    Mi Y. Linn, a Pioli employee, testified that, during contract negotiations,
    she was under the impression BMS would pay all charges incurred on Contract
    # 1. She confirmed Contract # 2 had nothing to do with BMS.
    A-2314-18T1
    6
    The trial judge found plaintiff and Pioli entered into a valid contract, which
    included the extensions of the initial scope of work. She found Mertz's testimony
    credible and noted the testimony from Pioli's principals conceded that the work
    reflected in plaintiff's billing related to the scope of the work in Contract # 1.
    The judge found the terms of the contracts, including Attachment A, clear and
    unambiguous and spoke for themselves. Based on this finding,
    [The] [c]ourt shall not consider any antecedent
    discussions, negotiations, or [parol] evidence to vary the
    terms of the contract as written and agreed upon. In this
    regard it is clear and undisputed that [Contract # 1]
    contains an integration provision within the standard terms
    and conditions in the first sentence of the first paragraph
    entitled agreement.
    The judge found it undisputed that Contracts # 1 and # 2 did not contain "any
    language that reflected BMS was obligated to pay [plaintiff] or that [plaintiff] would
    only be paid upon Pioli being paid by BMS." Further, the judge noted Pioli failed
    to present evidence that it sent BMS any of the bills it received from plaintiff nor did
    it dispute any invoices until plaintiff filed suit.
    The judge awarded plaintiff the full amount of Contract # 1 totaling
    $78,500.00. After deducting Pioli's two payments toward Contract # 2, the judge
    found the remaining balance on Contract # 2 and its two extensions equaled
    A-2314-18T1
    7
    $37,760.21. Therefore, the total amount owed on Contracts # 1 and # 2 totaled
    $116,261.21.
    Additionally, the judge awarded plaintiff attorney's fees and contractual
    interest of eighteen percent for any unpaid balance and attorney's fees and costs
    relating to collection efforts. The contractual interest amounted to $71,276.64 and
    the attorney's fees amounted to $66,647.02. The judge entered an order for judgment
    in favor of plaintiff in the amount of $254,183.87.
    The judge also found in favor of plaintiff on its quantum merit claim and ruled
    Pioli failed to refute any of the evidence plaintiff submitted. Specifically, the judge
    awarded plaintiff $8,126.92, which represented all of the work performed in excess
    of the face amounts of Contracts # 1 and # 2, plus prejudgment interest of $75.58,
    for a total judgment of $8,202.50.1 The judge explained,
    [E]ven though [plaintiff] did not obtain written
    authorization pursuant to the subject contract terms, [t]his
    [c]ourt finds that Pioli received all the work performed by
    [plaintiff]. That Pioli certainly received the benefit from
    [plaintiff's] work. That [plaintiff] clearly expected
    payment for the work it performed, and that Pioli's failure
    to pay [plaintiff] for all work performed beyond its
    contractual right enriched Pioli.
    1
    On Contract # 1, plaintiff's final bill exceeded the estimated cost by $1,440.47.
    On Contract # 2 and the extensions thereto, plaintiff's final bill exceeded the
    estimated cost by $6,686.45.
    A-2314-18T1
    8
    The judge granted the foreclosure of plaintiff's construction lien after finding
    Pioli breached both contracts. The judge limited the lien to the outstanding balances
    from the breach of contract claim – $116,261.21, plus any statutory interest and tax
    costs, which equaled $71,276.64, for a total lien of $187,536.85.
    The judge rejected Pioli's breach of contract counterclaim and dismissed it
    with prejudice. The judge found Pioli failed to meet its burden of establishing
    plaintiff performed incomplete or defective work. Additionally, the judge noted
    Pioli presented no evidence that it rejected any of plaintiff's invoices or objected to
    plaintiff's work as incomplete or defective.
    The judge also dismissed Pioli's good faith and fair dealing claim with
    prejudice, finding Pioli failed to prove plaintiff acted with any bad motive or
    intention in the performance of its contracts or provided any evidence plaintiff's
    work was "unwarranted, defective, . . . or incomplete." The judge reasoned plaintiff's
    proposed estimates were based on the circumstances known at the time they were
    given, and plaintiff performed its work in good faith. Additionally, the judge found
    that plaintiff properly adjusted the actual work performed and billed accordingly.
    II.
    "'Final determinations made by the trial court sitting in a non-jury case are
    subject to a limited and well-established scope of review.'"           D'Agostino v.
    A-2314-18T1
    9
    Maldonado, 
    216 N.J. 168
    , 182 (2013) (citation omitted). Appellate courts "give
    deference to the trial court that heard the witnesses, sifted the competing evidence,
    and made reasoned conclusions." Allstate Ins. Co. v. Northfield Med. Ctr., PC, 
    228 N.J. 596
    , 619 (2017) (citation omitted).
    "Deference is especially appropriate 'when the evidence is largely testimonial
    and involves questions of credibility.'" Sipko v. Koger, Inc., 
    214 N.J. 364
    , 376
    (2013) (citations omitted). The trial judge "has a better perspective than a reviewing
    court in evaluating the veracity of witnesses," and has "a 'feel' for the case that the
    reviewing court cannot enjoy." Twp. of W. Windsor v. Nierenberg, 
    150 N.J. 111
    ,
    132-33 (1997) (citation omitted).
    "[A]ppellate courts should 'not disturb the factual findings and legal
    conclusions of the trial judge' unless convinced that those findings and conclusions
    were 'so manifestly unsupported by or inconsistent with the competent, relevant and
    reasonably credible evidence as to offend the interests of justice.'" 
    Allstate, 228 N.J. at 619
    (quoting Rova Farms Resort, Inc. v. Investors Ins. Co. of Am., 
    65 N.J. 474
    ,
    484 (1974)).
    Pioli argues the trial judge failed to find "whether the parties ha[d] a meeting
    of minds on who will eventually pay for the services rendered by [plaintiff]" and
    only relied on the standard terms and conditions, which do not indicate who pays the
    A-2314-18T1
    10
    estimated costs. Specifically, Pioli claims Mertz told Pioli prior to the signing of the
    contract plaintiff "would forbear from seeking payment from Pioli for [Contract # 1]
    and that [plaintiff] would have BMS eventually pay for the work rendered by
    [them]."
    In reviewing disputed contract terms, we apply well-established guiding
    principles. A court interpreting a contract seeks "to ascertain the 'intention of the
    parties to the contract as revealed by the language used, taken as an entirety . . . , the
    situation of the parties, the attendant circumstances, and the objects the parties were
    striving to attain.'" Borough of Princeton v. Bd. of Chosen Freeholders of Mercer,
    
    333 N.J. Super. 310
    , 325 (App. Div. 2000) (alteration in original) (quoting Cruz-
    Mendez v. ISU/Ins. Servs., 
    156 N.J. 556
    , 570-71 (1999)).
    We "must consider contractual language in the context of the circumstances
    at the time of drafting and . . . apply a rational meaning in keeping with the expressed
    general purpose. [I]f the contract into which the parties have entered is clear, then
    it must be enforced as written." Serico v. Rothberg, 
    234 N.J. 168
    , 178 (2018)
    (alterations in original) (quoting In re Cty. of Atlantic, 
    230 N.J. 237
    , 254-55 (2017)).
    "Contracts should be read 'as a whole in a fair and common sense manner.'"
    Manahawkin Convalescent v. O'Neill, 
    217 N.J. 99
    , 118 (2014) (quoting Hardy ex
    rel. Dowdell v. Abdul-Matin, 
    198 N.J. 95
    , 103 (2009)). Courts generally give
    A-2314-18T1
    11
    contractual terms their plain and ordinary meaning. Schor v. FMS Fin. Corp., 
    357 N.J. Super. 185
    , 191 (App. Div. 2002). "A party that uses unambiguous terms in a
    contract cannot be relieved from the language simply because it had a secret,
    unexpressed intent that the language should have an interpretation contrary to the
    words' plain meaning." 
    Ibid. "Where the terms
    of an agreement are clear, [courts] ordinarily will not make
    a better contract for the parties than they have voluntarily made for themselves, nor
    alter their contract for the benefit or detriment of either, particularly in a commercial,
    arms-length setting." Carroll v. United Airlines, Inc., 
    325 N.J. Super. 353
    , 358-59
    (App. Div. 1999). In determining the parties' intent, "[t]he document . . . must be
    read as a whole, without artificial emphasis on one section, with a consequent
    disregard for others." Borough of 
    Princeton, 333 N.J. Super. at 325
    . "A basic
    principle of contract interpretation is to read the document as a whole in a fair and
    common sense manner." Porreca v. City of Millville, 
    419 N.J. Super. 212
    , 233 (App.
    Div. 2011) (quoting 
    Hardy, 198 N.J. at 103
    ).
    The trial judge found that the contractual language spoke for itself and the
    language in the contract – including Attachment A – was "clear and unambiguous."
    The judge found it was undisputed that no language in the contract pointed to BMS
    paying plaintiff for services rendered to Piloli. Plaintiff and Pioli are the only parties
    A-2314-18T1
    12
    stated in the first contract. In plain language, Contract # 1 incorporated Attachment
    A. Attachment A stated that it, along with Contract # 1, constituted the entire
    contract.
    We agree with the trial judge that the contract is clear and unambiguous.
    Contract # 1 concerns a service contract between plaintiff and Pioli. The only fair
    and reasonable interpretation of this contract is that Pioli would pay plaintiff for the
    services rendered to Pioli to address a contamination of Pioli's property.
    
    Manahawkin, 217 N.J. at 118
    . We must defer to the judge's findings because she
    reasonably based her decision on competent evidence, including the parties' contract
    and Mertz's credible testimony. 
    Allstate, 228 N.J. at 619
    .
    Pioli next argues the trial court erred in applying the parol evidence rule in
    regards to the incorporation clause set forth in the standard terms and conditions
    included in Attachment A. Pioli asserts the judge should have admitted extrinsic
    evidence, arguing it does not alter the meaning of the terms of the contract because
    the contract is silent regarding who pays plaintiff.
    Because the trial judge found Contract # 1 clear and unambiguous, she
    correctly applied the parol evidence rule. See Conway v. 287 Corporate Ctr.
    Assocs., 
    187 N.J. 259
    , 268 (2006) (holding the parol evidence rule prohibits the
    introduction of evidence that tends to alter an integrated written document).
    A-2314-18T1
    13
    Contract # 1 contains a clear merger and integration clause stating it is a final
    integrated document that includes Attachment A. Thus, the judge correctly ruled
    Pioli could not introduce extrinsic evidence regarding discussions that preceded the
    signing of Contract # 1 to try to prove its claim that plaintiff agreed BMS, not Pioli,
    would pay plaintiff for the work it performed on the property.
    Moreover, Pioli did not present any documentation that BMS acknowledged
    an obligation to pay plaintiff for its work. Thus, without any relevant admissible
    evidence referencing the parties' contracts, the record is devoid of any evidence the
    contracts did not represent the parties' final expression of their agreements. See
    Chance v. McCann, 
    405 N.J. Super. 457
    , 564 n.6 (App. Div. 2009) (holding a writing
    that reasonably appears to be a complete agreement is taken to be an integrated
    agreement unless it is established by other evidence that the writing did not
    constitute a final expression). Contract # 1 identifies Pioli as the "client" in the
    contract and outlines a procedure for payment. Pioli's argument that the parties'
    contracts do not constitute integrated written agreements clearly lacks substantive
    merit.
    III.
    Pioli further argues it proved by a preponderance of the evidence plaintiff
    acted "with bad motives or intentions or engaged in deception or evasion in the
    A-2314-18T1
    14
    performance of contracts and by such conduct denied Pioli" the benefit of its bargain.
    In addition, Pioli claims it proved plaintiff intentionally proceeded with specific
    tasks beyond the cost estimate without its authorization and overcharged on other
    tasks.
    "Every contract in New Jersey contains an implied covenant of good faith and
    fair dealing." R.J. Gaydos Ins. Agency, Inc. v. Nat'l Consumer Ins. Co., 
    168 N.J. 255
    , 276 (2001). "Proof of 'bad motive or intention' is vital to an action for breach
    of the covenant [of good faith and fair dealing]." 
    Id. at 225.
    (quoting Wilson v.
    Amerada Hess Corp., 
    168 N.J. 236
    , 251 (2001). "The party claiming a breach of the
    covenant of good faith and fair dealing must provide evidence sufficient to support
    a conclusion that the party alleged to have acted in bad faith had engaged in some
    conduct that denied the benefit of the bargain originally intended by the parties."
    
    Ibid. (internal quotations omitted).
    In support of its claim that plaintiff acted in bad faith, Pioli cites to Brunswick
    Hills Racquet Club, Inc. v. Route 18 Shopping Center Assocs., 
    182 N.J. 210
    , 230-
    231 (2005). In that case, a commercial tenant was lulled into a false sense of security
    that it had properly exercised an option for a ninety-nine-year lease nineteen months
    before the end of the lease term. 
    Id. at 216-19.
    The landlord failed to notify the
    tenant that the exercise of the option required payment of $150,000 and did not
    A-2314-18T1
    15
    respond to direct inquiries over many months. 
    Ibid. The landlord's conduct
    resulted
    in a "windfall increase" in the rental amount at the end of the lease term at the tenant's
    literal expense. 
    Id. at 231.
    The landlord achieved unjust enrichment by "lull[ing]
    plaintiff" through "a series of evasions and delays." 
    Ibid. In contrast to
    Brunswick Hills, plaintiff here repeatedly sent Pioli invoices
    reflecting the work it performed. Pioli never responded to the invoices plaintiff
    submitted and yet allowed plaintiff to continue working on its property. The trial
    judge found Pioli presented no evidence plaintiff's work was unwarranted or
    defective. Importantly, the judge found Mertz credible, accepting his explanation
    that obtaining approval for every task was not common practice. The judge further
    found plaintiff acted in good faith in submitting its invoices. Accordingly, the judge
    did not err in rejecting Pioli's claim that plaintiff breached the covenant of good faith
    and fair dealing. The judge came to a reasonable conclusion based on Mertz's
    credible testimony. The record simply lacks any credible evidence supporting the
    claim of a bad motive or intention on plaintiff's part.
    IV.
    Under the Construction Lien Law, a lien fund exists if a property owner has
    paid the general contractor less than the value of the work completed. N.J.S.A.
    2A:44A-9(a). A lien fund is limited to "the earned amount of the contract between
    A-2314-18T1
    16
    the owner and contractor minus any payments made prior to service of a copy of the
    lien claim." N.J.S.A. 2A:44A-9(b)(1). "[N]o lien fund exists, if, at the time of
    service of a copy of the lien claim, the owner . . . has fully paid the contractor for the
    work performed . . . ." N.J.S.A. 2A:44A-9(d).
    The primary purpose of the Construction Lien Law is to secure payment to
    subcontractors and others who provide work, services, or materials pursuant to a
    written contract. See NRG REMA, LLC v. Creative Envtl. Sols. Corp., 454 N.J.
    Super. 578, 587 (App. Div. 2018), certifs. denied, 
    234 N.J. 577
    , and 
    235 N.J. 111
    .
    Having found Pioli breached its contract, we agree with the trial judge that
    plaintiff was entitled to place a lien for its services rendered. See N.J.S.A. 2A:44A-
    9(b)(1). Additionally, Pioli concedes it "waived its objection on the timeliness of
    filing and service of the lien" but argues the lien has no merit because BMS was
    responsible for paying plaintiff. As previously noted, this claim finds no support in
    the record. We therefore conclude the judge correctly ruled in plaintiff's favor,
    entering a lien for the outstanding balance of $116,260.21, plus interest of
    $71,276.64 as provided in the parties' contract, for a total of $187,536.85.
    V.
    Quantum meruit is a form of quasi-contractual recovery that "rests on the
    equitable principle that a person shall not be allowed to enrich himself unjustly at
    A-2314-18T1
    17
    the expense of another." Starkey v. Estate of Nicolaysen, 
    172 N.J. 60
    , 68 (2002)
    (quoting Weichert Co. Realtors v. Ryan, 
    128 N.J. 427
    , 437 (1992)). To recover
    under a theory of quantum meruit, a party must establish: "(1) the performance of
    services in good faith, (2) the acceptance of the services by the person to whom they
    are rendered, (3) an expectation of compensation therefor, and (4) the reasonable
    value of the services." 
    Ibid. (quoting Longo v.
    Shore & Reich, Ltd., 
    25 F.3d 94
    , 98
    (2d Cir. 1994)). Courts may not impose additional contractual obligations under
    quasi-contract theories "where there is a valid unrescinded contract that governs their
    rights." Shalita v. Twp. of Washington, 
    270 N.J. Super. 84
    , 90 (App. Div. 1994).
    Unjust enrichment requires a party to "show both that [the other party]
    received a benefit and that retention of that benefit without payment would be
    unjust." VRG Corp. v. GKN Realty Corp., 
    135 N.J. 539
    , 554 (1994) (quoting
    Assocs. Commercial Corp. v. Wallia, 
    211 N.J. Super. 231
    , 243 (App. Div. 1986)).
    The party seeking payment under an unjust enrichment theory must also show it
    "expected remuneration from the defendant at the time it performed or conferred a
    benefit on defendant and that the failure of remuneration enriched defendant beyond
    its contractual rights." 
    Ibid. (quoting Wallia, 211
    N.J. Super. at 244).
    The trial judge initially determined plaintiff's billing on Contracts # 1 and # 2
    exceeded the estimated figures for both contracts, $1,440.47 for Contract # 1 and
    A-2314-18T1
    18
    $6,686.45 for Contracts # 2; however, the judge noted that these stated amounts were
    just that – estimates.
    In ruling on plaintiff's quantum meruit claim, the judge analyzed the relevant
    factors and came to a reasonable conclusion. The judge found no evidence plaintiff
    improperly manipulated the estimated costs; rather, she found plaintiff performed
    additional services at Pioli's request, the amounts stated in the contracts represented
    estimates, and Pioli did not object to the invoices rendered until plaintiff filed the
    current lawsuit. The record supports the judge's decision to award plaintiff
    $8,126.92 for work performed in addition to the work required by the contracts.
    The judge properly applied the quantum meruit doctrine. Allowing Pioli to
    retain the benefit of plaintiff's work, but not pay for it, would constitute an
    inequitable result. We discern no basis to disturb the trial judge's ruling on this
    issue.
    Any arguments not specifically addressed in this opinion lack sufficient merit
    to warrant discussion in a written opinion. R. 2:11-3(e)(1)(E)
    Affirmed.
    A-2314-18T1
    19