PETRIC & ASSOCIATES, INC. VS. CCA CIVIL, INC. (L-1596-16, HUDSON COUNTY AND STATEWIDE) ( 2020 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-3571-17T2
    PETRIC & ASSOCIATES, INC.,
    Plaintiff-Respondent,
    v.
    CCA CIVIL, INC.,
    Defendant-Appellant.
    ___________________________
    Argued December 9, 2019 – Decided June 8, 2020
    Before Judges Sumners, Geiger and Natali.
    On appeal from the Superior Court of New Jersey,
    Law Division, Hudson County, Docket No. L-1596-
    16.
    Lawrence S. Lustberg argued the cause for appellant
    (Gibbons PC, and Peckar & Abramson, PC, attorneys;
    Lawrence S. Lustberg, Jennifer Ann Hradil, Jason R.
    Halpin, Gerard J. Onorata, and Patrick Thomas
    Murray, on the briefs).
    Eliza D. Stahl argued the cause for respondent (The
    Law Office of Eliza D. Stahl PC, attorneys; Eliza D.
    Stahl, on the brief).
    PER CURIAM
    Defendant CCA Civil, Inc., appeals from a jury verdict awarding
    plaintiff Petric & Associates $1,850,000 in damages, comprised of:             1)
    $300,000 for fraud; 2) $800,000 for breach of contract; 3) $250,000 for
    violation of the Prompt Payment Act (PPA), N.J.S.A. 2A:30A-1 to -2; and 4)
    $500,000 in punitive damages. Defendant also appeals from a series of related
    pre- and post-trial motion orders and a separate award of $260,911.36 in
    attorney's fees.
    The jury considered a wealth of evidence that defendant fraudulently
    induced plaintiff to enter into a contract to install temporary shielding and
    work platforms on the Pulaski Skyway in Jersey City, Kearny, and Newark
    without informing plaintiff of the existence of high voltage Public Service
    Electric and Gas Company (PSE&G) wiring that not only would have altered
    plaintiff's decision to enter into the contract on the agreed terms, but also
    placed plaintiff's employees at significant risk of harm. The trial proofs also
    support the jury's determination that defendant breached the contract and acted
    with "actual malice" or "a wanton and willful disregard," see N.J.S.A. 2A:15-
    5.12, warranting the compensatory and punitive damages awards. However,
    A-3571-17T2
    2
    the trial proofs were insufficient for the jury to conclude that defendant
    violated the PPA.
    We accordingly affirm the court's December 15, 2017 order denying
    summary judgment to defendant, the jury's January 25, 2018 verdict finding
    defendant liable for fraudulent inducement and breach of contract, its attendant
    compensatory and punitive damages awards, and the trial court's March 16,
    2018 order denying defendant's motion to set aside the verdict or for a new
    trial.    We reverse, however, the jury's verdict concluding that defendant
    violated the PPA. Based on our reversal of that count, we vacate and remand
    the court's March 29, 2018 order granting attorneys' fees to plaintiff, including
    its decision to grant a ten percent fee enhancement.
    On appeal, defendant raises the following points for our consideration:
    POINT I
    THE TRIAL COURT ERRED BY FAILING TO
    REJECT PETRIC'S FRAUDULENT INDUCEMENT
    CLAIM AS A MATTER OF LAW.
    A.   The Trial Court Erred in Denying CCA Civil's
    Motion for Summary Judgment as to Petric's Fraud
    Claim.
    B.    The Trial Court erred in Denying CCA Civil's
    Motions for Judgment at Trial Because Petric Did Not
    Present Clear and Convincing Evidence of Fraud.
    A-3571-17T2
    3
    POINT II
    THE TRIAL COURT ERRED BY FAILING TO
    REJECT PETRIC'S BREACH OF CONTRACT
    CLAIM AS A MATTER OF LAW.
    A.   The Trial Court erred in Denying CCA Civil's
    Motion for Summary Judgment.
    B.    Because Petric Failed to Show at Trial that CCA
    Civil Did Anything Other Than Fully Comply With its
    Obligations Under the Subcontract, the Trial Court
    Erred by Sending the Breach of Contract Claim to the
    Jury.
    POINT III
    BECAUSE CCA CIVIL WAS WITHIN ITS RIGHTS
    UNDER THE SUBCONTRACT TO WITHHOLD
    PAYMENT FROM PETRIC, THE TRIAL COURT
    ERRED IN DENYING SUMMARY JUDGMENT AS
    TO PETRIC'S PROMPT PAYMENT ACT CLAIM.
    POINT IV
    THE JURY AWARDED DUPLICATIVE DAMAGES
    FOR PETRIC'S FRAUD AND CONTRACT
    CLAIMS, AND THE DAMAGE AWARD MUST BE
    REDUCED.
    A.   Petric's Contract Damages Can Not Exceed
    $382,373.87.
    B.     Petric's Vague Reference to Lost Profits Cannot
    Justify the Damages Award Because Petric Failed to
    Establish Lost Profits with Reasonable Certainty.
    A-3571-17T2
    4
    POINT V
    BECAUSE PETRIC OFFERED NO EVIDENCE
    THAT CCA CIVIL ACTED WITH "EVIL MOTIVE,"
    THE TRIAL COURT ERRED BY REFUSING TO
    ELIMINATE THE PUNITIVE DAMAGES AWARD.
    POINT VI
    THE TRIAL COURT'S AWARD OF ATTORNEY'S
    FEES MUST BE REDUCED BECAUSE PETRIC IS
    NOT ENTITLED TO ATTORNEY'S FEES FOR ALL
    OF ITS CLAIMS, NOR IS IT ENTITLED TO ANY
    ENHANCEMENT.
    I.
    We discuss the extensive procedural history and the trial evidence to
    provide context for our opinion.
    Plaintiff was a small, family-owned industrial painting company run by
    the Petrics, Ellen, and Steven, wife and husband. 1     Plaintiff had been in
    business for approximately thirty years, and in that time worked on between
    thirty and forty projects for the New Jersey Department of Transportation
    (NJDOT).    Steven, plaintiff's Vice President, testified that he was a civil
    engineer and a member of the Structural Steel Painting Council. In addition, at
    the time plaintiff bid on the Pulaski Skyway job, Steven had more than thirty
    1
    For ease of reference, we refer to Ellen and Steven Petric by their first
    names, intending no disrespect.
    A-3571-17T2
    5
    years' experience in the industry, had worked on public projects for NJDOT,
    and was familiar with NJDOT's procedures and specifications, including
    change orders.
    By letter dated June 28, 2013, defendant advised plaintiff of its intent to
    award plaintiff a subcontract to install temporary shielding and work platforms
    for the Pulaski Skyway project. On July 12, 2013, plaintiff submitted a formal
    bid to install a standard platform for $6.50 per square foot.
    At trial, Steven testified regarding the parties' approximate two-month
    negotiation of the subcontract.     He stated that the final design drawings
    revealed a complicated design, not the "standard" design originally anticipated
    by plaintiff, and they did not show any indication of PSE&G wire interference.
    He further testified that as a result of the more complicated design, plaintiff
    negotiated a higher unit price of $6.60 per square foot.
    Michael Grant, defendant's former employee who negotiated the
    subcontract on defendant's behalf, testified as a witness for plaintiff and noted
    that one of the primary issues regarding the subcontract negotiations was
    prompt payment to plaintiff.       He stated that because plaintiff "had just
    completed a project for which they had not received payment timely and they
    couldn't afford to finance" the current project, plaintiff was "in a precarious
    A-3571-17T2
    6
    financial position and . . . [defendant] knew it." In this regard, plaintiff agreed
    to perform the work for $6.60 per square foot, which Grant testified was "a
    much lower price to do the work than others would have given [defendant]," if
    defendant agreed to make timely payments.
    NJDOT kept notes from progress meetings regarding the project between
    August and September 2013, which were admitted at trial. At each meeting,
    PSE&G and representatives of defendant spoke regarding PSE&G wire
    interference with the project. By way of example, as early as an August 14,
    2013 meeting, the minutes provided that defendant's surveyor noticed a
    "PSE&G ramp close to installation of [the] electrical shield," and that "[a]t
    present it looks like issue of '[New Jersey High Voltage] Proximity Act'[2]
    violation."
    Similarly, according to the progress meeting notes from an August 20,
    2013 meeting, representatives from PSE&G indicated that within ten feet of
    the working area, "[t]here are open wires/exposed cover wires," which had "no
    insulation" and were unable to be insulated.           In response, defendant's
    representatives asked whether there was "potential de-energizing" in that area,
    2
    The New Jersey High Voltage Proximity Act (Proximity Act), N.J.S.A. 34:6-
    47.1 to -47.9, precludes contractors from performing work within a specified
    distance of high-voltage electrical lines.
    A-3571-17T2
    7
    and PSE&G responded in the negative. According to the sign-in sheets at each
    of the project meetings, Gregory Borovskis, defendant's project manager, and
    Dino Monioudis, defendant's assistant project manager, were present. Plaintiff
    did not have a representative at those meetings.
    At trial, Dennis Persico, defendant's corporate representative, testified
    by deposition that by the August 20, 2013 meeting, "[defendant] knew about
    the condition [of] the high voltage of the cable lines and the proximity of the
    cable lines," but "[defendant] did not know at the time [it] signed [the] prime
    contract."
    Steven performed a walk-through of the worksite along with plaintiff's
    superintendent/foreman Chad Eberle on August 22, 2013, prior to signing the
    subcontract, and both admitted seeing wires. Although the PSE&G wires were
    visible, both witnesses testified it was not apparent how close the wires would
    be in relation to the temporary shielding at the time of the walk-through. In
    this regard, Steven noted that he "was not allowed to climb up on the bridge
    and measure . . . how far it would be from [plaintiff's] work." Eberle likewise
    testified that though the PSE&G wires were visible from the ground, that
    perspective did not indicate their proximity in relation to the platform.
    A-3571-17T2
    8
    Further, as no platform had been designed when plaintiff inspected the
    site or bid on the project, and the wires were not identified on any NJDOT
    design drawings or specifications, Steven claimed that "because [he] didn't
    know the location of the platform in relation to those wires," he did not take
    them into account in preparing his bid.       Defendant, however, introduced
    documentary evidence indicating that at a coordination meeting dated
    September 5, 2013, an unidentified representative of plaintiff suggested that
    the PSE&G wires be hiked up so as not to interfere with the project.
    Plaintiff also introduced evidence that the high voltage nature of the
    PSE&G wires was not apparent at the time of the walk-through. For example,
    Eberle testified that when he eventually noticed the proximity of the wires, he
    "needed to contact [plaintiff] to get [defendant] to find out" whether the wires
    were high voltage or even live wires.      Likewise, Persico stated on cross-
    examination at his deposition that "[a]t the time that you were able to see the
    wires, [he did not] think anyone was aware of the voltage in those wires . . . ."
    He further noted that a person could not determine whether the wires were
    high voltage by looking at them.
    Steven testified that plaintiff "started getting ready to work" in early
    September before the subcontract was signed. On September 12, 2013, he was
    A-3571-17T2
    9
    approached in the field by Borovskis, who insisted he sign the subcontract.
    Steven initially declined because Ellen had negotiated the deal and he did not
    normally sign contracts on plaintiff's behalf. He called Ellen, who advised him
    the parties had agreed on final terms, so he signed the subcontract.
    Pursuant to the subcontract, plaintiff agreed to install the temporary
    shielding at the Pulaski Skyway project for $6,765,000.         Article 6 of the
    subcontract governed change orders on the project. Initially, it provided that
    "[a]ny change or adjustment in the [c]ontract price by virtue of . . . [a] Change
    Order shall be specifically stated in said Change Order." It also indicated that
    change orders "are subject to the terms of the subcontract," and that "[i]f
    [defendant] and/or [NJDOT] elects the option to direct the Change Order work
    to be done by [plaintiff] on a time and materials basis," plaintiff was obligated
    to "prepare daily time and materials invoices" to be submitted daily to
    defendant. Moreover, "[t]he allowable mark-up on time and material invoices
    [was] deemed to be full and complete compensation to [plaintiff] for all
    general and administrative expenses, overhead, supervision, and profit . . . ."
    Regarding plaintiff's total compensation for change orders, Article 6
    stated that plaintiff would not receive "any compensation or allowance for any
    Change Order in an amount greater than that which [defendant] actually
    A-3571-17T2
    10
    receives from [NJDOT], less a reasonable deduction for work incorporated
    therein which is performed by [defendant], as well as [defendant]'s overhead
    and profit."
    Article 7 of the subcontract provided for claims by plaintiff "for extra
    work, additional and increased costs of contract work, delay and interference
    in the performance of its work, and/or for other damages for any cause
    whatsoever in connection with the performance of the [s]ubcontract . . . ."
    Where those costs are "directly or indirectly attributable to or arise out of the
    acts and omissions of [NJDOT] or [an architect/engineer]," they were not
    "chargeable to or recoverable from [defendant], and any legal right of
    [plaintiff] to otherwise assert such claim against [defendant] shall be fully
    liquidated by whatever recovery, if any, may be obtained on [plaintiff]'s behalf
    in the prosecution of its claim by [defendant] against [NJDOT] . . . ." Article 7
    further permitted defendant, "in its sole discretion, [to] settle its entire claim,
    including that of [plaintiff], with [NJDOT]" and stated that plaintiff "expressly
    releases and discharges [defendant] from any and all liability for any such
    claims, except to the extent of any recovery as aforesaid."
    The subcontract was supplemented and modified by Exhibit A and its
    accompanying Rider. Exhibit A to the subcontract, entitled "Scope of Work
    A-3571-17T2
    11
    and Subcontract Price," provided that where the subcontract conflicts with
    Exhibit A or the Rider, the provision in Exhibit A or the Rider would control.
    Further, Exhibit A required that defendant "provide monthly payments to
    [plaintiff] equal to wage and benefit costs incurred by [plaintiff] for work
    performed up to what [plaintiff] earned the previous month."         It further
    provided that if NJDOT were to "make any monetary deductions from
    [defendant] due to work covered by this agreement, these deductions shall be
    made to [plaintiff]'s payment."
    The Rider to Exhibit A also provided that "[plaintiff] agrees, for
    additional compensation, to perform extra work, conform and abide by all
    decisions issued by [defendant], when [defendant] has been directed to
    perform extra work, conform and abide by similar decisions issued by
    [NJDOT]." Further, under the Rider, plaintiff was "not . . . responsible for
    hidden conditions not detectable upon a reasonable inspection of the jobsite
    conditions" and, as noted, defendant was to "assist [plaintiff] to pursue
    additional compensation" pursuant to Article 6 of the subcontract.
    Where additional work was proposed, plaintiff was "not . . . obligated to
    proceed . . . unless a price [was] agreed upon in writing." In the event an
    agreement could not be reached, defendant retained the ability to, "direct, in
    A-3571-17T2
    12
    writing, for [plaintiff] to perform the work on a time and material plus
    allowable markup per the [p]rime [c]ontract and Article 6" of the subcontract.
    The Rider also stated that "[p]laintiff shall receive full compensation for
    all work performed including [c]hange [o]rder work as long as work is
    acceptable to [defendant] and [NJDOT]," and that compensation was not to be
    "unreasonably withheld and shall be given in a timely manner." Finally, the
    Rider revised Article 25 of the subcontract "to provide that the losing party
    shall be responsible for all costs, disbursements, and expenses, including
    reasonable attorney fees incurred by the prevailing party as a result of any
    claim or dispute between [plaintiff] and [defendant] if so directed by . . . the
    court."
    As noted, Steven testified that he did not know about the PSE&G wire
    interference prior to bidding on the project or signing the subcontract and that
    had he known about the interference, he would never have signed it. "[E]xtra
    work," under the subcontract, payable on a time and material basis, had a
    lower percentage mark-up for profit and overhead than Steven testified he
    would have included in a bid. He explained: "If I were to price that PSE&G
    extra work when I bid the original quote, because of all the uncertainties and
    A-3571-17T2
    13
    actual overhead and actual profit that we normally use in our bidding, it would
    be $1 million."
    Steven also testified at trial that on September 16, 2013, plaintiff began
    work on the project.    The following day, plaintiff discovered that certain
    PSE&G wires were too close to the platform as designed. Immediately after
    discovering the PSE&G wire interference, Steven and Eberle notified
    Monioudis and Victor Uscilla, defendant's project field engineer, who stated
    they were "shocked" at the discovery.
    Grant testified that he had no idea about the potential PSE&G wire
    interference until after the subcontract had been signed. According to Grant,
    "it was to [defendant]'s advantage to tell him everything that [defendant] knew
    or should have known in order to protect [defendant] when [he] wrote the
    schedule. So if . . . there was something wrong in the access to the job site,
    [defendant] could claim against [NJ]DOT."
    The proximity of the high voltage PSE&G wires caused the plans for the
    installation of the temporary shielding to be altered. When plaintiff contacted
    defendant and described the updated plan, defendant directed plaintiff to
    proceed with the change and extra work related to the PSE&G wire
    interference on a time and material basis and plaintiff complied with that
    A-3571-17T2
    14
    directive. As a result of the PSE&G wire interference, plaintiff had to change
    the coordination and scheduling of its work, as well as the methods used to
    complete it. In this regard, plaintiff had to deliver materials from the ground
    up, instead of lowering them down from the bridge, which was more costly.
    Furthermore, Steven testified that prior to discovering the PSE&G wire
    interference, plaintiff had planned on working one shift per day. However,
    even after the discovery, Steven stated that because the project operated on a
    fixed schedule, "there [were] no extensions allowed . . . which made it very
    difficult." Plaintiff had to increase its manpower in order to accommodate the
    schedule. As a result, plaintiff's employees worked triple shifts, twenty-four
    hours a day, seven days a week, and through rain and snow to make up for the
    delays caused by the wire interference. Steven testified he slept in a trailer on
    site most nights.   Because of these changes, plaintiff began to experience
    further financial difficulties but nevertheless completed its work, on time, by
    the end of May 2014.
    Defendant then filed a claim with NJDOT alleging that it was entitled to
    additional compensation because the PSE&G wire interference was an
    "existing latent condition."    Defendant and plaintiff worked together to
    A-3571-17T2
    15
    produce a claims package for the additional work, using plaintiff 's time and
    material costs documentation.
    On May 12, 2014, defendant submitted a final claim package to NJDOT,
    in which it used minutes from the aforementioned project meetings to
    determine the amount of extra compensation needed.           Defendant's claim
    included the total amount of plaintiff's time and material costs, which totaled
    $697,380.86. The entire claim, including the amounts claimed by defendant
    and other subcontractors, was approximately $1.2 million.
    After meetings and discussions between NJDOT, defendant, and
    plaintiff, NJDOT discounted the claim based upon its specifications and
    offered $441,482.79 to plaintiff for the extra work on the PSE&G wire
    interference. Defendant communicated NJDOT's offer by way of e-mail to
    Ellen, who responded: "Please settle [plaintiff]'s portion of the PSE&G extra
    for $441,482.79."
    Ellen testified that, meanwhile, in May 2014, when plaintiff had nearly
    completed its work on the project, defendant advised plaintiff that it would not
    be paid for its time and material costs related to the PSE&G wire interference
    until defendant was paid by NJDOT. By that time, plaintiff was due over
    $697,000 for the time and material costs related to the wire interference. In
    A-3571-17T2
    16
    response, plaintiff expressed its desire to pay its suppliers, unions, and
    insurance premiums, but defendant refused to make any payment because
    plaintiff "owed . . . too much to the vendors and the unions." Ellen stated she
    continued requesting the payments and began "begging" defendant because
    plaintiff "was desperate to get payments."          Eventually, in March 2015,
    defendant used some of plaintiff's funds to pay two suppliers directly but
    maintained its refusal to pay plaintiff's union benefits.
    As a result of plaintiff's inability to pay its bills, it received violation
    notices from the New Jersey Department of Labor, with interest, totaling
    approximately $126,000. On June 8, 2015, plaintiff was "debarred," meaning
    it was not allowed to work on public works projects for three years. Ellen and
    Steven were also personally debarred. As a result of those violations and the
    debarment, plaintiff was "effectively . . . put out of business" and at the time of
    Ellen's testimony at trial, was "no longer operating."
    In November 2015, after plaintiff's debarment, defendant paid the unions
    with plaintiff's money.      Notwithstanding the fact that the unions were
    eventually paid, plaintiff incurred interest and penalties on the late payment
    and remained debarred, and the Department of Labor turned over the debt
    A-3571-17T2
    17
    owed by plaintiff to a collection agency. Furthermore, at the time of trial,
    defendant still withheld $66,221.14 that was owed to plaintiff.
    On April 19, 2016, plaintiff filed a complaint against defendant alleging:
    1) violation of the PPA; 2) breach of contract; 3) unjust enrichment; 4)
    quantum meruit; 5) fraudulent inducement; and 6) breach of the covenant o f
    good faith and fair dealing.
    On November 3, 2017, defendant filed a motion for partial summary
    judgment on the breach of contract, unjust enrichment, quantum meruit,
    fraudulent inducement, and breach of the covenant of good faith and fair
    dealing counts. In support of its motion, defendant argued that the matter was
    "controlled by plain and unambiguous contract language," which defendant
    claimed it complied with "to the letter." Defendant contended that it "held full
    discretion to settle the claim itself . . ., but still only settled the claim once
    [plaintiff] gave its express written consent." It also maintained that plaintiff
    was "bound by the subcontract terms limiting its legal rights to assert any
    claim for further compensation, because recovery is capped by any such
    recover[y] that [defendant] could obtain on [plaintiff]'s behalf for the claim."
    Finally, defendant argued that plaintiff's claim was barred by the doctrine of
    accord and satisfaction.
    A-3571-17T2
    18
    The following month, plaintiff filed a cross-motion for partial summary
    judgment on the PPA, breach of contract, fraudulent inducement, and
    attorneys' fees counts.    The court found genuine issues of material fact
    regarding all claims and denied both parties' motions.
    The matter proceeded to a jury trial which took place between January 9,
    2018 and January 25, 2018. At trial, plaintiff presented live testimony from
    the Petrics, Jeffrey Overton, a NJDOT manager, Peter Wu, defendant's
    chairman, Eberle, and Grant, as well as documentary evidence. As noted, it
    also presented the deposition testimony of Persico.
    Defendant presented testimony from Uscilla, Jennifer Sokoloski, senior
    project engineer of defendant, and Thomas McIntyre, the former project
    superintendent for defendant's consultant on the project, and documentary
    evidence.   At the close of plaintiff's case-in-chief, defendant moved for
    involuntary dismissal of plaintiff's fraud and contract claims, which the court
    denied. At the close of the evidence, defendant moved for a directed verdict
    on plaintiff's fraud claim. The court denied that motion as well.
    As noted, the jury returned a verdict in favor of plaintiff on the PPA,
    breach of contract, and fraud claims and awarded plaintiff $1,850,000 in
    damages. The same day, the court entered a judgment reflecting that verdict.
    A-3571-17T2
    19
    Three weeks later, defendant moved for judgment notwithstanding the
    verdict (JNOV) pursuant to Rule 4:40-2(b), for a new trial pursuant to Rule
    4:49-1, and/or for a new trial on damages or for a remittitur. After hearing
    oral argument, the court issued an oral decision and a corresponding March 16,
    2018 order in which it denied defendant's motion for a new trial and left the
    liability verdict undisturbed. It also denied defendant's motion for a new trial
    or to set aside the verdict as to the fraudulent inducement claim and upheld the
    punitive damages award. The court, however, reduced the amount of the jury
    award for plaintiff's PPA claim from $250,000 to $66,221.04. 3
    In support of its decision to deny defendant a new trial or set aside the
    verdict with respect to the fraud claim, the court explained that the trial
    evidence "established that [defendant] knew about a potential 'Proximity Act'
    violation as of at least August 14, 2013." Further, the court stated that the jury
    knew that "[plaintiff] was facing financial difficulties prior to . . . entering into
    the subcontract" and that Steven "stated that the project would have been bid
    higher" had plaintiff been aware of the latent site condition. In this regard, the
    court determined that "[i]t was not unreasonable for the jury to find that
    3
    The court, on March 27, 2018, amended its March 16, 2018 orders to reflect
    the correct dates that the orders were signed.
    A-3571-17T2
    20
    knowledge of the proximity of live wires to the shielding that was to be
    installed by [plaintiff] was a material misrepresentation that should have been
    disclosed when the amount of the subcontract was negotiated . . . ."
    Regarding the breach of contract claim, the court stated that sufficient
    evidence had been presented a trial to permit the jury to award plaintiff
    $800,000 in compensatory damages as "[t]hey were given the exact
    calculations down to . . . $751,596.91" and were informed that plaintiff was
    "entitled to damages resulting from [defendant]'s violation of the [PPA] as
    well as lost profits in any amount to be determined at trial suffered by
    [plaintiff]." Finally, the court determined that the jury could reasonably have
    concluded that defendant concealed the latent PSE&G site condition to obtain
    more favorable pricing for the job from plaintiff.
    Plaintiff moved for attorneys' fees under the PPA and the subcontract
    and requested a fifty percent fee enhancement. After hearing oral arguments,
    the court awarded plaintiff a total of $260,911.36. That award was comprised
    of $220,243.50 in attorneys' fees, $18,643.51 in costs, and a ten percent
    enhancement equaling $22,024.35. In support of its determination, the court
    issued a March 29, 2019 oral decision and corresponding order. In its oral
    decision, the court found that "the billing in this case was appropriate," and
    A-3571-17T2
    21
    that it was proper to award plaintiff attorneys' fees incurred prior to the filing
    of the complaint because "it all seemed related to the same issue, which is . . .
    the shielding work that was done on this project." This appeal followed.
    II.
    Defendant first argues that the trial court erred in denying its motion for
    partial summary judgment on the fraud claim. Next, it maintains that the court
    erred by denying summary judgment on plaintiff's breach of contract claim
    because, as provided for in the subcontract, plaintiff received the monetary
    amount that was approved by NJDOT. Defendant also contends that summary
    judgment was warranted in its favor on plaintiff's PPA claim because the PPA
    is inapplicable when the parties have agreed to an alternative payment
    mechanism, such as the subcontract here which permitted defendant to
    withhold funds to pay plaintiff's vendors and suppliers. We first address the
    applicable standard of review and then each of defendant's claims in the order
    presented.
    Our review of a ruling on summary judgment is de novo, applying the
    same legal standard as the trial court. Townsend v. Pierre, 
    221 N.J. 36
    , 59
    (2015). "Summary judgment must be granted if 'the pleadings, depositions,
    answers to interrogatories and admissions on file, together with the affidavits,
    A-3571-17T2
    22
    if any, show there is no genuine issue as to any material fact challenged and
    that the moving party is entitled to a judgment . . . as a matter of law. '" Town
    of Kearny v. Brandt, 
    214 N.J. 76
    , 91 (2013) (quoting R. 4:46-2). We accord
    no special deference to the trial judge's conclusions on issues of law. Nicholas
    v. Mynster, 
    213 N.J. 463
    , 478 (2013).
    A. Fraud
    As noted, defendant contends in Point I.A of its merits brief that the trial
    court committed error when it denied defendant's motion for summary
    judgment on plaintiff's fraud claim. Specifically, it contends that as a matter
    of law, plaintiff failed to establish a prima facie claim of fraud because: 1) the
    subcontract required plaintiff to inspect the site, and thus any alleged fraud is
    not cognizable in conjunction with a contract claim; 2) plaintiff knew about the
    existence of the PSE&G wires but made no inquiry into a potential Proximity
    Act violation and could not have reasonably relied on any omission by
    defendant; and 3) plaintiff failed to establish that defendant owed it a duty to
    disclose the proximity of the PSE&G wires. We disagree.
    Initially, we note that defendant's arguments in its moving brief
    submitted to the trial court related to the fraud claim were extremely limited.
    In fact, that brief contained no point heading regarding the fraud claim and
    A-3571-17T2
    23
    stated only, within its breach of contract analysis, that "[plaintiff]'s claim
    related to the PSE&G extra work rises and falls based upon the express
    contract language of the subcontract" and that "[plaintiff] has no right for
    further recovery on the PSE&G claim . . . that has [not] already been presented
    to the NJDOT by [defendant] and [plaintiff] and fully resolved." Defendant
    did not use the word "extraneous," argue that no duty to disclose existed, nor
    contend that any reliance by plaintiff was unreasonable. Even in its reply
    brief, which addressed plaintiff's fraud claim in more detail, defendant limited
    its argument to plaintiff's failure to show that "(1) [defendant] knew of any
    falsity, (2) that [plaintiff] itself did not know of the allegedly concealed
    PSE&G condition, and (3) that [plaintiff] was even damaged since the PSE&G
    claim was ultimately presented to the NJDOT, negotiated, and settled at the
    direction of [plaintiff]."
    Likewise, defendant did not present these arguments in support of either
    motion to dismiss at trial. On its motion at the close of plaintiff's evidence,
    counsel merely argued that plaintiff had not "identified a person . . . [or] a
    date" of the alleged fraud and that "[Steven] was aware of the PSE&G line."
    Further, at the close of all of the evidence, defense counsel stressed the clear
    and convincing evidence standard and characterized the case as "as best . . . a
    A-3571-17T2
    24
    case about . . . a utility line that may or may not have impacted [plaintiff's]
    work" and not one of fraud. And, in its brief in support of its motion for
    JNOV and/or a new trial, other than a spare quotation regarding a duty to
    disclose from an unreported opinion, defendant again failed to put forth any of
    the arguments it advances on appeal.         Instead, as on the prior motions,
    defendant's fraud argument revolved around whether it acted with intent in
    concealing the PSE&G wire interference, whether plaintiff knew or could have
    known of the condition, and whether plaintiff was actually damaged.
    Defendant's generalized statements throughout the litigation did not
    suffice to preserve the arguments it seeks to advance on appeal, and we
    consider those contentions waived. See Nieder v. Royal Indem. Ins. Co., 
    62 N.J. 229
    , 234 (1973) ("[A]ppellate courts will decline to consider questions or
    issues not properly presented to the trial court when an opportunity for such a
    presentation is available 'unless the questions so raised go to the jurisdiction of
    the trial court or concern matters of great public interest.'"). Such arguments
    should be raised specifically in order to be preserved for appeal, not swept into
    general requests for dismissal. See United States v. Hoffecker, 
    50 F.3d 137
    ,
    162 (3d. Cir. 2008) ("A skeletal 'argument,' really nothing more than an
    assertion, does not preserve a claim. Especially not when the brief presents a
    A-3571-17T2
    25
    passel of other arguments, as [defendant]'s did." (alteration in original)
    (quoting United States v. Dunkel, 
    927 F.2d 955
    , 956 (7th Cir. 1991))). For
    purposes of completeness, however, we address and reject defendant's
    contentions on the merits.
    In order to establish a claim for fraudulent inducement, a plaintiff must
    prove a misrepresentation of material fact, knowledge of belief by the
    defendant   of   its   falsity, intent    that   the   other   party   rely   on    the
    misrepresentation, and reasonable reliance thereon by the other party. Nolan
    v. Lee Ho, 
    120 N.J. 465
    , 472 (1990). Fraud in the inducement does not differ
    materially from common law fraud, as it provides a cognizable basis for
    equitable relief in the event a false promise induced reliance. See Lipsit v.
    Leonard, 
    64 N.J. 276
     (1974). Plaintiff must prove each element by "clear and
    convincing evidence." Stochastic Decisions, Inc. v. DiDomenico, 
    236 N.J. Super. 388
    , 395 (App. Div. 1989).
    However, a plaintiff is prohibited "'from recovering in tort economic
    losses to which their entitlement only flows from contract.'"                  Bracco
    Diagnostics, Inc. v. Bergen Brunswig Drug Co., 
    226 F. Supp. 2d 557
    , 562
    (D.N.J. 2002) (quoting Duquesne Light Co. v. Westinghouse Elec. Co., 
    6 F.3d 604
    , 618 (3d Cir. 1995)). This doctrine "functions to eliminate recovery on 'a
    A-3571-17T2
    26
    contract claim in tort clothing.'" G&F Graphic Servs. v. Graphic Innovators,
    Inc., 
    18 F. Supp. 3d 583
    , 588-89 (D.N.J. 2014) (quoting SRC Constr. Corp. v.
    Atl. City Hous. Auth., 
    935 F. Supp. 2d 796
    , 801 (D.N.J. 2013)); see also New
    Mea Constr. Corp. v. Harper, 
    203 N.J. Super. 486
    , 494 (App. Div. 1985)
    (finding that defendant's failure to use construction material specified in the
    parties' contract was a type of conduct "not ordinarily alleged in a tort case"
    and could not give rise to a separate claim by "[m]erely nominally casting [the]
    cause of action" as a tort claim).
    While New Jersey courts have applied this doctrine in the strict liability
    and negligence contexts, see, e.g. Spring Motors Distribs., Inc. v. Ford Motor
    Co., 
    98 N.J. 555
     (1985); Alloway v. General Marine Indus., L.P., 
    149 N.J. 620
    (1997), "[n]o New Jersey Supreme Court case holds that a fraud claim cannot
    be maintained if based on the same underlying facts as a contract claim."
    Gleason v. Norwest Mortgage, Inc., 
    243 F.3d 130
    , 144 (3d Cir. 2001). In fact,
    the law on whether a plaintiff may recover for purely economic loss on
    concurrent fraud and contract claims has arisen predominantly out of the New
    Jersey federal courts and other jurisdictions, not our state courts.
    Generally, "[t]he pattern that has emerged in New Jersey decisional law
    is that claims for fraud in the performance of a contract, as opposed to fraud in
    A-3571-17T2
    27
    the inducement of a contract, are not cognizable under New Jersey law."
    Bracco, 
    226 F. Supp. 2d at 564
    .        "Courts have continued to affirm 'the
    conceptual distinction between a misrepresentation of statement of intent at the
    time of contracting, which then induces detrimental reliance on the part of the
    promisee, and the subsequent failure of the promisor to do what he has
    promised.'" 
    Id. at 564
     (quoting LoBosco v. Kure Eng'g Ltd., 
    891 F. Supp. 1020
    , 1032 (D.N.J. 1995)).       In this regard, only those pre-contractual
    misrepresentations that are extraneous to the parties' contract may be brought
    alongside a breach of contract claim. Ibid; see also G&F, 18 F. Supp. 3d at
    593 (permitting common law fraud claim based on alleged pre-contractual
    misrepresentation which was "necessarily extraneous to the contract"); Florian
    Greenhouse, Inc. v. Cardinal IG Corp., 
    11 F. Supp. 2d 521
    , 528 (D.N.J. 1998)
    (permitting fraud claim but explaining that "the factual basis for the alleged
    fraud is extraneous to the contract"); Genovese v. State Farm Mut. Ins. Co.,
    
    106 A.D. 3d 866
    , 867 (N.Y. App. Div. 2013) (holding that the plaintiff could
    not maintain a fraud action alongside its breach of contract action because the
    fraud claim was "based on the same allegations as the breach of contract"
    claim); S&D Maintenance Co. v. City of New York, 
    169 A.D. 2d 417
    , 418
    (N.Y. App. Div. 1991) (same).
    A-3571-17T2
    28
    Where a pre-contractual misrepresentation relates to a defendant's future
    intent to perform under the contract, it will be considered intrinsic to the
    contract, and any related fraud claims will be dismissed. RNC Sys. v. Modern
    Tech. Grp., Inc., 
    861 F. Supp. 2d 436
    , 451 (D.N.J. 2012); see also Wyle Inc. v.
    ITT Corp., 
    13 N.Y.S. 3d 375
    , 376 (N.Y. App. Div. 2015) (stating that
    "pleadings must allege misrepresentations of present fact, not merely
    misrepresentations of future intent to perform under the contract, in order to
    present a viable claim that is not duplicative of a breach of contract claim");
    Vives v. Rodriguez, 
    849 F. Supp. 2d 507
    , 521 (E.D. Pa. 2012) (dismissing
    because the misrepresentations as to defendant's duties were later enshrined in
    the contract). Cf. Ohm NYC LLC v. Times Sq. Assoc. LLC, 
    96 N.Y.S. 3d 198
    , 199 (N.Y. App. Div. 2019) (holding that a landlord's misrepresentations
    as to the leased premises were "misrepresentations of a then present fact"
    creating a "cause of action for fraudulent inducement that is not duplicative of
    the breach of contract claim").
    Moreover, without an "independent duty imposed by law," a fraud claim
    is not extraneous to the contract. Saltiel v. GSI Consultants, Inc., 
    170 N.J. 297
    , 310 (2001); see also Int'l Minerals & Mining Corp. v. Citicorp N.A., Inc.,
    
    736 F. Supp. 587
    , 597 (D.N.J. 1990) ("It has . . . consistently been held that an
    A-3571-17T2
    29
    independent tort action is not cognizable where there is no duty owed to the
    plaintiff other than the duty arising out of the contract itself."); Galdieri v.
    Monsanto Co., 
    245 F. Supp. 2d 636
    , 650-51 (E.D. Pa. 2002) (granting
    defendant's motion for summary judgment on plaintiffs' misrepresentation
    claim because each alleged misrepresentation "addresse[d] a breach of duty
    incorporated into the parties' various agreements" and was thus "'intertwined'
    with plaintiff's breach of contract claim").
    New Jersey courts have concluded that "[s]ilence in the face of a duty to
    disclose" constitutes fraud in the following circumstances:             1) "fiduciary
    relationships such as principal and agent or attorney and client"; 2) where
    either party, by entering the transaction, "'expressly reposes . . . a trust or
    confidence in the other . . . or [because of the] circumstances of the case, the
    nature of their dealings, or their position towards each other, such a trust and
    confidence . . . is necessarily implied'"; and 3) "contracts or transactions which
    in their essential nature, are 'intrinsically fiduciary,' and . . . 'necessarily call[]
    for perfect good faith and full disclosure.'" United Jersey Bank v. Kensey, 
    306 N.J. Super. 540
    , 551 (App. Div. 1997) (quoting Berman v. Gurwicz, 
    189 N.J. Super. 89
    , 93-94 (Ch. Div. 1981)). In the second class of transactions, "[t]he
    nature of the transaction is not the test," but rather "[e]ach case must depend
    A-3571-17T2
    30
    on its own circumstances" because "[t]he trust and confidence, and the
    consequent duty to disclose, . . . may be necessarily implied from [the parties']
    acts and other circumstances."          3 J. Pomeroy, A Treatise on Equity
    Jurisprudence 553 (5th ed. 1941).
    Similarly, courts do not consider fraud claims extraneous to contract
    claims where both claims possess "the same measure of damages." RNC Sys.,
    861 F. Supp. 2d at 454; see also Manas v. VMS Assocs, LLC, 
    863 N.Y.S.2d 4
    ,
    7-8 (N.Y. App. Div. 2008) (holding that "the fraud-based causes of action are
    duplicative of the breach of contract cause of action" where "plaintiff did not
    allege that she sustained any damages that would not be recoverable under her
    breach of contract cause of action").          Essentially, in order to maintain
    simultaneous claims in tort and contract, a defendant must "cause harm to the
    plaintiff distinct from those caused by the breach of contract." Pub. Serv. Ent.
    Grp., Inc. v. Philadelphia Elec. Co., 
    722 F. Supp. 184
    , 201 (D.N.J. 1989); see
    also Saltiel, 170 N.J. at 310 (holding that the failure of the defendant to apply
    "specific technical skills" required under a construction contract was "a breach
    of its contractual duties," but did not constitute a separate tort).
    Applying the facts against these legal principles, we conclude that
    plaintiff's fraud claim was extraneous to the parties' subcontract and that the
    A-3571-17T2
    31
    court properly permitted the claim to survive summary judgment. The record
    indicates that defendant was aware of the wire interference as early as the
    August 14, 2013 NJDOT progress meeting. Steven signed the subcontract on
    September 12, 2013, and plaintiff did not discover the latent condition
    independently, despite a prior walk-through of the premises, until September
    17, 2013.4 At his deposition, Steven stated that had he known of the wire
    interference, he would have bid $1 million on the project instead of the
    $697,000 that plaintiff ultimately bid. Further, defendant's omission was that
    of a present fact, not a future intent to perform. Therefore, plaintiff's claim
    clearly relates to reliance on pre-contractual misrepresentations.
    4
    While we note that defendant indicated in its reply brief in support of its
    partial summary judgment motion that representatives from plaintiff attended a
    September 5, 2013 meeting in which the parties discussed the PSE&G wire
    interference, the document it references was not included in the record on
    appeal. In any event, as the motion record also contained evidence that
    plaintiff was unaware of the wire interference, the issue of whether plaintiff
    knew of the wire interference was, at most, a disputed material fact and
    precluded the granting of partial summary judgment to defendant on the fraud
    claim. Likewise, defendant raised the same issue at the close of plaintiff's
    evidence, at the close of all the evidence, and at oral argument in support of its
    motion for JNOV or a new trial. All motions were properly denied for the
    same reason, as the jury heard Steven and Eberle testify that plaintiff was
    unaware of the wire interference. Thus, a judgment in defendant's favor was
    unwarranted based on the evidence adduced at trial, and we defer to the jury's
    verdict and its role in determining witness credibility.
    A-3571-17T2
    32
    Sufficient evidence in the motion record also existed for the court to
    conclude that defendant violated an independent duty to disclose when it failed
    to inform plaintiff of the PSE&G wire interference prior to entering into the
    subcontract.   Given that the subcontract related to a potentially dangerous
    construction project, the circumstances indicate that it was "necessarily
    implied" that defendant would make plaintiff aware of a situation, such as high
    voltage wires in proximity to the work site, which could result in grave injury
    to plaintiff's employees. See United Jersey Bank, 306 N.J. Super. at 551.
    Defendant's reliance on Globe Motor Car Co. v. First Fidelity Bank, 
    273 N.J. Super. 388
    , 395 (Law Div. 1993) for the proposition that "a party has 'no
    duty to disclose matters of which the other party has actual or constructive
    knowledge or as to which the information or means of acquiring information of
    the two parties is equal'" is misplaced. Defendant claims that because plaintiff
    knew that the PSE&G wires existed, "it had at least equal means of acquiring
    information about the potential for the wires to interfere with its work."
    Defendant reads Globe Motor Car too broadly. That case involved a car
    dealership whose employee committed embezzlement by falsifying records.
    The car dealership sued a bank whose role it was to extend credit to the
    dealership and to "inspect Globe's records and the vehicles" as the bank saw
    A-3571-17T2
    33
    fit. 
    Id. at 391
    . The Law Division found that the bank did not have a fiduciary
    duty to uncover and notify the plaintiff of its own employee's embezzlement
    scheme based on the parties' relationship as debtor and creditor. 
    Id. at 394
    . In
    this regard, it noted that the bank did not possess knowledge of the
    embezzlement, but that the plaintiff could have simply examined the bank 's
    monthly reports to determine whether "any deposits [were] missing or if
    checks [were] drawn without authority." 
    Id. at 394-95
    .
    Here, however, the motion record supported the reasonable inference
    that plaintiff had neither actual nor constructive knowledge of the wires '
    voltage and proximity to the platform.     As Steven and Eberle both noted,
    plaintiff could not have identified as much during their walk-through because
    the platform had not yet been built. Further, unlike the bank in Globe Motor
    Car, defendant was in a much better position to discover and discern the
    voltage and proximity of the wires because it was involved the design of the
    platform and attended various meetings with PSE&G. As such, the parties did
    not have equal means of identifying the voltage and proximity of the wires.
    Moreover, as discussed infra Section IV, plaintiff's claimed damages for
    fraud arise separately from its claimed damages for breach of contract. As
    noted, at Steven's deposition, he testified that he would have bid $1 million on
    A-3571-17T2
    34
    the project instead of $697,000. Those damages stem from defendant's failure
    to disclose the PSE&G wire interference to plaintiff before the subcontract was
    signed.   The remainder of the evidence in the motion record regarding
    plaintiff's claimed damages – i.e., $66,221.04 in payments that defendant
    failed to disburse, $255,517 representing the difference between pl aintiff's
    $697,000 bid and the $441,482.79 that the NJDOT approved, $126,856.66 in
    fees and penalties from the Department of Labor, and other costs related to
    billing – arise out of defendant's performance under the subcontract. As such,
    we conclude that defendant did "cause harm to the plaintiff distinct from those
    caused by the breach of contract." Pub. Serv. Ent. Grp., Inc., 
    722 F. Supp. at 201
    .
    Defendant's reliance on P.T. & L. Constr. Co. v. Dep't of Transp., 
    108 N.J. 539
     (1987) is also misplaced. Defendant contends that P.T. & L. supports
    the proposition that "where there is a false representation about, or actual
    concealment of information regarding site conditions, a contractor is entitled to
    compensation of extra work . . . [b]ut . . . the claim remains a breach of
    contract claim" and not a fraud claim.
    In P.T. & L., the plaintiff construction company contracted with the
    State to perform site clearance, underground, and roadway work, including
    A-3571-17T2
    35
    "stripping" on Route 78 in Springfield. 
    Id. at 542
    . Because of poor working
    conditions which led to flooding on the west end of the work site, the
    "stripping" took 171 days instead of the 3 days allocated. 
    Id. at 543
    . The
    plaintiff contended that "the State, through the contract process, had misled it
    into believing that it would be working under dry or normal working
    conditions by use of the term 'stripping,'" ibid., and argued that "the work
    should have been described to bidders as 'wet excavation,'" 
    id. at 546
    . It also
    asserted that certain specified materials and elements of the design drawings
    indicated "dry conditions" of work. 
    Id. at 547
    .
    The P.T. & L. Court held that "the State's nondisclosure of material facts
    constituted a misrepresentation of site conditions" and allowed the plaintiff to
    recover for breach of contract. 
    Id. at 541
    . In doing so, it distinguished a claim
    based only on "implicit" representations, which would not support recovery, as
    opposed to "a claim founded on the State's withholding information that
    conditions would be wet." 
    Id. at 541-42
    .
    Notably, the P.T. & L. Court did not address the propriety of a fraud
    claim under those circumstances at all, as the plaintiff in that case asserted
    only a claim for breach of contract. While defendant argues that P.T. & L.
    held that "even where an owner or contractor is alleged to have misrepresented
    A-3571-17T2
    36
    site conditions . . . the damages, if any, are contract damages and depend upon
    the   specificity   of   the   allegedly   misrepresented   site   conditions    or
    specifications," our Supreme Court did not so limit a plaintiff's recourse
    regarding a fraud allegation. The mere fact that the P.T. & L. Court permitted
    a plaintiff to recover for breach of contract does not preclude plaintiff in this
    case from recovering under a fraud claim.
    As we have concluded that plaintiff's fraudulent inducement claim is
    extraneous to its contract claim and that defendant had a duty to disclose the
    latent wire interference, the final step in the analysis is to determine whether
    plaintiff reasonably relied on defendant's omission.         Steven certified in
    plaintiff's opposition to defendant's motion for partial summary judgment that
    at the time plaintiff submitted its bid, it was impossible for it to know of the
    wire interference, as the wires "[were] not identified on any of the Project
    plans or specifications" prepared by defendant and Safespan, and that despite a
    walk-through of the work site, "it was not apparent that the cables were
    proximate to the area where the temporary shielding would eventually be
    installed." Given that defendant took part in designing the platform and did
    not disclose the proximity of the wires and that Steven indicated his bid would
    have been significantly different had he been made aware of the dangerous
    A-3571-17T2
    37
    conditions known by defendant, we conclude sufficient evidence existed for
    the court to deny defendant's summary judgment motion, and for the jury to
    have concluded, that plaintiff reasonably relied on that omission in submitting
    its bid. As such, because defendant misrepresented a present fact prior to
    entering into the subcontract, which it had a separate duty to disclose, and
    plaintiff reasonably relied on that nondisclosure, we conclude the trial court
    properly denied summary judgment on the fraud claim.
    B. Breach of Contract
    In Point II.A, defendant maintains that "the [s]ubcontract unambiguously
    provided that, in exchange for extra work, [plaintiff] was only entitled to as
    much compensation as . . . the NJDOT was willing to pay" under both Articles
    6 and 7, and that the trial court misconstrued the subcontract.       Defendant
    further asserts that the court should have found that defendant satisfied its
    contractual duties with respect to plaintiff's PSE&G claim at the summary
    judgment stage. We disagree.
    At the appellate level, "[i]nterpretation and construction of a contract is
    a matter of law for the court subject to de novo review."         Fastenberg v.
    Prudential Ins. Co., 
    309 N.J. Super. 415
    , 420 (App. Div. 1998). Appellate
    courts decide such purely legal questions without deferring to a lower court 's
    A-3571-17T2
    38
    "interpretation of the law and the legal consequences that flow from
    established facts." Manalapan Realty, LP v. Twp. Comm. of Manalapan, 
    140 N.J. 366
    , 378 (1995); see also Zaman v. Felton, 
    219 N.J. 199
    , 216 (2014).
    When interpreting a contract, the court should consider the plain
    language of the contract, the circumstances surrounding the contract, and the
    contract's purpose. Highland Lakes Country Club & Cmty. Ass'n v. Franzino,
    
    186 N.J. 99
    , 115-16 (2006).      In doing so, and in determining whether a
    contract is ambiguous, courts may consider extrinsic evidence offered in
    support of conflicting interpretations. Teamsters Indus. Emps. Welfare Fund
    v. Rolls-Royce Motor Cars, Inc., 
    989 F.2d 132
    , 135 (3d Cir. 1993). Such
    evidence may include the structure of the contract, the parties' bargaining
    history, and the conduct of the parties that reflects their understanding of the
    contract's meaning. 
    Ibid.
    Although courts may use course of performance and course of dealing in
    interpreting contract terms, "express terms are given greater weight than
    course of performance [and] course of dealing."       Restatement (Second) of
    Contracts § 203(b) (Am. Law. Inst. 1981). However, "where the terms of a
    contract are clear and unambiguous there is no room for interpretation or
    construction and the courts must enforce those terms as written." Karl's Sales
    A-3571-17T2
    39
    & Serv., Inc. v. Gimbel Bros., 
    249 N.J. Super. 487
    , 493 (App. Div. 1991). It
    should not "rewrite a contract for the parties better than or different from the
    one they wrote for themselves."      Kieffer v. Best Buy, 
    205 N.J. 213
    , 223
    (2011).
    Contrary to defendant's contention, plaintiff's interpretation is supported
    by the clear language of Exhibit A and the Rider to Exhibit A, which
    specifically modify or supersede the terms of the subcontract. In this regard,
    the Rider to Exhibit A states that plaintiff was entitled to "full compensation
    for all work performed including [c]hange [o]rder work as long as work is
    acceptable to [defendant] and [NJDOT].         Such compensation shall not be
    unreasonably withheld and shall be given in a timely manner." Both Article 6
    and Exhibit A define "full compensation" as time and material costs plus
    allowable markup. The record indicates that even considering the additional
    unexpected change order work, plaintiff completed its work within the original
    timeframe contemplated by the parties under the subcontract and there is no
    indication in the record that either defendant or NJDOT deemed plaintiff's
    work unacceptable. Moreover, it is undisputed that plaintiff did not receive
    full compensation for its change order work.
    A-3571-17T2
    40
    Further, a genuine issue of material fact existed as to whether
    compensation to plaintiff was, as proscribed by the Rider to Exhibit A,
    "unreasonably withheld and . . . given in a timely manner." Indeed, as noted,
    neither party disputes that plaintiff has yet to receive the full amount to wh ich
    defendant alleges plaintiff is entitled.     As such, summary judgment for
    defendant would have been improper on plaintiff's contract claim as well.
    C. Prompt Payment Act
    In Point III, defendant argues that the trial court erred in denying
    summary judgment on plaintiff's PPA claim.          Specifically, it asserts that
    "[b]ecause the summary judgment record undisputedly established that
    [plaintiff] had failed to timely pay its vendors and suppliers, there was no
    genuine issue of material fact as to whether the [s]ubcontract entitled
    [defendant] to withhold payment from [plaintiff]." In this regard, defendant
    maintains that the subcontract entitled it "to withhold funds in order 'to assure
    payment of [plaintiff]'s unpaid obligations.'" In opposition, plaintiff correctly
    notes that defendant did not move for summary judgment on that claim in the
    trial court.
    We reject defendant's argument that it was entitled to summary judgment
    on the PPA claim, as it never moved for summary judgment below on that
    A-3571-17T2
    41
    claim. "[A]ppellate courts will decline to consider questions or issues not
    properly presented to the trial court when an opportunity for such a
    presentation is available 'unless the questions so raised go to the jurisdiction of
    the trial court or concern matters of great public interest.'" Nieder, 62 N.J. at
    234.    As defendant's summary judgment claim fulfills neither of those
    conditions, we decline to address its argument in the context of whether
    defendant was entitled to summary judgment.
    However, we note that by raising the issue in opposition to plaintiff's
    motion for partial summary judgment, defendant properly preserved the
    argument that the PPA is subordinate to the parties' subcontract and address
    that argument on the merits.      See Nat'l Westminster Bank N.J. v. Anders
    Eng'g, Inc., 
    289 N.J. Super. 602
    , 609-610 (App. Div. 1996) (finding defendant
    sufficiently preserved a defense for appellate review where that defense was
    raised in its trial level opposition brief).       As such, we conclude that
    insufficient evidence supported a jury verdict on the PPA and reverse that
    portion of the verdict.
    N.J.S.A. 2A:30A-2(b) provides that where a subcontractor "has
    performed in accordance with the provisions" of a subcontract, the prime
    contractor has accepted the work, and "the parties have not otherwise agreed in
    A-3571-17T2
    42
    writing, . . . the prime contractor shall pay to its subcontractor . . . within [ten]
    calendar days of the receipt of each . . . payment . . . the full amount received
    for the work of the subcontractor . . . based on the work completed or the
    services rendered . . . ." (emphasis added). Where "a payment due pursuant to
    . . . this section is not made in a timely manner, the delinquent party shall be
    liable for the amount of money owed under the contract, plus interest at a rate
    equal to the prime rate plus 1%." N.J.S.A. 2A:30A-2(c).
    Here, the subcontract permits defendant to withhold funds from plaintiff
    "to ensure payment of [plaintiff]'s obligations," such as the unions and
    vendors. The trial court noted as much in denying plaintiff's motion for
    summary judgment, stating that defendant "argue[d] that the withholding of
    the funds was necessary in order to pay those vendors." As such, based on a
    plain reading of the statute, the parties "otherwise agreed in writing" on the
    conditions by which defendant would disburse payments to plaintiff. Plaintiff
    does not dispute that it owed payments to its vendors and unions. Therefore,
    defendant's failure to disburse funds to plaintiff was governed by the
    subcontract and not the PPA, and there was insufficient evidence to support a
    jury verdict for plaintiff under the statute.
    A-3571-17T2
    43
    III.
    In Point II.B, defendant argues that the trial court erred in denying its
    motions for involuntary dismissal of plaintiff's contract claim at the close of
    plaintiff's evidence, as well as its motion for judgment notwithstanding the
    verdict and/or for a new trial on the contract claim. Specifically, it contends
    that the breach of contract claim should not have been submitted to the jury
    because plaintiff "failed to show that [defendant] did anything other than fully
    comply with its obligations under the [s]ubcontract." According to defendant,
    "[a]t trial, the evidence unequivocally showed that [defendant] paid [plaintiff]
    all amounts required under the [s]ubcontract." Defendant also contends the
    trial court erred "by deeming the [s]ubcontract ambiguous and permitting parol
    evidence to 'interpret' it." We disagree.
    A motion for judgment may be made at the close of plaintiff's case, Rule
    4:37-2(b) or after the verdict, Rule 4:40-2(b). Both motions are governed by
    the same evidential standard: "[I]f, accepting as true all the evidence which
    supports the position of the party defending against the motion and according
    [it] the benefit of all inferences which can reasonably and legitimately be
    deduced therefrom, reasonable minds could differ, the motion must be denied
    . . . ." Verdicchio v. Ricca, 
    179 N.J. 1
    , 30 (2004) (quoting Estate of Roach v.
    A-3571-17T2
    44
    TRW, Inc., 
    164 N.J. 598
    , 612 (2000)); see also ADS Assocs. Grp., Inc. v.
    Oritani Sav. Bank, 
    219 N.J. 496
    , 511 (2014). We apply the same standard on
    appeal. Estate of Roach, 
    164 N.J. at 612
    .
    Moreover, Rule 4:49-1(a) provides that a trial court shall grant a new
    trial if, "having given due regard to the opportunity of the jury to pass upon the
    credibility of the witnesses, it clearly and convincingly appears that there was
    a miscarriage of justice under the law." A "miscarriage of justice" is defined
    as a "pervading sense of 'wrongness'" that stems from a "manifest lack of
    inherently credible evidence to support the finding, obvious overlooking or
    undervaluation of crucial evidence, [or] a clearly unjust result."         Risko v.
    Thompson Muller Auto. Grp., 
    206 N.J. 506
    , 521 (2011) (quoting Lindenmuth
    v. Holden, 
    296 N.J. Super. 42
    , 48 (App. Div. 1996)). "[T]he standard for
    authorizing a new trial . . . requires a determination that the jury 's verdict is
    'contrary to the weight of the evidence or clearly the product of mistake,
    passion, prejudice, or partiality.'" Crawn v. Crampo, 
    136 N.J. 494
    , 512 (1994)
    (quoting Lanzet v. Greenberg, 
    126 N.J. 168
    , 175 (1991)).
    As noted, the clear and unambiguous language of Exhibit A and its
    accompanying     Rider   establishes   that   plaintiff   was   entitled   to   "full
    compensation for all work performed including [c]hange [o]rder work," which
    A-3571-17T2
    45
    it did not receive. In this regard, the jury heard Ellen testify that she did not
    sign the change order form and that plaintiff "did not accept the sum of
    $441,482.79 in full satisfaction of its claim against [defendant]."5 Further,
    Ellen testified that when she sent the e-mail authorizing defendant to settle
    plaintiff's claim with NJDOT, her decision was spurred by "a phone call from
    . . . Antoun threatening that if she did not send the e-mail, [plaintiff] would get
    nothing."   Ellen also stated that plaintiff received no payment.        As such,
    questions of fact existed as to whether defendant fully discharged its
    contractual duties, and denial of defendant's motions for involuntary dismissal
    and JNOV was proper. And, based on the evidence adduced at trial, it does
    not clearly and convincingly appear that there was a miscarriage of justice
    under the law warranting a new trial. R. 4:49-1(a); see also Barber, 406 N.J.
    Super. at 51.
    5
    Although plaintiff accuses defendant of attempting to resurrect its accord
    and satisfaction defense on appeal, we note that defendant makes clear in its
    reply brief that "this [is not] a matter of 'accord and satisfaction,' . . . it is
    simply a matter of [defendant] having fully performed its obligations under the
    Subcontract."
    A-3571-17T2
    46
    IV.
    Defendant asserts in Point IV that the jury's compensatory damages
    award was excessive, and therefore, the trial court erred in denying its motion
    for a new trial on damages or for a remittitur. Specifically, it contends that
    based on the evidence presented at trial, the jury's award on plaintiff's breach
    of contract claim could not have exceeded $382,373.87. 6 In this regard, it
    argues that the jury's $800,000 award on plaintiff's contract claim "could only
    have resulted from double-counting" the PPA and fraud damages in calculating
    the damages award. It further avers that the trial court erred by justifying the
    damages award based on plaintiff's "vague statement" in its responses to
    interrogatories that it suffered lost profits. We disagree.
    The award of damages is left to the sound discretion of the trier of fact.
    Mandia v. Applegate, 
    310 N.J. Super. 435
    , 446 (App. Div. 1998).               An
    appellate court should not disturb the amount of damages awarded unless the
    6
    Defendant also claims that plaintiff stipulated and explained to the jury that
    it would be limited to "the amount of damages . . . explained on page [five] of
    [plaintiff's] interrogatories," which totaled $751,594.91. Nevertheless, "a jury
    is free to reject any evidence, including that which is uncontroverted,"
    including any stipulation plaintiff may have made. State v. Wesner, 
    372 N.J. Super. 489
    , 494 (App. Div. 2004); see also AGS Computs., Inc. v. Bear,
    Stearns & Co., 
    244 N.J. Super. 1
    , 5 (App. Div. 1990); Biunno, Weissbard &
    Zegas, Current N.J. Rules of Evidence, cmt. 4(a) on N.J.R.E. 101(a)(4) (2020).
    A-3571-17T2
    47
    award is plainly wrong, constitutes a manifest injustice, or shocks the court 's
    conscience. Carey v. Lovett, 
    132 N.J. 44
    , 66 (1993). Thus, if the record
    supports "a reasonable estimate of damages, based upon more than mere
    speculation, a damage award can be affirmed." Fort Lee v. Banque Nat'l De
    Paris, 
    311 N.J. Super. 280
    , 291 (App. Div. 1998). Moreover, a damage award
    should be affirmed if evidence is adduced "which affords a basis for estimating
    damages with some reasonable degree of certainty." Viviano v. CBS, Inc., 
    251 N.J. Super. 113
    , 129 (App. Div. 1991).
    The purpose of compensatory damages is to compensate the plaintiff for
    his or her actual loss. Nappe, 97 N.J. at 48. "It is well-settled that the 'law
    abhors damages based on mere speculation.'" Mosley v. Femina Fashions,
    Inc., 
    356 N.J. Super. 118
    , 128 (App. Div. 2002) (quoting Caldwell v. Haynes,
    
    136 N.J. 422
    , 442 (1994)). However, "[w]here a wrong has been committed,
    and it is certain that damages have resulted, mere uncertainty as to the amount
    will not preclude recovery – courts will fashion a remedy even though the
    proof on damages is inexact." Kozlowski v. Kozlowski, 
    80 N.J. 378
    , 388
    (1979). A plaintiff is only required to "prove damages with such certainty as
    the nature of the case may permit, laying a foundation which will enable the
    A-3571-17T2
    48
    trier of the facts to make a fair and reasonable estimate." Lane v. Oil Delivery,
    Inc., 
    216 N.J. Super. 413
    , 420 (App. Div. 1987).
    "[I]t is fundamental that no matter under what theories liability may be
    established, there cannot be any duplication of damages." Ptaszynski v. Atl.
    Health Sys., Inc., 
    440 N.J. Super. 24
    , 39-40 (App. Div. 2015) (quoting P. v.
    Portadin, 
    179 N.J. Super. 465
    , 472 (App. Div. 1981)).        Thus, courts have
    consistently precluded recovery of duplicative damages predicated on the same
    injuries. See, e.g., Battaglia v. United Parcel Serv. Inc., 
    214 N.J. 518
    , 562
    (2013) (holding that where a jury awarded a plaintiff damages under the Law
    Against Discrimination, the plaintiff could not recover on his implied contract
    claim because any recovery "would be entirely co-extensive with the verdict
    [he] has already received"); Ptaszynski, 440 N.J. Super. at 40 (holding that the
    trial judge erred in not instructing the jury "that it could not award plaintiff
    damages for defendant's violations of [a statute] and its negligence based upon
    the same injuries or harm to [plaintiff]").
    Here, the jury's $800,000 award of compensatory damages on the breach
    of contract verdict is supported by the record without double counting the
    fraud damages. Initially, defendant concedes that Ellen testified at trial to the
    following damages claims relating to breach of contract:        1) $255,517.21,
    A-3571-17T2
    49
    which represented the difference between plaintiff's $697,000 proposal for the
    balance of the PSE&G work and the $441,482.79 that NJDOT approved; 2)
    $66,221.04 for the unpaid balance of that $441,482.79; and 3) $126,856.66,
    which represented fees and penalties imposed by the Department of Labor.
    The total amount of those damages was $448,594.91. 7
    Other evidence adduced at trial further supports the jury's $800,000
    award on defendant's breach of contract. For example, while we recognize that
    Ellen was subject to robust cross-examination, she testified and plaintiff
    presented documentary evidence regarding its incurred damages with respect
    to the center platform in the amount of $246,408.97.8 In addition, the jury
    7
    Defendant concedes that the $66,221.04 was "expressly included in the
    elements of [plaintiff]'s contract damages . . . at trial," but argues that since the
    trial court modified the jury's PPA verdict to represent that sum, it cannot be
    applied to the breach of contract damages. After subtracting that number from
    the $448,594.91 amount, defendant contends that plaintiff's award of
    compensatory damages for breach of contract cannot exceed $382,373.87.
    However, as we reverse the PPA verdict, we conclude that the $66,221.04 was
    a proper consideration for damages under the breach of contract claim and was
    consistent with the jury charge on breach of contract which said that plaintiff
    was to be placed "in as good a monetary position as he or she would have
    enjoyed if the contract had been performed as promised."
    8
    At trial, Ellen testified that plaintiff completed 48,000 square feet of work on
    the center platform at the $6.60 per square foot contract price, for a total of
    $316,000 value under the contract. However, she stated that "the cost to
    complete the center section of the platform" ended up totaling $563,208.97. In
    A-3571-17T2
    50
    heard testimony that defendant improperly deducted $50,566.56 from
    plaintiff's time and material billing "for equipment costs directly incurred by
    [plaintiff]."   Combining defendant's admitted damages with the additional
    evidence adduced at trial equals $745,570.44. 9 Thus, the record supports "a
    reasonable estimate of damages, based upon more than mere speculation," Fort
    Lee, 311 N.J. Super. at 291, and we accordingly affirm as to the jury's
    compensatory damages award for breach of contract.
    With respect to the fraud damages, there was also evidence presented at
    trial to support the jury's award without it having double-counted damages.
    For example, Steven testified that had he known of the wire interference prior
    to entering his bid, he would have bid using a 20% to 25% profit margin and a
    25% overhead margin, not the allowable 10% markup for profit and 15%
    markup for overhead as provided for change or extra work in the subcontract.
    its merits brief, plaintiff explains that the jury could reasonably have
    determined that defendant's breach led to plaintiff's loss of the difference
    between these two values, $246,408.97.
    9
    We note that in plaintiff's merits brief, it also maintains that the damages
    award for breach of contract could be supported in part by the $121,000
    difference between the $818,000 claim on the change order submitted by
    defendant to NJDOT "for the value of [plaintiff]'s work, which [defendant]
    admitted was a valid claim supported by documentary evidence," and the
    $697,000 amount which was eventually claimed by plaintiff.
    A-3571-17T2
    51
    Moreover, he testified the time and material amounts he provided in
    conjunction with the change order work did not include salary for Ellen or
    himself, and that would have been included in a bid. In this regard, Steven
    testified that had defendant not concealed the PSE&G wire interference,
    plaintiff's bid on the project would have been $1 million as opposed to
    $697,000. Thus, the $303,000 difference provided a permissible basis for the
    jury to arrive at a $300,000 award for fraud without double counting that
    amount in the $800,000 contract damages award.
    V.
    Defendant further argues, in Point V, that the trial court erred by failing
    to vacate the $500,000 punitive damages award.10 Defendant maintains that
    plaintiff was not entitled to punitive damages because it "did not present any
    evidence that [defendant] acted with 'actual malice' or 'wanton and willful
    disregard'" pursuant to the New Jersey Punitive Damages Act, N.J.S.A. 2A:15-
    5.12. We disagree.
    10
    We note that defendant does not challenge the quantum of the punitive
    damages award on appeal, merely the fact that the jury awarded punitive
    damages. As such, we do not address the propriety of the amount of damages
    awarded.
    A-3571-17T2
    52
    We review the trial court's decision to award punitive damages for an
    abuse of discretion. Maudsley v. State, 
    357 N.J. Super. 560
    , 590 (App. Div.
    2003). An abuse of discretion can be shown "if the discretionary act was not
    premised upon consideration of all relevant factors, was based upon
    consideration of irrelevant or inappropriate factors, or amounts to a clear error
    of judgment." Flagg v. Essex Cty. Prosecutor, 
    171 N.J. 561
    , 571 (2002).
    A court may award punitive damages "as punishment or deterrence for
    particularly egregious conduct."     Nappe v. Anschelewitz, Barr, Ansell &
    Bonello, 
    97 N.J. 37
    , 49 (1984); see also Maudsley, 
    357 N.J. Super. at 590
    . To
    impose punitive damages, "a defendant's conduct must be willfully and
    wantonly reckless or malicious." Gennari v. Weichert Co. Realtors, 
    148 N.J. 582
    , 610 (1997). Punitive damages require "an intentional wrongdoing in the
    sense of an 'evil-minded act' or an act accompanied by a wanton and willful
    disregard of the rights of another." Smith v. Whitaker, 
    160 N.J. 221
    , 241
    (1999) (quoting Nappe, 
    97 N.J. at 49
    ). A plaintiff "must prove by clear and
    convincing evidence a 'deliberate act or omission with knowledge of a high
    degree of probability of harm and reckless indifference to the consequences.'"
    Id. at 242 (quoting Berg v. Reaction Motors Div., Thiokol Chem Corp., 
    37 N.J. 396
     (1962)).
    A-3571-17T2
    53
    Further, juries are permitted to award punitive damages in cases which
    include causes of action in addition to fraud. See, e.g., Velop, Inc. v. Kaplan,
    
    301 N.J. Super. 32
    , 70-71 (App. Div. 1997) (upholding punitive damages
    award where a jury found defendants liable for fraud, breach of contract,
    conversion, and tortious interference); Perth Amboy Iron Works, Inc. v. Am.
    Home Assur. Co., 
    226 N.J. Super. 200
    , 227 (App. Div. 2000) (reversing
    dismissal of fraud and punitive damages claims where the only jury verdict
    was on breach of warranty and noting that while punitive damages "would not
    generally be awardable on a warranty theory of liability, . . . if defendants'
    conduct is found to be fraudulent" on remand, "the imposition of punitive
    damages might be warranted").
    As discussed, the jury did not err in finding that defendant committed
    fraud as there was substantial evidence that defendant failed to disclose the
    PSE&G wire interference to induce plaintiff to enter the contract. Further,
    there was sufficient evidence adduced at trial to establish that defendant acted
    with a "conscious and deliberate disregard of the interests of others ." As the
    court noted when it denied defendant's motion for a new trial or a remittitur,
    the trial evidence supports the conclusion that defendant knew of a potential
    Proximity Act violation prior to the signing of the subcontract but did not
    A-3571-17T2
    54
    disclose that information to plaintiff because it knew that it "was obtaining a
    better price" in contract negotiations. Defendant's conduct induced plaintiff to
    engage in a potentially life-threatening activity while also depriving plaintiff
    of the opportunity to negotiate the fair value for the work required to complete
    the project. In this regard, defendant's conduct demonstrated a "wanton and
    willful disregard" of plaintiff's rights.
    Moreover, according to Grant, who negotiated the subcontract on behalf
    of defendant, defendant was aware that plaintiff was facing financial
    difficulties at the time it executed the subcontract. Defendant nevertheless
    failed to pay plaintiff for the work it performed on the project, instead taking
    the position that plaintiff knew or should have known of the proximity of the
    PSE&G wires and the attendant financial and work-related consequences on
    the project. Defendant refused to make timely progress payments even despite
    plaintiff's notifications that it needed to pay its vendors, suppliers, and unions.
    Indeed, in April 2015, defendant was directly notified by the New Jersey
    Department of Labor that plaintiff was facing prosecution, fines, and/or
    penalties for failing to pay union benefits. Defendant did not pay the unions
    until October 2015 and January 2016, after plaintiff was debarred from public
    A-3571-17T2
    55
    contracts. Based on that evidence, the court did not abuse its discretion in
    denying a new trial on punitive damages.
    VI.
    Defendant maintains that plaintiff should not have received attorneys'
    fees as it should not have been considered a prevailing party.        It argues,
    however, that even were we to uphold the jury verdicts on all of the claims on
    which plaintiff prevailed below, plaintiff would not be entitled to attorneys '
    fees on the fraud claim. Further, defendant contends that "unless the PPA
    verdict is upheld, [plaintiff] is not, as a matter of law, entitled to an
    enhancement of the lodestar amount." Based on our reversal of the jury's PPA
    verdict, we vacate and remand for the trial court to determine whether
    attorneys' fees and an attendant fee enhancement are warranted.
    "[F]ee determinations by trial courts will be disturbed only on the rarest
    of occasions, and then only because of a clear abuse of discretion." Rendine v.
    Pantzer, 
    141 N.J. 292
    , 317 (1995).        We award attorneys' fees only where
    "expressly provided for by statute, court rule, or contract." Litton Indus., Inc.
    v. IMO Indus., Inc., 
    200 N.J. 372
    , 385 (2009) (quoting Packard-Bamberger &
    Co. v. Collier, 
    167 N.J. 427
    , 440 (2001)).
    A-3571-17T2
    56
    "The starting point in awarding attorneys' fees is the determination of the
    'lodestar,' which equals the 'number of hours reasonably expended multiplied
    by a reasonable hourly rate.'" Furst v. Einstein Moomjy, Inc., 
    182 N.J. 1
    , 21
    (2004) (quoting Rendine, 
    141 N.J. at 335
    ). "In determining the reasonableness
    of a fee, the factors in RPC 1.5(a) must be considered." Stoney v. Maple
    Shade Twp., 
    426 N.J. Super. 297
    , 318 (App. Div. 2012) (citing Furst, 182 N.J.
    at 22).
    "In cases where plaintiff presents 'distinctly different claims for relief' in
    one lawsuit, work on those unrelated claims cannot be deemed in pursuit of the
    ultimate result achieved." Silva v. Autos of Amboy, Inc., 
    267 N.J. Super. 546
    ,
    556 (App. Div. 1993) (quoting Hensley v. Eckerhart, 
    461 U.S. 424
    , 434-35
    (1983)). However, "when the plaintiff's claims for relief 'involve a common
    core of facts or will be based on related legal theories,' such a suit cannot be
    viewed as a series of discrete claims." 
    Ibid.
     (quoting Hensley, 
    461 U.S. at 435
    ).
    "[I]f a plaintiff's unsuccessful claims are related to the successful claims,
    either by a 'common core of facts' or 'related legal theories,' the court must
    consider the significance of the overall relief obtained to determine whether
    those hours devoted to the unsuccessful claims should be compensated."
    A-3571-17T2
    57
    Singer v. State, 
    95 N.J. 487
    , 500 (1984) (quoting Hensley, 
    461 U.S. at 435
    ).
    Therefore, "[i]f the results obtained are fully effective in vindicating plaintiff 's
    rights, counsel should recover for all hours reasonably expended on the
    litigation." 
    Ibid.
     On the other hand, "if a successful plaintiff has achieved
    only limited relief in comparison to all of the relief sought, the court must
    determine whether the expenditure of counsel's time on the entire litigation
    was reasonable in relation to the actual relief obtained, . . . and, if not, reduce
    the award proportionately." 
    Ibid.
     However, "there need not be proportionality
    between the damages recovered and the attorney-fee award itself." Furst, 182
    N.J. at 23 (citing Rendine, 
    141 N.J. at 336
    ).
    After determining the lodestar, the court must consider whether an
    enhancement is appropriate "to reflect the risk of nonpayment in all cases in
    which the attorney's compensation entirely or substantially is contingent on a
    successful outcome." Rendine, 
    141 N.J. at 337
    . This determination hinges on
    "the actual risks or burdens that are borne by the lawyer or lawyers." 
    Id. at 339-40
     (quoting Pennsylvania v. Del. Valley Citizens' Council for Clean Air,
    
    483 U.S. 711
    , 747 (1987) (Blackmun, J., dissenting)). An enhancement may
    not be appropriate under certain circumstances, such as where an attorney is
    paid a portion of his or her hourly fee regardless of results; where the damages
    A-3571-17T2
    58
    sought are so substantial that the contingent fee could exceed the lodestar
    amount; or where "the likelihood of success is unusually strong." 
    Id.
     at 340-
    41; see also Litton, 
    200 N.J. at 389
     ("Unlike the traditional fee-shifting case in
    which enhancement has some relevancy as a type of encouragement to
    represent a party . . . the opposite applies in a contract case.").
    Here, it is undisputed that the subcontract entitled plaintiff to attorneys '
    fees. The parties provided, under paragraph 21 of the Rider to Exhibit A, tha t
    Article 25 of the subcontract would be revised to state "that the losing party
    shall be responsible for all costs, disbursements, and expenses[,] including
    reasonable attorney fees incurred by the prevailing party as a result of any
    claim or dispute between [plaintiff] and [defendant] if so directed by the
    arbitrator or the court."
    In awarding a $220,243.50 lodestar amount, however, the trial court
    necessarily considered plaintiff's counsel's work on obtaining the PPA verdict.
    As we reverse as to that claim, we vacate and remand the trial court's March
    29, 2018 order granting plaintiff's application for attorneys' fees, as well as the
    portion of that order granting a fee enhancement to plaintiff. While the trial
    court stated that based on its review, plaintiff's billing "all seemed related to
    the same issue, which is the contract issue, the shielding work that was done
    A-3571-17T2
    59
    on this project," we note that as its review inherently included work on the
    PPA claim, the court should reconsider that conclusion on remand. In this
    regard, the court should determine the degree to which "plaintiff's unsuccessful
    claims are related to the successful claims, either by a 'common core of facts'
    or 'related legal theories,'" Singer, 
    95 N.J. at 500
     (quoting Hensley, 
    461 U.S. at 435
    ), and recalculate any fee award and attendant enhancement pursuant to the
    aforementioned principles.
    VII.
    In sum, we affirm the trial court's December 15, 2017 order denying
    summary judgment, its March 16, 2018 order denying defendant's motion for
    JNOV or a new trial, and the jury's January 25, 2018 verdict only to the extent
    that they relate to plaintiff's breach of contract and fraud claims and the jury's
    attendant $800,000 compensatory damages award for breach of contract and
    $300,000 award for fraud.       We reverse, however, the jury's verdict that
    defendant violated the PPA.      We also affirm the jury's $500,000 punitive
    damages award. Finally, we vacate and remand the court's March 29, 2018
    order granting plaintiff's application for attorneys' fees and a fee enhancement
    and remand for further proceedings to determine whether plaintiff is entitled to
    a fee award.
    A-3571-17T2
    60
    We stress that this verdict and the attendant damages award were the
    result of a jury trial.    The jury considered a wealth of evidence and we
    necessarily defer to their findings. See Cuevas v. Wentworth Grp., 
    226 N.J. 480
    , 499 (2016) ("A jury's verdict, including an award of damages, is cloaked
    with a 'presumption of correctness.'") (quoting Baxter v. Fairmont Food Corp.,
    
    74 N.J. 588
    , 598 (1977)).
    To the extent we have not addressed any of defendant's arguments it is
    because we have concluded they lack sufficient merit to warrant discussion in
    a written opinion. R. 2:11-3(e)(1)(E).
    Affirmed in part, reversed in part, vacated and remanded in part. We do
    not retain jurisdiction.
    A-3571-17T2
    61